SPS LS1Planning meeting (N09)

13/03/13

David Mcfarlane

Page 2: SPS LS1 Planning meeting (N09) 13/03/13 David Mcfarlane 1SPS.Technical-Coordination@Cern.ch

[email protected] 2

Topics

• Key dates at the start of LS1.• Magnet testing• Lifts and Monte-charges• Consignations• Impacts• Test AUGs and back holidays• Planning (Now to the end of April)• False floors lifted in Surface Bas• New DMCs• E.C.Rs• Incident in the PS Booster• A.O.B

Page 3: SPS LS1 Planning meeting (N09) 13/03/13 David Mcfarlane 1SPS.Technical-Coordination@Cern.ch

[email protected] 3

Key dates at the start of LS1Description Date

End of Physics 16th February 2013 (09:00 hrs)SPS radiation cool-down period 16th February to 26th February 2013High power RF tests (BE/RF) 18th February to 21st FebruaryDetection Incendie BA2 (No Access BA2) 19th to 21st February 2013Detection Incendie BA3 (No Access BA3) 22nd to 24th February 2013RP survey and patrol 22nd February to 26th February 2013Magnets tests and inspections. 27th February to 26th March 2013Lift and Monte-charge Maintenance 21st February to the 26th March 2013.Visits by the Pompiers (To be organized) 4th March to 22nd March (Evenings only)Replacement of IT “Starpoints” at each BA 4th March to 22nd March(To be organized)

1 day at each BA, access system will be offline.

Page 4: SPS LS1 Planning meeting (N09) 13/03/13 David Mcfarlane 1SPS.Technical-Coordination@Cern.ch

[email protected] 4

Magnet testing27th February to the 26th March

This work is being overseen by Jeremie Bauche (TE/MSC)

Page 5: SPS LS1 Planning meeting (N09) 13/03/13 David Mcfarlane 1SPS.Technical-Coordination@Cern.ch

[email protected] 5

Monte-charge works

Page 6: SPS LS1 Planning meeting (N09) 13/03/13 David Mcfarlane 1SPS.Technical-Coordination@Cern.ch

[email protected] 6

Lift Maintenance March / April

Page 7: SPS LS1 Planning meeting (N09) 13/03/13 David Mcfarlane 1SPS.Technical-Coordination@Cern.ch

[email protected] 7

Key dates at the start of LS1

Description DateHV Tests Monday the 25th March 2013

GS/ASE will switch each access point over to “General Access” mode Tuesday the 26th March 2013

General access into the SPS/BA7/TI2/TI8/TT10 allowed

Wednesday the 27th March 2013

Technical network disconnection test 27th March 2013 (10:00 to 13:00)Controls maintenance 2nd April to 4th April 2013 (TBC)The SF1 cooling towers will cleaned.This will effect primary water to BA6. 1st May to the 4th May 2013

LIMITED Access into BA80 25th September 2013

Page 8: SPS LS1 Planning meeting (N09) 13/03/13 David Mcfarlane 1SPS.Technical-Coordination@Cern.ch

[email protected] 8

Controls maintenanceDear colleagues, Please find for information the list of activities that BE-CO and IT-CS will do on April 2-3-4.The impact of these activities shall be limited (but better to check inside your facilities).The only perturbation which is foreseen is the perturbation on the video of PS and SPS on April 2nd at 14:00 Moreover, as a reminder during the disconnection test on March 27th, from 10:30 to 13:00, it will be impossible to communicate between IMPACT system and the access system (meaning IMPACT requests modified or approved during this time slot will not be deployed on the access system). With best regardsK. Foraz

http://wikis.cern.ch/display/DEVOPS/To-do+list+for+Controls+Maintenance+Easter+2013

Page 9: SPS LS1 Planning meeting (N09) 13/03/13 David Mcfarlane 1SPS.Technical-Coordination@Cern.ch

[email protected] 9

Please remember the following!!

• All services must remain on until the 27th March 2013!!!!!!!

• Only works that do not require access and do not affect the operational mode of the SPS will be allowed to be scheduled before the 27th March 2013!

• If you are not sure then check with myself and Operations first!!!!

Page 10: SPS LS1 Planning meeting (N09) 13/03/13 David Mcfarlane 1SPS.Technical-Coordination@Cern.ch

[email protected] 10

Consignations

• Please ensure that The coordination team has a copy of all main consignations of the SPS.

• It is the responsibility of the Equipment owner to consign any equipment that they will be working on.

• Do not assume something is consigned. Check first.

