SPS LS1 Planning meeting (No.39) 25/06/14. David Mcfarlane. Topics. Lifts and Monte-charges . GE/ASE Access tests. Cleaning campaign dates. EPC tests of the Auxiliary Converters. The end of LS1. Access after the 27 th June. Planning. Rubbish. E.C.Rs. Important Information . - PowerPoint PPT Presentation

TRANSCRIPT

[email protected] 1

SPS LS1Planning meeting (No.39)

25/06/14

David Mcfarlane

[email protected] 2

Topics• Lifts and Monte-charges. • GE/ASE Access tests.• Cleaning campaign dates.• EPC tests of the Auxiliary Converters.• The end of LS1.• Access after the 27th June.• Planning.• Rubbish.• E.C.Rs.• Important Information.• A.O.B.

[email protected] 3

Last works on lifts

[email protected] 4

GE/ASE Access tests

[email protected] 5

Cleaning campaign

[email protected] 6

EPC tests of the Auxiliary Converters

With this planning, OP can start the commissioning of the Software with a 1 week delay from our activities: e.g, OP tests for BA2 could start on 9th June. What we need:• The magnet interlocks shall be tested in May by MPE (R.Mompo/P.Dahlen): support from EPC is requested during this period,

• Services shall be present in each BA in time: water (magnet + surface building), no consignation (except BA1 until end of June),

• A general signalisation that some tests are ongoing: coordination EPC/MSC,

• EIS (https://edms.cern.ch/document/991272): from past experiences, this is a difficult point for us during our tests, especially for TI2/TI8. I propose that when the planning is agreed on, Marc Tavlet will be contacted by EPC.

[email protected] 7

The end of LS1

[email protected] 8

Access after the 27th June.• ALL LS1-SPS IMPACTs will end on the 27th June!• Any accesses into any area of the SPS after this date will require a

NEW IMPACT. • You must enter the correct “intervention period” depending on

where you will be accessing.

– LS1-HWT-SPS (valid from 28th June to 31st August)• Access into the SPS during Hardware commissioning phase

– LS1-BA80-SPS (valid from now to 30th September)• Allowing continued access into BA80

– TAG41- AWAKE (Valid from now until October 2016)• Allowing continued access into TAG41

[email protected] 9

LS1-BA80-SPS (valid from now to 30th September)

TAG41- AWAKE(Valid from now until October 2016)

LS1-HWT-SPS(valid from 28th June to 31st August)

[email protected] 10

Access during July/August

• Access will once again be controlled by the CCC.

• There will be informal morning meetings everyday in the CCC to discuss if and when any accesses can be made.

• There is a meeting in the CCC today at 16:30 to finalize these details.

[email protected] 11

BA1 works• Reinstallation of the beam line and equipment in LSS1

– https://edms.cern.ch/document/1293491/6.0/TAB3

[email protected] 16

What a load of RUBBISH!!

• Its very important to ensure that you leave the work site clean and tidy.

• REMOVE ALL OF YOUR RUBBISH FROM THE TUNNEL NOW!!!!!!!!!

[email protected] 32

Engineering Change Requests• Any and all new equipment being installed in the SPS requires

an ECR BEFORE it can be installed. It must also be approved by planning and coordination.

• Templates and Guidelines for Engineering Change Requests:– EDMS: 1271880

• SPS ECR template (in DFS):– https

://dfsweb.web.cern.ch/dfsweb/Services/DFS/DFSBrowser.aspx/Applications/CERN/Workgroup%20Templates/SPS/ECR-Template-SPS.dotx

[email protected] 33

Current ECR’s for LS1https://edms.cern.ch/nav/P:CERN-0000076703:V0/P:CERN-0000096067:V0/TAB3

1. Removal of AEWB Pick-up from position 31932 to 31502 • (EDMS No. 1245361) UNDER IMPLEMENTATION

2. Removal of a BPWA Pick-up from position 31931 to 31101 • (EDMS No. 1245393) UNDER IMPLEMENTATION

3. Installation of a new Wideband Kickers system in position 32173 • (EDMS No. 1245400) UNDER IMPLEMENTATION

4. Installation of a new HBW Damper Pick-up in place of BPWA 31931 & AEWB 31932• (EDMS No. 1245401) RELEASED

5. Replacement of 4 old BPA and 2 BPD by 6 BPCE in LSS1 & LSS2• (EDMS No. 1246559) UNDER IMPLEMENTATION

6. Reinstallation of pump and gauges (Pirani + Penning) in 11993 (vacuum sector 150)• (EDMS No. 1249305) RELEASED

7. Modification LSS1 sectorization (new VVSF + displacement VVSB 11772)• (EDMS No. 1249307 v.2) RELEASED

8. Installation of 3 BCT in LSS5 for North Area protection during Ions operations in SPS.• (EDMS No. 1075945) UNDER IMPLEMENTATION

[email protected] 34

Current ECR’s for LS1https://edms.cern.ch/nav/P:CERN-0000076703:V0/P:CERN-0000096067:V0/TAB3

9. Transfer of the Fast Beam Current Transformers (BCTFR.31451) for the SPS circulating beam from LSS3 to LSS5.• (EDMS No. 1221341) RELEASED

