Hello to all , hope you all had a good weekend.
The following is a record of what was done during the last working week and a forecast of the Next week.....
Initial Points
Projects and Deadlines
Design
Installation Panel Build
Mater Dei Hospital PPM
Business Development
New employees – David Abela and Francisco Rupérez Herrera
Welcome to our ESI Team group
Some Points Before Starting
The AJA external audit will be held on week of 2nd May 2017Staff training is on 21st April 2017I need the procedures you will be presenting in the staff training by 10th April 2017
Miltiadis Charalampidis (AKA Miltos) – awaiting you to join on the Linkedin
group
Clifton will soon be going on long leave from 6/7/2017 – 18/8/2017 both days included
Projects and Deadlines
16_025_DeLaRue_OFX
50% of the machines have been commissioned by CFH
14_069_OTM Additions
Q019 AS410 – We are proceeding with works here in conjunction with Gruppo Sett in Italy- our high level target is to change over in May/June 2017This week we will do some important tests on this change over
Q021_TF4- We have done progress here
16_007_LeMeridien
Here we need to re group and re plan our works- I will revise a plan with CVA
16_066_Sterling_DCS_Line2
We have started detailed engineering here- we need to keep to the plan of having P&Ids by 10th April and panel drawing by end of April-
This will be a first major project with the Siemens S1500 family of PLCs
16_040_Playmobil_Factory
We have started the panel build on MCC1 &2 (In Malta and Gozo)
We have done most orders and we now need to plan for the software development for this project
Projects and Deadlines
16_023_GGY
We have some snags pending - we also have to transfer the old GGY system to the new platform
15_011- Sliema apartments
We are finalising the 3rd fix on this project here
15_023_FM panels
15_023 Q012 [D10 Endicare 230V] - Beginning april 2017
Q004_013_D5M ASRD 110 PPA is scheduled for 30th April – we also have another scheduled for 30th Sept
16_041_RSM_Security
We need to close off here – the sooner the better – we are very close here
17_002 Flooring DAC
During next week we should complete the 1st and 2nd fix for this project
SAI/CCI please give me a list of parts required
Projects and Deadlines
12_043_LSP
There are some points on the tenant billing application which we are tackling
13_031_CCA
We have a number of snags here , which are to be put to bed once and for all!!
The snags are centred around the AC controls and the NUOO CCTV system
14_08_Siggiewi School-
We have made a commitment to give our contractual obligation of 100 hours as follows Training/ Data gathering and back up / Preventative maintenance on hardware /Transfer of server to SHE set up at MITA/Reactive maintenance/emergency call outs/Fine tuning / re commissioning of louvers –
14_083_Interconti
We have commissioned the system with snags - we will return to site when snags are done by others-
We also have to deliver the pool panel
15_038_new_HA_Ovt and 15_026_Apap
Residence
These two home automation projects are now urgent- we need to complete all installation
We also need to start working of the software development- they are urgent and we have to perform
Projects and Deadlines
SCM Support 13_012
I will be meeting the team to start up this SISA agreement shortly
13_070- SCM Lagoona Plant room
We have concluded the required installation and programming but commissioning is on hold till the client asks us to continue
13_075_Bosch_ProWatch_Genetec_Interface
The Bosch HSDK interface is well advanced and we have documented and we should shortly be expecting to go overseas to commission
12_025_SCM PH2
The last issues on the DAC for SCM PH2- IT IS NOW A PRORITY AND WE NEED TO GET COMPLETION CERTIFICATION- SCM PH2 needs also some attention on the tagging purchase order for the BMS- CVA is to work on this
01 02 03 04
DesignFor the Past week we have been working on the following
Playmobil –Design brief to Lino / Co-ordinated hand-over of partsPlaymobil – released on-hold VSDs (except PRPC1_2) to Shridar
Design
Sterling DCS Line2 – after meeting with SSa, generated preliminary footprint of MCC3Sterling DCS Line2 – Site meeting, (MCC3 footprint approved, etc)
OTM- Q021 docs update
01 02 03 04
DesignAnd next week… we will work on
Sterling DCS Line2 – Start P&IDs
Design
OTM– conclude Q021OTM – start 03NVL1.
This is what the Installation team have been working on last week
Life sciences water meter readings
OVT terminations and intruder panel installation
Installation
Flooring technologies 1st and 2nd fix
Sliema Apartments – installation and terminations
….. And this is what is planned for next week
Sliema Apartments – installation and terminations
Flooring technologies 1st and 2nd fix
Installation
OVT terminations and finalization of installation
Installation Planning
Installation
For the next 2 weeks the following is the schedule
https://calendar.google.com/calendar/embed?src=esimalta1%40gmail.com&ctz=Europe/Malta
Next week we will • FM Env D10_Endicare_230– This will be built by a sub
contractor• MCC1 • MCC2 by sub contractor
Panel Build
Panel Build
Week start 27.03.2017 Yearly Field devices checks, IR images & coordinated tests Mar-- E01-CC1, E02-CC1, EP1-CC1, E01-CC2, E01-CC3 Quarterly panel checks Mar -- H01-CC1, HP1-CC1, P04-CC1, P02-CC1, P03-CC1, T01-CC1, T02-CC1 E01-CC1, E02-CC1, EP1-CC1, F01-CC1, F02-CC1, F05-CC4, F05-CC5, F03-CC1, F04-CC1, F05-CC1 Weekly update of antivirus on all BMS stations
Mater Dei Maintenance
ReactiveHandling of reactive work orders OthersParticipating in weekly fire drillsTraining of new team memberQxxx_ShiftingOfFridgeD109080
Next week Siemens will be at Mater Dei to make an infrastructure technical audit- thanks to Silvio , Chris and John for organizing this.
Mater Dei Maintenance
Crane Currency BMS and ELV Proposals
Actavis Solvent area Process quote
De La Rue BMS
These are the quotes the business development
team have been working on
Business Development
I await all your feedback on all the ESI discussions – without this feedback – this group will not be alive and fruitful- so take time off from your busy agendas, read what we have and participate and comment
Share your thoughts and participate actively on this blog- make this YOUR blog- your comments on this blog are always welcome and eagerly awaited for
I urge you all to follow this blog and keep up to
date with what is happening at ESI
Lets all work to get the work done on time, on
budget and to the required quality
We need to communicate, pull the rope in the
same direction to make our projects a success
and profitable
Some Last Thoughts
I wish you all a good and productive
week