Hello to all , hope you all had a good weekend.

The following is a record of what was done during the last working week and a forecast of the Next week.....

Initial Points

Projects and Deadlines

Design

Installation Panel Build

Mater Dei Hospital PPM

Business Development

Page 3: TW@ESI 12th March 2017

New employee - Miltiadis Charalampidis (AKA Miltos) – Please join us on Linkedin

Some Points Before Starting

Shridar will be on long leave from 17 Feb 2017 to 20th March

Dennis Smith has resigned from his post as Projects Co Ordinator will

work till 17th March 2017 - We will struggle to fill in Dennis’ shoes and I will need everyone’s help until we

find his replacement- I would like to thank Dennis for the service he gave ESI and wish him luck on his

future

A New employee - Francisco Rupérez Herrera (Spanish

Nationaliity) will be joining us as of 16th March 2017- he will

be working as a technician with SSA and CFH

We have a new intern Redis Ziu (Italian Nationaility) who is

working with SSA/CFH

Page 4: TW@ESI 12th March 2017

Projects and Deadlines

16_025_DeLaRue_OFX

50% of the machines have been commissioned by CFH

14_069_OTM Additions

Q019 AS410 – We are proceeding with works here in conjunction with Gruppo Sett in Italy- our high level target is to change over in May/June 2017

Q021_TF4- Panel is on site and installed- we have powered up the panel and started connecting and powering up MOVs

16_007_LeMeridien

We have started working on phase 1 panels – phase 1 which has to be completed by Feb 2017-

We have so far done 2 panels – we need to do 5 by end of Feb 2017- so we are a little behind here

16_066_Sterling_DCS_Line2

We have started some preliminary engineering here.... We will now proceed to detailed engineering

16_040_Playmobil_Factory

We have started design and engineering here on MCC1 and 2 and I have started placing major orders

Page 5: TW@ESI 12th March 2017

Projects and Deadlines

16_023_GGY

We have some snags pending (Savant with Android TV, integration with Acs, under floor heating functionality) - we also have to transfer the old GGY system to the new platform

15_011- Sliema apartments

We have done most terminations and panel build is completed too. We are trying to finalise the installation and then testing and commissioning would be next... The completion date here is for March 2017

15_023_FM panels

D20 ASRD being built by sub contractor and scheduled for 9th March 2017

15_023 Q012 [D10 Endicare 230V] - Beginning april 2017

Q004_013_D5M ASRD 110 PPA is scheduled for 30th April – we also have another scheduled for 30th Sept

16_041_RSM_Security

We need to close off here – the sooner the better

SAI needs to give a date by when ESI will be completed from all works (works pending from others excluded)

16_058_Methode

Another fast tack project Jace Based AHU control system here

We have done some giant steps on Testing and commissioning – still an amount to do after other finish their works

Page 6: TW@ESI 12th March 2017

Projects and Deadlines

12_043_LSP

There are some points on the tenant billing application which we are tackling

13_031_CCA

We have a number of snags here , which are to be put to bed once and for all!!

The snags are centred around the AC controls and the NUOO CCTV system

14_08_Siggiewi School-

We have made a commitment to give our contractual obligation of 100 hours as follows Training/ Data gathering and back up / Preventative maintenance on hardware /Transfer of server to SHE set up at MITA/Reactive maintenance/emergency call outs/Fine tuning / re commissioning of louvers –

14_083_Interconti

We have commissioned the system with snags - we will return to site when snags are done by others-

We also have to deliver the pool panel

15_038_new_HA_Ovt and 15_026_Apap

Residence

These two home automation projects are now urgent- we need to complete all installation

We also need to start working of the software development- they are urgent and we have to perform

Page 7: TW@ESI 12th March 2017

Projects and Deadlines

12_025_SCM PH2

The last issues on the DAC for SCM PH2- IT IS NOW A PRORITY AND WE NEED TO GET COMPLETION CERTIFICATION- SCM PH2 needs also some attention on the tagging purchase order for the BMS- CVA is to work on this

13_070- SCM Lagoona Plant room

We have concluded the required installation and programming but commissioning is on hold till the client asks us to continue

13_075_Bosch_ProWatch_Genetec_Interface

The Bosch HSDK interface is well advanced and we have documented and we should shortly be expecting to go overseas to commission

Page 8: TW@ESI 12th March 2017

01 02 03 04

DesignFor the Past week we have been working on the following

OTM – Continued Q020 Netherlocks remaining Design )OTM – Started SSA’s Q021 docs revision request

Playmobil HF80 – completed Panel Design of MCC1 & MCC2released MCC2 to for DraughtingPlaymobil HF80 – started draughting of MCC1

Design

Started & completed new FM Env. Sent to CFH to submit

Page 9: TW@ESI 12th March 2017

01 02 03 04

DesignAnd next week… we will work on

Playmobil HF80 – continue complete draughting of MCC1Playmobil HF80 – Dimensions & labels for MCC1 – Continue Draughting of MCC2

Design

Page 10: TW@ESI 12th March 2017

This is what the Installation team have been working on last week

Completed power and bms install at Methode

Completed panel terminations on Level 1,2 and 3 at Graham

Installation

Installation of water meters at Graham

Completed most of the commissioning at Methode

Continued with panel terminations at OVT

Page 11: TW@ESI 12th March 2017

….. And this is what is planned for next week

Continue with commissioning at Intercontinental

Testing of louvers at Siggiewi primary

Tackle snags at Methode

Installation

Updating of panel drawings at OTM

Sterling PPM cleaning

Page 12: TW@ESI 12th March 2017

Next week we will • FM Env D10_Endicare_230– This will be built by a sub

contractor

Panel Build

Panel Build

Page 13: TW@ESI 12th March 2017

Week 11PPMYearly Field devices checks, IR images & coordinated tests Mar-- E01-CC1, E02-CC1, EP1-CC1, E01-CC2, E01-CC3 Quarterly panel checks Mar -- H01-CC1, HP1-CC1, P04-CC1, P02-CC1, P03-CC1, T01-CC1, T02-CC1 E01-CC1, E02-CC1, EP1-CC1, F01-CC1, F02-CC1, F05-CC4, F05-CC5, F03-CC1, F04-CC1, F05-CC1 Weekly update of antivirus on all BMS stations

Mater Dei Maintenance

ReactiveHandling of reactive work orders OthersParticipating in weekly fire drillsTraining of new team memberQxxx_NewCPRalarmsWO-000117205926_ModifyC01-AHU1

Mater Dei Maintenance

Page 14: TW@ESI 12th March 2017

Crane Currency BMS and ELV Proposals

Actavis Solvent area Process quote

De La Rue BMS

These are the quotes the business development

team have been working on

Business Development

Page 15: TW@ESI 12th March 2017

\

HAPPY BIRTHDAYCLIFTON CAMENZULI – 16TH MARCH

Page 16: TW@ESI 12th March 2017

I await all your feedback on all the ESI discussions – without this feedback – this group will not be alive and fruitful- so take time off from your busy agendas, read what we have and participate and comment

Share your thoughts and participate actively on this blog- make this YOUR blog- your comments on this blog are always welcome and eagerly awaited for

I urge you all to follow this blog and keep up to

date with what is happening at ESI

Lets all work to get the work done on time, on

budget and to the required quality

We need to communicate, pull the rope in the

same direction to make our projects a success

and profitable

Some Last Thoughts