Page 11: SPS LS1 Planning meeting (N09) 13/03/13 David Mcfarlane 1SPS.Technical-Coordination@Cern.ch

[email protected] 11

“Standard” IMPACTsDiscipline / Spécialité Description Commentaires No. Impact Responsable

BE/ABP IMPACT STANDARD: campagnes générales de relevés géométriques

24163 Patrick Bestmann

BE/BI IMPACT STANDARD: maintenances générales de l’instrumentation 24203 Stephan Burger

BE/CO IMPACT STANDARD: maintenances générales syst. contrôle

24204 Claude Dehavay

BE/RF IMPACT STANDARD: maintenances générales syst. RF 24206 Christophe Renaud

EN/CV IMPACT STANDARD: maintenance générale syst refr. et ventilation

24207 Bill Bannister

EN/EL IMPACT STANDARD: interventions électriques générales (câbles, connecteurs, éclairage, coffrets, …)

24208 Guillaume Gros

EN/EL/CF IMPACT STANDARD: interventions fibre optics

24209 Simao Pedro Costa

MachadoEN/EL/OP IMPACT STANDARD: interventions

Opération Réseaux

24210 Denis Ribiollet

EN/HE - transport

IMPACT STANDARD: transports – manutentions

24212 Patrick Vallet

EN/HE - maintenance

IMPACT STANDARD: maintenances générales des équipements de transport, levage et ascenseurs

24202 Nicolas Perez

Page 12: SPS LS1 Planning meeting (N09) 13/03/13 David Mcfarlane 1SPS.Technical-Coordination@Cern.ch

[email protected] 12

“Standard” IMPACTsDiscipline / Spécialité Description Commentaires No. Impact Responsable

EN/STI - stoppers

IMPACT STANDARD: maintenances générales beam stoppers 24213 Jerome Lendaro

EN/STI – UA9 IMPACT STANDARD: maintenances générales UA9 Experience 24214 Jerome Lendaro

GS/ASE IMPACT STANDARD: interventions générales syst. accès, alarme, détection incendie

24216 Didier Vaxelaire / Denis

Raffourt

GS/SE IMPACT STANDARD: maintenances et réparation ouvrages souterrains 24217 Richard Morton

TE/ABT - kickers IMPACT STANDARD: maintenances générales kickers 24218 Francesco Castronuovo

TE/ABT - septa IMPACT STANDARD: maintenances générales septa 24219 Cedric Baud

TE/MSC IMPACT STANDARD: maintenance générale sur les aimants

« magnet patrols » et tests HV feront plutôt l’objet d’un Impact spécifique

24222 Jeremie Bauche

TE/VSC IMPACT STANDARD: maintenance générale sur les équipements Vide

24224 Jose A. Ferreira

TE/EPC IMPACT STANDARD: maintenance transformers

24226 Gilles Le Godec

Visites et Inspections - Coordination

IMPACT STANDARD: coordination générale, suivi des activités, vérification des plans de layout, …

essentiellement groupe EN/MEF 24227 David Mcfarlane / Franck

Bais / Frederic Galleazzi

Page 13: SPS LS1 Planning meeting (N09) 13/03/13 David Mcfarlane 1SPS.Technical-Coordination@Cern.ch

[email protected] 13

“Standard” IMPACTsDiscipline / Spécialité Description Commentaires No. Impact Responsable

Visites et Inspections - RP

IMPACT STANDARD: contrôles RP, suivi des activités par RP

essentiellement section DGS/RP/AS 24229 Christophe Tromel /

Angelito HerveVisites et Inspections - OP

IMPACT STANDARD: patrouilles, tests DSO, réarmements portes, …

essentiellement groupe BE/OP 24230 James Ridewood

Visites et Inspections - Sécurité

IMPACT STANDARD: inspections sécurité, VIC, pompiers, gardiennage…

24231 Emmanuel Paulat / John

Etheridge

Visites et Inspections - Visiteurs

IMPACT STANDARD: visiteurs externes, visites professionnelles, …

24233

Franck Bais / Marc Tavlet / Steve Hutchins /

John PedersenRP piquet Piquet radioprotection

24334 C. Tromel

EN/EL/BT IMPACT STANDARD: Maintenance électriques générales (transformateurs, 48V, éclairage, coffrets, tableaux basse tension)

24506 Stephane Delarue

TE/MPE IMPACT STANDARD: maintenances générales des équipements de TE/MPE

24885 Richard Mompo

IS/CS IT/CS piquet25005 Gyorgy Balazs

Page 14: SPS LS1 Planning meeting (N09) 13/03/13 David Mcfarlane 1SPS.Technical-Coordination@Cern.ch

[email protected] 14

Test AUG/ Bank holidays(Access will be blocked)

Location Date

Good Friday 29th March

Easter Monday 1st April

BA1 2nd April

BA2 3rd April

BA3 4th April

BA4 9th April

BA5 10th April

BA6 7th May

BA7 11th April

Les maintenance des tableaux électrique EBD% des BA1 – BA3 – BA4 – BA6 – BA7 – se dérouleront le même jour que les TEST AUG. Ceci pour ne pas couper l’électricité une seconde fois cette année sur chaque point du SPS.Les coupures dureront donc de 7h00 à 22h00 lors des test AUG et maintenance.Les notes de coupures suivront et seront diffusées.

