sps ls1 planning meeting (n018) 31/07/13 david mcfarlane [email protected]
TRANSCRIPT
Topics
• Lifts and Monte-charges.• Removal of equipment in LSS1+• Unclaimed cables in BA1• ECX5• Works around the CCC (Surface)• Shielding Wall between TT40 and TJ8• Planning.• False floors open in the BAs• E.C.Rs.• Access rights and safety equipment• Important Information.• A.O.B
Lift Maintenance July/August
Removal of equipment in LSS1+
• The work is proceeding well• All 3 dumps have been removed and the dose
rate was a lot lower than foreseen.• There are status update meetings every
Monday morning detailing the works planned for the coming week.
LSS1+ planning for week 30
29 July – 02 AugustMonday morning Remove TBSJB11995
Monday afternoon Remove remaining BLM
Tuesday – Wednesday Disconnect vacuum up to 11870Prepare QDA and QFA
Thursday Remove the (not so radioactive) QFA11810
Remove QDA11910
MDVA11904
Start labelling cable positions
Unclaimed cables in BA1Je suis en train de traiter chacun d’entre eux, mais après avoir fait un petit point sur la situation, il s’avère que certains des câbles n’ont été checkés par aucun utilisateur.Sur les 1112 câbles concernés par la campagne, j’ai reçu 830 validations. Il me reste donc 230 câbles « orphelins ».
Pour certains, je n’ai pas eu de retour de la part des utilisateurs, merci de me le faire suivre urgemment.Pour d’autres, ils devaient faire des recherches plus approfondies afin de s’assurer de la décision à prendre, merci de me tenir informé si les choses ont évolué. Je vous demanderais s’il vous plait, de regarder à nouveau la liste en attachement, et me faire savoir si certains des câbles seraient passés à travers « les mailles du filet ». Dans le cas ou personne serai en mesure de se prononcer sur les câbles restant, je demanderai à la coordination et responsables du complexe SPS, de me donner leur aval pour la suppression de ces derniers. En vous remerciant par avance de votre coopération, Salutations Guillaume Gros
ECX5
Works around the CCC
• Installation of new Transformers• Creation of the new cable trench from the CCC to BA3• Works inside Building 874 (this includes works on the outside of the
building.• Access required around CCC for HVAC replacement works• Installation of PIPES trench between CCC and 774• Installation of CABLE trench between CCC and 774• Installation of WASTE WATER trench between CCC and 774 (near Jura)• Waste water pump and pipe work (Seleve side of CCC)• Changing of SPS ring-main valves• Fibre Optics Works (Jura side of CCC)
Planning for the next few months
Shielding Wall between TT40 and TJ8
Dear all, We are re-measuring all the links between the different accelerators and we got trouble with one shielding wall between TT40 and TJ8.In order to pass the horizontal measurements from the SPS through TT40 and TI8 towards the LHC we would need to pass the shielding wall in TT40.This link has not been done since the installation in 2002 and it would be a unique opportunity to do this and to modify the shielding to allow an easier opening in the future.I have met Sylvain this afternoon to have a look on site. In a first approach I`m asking for the partial opening of the shielding to allow the line of sight to pass.I will make the EDH request right now. Does anybody, in particular RP has any objections for the opening?In a second approach one needs to see if the shielding wall can be closed in an way that will allow an easier opening in the future….Please find enclosed a description of the needed modification. Best regards,Patrick
EN
UndergroundSur
BA1
UndergroundSur
BA2
UndergroundSur
BA3
UndergroundSur
BA4
UndergroundSur
BA5
UndergroundSur
BA6
TI8TI2
TRANSFER TUNNELS
UndergroundSur
BA7
UndergroundSur
BA80/TCC2
2013
2014
2015
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
2013
2014
2015
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
May
Jun.
Jul.
Aug.
Sep.
Oct.
Nov.
Dec.
Jan.
Feb.
Mar.
Apr.
