TW@ESI26TH FEBRUARY 2017
Greetings from 26,000feet on my way back from Dubai
The following is a record of what was done during the last working week and a forecast of the Next week.....
Initial Points
Projects and Deadlines
Design
Installation Panel Build
Mater Dei Hospital PPM
Business Development
Next Friday 3rd March I am inviting you all to after work
drinks at City of London Bar St Julians... It will be a nice
occasion for us to have our last drink with some employees
who will be leaving us.
Some Points Before Starting
Dennis will be on leave till 2nd March and Shridar will be on long leave from 17 Feb 2017 to 20th March
On Wednesday 1st March new employee Miltiadis Charalampidis (Greek nationality) will be joining ESI as an Assistant Project Co-
ordinator. He will replace Shawn on MDH team.
Projects and Deadlines
16_025_DeLaRue_OFX
During the next week, we will be proceeding to commission 4 machines- 50% of the machines
14_069_OTM Additions
Q019 AS410 – We are proceeding with works here in conjunction with Gruppo Sett in Italy- our high level target is to change over in May/June 2017
Q021_TF4- Panel is on site and installed- we have powered up the panel and started connecting and powering up MOVs
16_007_LeMeridien
We have started working on phase 1 panels – phase 1 which has to be completed by Feb 2017-
We have so far done 2 panels – we need to do 5 by end of Feb 2017- so we are a little behind here
16_066_Sterling_DCS_Line2
We have started some preliminary engineering here.... Kick off is scheduled for 7th March
16_040_Playmobil_Factory
We have started design and engineering here on MCC1 and 2 and I have started placing major orders .... Kick off is scheduled for 7th March
Projects and Deadlines
16_023_GGY
We have some snags pending (Savant with Android TV, integration with Acs, under floor heating functionality) - we also have to transfer the old GGY system to the new platform
15_011- Sliema apartments
We have done most terminations and panel build is completed too. We are trying to finalise the installation and then testing and commissioning would be next... The completion date here is for March 2017
15_023_FM panels
D20 ASRD being built by sub contractor and scheduled for 9th March 2017
D05 M 110 – scheduled for 1st May 2017
D20 ASRD 690 is presently in quotation stage
16_041_RSM_Security
We need to close off here – the sooner the better
SAI needs to give a date by when ESI will be completed from all works (works pending from others excluded)
16_058_Methode
Another fast tack project Jace Based AHU control system here
We now push our sub contractors to complete the required cable pulling and terminations
CCI/CVA are to proceed with programming
Projects and Deadlines
12_043_LSP
We have an important and urgent snag to be rectified ASAP – treating the rust on enclosures
There are some points on the tenant billing application which we are tackling
13_031_CCA
We have a number of snags here , which are to be put to bed once and for all!!
The snags are centred around the AC controls and the NUOO CCTV system
14_08_Siggiewi School-
We have made a commitment to give our contractual obligation of 100 hours as follows Training/ Data gathering and back up / Preventative maintenance on hardware /Transfer of server to SHE set up at MITA/Reactive maintenance/emergency call outs/Fine tuning / re commissioning of louvers –
14_083_Interconti
We have commissioned the system with snags - we will return to site when snags are done by others-
We also have to deliver the pool panel
15_038_new_HA_Ovt and 15_026_Apap
Residence
These two home automation projects are now urgent- we need to complete all installation
We also need to start working of the software development- they are urgent and we have to perform
Projects and Deadlines
12_025_SCM PH2
The last issues on the DAC for SCM PH2- IT IS NOW A PRORITY AND WE NEED TO GET COMPLETION CERTIFICATION- SCM PH2 needs also some attention on the tagging purchase order for the BMS- CVA is to work on this
13_070- SCM Lagoona Plant room
We have concluded the required installation and programming but commissioning is on hold till the client asks us to continue
13_075_Bosch_ProWatch_Genetec_Interface
The Bosch HSDK interface is well advanced and we have documented and we should shortly be expecting to go overseas to commission
01 02 03 04
DesignFor the Past week we have been working on the following
OTM – Q020 Netherlocks – BH1_NVC_001 – completed & submitted on 21/2/2017TF3_NVC_004 TF3_NVC_002 revised as per Client feedback
Playmobil HF80 –completed 1st run of P&IDs for MCC1 and MCC2Various RFI replies, fine-tuning of Points lists, etc
FM Environmental – Updated as per CFH feedback, re-sent to CFH to re-submit
Design
AAP – completed implementation of Additions, distributed to all
01 02 03 04
DesignAnd next week… we will work on
Vibrant – Ask CCI for As built feedback, implement accordingly
Playmobil HF80 – Status review withStart Panel Design sketching for MCC1, and release Material quote request
Design
OTM – Start SSA’s Q021 docs revision requestContinue Q020 Netherlocks remaining Design, after receipt from SSA
This is what the Installation team have been working on last week
Started with canalization and cable pulling at Methode
Continued with commissioning at RSM
Methode panel delivered on site - Mounting of panel on site at Methode
Installation
Installed VSD at Medichem
Repairs at Lasco
Cleared up Mosta Workshop
….. And this is what is planned for next week
Complete commissioning at RSM
Continue with terminations at OVT
Installation
Complete works at Methode
Continue with PIR installation at Graham
Next week we will • FM Env D20-ASRD – This will be built by a sub contractor
Panel Build
Panel Build
Week 09PPMYearly Field devices checks, IR images & coordinated tests Feb-- D11-CC2, D12-CC1, F02-CC1, F05-CC1, F05-CC4, F05-CC5
Quarterly panel checks Feb -- D00-CC1, D01-CC1, DP1-CC1, D02-CC1, DP2-CC1, D04-CC1, DP3-CC1, D04-CC2, D04-CC3, DO5-CC1, D05-CC2, D06-CC1, DP4-CC1, D06-CC2, D06-CC3D07-CC1, D07-CC2, D08-CC1, DP5-CC1, D08-CC2, D08-CC3, D09-CC1, D09-CC2, D10-CC1, D10-CC2, D10-CC3, DP6-CC1, D11-CC1, D11-CC2,D12-CC1
Weekly update of antivirus on all BMS stations
Mater Dei Maintenance
ReactiveHandling of reactive work orders OthersParticipating in weekly fire drillsTraining of new team member
Mater Dei Maintenance
lighting control systems in Qatar
Offer for Neatherlocks at OTM
Building automation in a private clinic
MCC for an officeThese are the quotes the business development
team have been working on
Business Development
\
HAPPY BIRTHDAYDANIELLE LUNETTI MARCH 5TH
I await all your feedback on all the ESI discussions – without this feedback – this group will not be alive and fruitful- so take time off from your busy agendas, read what we have and participate and comment
Share your thoughts and participate actively on this blog- make this YOUR blog- your comments on this blog are always welcome and eagerly awaited for
I urge you all to follow this blog and keep up to
date with what is happening at ESI
Lets all work to get the work done on time, on
budget and to the required quality
We need to communicate, pull the rope in the
same direction to make our projects a success
and profitable
Some Last Thoughts
I wish you all a good and productive
week