Page 15: SPS LS1 Planning meeting (N09) 13/03/13 David Mcfarlane 1SPS.Technical-Coordination@Cern.ch

[email protected] 15

PlanningBE/BI works

Page 16: SPS LS1 Planning meeting (N09) 13/03/13 David Mcfarlane 1SPS.Technical-Coordination@Cern.ch

[email protected] 16

False floors lifted in Surface BAs

BAs Cabling pulling start Cable pulling end

BA1 (TS1- works)BA1 (Kicker cable works)BA1 (Irradiated cable works)

30/04/201309/10/201304/12/2013

05/08/201304/12/201317/02/2014

BA2 06/01/2014 11/03/2014

BA3 27/03/2013 31/05/2013

BA4 05/08/2013 23/09/2013

BA5 27/03/2013 07/06/3013

BA6 16/10/2013 20/11/2013

BA7 16/10/2013 07/11/2013

• Below is a table showing the dates that EL will be pulling cables at each point of the SPS.• During these periods large sections of the false floor in these surface buildings will be lifted.• Any works in the BA’s that involve lifting of the false floors MUST be reported to the

Coordination team

• If you require access to racks or other equipment in the surface buildings during these periods you must check with planning first.

Page 17: SPS LS1 Planning meeting (N09) 13/03/13 David Mcfarlane 1SPS.Technical-Coordination@Cern.ch

[email protected] 17

Engineering Change Requests

• ECR link– http://sps.web.cern.ch/SPS/quality.htm

• ECR Procedure– http://sps.web.cern.ch/SPS/files/quality/ECR_note_gestion_rev02.pdf

• ECR Template– http://sps.web.cern.ch/SPS/files/quality/ECR_SPS_formulaire_FR.pdf

• All ECRs must be submitted to Jerome Axensalva (BE/OP) AND myself.

Page 18: SPS LS1 Planning meeting (N09) 13/03/13 David Mcfarlane 1SPS.Technical-Coordination@Cern.ch

[email protected] 18

Current ECR’s for LS1https://edms.cern.ch/nav/P:CERN-0000076703:V0/P:CERN-0000096067:V0/TAB3

1. Removal of AEWB Pick-up from position 31932 to 31502 • (EDMS No. 1245361) RELEASED

2. Removal of a BPWA Pick-up from position 31931 to 31101 • (EDMS No. 1245393) RELEASED

3. Installation of a new Wideband Kickers system in position 32173 • (EDMS No. 1245400) RELEASED

4. Installation of a new HBW Damper Pick-up in place of BPWA 31931 & AEWB 31932• (EDMS No. 1245401) RELEASED

5. Replacement of 4 old BPA and 2 BPD by 6 BPCE in LSS1 & LSS2• (EDMS No. 1246559) RELEASED

6. Reinstallation of pump and gauges (Pirani + Penning) in 11993 (vacuum sector 150)• (EDMS No. 1249305) RELEASED

7. Modification LSS1 sectorization (new VVSF + displacement VVSB 11772)• (EDMS No. 1249307) RELEASED

8. Installation of 3 BCT in LSS5 for North Area protection during Ions operations in SPS.• (EDMS No. 1075945) UNDER IMPLEMENTATION

Page 19: SPS LS1 Planning meeting (N09) 13/03/13 David Mcfarlane 1SPS.Technical-Coordination@Cern.ch

[email protected] 19

Current ECR’s for LS1https://edms.cern.ch/nav/P:CERN-0000076703:V0/P:CERN-0000096067:V0/TAB3

9. Transfer of the Fast Beam Current Transformers (BCTFR.31451) for the SPS circulating beam from LSS3 to LSS5.• (EDMS No. 1221341) RELEASED

10. SPS Beam Position Monitoring Prototyping Setup in LSS4.• (EDMS No. 1099630) RELEASED

11. Installation de 4 moniteurs de position (2 BPH, 2 BPV), dédiés au système Damper.• (EDMS No. 1251693) RELEASED

12. Installation d'un nouveau moniteur de position de type BPCR en LSS2 au 22105.• (EDMS No. 1251695) UNDER APPROVAL

13. Displacement of Door PPG2145 separating the LHC and the SPS in the TI2 tunnel.• (EDMS No. 1253832) UNDER APPROVAL

14. Interlocking of Injection Tunnel upstream areas with LHC powering.• (EDMS No. 1257949) UNDER APPROVAL

15. Move of BPH.31998 to BPH.42173.• (EDMS No. 1272718) UNDER APPROVAL

16. Optical Fibre Racks.• (EDMS No. 1273766) UNDER APPROVAL

Page 20: SPS LS1 Planning meeting (N09) 13/03/13 David Mcfarlane 1SPS.Technical-Coordination@Cern.ch

