TW@ESI2ND APRIL 2017

Page 2: TW@ESI 2nd April 2017

Hello to all , hope you all had a good weekend.

The following is a record of what was done during the last working week and a forecast of the Next week.....

Initial Points

Projects and Deadlines

Design

Installation Panel Build

Mater Dei Hospital PPM

Business Development

Page 3: TW@ESI 2nd April 2017

New employees – David Abela and Francisco Rupérez Herrera

Welcome to our ESI Team group

Some Points Before Starting

The AJA external audit will be held on week of 2nd May 2017Staff training is on 21st April 2017I need the procedures you will be presenting in the staff training by 10th April 2017

Miltiadis Charalampidis (AKA Miltos) – awaiting you to join on the Linkedin

group

Clifton will soon be going on long leave from 6/7/2017 – 18/8/2017 both days included

Page 4: TW@ESI 2nd April 2017

Projects and Deadlines

16_025_DeLaRue_OFX

50% of the machines have been commissioned by CFH

14_069_OTM Additions

Q019 AS410 – We are proceeding with works here in conjunction with Gruppo Sett in Italy- our high level target is to change over in May/June 2017This week we will do some important tests on this change over

Q021_TF4- We have done progress here

16_007_LeMeridien

Here we need to re group and re plan our works- I will revise a plan with CVA

16_066_Sterling_DCS_Line2

We have started detailed engineering here- we need to keep to the plan of having P&Ids by 10th April and panel drawing by end of April-

This will be a first major project with the Siemens S1500 family of PLCs

16_040_Playmobil_Factory

We have started the panel build on MCC1 &2 (In Malta and Gozo)

We have done most orders and we now need to plan for the software development for this project

Page 5: TW@ESI 2nd April 2017

Projects and Deadlines

16_023_GGY

We have some snags pending - we also have to transfer the old GGY system to the new platform

15_011- Sliema apartments

We are finalising the 3rd fix on this project here

15_023_FM panels

15_023 Q012 [D10 Endicare 230V] - Beginning april 2017

Q004_013_D5M ASRD 110 PPA is scheduled for 30th April – we also have another scheduled for 30th Sept

16_041_RSM_Security

We need to close off here – the sooner the better – we are very close here

17_002 Flooring DAC

During next week we should complete the 1st and 2nd fix for this project

SAI/CCI please give me a list of parts required

Page 6: TW@ESI 2nd April 2017

Projects and Deadlines

12_043_LSP

There are some points on the tenant billing application which we are tackling

13_031_CCA

We have a number of snags here , which are to be put to bed once and for all!!

The snags are centred around the AC controls and the NUOO CCTV system

14_08_Siggiewi School-

We have made a commitment to give our contractual obligation of 100 hours as follows Training/ Data gathering and back up / Preventative maintenance on hardware /Transfer of server to SHE set up at MITA/Reactive maintenance/emergency call outs/Fine tuning / re commissioning of louvers –

14_083_Interconti

We have commissioned the system with snags - we will return to site when snags are done by others-

We also have to deliver the pool panel

15_038_new_HA_Ovt and 15_026_Apap

Residence

These two home automation projects are now urgent- we need to complete all installation

We also need to start working of the software development- they are urgent and we have to perform

Page 7: TW@ESI 2nd April 2017

Projects and Deadlines

SCM Support 13_012

I will be meeting the team to start up this SISA agreement shortly

13_070- SCM Lagoona Plant room

We have concluded the required installation and programming but commissioning is on hold till the client asks us to continue

13_075_Bosch_ProWatch_Genetec_Interface

The Bosch HSDK interface is well advanced and we have documented and we should shortly be expecting to go overseas to commission

12_025_SCM PH2

The last issues on the DAC for SCM PH2- IT IS NOW A PRORITY AND WE NEED TO GET COMPLETION CERTIFICATION- SCM PH2 needs also some attention on the tagging purchase order for the BMS- CVA is to work on this

Page 8: TW@ESI 2nd April 2017

01 02 03 04

DesignFor the Past week we have been working on the following

Playmobil –Design brief to Lino / Co-ordinated hand-over of partsPlaymobil – released on-hold VSDs (except PRPC1_2) to Shridar

Design

Sterling DCS Line2 – after meeting with SSa, generated preliminary footprint of MCC3Sterling DCS Line2 – Site meeting, (MCC3 footprint approved, etc)

OTM- Q021 docs update

Page 9: TW@ESI 2nd April 2017

01 02 03 04

DesignAnd next week… we will work on

Sterling DCS Line2 – Start P&IDs

Design

OTM– conclude Q021OTM – start 03NVL1.

Page 10: TW@ESI 2nd April 2017

This is what the Installation team have been working on last week

Life sciences water meter readings

OVT terminations and intruder panel installation

Installation

Flooring technologies 1st and 2nd fix

Sliema Apartments – installation and terminations

Page 11: TW@ESI 2nd April 2017

….. And this is what is planned for next week

Sliema Apartments – installation and terminations

Flooring technologies 1st and 2nd fix

Installation

OVT terminations and finalization of installation

Page 12: TW@ESI 2nd April 2017

Installation Planning

Installation

For the next 2 weeks the following is the schedule

https://calendar.google.com/calendar/embed?src=esimalta1%40gmail.com&ctz=Europe/Malta

Page 13: TW@ESI 2nd April 2017

Next week we will • FM Env D10_Endicare_230– This will be built by a sub

contractor• MCC1 • MCC2 by sub contractor

Panel Build

Panel Build

Page 14: TW@ESI 2nd April 2017

Week start 27.03.2017 Yearly Field devices checks, IR images & coordinated tests Mar-- E01-CC1, E02-CC1, EP1-CC1, E01-CC2, E01-CC3 Quarterly panel checks Mar -- H01-CC1, HP1-CC1, P04-CC1, P02-CC1, P03-CC1, T01-CC1, T02-CC1 E01-CC1, E02-CC1, EP1-CC1, F01-CC1, F02-CC1, F05-CC4, F05-CC5, F03-CC1, F04-CC1, F05-CC1 Weekly update of antivirus on all BMS stations

Mater Dei Maintenance

ReactiveHandling of reactive work orders OthersParticipating in weekly fire drillsTraining of new team memberQxxx_ShiftingOfFridgeD109080

Next week Siemens will be at Mater Dei to make an infrastructure technical audit- thanks to Silvio , Chris and John for organizing this.

Mater Dei Maintenance

Page 15: TW@ESI 2nd April 2017

Crane Currency BMS and ELV Proposals

Actavis Solvent area Process quote

De La Rue BMS

These are the quotes the business development

team have been working on

Business Development

Page 16: TW@ESI 2nd April 2017

I await all your feedback on all the ESI discussions – without this feedback – this group will not be alive and fruitful- so take time off from your busy agendas, read what we have and participate and comment

Share your thoughts and participate actively on this blog- make this YOUR blog- your comments on this blog are always welcome and eagerly awaited for

I urge you all to follow this blog and keep up to

date with what is happening at ESI

Lets all work to get the work done on time, on

budget and to the required quality

We need to communicate, pull the rope in the

same direction to make our projects a success

and profitable

Some Last Thoughts

Page 17: TW@ESI 2nd April 2017

I wish you all a good and productive

week