Greetings from 26,000feet on my way back from Dubai

The following is a record of what was done during the last working week and a forecast of the Next week.....

Initial Points

Projects and Deadlines

Design

Installation Panel Build

Mater Dei Hospital PPM

Business Development

Page 3: TW@ESI 26th February 2017

Next Friday 3rd March I am inviting you all to after work

drinks at City of London Bar St Julians... It will be a nice

occasion for us to have our last drink with some employees

who will be leaving us.

Some Points Before Starting

Dennis will be on leave till 2nd March and Shridar will be on long leave from 17 Feb 2017 to 20th March

On Wednesday 1st March new employee Miltiadis Charalampidis (Greek nationality) will be joining ESI as an Assistant Project Co-

ordinator. He will replace Shawn on MDH team.

Page 4: TW@ESI 26th February 2017

Projects and Deadlines

16_025_DeLaRue_OFX

During the next week, we will be proceeding to commission 4 machines- 50% of the machines

14_069_OTM Additions

Q019 AS410 – We are proceeding with works here in conjunction with Gruppo Sett in Italy- our high level target is to change over in May/June 2017

Q021_TF4- Panel is on site and installed- we have powered up the panel and started connecting and powering up MOVs

16_007_LeMeridien

We have started working on phase 1 panels – phase 1 which has to be completed by Feb 2017-

We have so far done 2 panels – we need to do 5 by end of Feb 2017- so we are a little behind here

16_066_Sterling_DCS_Line2

We have started some preliminary engineering here.... Kick off is scheduled for 7th March

16_040_Playmobil_Factory

We have started design and engineering here on MCC1 and 2 and I have started placing major orders .... Kick off is scheduled for 7th March

Page 5: TW@ESI 26th February 2017

Projects and Deadlines

16_023_GGY

We have some snags pending (Savant with Android TV, integration with Acs, under floor heating functionality) - we also have to transfer the old GGY system to the new platform

15_011- Sliema apartments

We have done most terminations and panel build is completed too. We are trying to finalise the installation and then testing and commissioning would be next... The completion date here is for March 2017

15_023_FM panels

D20 ASRD being built by sub contractor and scheduled for 9th March 2017

D05 M 110 – scheduled for 1st May 2017

D20 ASRD 690 is presently in quotation stage

16_041_RSM_Security

We need to close off here – the sooner the better

SAI needs to give a date by when ESI will be completed from all works (works pending from others excluded)

16_058_Methode

Another fast tack project Jace Based AHU control system here

We now push our sub contractors to complete the required cable pulling and terminations

CCI/CVA are to proceed with programming

Page 6: TW@ESI 26th February 2017

Projects and Deadlines

12_043_LSP

We have an important and urgent snag to be rectified ASAP – treating the rust on enclosures

There are some points on the tenant billing application which we are tackling

13_031_CCA

We have a number of snags here , which are to be put to bed once and for all!!

The snags are centred around the AC controls and the NUOO CCTV system

14_08_Siggiewi School-

We have made a commitment to give our contractual obligation of 100 hours as follows Training/ Data gathering and back up / Preventative maintenance on hardware /Transfer of server to SHE set up at MITA/Reactive maintenance/emergency call outs/Fine tuning / re commissioning of louvers –

14_083_Interconti

We have commissioned the system with snags - we will return to site when snags are done by others-

We also have to deliver the pool panel

15_038_new_HA_Ovt and 15_026_Apap

Residence

These two home automation projects are now urgent- we need to complete all installation

We also need to start working of the software development- they are urgent and we have to perform

Page 7: TW@ESI 26th February 2017

Projects and Deadlines

12_025_SCM PH2

The last issues on the DAC for SCM PH2- IT IS NOW A PRORITY AND WE NEED TO GET COMPLETION CERTIFICATION- SCM PH2 needs also some attention on the tagging purchase order for the BMS- CVA is to work on this

13_070- SCM Lagoona Plant room

We have concluded the required installation and programming but commissioning is on hold till the client asks us to continue

13_075_Bosch_ProWatch_Genetec_Interface

The Bosch HSDK interface is well advanced and we have documented and we should shortly be expecting to go overseas to commission

Page 8: TW@ESI 26th February 2017

01 02 03 04

DesignFor the Past week we have been working on the following

OTM – Q020 Netherlocks – BH1_NVC_001 – completed & submitted on 21/2/2017TF3_NVC_004 TF3_NVC_002 revised as per Client feedback

Playmobil HF80 –completed 1st run of P&IDs for MCC1 and MCC2Various RFI replies, fine-tuning of Points lists, etc

FM Environmental – Updated as per CFH feedback, re-sent to CFH to re-submit

Design

AAP – completed implementation of Additions, distributed to all

Page 9: TW@ESI 26th February 2017

01 02 03 04

DesignAnd next week… we will work on

Vibrant – Ask CCI for As built feedback, implement accordingly

Playmobil HF80 – Status review withStart Panel Design sketching for MCC1, and release Material quote request

Design

OTM – Start SSA’s Q021 docs revision requestContinue Q020 Netherlocks remaining Design, after receipt from SSA

Page 10: TW@ESI 26th February 2017

This is what the Installation team have been working on last week

Started with canalization and cable pulling at Methode

Continued with commissioning at RSM

Methode panel delivered on site - Mounting of panel on site at Methode

Installation

Installed VSD at Medichem

Repairs at Lasco

Cleared up Mosta Workshop

Page 11: TW@ESI 26th February 2017

….. And this is what is planned for next week

Complete commissioning at RSM

Continue with terminations at OVT

Installation

Complete works at Methode

Continue with PIR installation at Graham

Page 12: TW@ESI 26th February 2017

Next week we will • FM Env D20-ASRD – This will be built by a sub contractor

Panel Build

Panel Build

Page 13: TW@ESI 26th February 2017

Week 09PPMYearly Field devices checks, IR images & coordinated tests Feb-- D11-CC2, D12-CC1, F02-CC1, F05-CC1, F05-CC4, F05-CC5

Quarterly panel checks Feb -- D00-CC1, D01-CC1, DP1-CC1, D02-CC1, DP2-CC1, D04-CC1, DP3-CC1, D04-CC2, D04-CC3, DO5-CC1, D05-CC2, D06-CC1, DP4-CC1, D06-CC2, D06-CC3D07-CC1, D07-CC2, D08-CC1, DP5-CC1, D08-CC2, D08-CC3, D09-CC1, D09-CC2, D10-CC1, D10-CC2, D10-CC3, DP6-CC1, D11-CC1, D11-CC2,D12-CC1

Weekly update of antivirus on all BMS stations

Mater Dei Maintenance

ReactiveHandling of reactive work orders OthersParticipating in weekly fire drillsTraining of new team member

Mater Dei Maintenance

Page 14: TW@ESI 26th February 2017

lighting control systems in Qatar

Offer for Neatherlocks at OTM

Building automation in a private clinic

MCC for an officeThese are the quotes the business development

team have been working on

Business Development

Page 15: TW@ESI 26th February 2017

\

HAPPY BIRTHDAYDANIELLE LUNETTI MARCH 5TH

Page 16: TW@ESI 26th February 2017

I await all your feedback on all the ESI discussions – without this feedback – this group will not be alive and fruitful- so take time off from your busy agendas, read what we have and participate and comment

Share your thoughts and participate actively on this blog- make this YOUR blog- your comments on this blog are always welcome and eagerly awaited for

I urge you all to follow this blog and keep up to

date with what is happening at ESI

Lets all work to get the work done on time, on

budget and to the required quality

We need to communicate, pull the rope in the

same direction to make our projects a success

and profitable

Some Last Thoughts