tw@esi 27th march 2016

20
TW@ESI 27 th March 2016 Hope that you and all your families had a good weekend- I am back in one piece The following is a forecast of the next week.....

Upload: simon-abela

Post on 15-Apr-2017

199 views

Category:

Business


2 download

TRANSCRIPT

Page 1: TW@ESI 27th March 2016

TW@ESI27th March 2016Hope that you and all your families had a good weekend- I am back in one piece

The following is a forecast of the next week.....

Page 2: TW@ESI 27th March 2016

A General Note before we startI would like to thank once again all the team for the efforts to complete the offices upstairs. The plan next for this week is: a) Pass all PIR cables and AC control cablesb) Finish all paintwork upstairsc) Next stage will involve works in design and

technical office- before this is done the show room area must be closed off and electrical supply made permanent with Enemalta (to allow people to relocate to here)

Page 3: TW@ESI 27th March 2016

Projects and deadlines• 15_033_Westin_7-AHU- With everyone’s effort we have

managed to change over the Banquet hall AHUs- not only but start these remotely from the engineering PC- Next target- finish all Testing and commissioning works by end of month (March 2016)

• 13_070_SCM Lagoona_Pump room- We have pulled most cables and need to now start terminations on site... This, too, is going to become a hot project- All terminations possible are to be completed ASAP

• 14_001_Fadalah- CVA will be going to site to a ship yard in Greece (not Istanbul) and commissioning this as of tomorrow 28/3 (for all the week).

Page 4: TW@ESI 27th March 2016

Projects and deadlines• 15_044_Hilton_Restaurant_Kitchen_AHU and

15_034_Hilton_Calorifier_Monitoring- Panels to be completed by 23/3/2016. All installation and manual start up by end first week of April 2016- Manual start-up, soon after. Full T&C by end of April 2015. We have given most of the installation works to Panta and we need to ensure that Panta’s work is to the required standard.

• Projects 12_026 SCM Buildings 02, 03, R3 & R4 and 12_027 Security Systems Parliament- LVA and JPO will put whatever efforts necessary to close off whatever can be closed off by 1st April 2016.

Page 5: TW@ESI 27th March 2016

Projects and deadlines• 15_008 - Aurobindo PH02 BMS- We have made

progress on commissioning here- we will also soon need to come up with a plan and target date here.

• 13_052 New offices- Get the Automation in the new area offices ready by March 2016!! Make sure it is fully functional and de snagged- Installation upstairs are to be completed shortly.... Design and Technical offices will be moved soon after that!

Page 6: TW@ESI 27th March 2016

DesignLast week• City Gate Parliament – Additional Lift – implemented As Built

update from LVa• Siggiewi Primary School – Gathered Clifford As Built Feedback,

started implementing it• OVt New Residence 15_038 – trashed queries with TBR,

released queries to C Schranz & DLI, started Points Lists• Aurobindo – released additional CP02 pump starter for Lino to

install on site• ESI – Handover from GMe for Shireburn software installations

(WinSims & Timesheets, pending Finance & Payroll software)• ESI – new user on Server for Marita Fenech, relevant settings /

installations on JFH PC – set in GME office

Page 7: TW@ESI 27th March 2016

DesignNext Week:• Siggiewi Primary School – Gather Clifton As Built Feedback ,

implement• Siggiewi Primary School – continue Implementing Cliffiord As Built

feedback• ESI – Handover from GMe - Finance & Payroll software• ESI – Install Payroll & Finance on Marita PC• Hilton Restaurant & Kitchen AHUs - Compile Terminating Matrix• MDH MAU – Print 5x P&IDs & Panel Drawings (subject to

confirmation from Sandro Mekanika)• MDH MAU – conclude quote for Plastic rivets for Engraved Labels

for D00-CC1• OVt New Residence 15_038 – continue on Points Lists, start P&IDs

Page 8: TW@ESI 27th March 2016

InstallationPast week:– Completed mesh tray and started cable pulling in

plant room at Hilton (by Panta)– Installed all panels at Hilton– Modifications on panel at Aurobindo– Commissioning of cctv and DAC at parliament– Completed cable labelling and other small works at

Westin– Terminations at Smart City Lagoon

Page 9: TW@ESI 27th March 2016

InstallationNext week:– Finish cable pulling and start installing field devices

at Hilton (by Panta)– Existing panels modification at Hilton– Start panel terminations at Hilton– Pass A/C and intruder cables at ESI offices Level 1– Finish terminations at SCM Lagoon– Panel modifications at SCM Lagoon– Commissioning at Life Sciences