General maintenance
Cold check out & Start-upDSO tests/HV tests
EPC Commissioning tests
Vacuum
Ions to NA61
General
Maintenance
General
Maintenance
General
Maintenance
General maintenance
General Maintenance
General Maintenance
General Maintenance
UA9 w
orks
RF upgrade works
EPC works
Civil Engineering
RF upgrade works
RF Upgrade works
RF Upgrade works
RF Upgrade works
SurveyHorizontal
Verticalsmoothing
Cables
Cables
Irradiated Cables
Cables
Re-route Cabling
Cables
Cables
CablesCables EL Studies
Prep work in
LSS1
Re-install equipment removed for cable works
Survey
SurveySurvey
Survey
Survey Survey SurveySurvey
SPS LS1 schedule
Beam onCool down/RP survey and Magnet tests
Protons to the North Area
Protons to LHC
Cool downNO
ACCESS
Cool downLimited ACCESS
Magnets
Magnets MagnetsMagnetsMagnetsMagnets
Magnets
Magnets
Magnets
Magnets
Magnets
Magnets
Magnets
Beam off : 16/02/13Beam on: 13/10/14
Open Access : 27/03/13Close Access : 27/06/14
Fibres
CV works
CV studies
CV Controls upgrade
Vacuum
TT10 Consolidation
18 KV
18 KV
18 KV
18 KV
Septa works
Kicker
Septa works
Kicker
TT20 pipew
ork
Magnets
Magnets
18 KV
Civil Engineering
Civil Engineering Civil EngineeringCivil Engineering
Civil Engineering
Magnets
Ring-main
Ring-main
Ring-main
Ring-main
Ring-main
Ring-main
Vacuum
VacuumVacuum
Vacuum
Crab Cavities
Crab Cavities
EPC works
Cooling tower 863
Ring-main
Cables
Fibres
18 KV
Civil Engineering in TT10
Fibres
Fibres
Fibres Fibres
CV maintenanceCV maintenance
CV maintenance
Cables
Kicker
Cables
RAL
Septareplacem
ent
False floors lifted in Surface BAs
BAs Cabling pulling start Cable pulling end
BA1 (TS1- works)BA1 (Irradiated cable works)BA1 (Fibre Optics)
29/04/201308/10/201308/04/2013
02/08/201314/02/201424/04/2013
BA2 06/01/2014 11/03/2014
BA3BA3 (Fibre Optics)
27/03/201322/04/2014
31/05/201306/05/2014
BA4 27/05/2013 12/07/2013
BA5BA5 (Fibre Optics)
27/03/201330/09/2013
24/05/301311/10/2013
BA6BA6 (Fibre Optics)
30/09/201313/5/2013
18/10/201324/05/2013
BA7 16/10/2013 07/11/2013
• Below is a table showing the dates that EL will be pulling cables at each point of the SPS.• During these periods large sections of the false floor in these surface buildings will be lifted.• Any works in the BA’s that involve lifting of the false floors MUST be reported to the Coordination team
• If you require access to racks or other equipment in the surface buildings during these periods you must check with planning first.
Engineering Change Requests
• Templates and Guidelines for Engineering Change Requests:– EDMS: 1271880
• SPS ECR template (in DFS):– https
://dfsweb.web.cern.ch/dfsweb/Services/DFS/DFSBrowser.aspx/Applications/CERN/Workgroup%20Templates/SPS/ECR-Template-SPS.dotx
Current ECR’s for LS1https://edms.cern.ch/nav/P:CERN-0000076703:V0/P:CERN-0000096067:V0/TAB3
1. Removal of AEWB Pick-up from position 31932 to 31502 • (EDMS No. 1245361) RELEASED
2. Removal of a BPWA Pick-up from position 31931 to 31101 • (EDMS No. 1245393) RELEASED
3. Installation of a new Wideband Kickers system in position 32173 • (EDMS No. 1245400) RELEASED
4. Installation of a new HBW Damper Pick-up in place of BPWA 31931 & AEWB 31932• (EDMS No. 1245401) RELEASED
5. Replacement of 4 old BPA and 2 BPD by 6 BPCE in LSS1 & LSS2• (EDMS No. 1246559) RELEASED
6. Reinstallation of pump and gauges (Pirani + Penning) in 11993 (vacuum sector 150)• (EDMS No. 1249305) RELEASED
7. Modification LSS1 sectorization (new VVSF + displacement VVSB 11772)• (EDMS No. 1249307 v.2) RELEASED
8. Installation of 3 BCT in LSS5 for North Area protection during Ions operations in SPS.• (EDMS No. 1075945) UNDER IMPLEMENTATION