10. SPS Beam Position Monitoring Prototyping Setup in LSS4.• (EDMS No. 1099630) RELEASED

11. Installation de 4 moniteurs de position (2 BPH, 2 BPV), dédiés au système Damper.• (EDMS No. 1251693) RELEASED

12. Installation de 2 nouveaux moniteurs de position de type BPCR en LSS2 au 21459 et 22172.• (EDMS No. 1251695) UNDER IMPLEMENTATION

13. Displacement of Door PPG2145 separating the LHC and the SPS in the TI2 tunnel.• (EDMS No. 1253832) UNDER IMPLEMENTATION

14. Interlocking of Injection Tunnel upstream areas with LHC powering.• (EDMS No. 1257949) RELEASED

15. Move of BPH.31998 to BPH.42173.• (EDMS No. 1272718) RELEASED

16. Optical Fibre Racks.• (EDMS No. 1273766) UNDER IMPLEMENTATION

[email protected] 35

Current ECR’s for LS1https://edms.cern.ch/nav/P:CERN-0000076703:V0/P:CERN-0000096067:V0/TAB3

17. Removal of old fixed TMP vacuum groups in 11655-11691.• (EDMS No. 1273232) UNDER IMPLEMENTATION

18. BYBPM racks under the SPS dipole magnets as part of the Upgrade of Beam Position Monitors electronics (MOPOS).• (EDMS No. 1282651) UNDER IMPLEMENTATION

19. Installation de Coffrets d'Alimentation en LSS1 et TT10.• (EDMS No. 1282860) UNDER IMPLEMENTATION

20. Installation d'un rack de jonction RX11695=TS1 au BA1, afin de limiter les longueurs des câbles à changer lors d'un futur remplacement.• (EDMS No. 1288607) UNDER IMPLEMENTATION

21. Installation de nouveaux chemins de câbles en LSS1+ du SPS.• (EDMS No. 1291889 v.2) RELEASED

22. TPSN replacement in LSS2 of SPS.• (EDMS No. 1302672 v.1) UNDER IMPLEMENTATION

23. Replacement of pumps in 3 tanks MKP in LSS1 of the SPS .• (EDMS No. 1328248 v. 0.1) RELEASED

24. Suppression of VVFA 11899 in LSS1 of SPS.• (EDMS No. 1328249v. 0.1) RELEASED

[email protected] 36

Current ECR’s for LS1https://edms.cern.ch/nav/P:CERN-0000076703:V0/P:CERN-0000096067:V0/TAB3

25. New shielding wall behind TIDV 11892 in SPS .• (EDMS No. 1331621v. 0.1) RELEASED

26. Modification of Numbering of SPS Civil Works.• (EDMS No. 1346653v. 0.1) UNDER IMPLEMENTATION

27. New Cable Tray in LSS5- of SPS.• (EDMS No. 1346655v. 0.1) UNDER IMPLEMENTATION

28. Helium 2K Pumping Units Installation in the Alcove Region of SPS Point 4 (BA4).• (EDMS No. 1354826v. 1.0) UNDER IMPLEMENTATION

29. Installation of a wire scanner BWSRE in LSS5 of the SPS.• (EDMS No. 1356736v. 0.1) UNDER IMPLEMENTATION

30. Increase of the MDHD 11832 steering strength for the LIU-SPS Q20 optics.• (EDMS No. 1359692v. 0.1) RELEASED

31. Modification of 2 Shielding Towers in LSS5 of the SPS.• (EDMS No. 1360306v. 0.1) UNDER IMPLEMENTATION

32. Upgrade of the UA9 equipment during LS1.• (EDMS No. 1365265v. 1.0) UNDER IMPLEMENTATION

[email protected] 37

Current ECR’s for LS1https://edms.cern.ch/nav/P:CERN-0000076703:V0/P:CERN-0000096067:V0/TAB3

33. Removal of a BCT in TT10 during LS1.• (EDMS No. 1368378v. 1.0) RELEASED

34. Modification of the magnetic bumps for safe operation of the BIPM in SPS LSS5.• (EDMS No. 1377890v. 1.0) UNDER IMPLEMENTATION

35. New in situ SEY measurement system in LSS5 of the SPS.• (EDMS No. 1380468v. 1.0) IN WORK

36. New HBW Damper Kickers.• (EDMS No. 1391500v. 0.1) IN WORK

[email protected] 38

Important information• Useful Contact Numbers

– SPS Coordination Team• David MCFARLANE- 164247• Franck BAIS – 165467• James RIDEWOOD - 160590

– Control Room• SPS CCC – 77500• TI CCC – 72201• CSA - 62511

– RP• Christophe Tromel – 163199• Angelito Herve – 163168• Nadine Conan (BA1) – 160641• Elodie Aubert - 169097• Kurt Weiss (BA1) -160759

– Coordination Safety• Emmanuel Paulat – 163870• John Etheridge - 164647

[email protected] 39

• There are currently 58 IMPACTs that are “LATE”. If you have completed your work then you need to close the related IMPACT.

A.O.B.

[email protected] 40

ONLY 2 DAYS LEFT!!!!

[email protected] 41

SPS coordination website

http://sps.web.cern.ch/SPS/

http://cern.ch/LS1planning

\\cernhomeJ.cern.ch\J\jocksoft\Public\LS1

Next meetingTo Be Annnounced