Page 10: TW@ESI 27th March 2016

Panel Build• Terminations of Hilton Panels

Page 11: TW@ESI 27th March 2016

Mater DeiThe following are the tasks being worked on and planned for the next weeks• Coordinated Checks of Alarms from 3rd Party Devices D10-CC1, D10-CC2, D10-CC3,

D11-CC1, DP6-CC1• FIELD DEVICES CHECKS FROM SITE/HMI D10-CC1, D10-CC2, D10-CC3, D11-CC1,

DP6-CC1• FIELD DEVICES CHECKS FROM SITE/HMI D11-CC2, D12-CC1• MCC PANEL CHECKS/UPS IN BMS PANEL E01-CC1, E02-CC1. EP1-CC1, F01-CC1, F02-

CC1, F05-CC4, F05-CC5, F03-CC1, F04-CC1, F05-CC1• COORDINATED CHECKS OF ALARMS FROM 3RD PARTY DEVICES E01-CC1, E02-CC1,

EP1-CC1• COORDINATED FRIDGE / FREEZER TEST BETWEEN ESI AND BIOMEDICAL - MARCH• PANEL THERMOGRAPHICAL IMAGES E01-CC1, E02-CC1, EP1-CC1• FIELD DEVICES CHECKS FROM SITE E01-CC1, E02-CC1, EP1-CC1• MCC PANEL CHECKS/UPS IN BMS PANEL H01-CC1, HP1-CC1, P04-CC1, P02-CC1, P03-

CC1, T01-CC1, T02-CC1• WEEKLY UPDATE OF ANTI-VIRUS ON ALL BMS STATIONS• Preparation work for new HMIs for D05-CC1, D06-CC1, D07-CC1

Page 12: TW@ESI 27th March 2016

Development and Commissioning• We have done large important steps on finishing off the

Parliament we need to get the documentation out of the way too to avoid us going time and time again on site- IT IS NOW A PRORITY AND WE NEED TO GET A COMPLETION

• The last issues on the DAC for SCM PH2- IT IS NOW A PRORITY AND WE NEED TO GET COMPLETION CERTIFICATION

• Life Sciences- We have also concluded with Training now... Documentation and some snags are pending

• SCM PH2 needs also some attention on the tagging purchase order for the BMS- CVA is to work on this

• The Bosch HSDK interface is well advanced and we awaiting the client

Page 13: TW@ESI 27th March 2016

Development and Commissioning

• OTM urgent jobs and snags were also done in the last weeks• Another project that needs attention is CCA Villa ... There are

still some snags to be addressed –intruder alarm integration• Oncology 14_066- We have done most of the work here and

are waiting from Panta on this• The Siggiewi Primary school project – we need to close off –

there is very little left here• Aurobindo we are proceeding with software development

and we have done quite some progress – we are also now commissioning this project- we will need to come up with a plan here.

Page 14: TW@ESI 27th March 2016

Development and Commissioning• 16_004_Microbiz_PW_Otis_Interface- We are

presently working on a task list and POW as well as setting up the test rigs

Page 15: TW@ESI 27th March 2016

Sales and Business Development

• We have been working on Home automation offerings and quotes for OTM (some of which are quite large) , a quote for CCTV at Enemalta and quotes for variations for existing projects.

Page 16: TW@ESI 27th March 2016

Birthday wishes go to

Lino Cordina 28th March

Page 17: TW@ESI 27th March 2016

Date – Friday 1st April 2016Time – 1600hrs onwardsVenue- Tico Tico Bar – Strait Street, Valletta

Page 18: TW@ESI 27th March 2016

• More lessons to follow shortly – this next week

Page 19: TW@ESI 27th March 2016

Team ESI• I urge you all to follow this blog and keep up to date with

what is happening at ESI • I await all your feedback on all the ESI discussions –

without this feedback – this group will not be alive and fruitful- so take time off from your busy agendas, read what we have and participate and comment

• Please urge and assist all you colleagues to have a linkedin profile and join this discussion group

• Share your thoughts and participate actively on this blog- make this YOUR blog- your comments on this blog are always welcome and eagerly awaited for

Page 20: TW@ESI 27th March 2016

Team ESI

• Lets all work to get the work done on time, on budget and to the required quality

• We need to communicate, pull the rope in the same direction to make our projects a success and profitable

• Have a good week