Current ECR’s for LS1https://edms.cern.ch/nav/P:CERN-0000076703:V0/P:CERN-0000096067:V0/TAB3
9. Transfer of the Fast Beam Current Transformers (BCTFR.31451) for the SPS circulating beam from LSS3 to LSS5.• (EDMS No. 1221341) RELEASED
10. SPS Beam Position Monitoring Prototyping Setup in LSS4.• (EDMS No. 1099630) RELEASED
11. Installation de 4 moniteurs de position (2 BPH, 2 BPV), dédiés au système Damper.• (EDMS No. 1251693) RELEASED
12. Installation d'un nouveau moniteur de position de type BPCR en LSS2 au 22105.• (EDMS No. 1251695) RELEASED
13. Displacement of Door PPG2145 separating the LHC and the SPS in the TI2 tunnel.• (EDMS No. 1253832) RELEASED
14. Interlocking of Injection Tunnel upstream areas with LHC powering.• (EDMS No. 1257949) RELEASED
15. Move of BPH.31998 to BPH.42173.• (EDMS No. 1272718) RELEASED
16. Optical Fibre Racks.• (EDMS No. 1273766) RELEASED
Current ECR’s for LS1https://edms.cern.ch/nav/P:CERN-0000076703:V0/P:CERN-0000096067:V0/TAB3
17. Removal of old fixed TMP vacuum groups in 11655-11691.• (EDMS No. 1273232) RELEASED
18. BYBPM racks under the SPS dipole magnets as part of the Upgrade of Beam Position Monitors electronics (MOPOS).• (EDMS No. 1282651) UNDER IMPLEMENTATION
19. Installation de Coffrets d'Alimentation en LSS1 et TT10.• (EDMS No. 1282860) RELEASED
20. Installation d'un rack de jonction RX11695=TS1 au BA1, afin de limiter les longueurs des câbles à changer lors d'un futur remplacement.• (EDMS No. 1288607) RELEASED
21. Installation de nouveaux chemins de câbles en LSS1+ et LSS2- du SPS.• (EDMS No. 1291889 v.2) IN WORK
22. TPSN replacement in LSS2 of SPS.• (EDMS No. 1302672 v.1) UNDER APPROVAL
Access rights and safety equipment• Everyone who enters the SPS MUST have the following:
– Completed the correct courses.• Safety course levels 1,2 and 3.• Habilitation Electrique.• Radiological Protection.• Self Rescue Mask Training.
– The correct access authorisation (via EDH).– A valid approved IMPACT. (with their name included on this IMPACT)– They must know the number of this IMPACT.– Safety shoes.– Biocell.– Electronic dosimetre.– Passive dosimetre.– Helmet plus Light.
• Please note that the medical service no longer contact you when your medical is about to expire!!!!!!!– You will receive an e-mail 2 months before informing you that some of your access rights will soon
expire.– It is up to you to contact the medical service to arrange a medical.
Important information• Useful Contact Numbers
– SPS Coordination Team• David MCFARLANE- 164247• Franck BAIS – 165467• James RIDEWOOD - 160590
– Control Room• SPS CCC – 77500• TI CCC – 72201• CSA - 62511
– RP• Christophe Tromel – 163199• Angelito Herve – 163168• Nadine Conan (BA1) – 160641• Elodie Aubert - 169097• Kurt Weiss (BA1) -160759
– Coordination Safety• Emmanuel Paulat – 163870• John Etheridge - 164647
• The new date for the test AUTOTRANSFERT will probably be on 30th and 31st of August. This work should be transparent and not affect access into the SPS.
• There are currently 38 IMPACTs that are “LATE”. If you have completed your work then you need to close the related IMPACT.
• Franck and myself have moved office. We are now in 112 4-B10 (same phone numbers)• I will be absent from CERN from Monday the 5th August until Monday the 26th August. You
can contact Franck or James on matter concerning the SPS.– TT10 – James Ridewood– LSS1+ - Sven De Man/ Nadine Conan– TSO/IMPACT related - Franck Baïs
A.O.B.
SPS coordination website
http://sps.web.cern.ch/SPS/
http://cern.ch/LS1planning
\\cernhomeJ.cern.ch\J\jocksoft\Public\LS1
Next meeting28/08/2013892-1-D20