[email protected] 20

Have you got your new DMC??Chers collègues, Vous recevez cet email car un (ou plusieurs) dosimètre(s) opérationnel(s) vous est attribué ou parce que vous avez récemment été utilisateur d’un dosimètre opérationnel. Les dosimètres opérationnels (DMC) doivent être calibrés chaque année. Vous ne nous avez pas encore rapporté les DMC sous votre responsabilité, nous vous demandons donc de les rapporter au B.561 ou au B.152 dans l’une des boites aux lettres prévues à cet effet. Ils seront calibrés et vérifiés. N.B. : un nouveau système de dosimétrie opérationnel (bornes de lecture électronique) sera mis en service au cours du mois de mars, si vous ne rapportez pas votre DMC il ne pourra pas fonctionner avec le nouveau système, lors de la calibration nous devons en effet modifier les paramètres pour rendre chaque DMC compatible avec le nouveau système. Dès que vous aurez rendu votre DMC actuel, vous pourrez vous rendre au bâtiment 55 pour en récupérer un autre. L’attribution ne sera permanente que si vous accédez régulièrement en Zone Contrôlée de Séjour Limitée ou de Haute Radiation (> 2 fois/mois), sinon nous vous demandons d’emprunter le DMC pour votre intervention et de le rapporter ensuite au bâtiment 55. Pour plus d’information, veuillez consulter la brochure ci-jointe et également disponible sur EDMS : https://edms.cern.ch/document/1264719

CordialementGérald Dumont.

Page 21: SPS LS1 Planning meeting (N09) 13/03/13 David Mcfarlane 1SPS.Technical-Coordination@Cern.ch

Les faits (sur la base des informations recueillies et/ou constatations visuelles)La victime travaille sur un chantier de démontage de câble.

Elle a voulu déplacer un bac à ferraille présent sur les lieux de son activité.

En déplaçant le bac, la victime a coincé sa main droite entre le bac à ferraille et le mur.

La victime a une plaie au niveau du majeur de la main droite

La personne s’est rendue à l’infirmerie.

Mesures immédiates préconisées/prises par HSE: Visite des lieux par HSE unit

Evénement : Coupure (Accident in the PS Booster)

Constat immédiat : La personne se rend chez un médecin

Date et heure 11/03/2013 - vers 10H15

Lieu Bâtiment 361 - BCER

Contexte Coupure du majeure droit en manipulant un bac à ferraille

Dép. - DSO/DDSO EN – J. Pedersen/ T. Wijnands

TSO D. Hay

Astreinte / unité HSE informée 11/03/2013 à 10h40

Relevé des faits/indices effectué 11/03/2013 à 10h50

Investigateurs HSEL. Wohlgemuth

Conséquences connues au moment du relevé des faits/indices La personne se rend chez un médecin

Gestion des événements redoutés - Relevé SEE des faits et indices et premier constat des conséquences et mesures immédiates applicables – EDMS 1255982

Classification exclusivement réservée à l’Unité HSE dans le cadre de la gestion des événements redoutés

Health & Safety Hazardous situation Nearmiss HS-0 HS-1 HS-2 HS-3 HS-4Environment Hazardous situation Nearmiss EN-0 EN-1 EN-2 EN-3 EN-4Operation Hazardous situation Nearmiss OP-0 OP-1 OP-2 OP-3 OP-4Radiological consequences? YES NO

Zone de démantèlement de câbles

Espace entre le bac et le mur

Page 22: SPS LS1 Planning meeting (N09) 13/03/13 David Mcfarlane 1SPS.Technical-Coordination@Cern.ch

[email protected] 22

Important information• Access requests

– Ensure everyone entering the SPS has the correct access authorisation (via EDH) and has completed the correct courses.

• The following safety equipment is Obligatory in the SPS for EVERYONE!– Safety shoes– Biocell– Electronic dosimetre (Make sure you have your new one from Building 55!)– Passive dosimetre– Helmet plus Light

• Useful Contact Numbers– SPS Coordination Team

• David MCFARLANE- 164247• Franck BAIS - 165467

– Control Room• SPS CCC – 77500• TI CCC – 72201

– RP• Christophe Tromel – 163199• Angelito Herve - 163168

– Coordination Safety• Emmanuel Paulat – 163870• John Etheridge - 164647

Page 23: SPS LS1 Planning meeting (N09) 13/03/13 David Mcfarlane 1SPS.Technical-Coordination@Cern.ch

[email protected] 23

A.O.B.

Page 24: SPS LS1 Planning meeting (N09) 13/03/13 David Mcfarlane 1SPS.Technical-Coordination@Cern.ch

[email protected] 24

SPS coordination website

http://sps.web.cern.ch/SPS/

http://cern.ch/LS1planning

\\cernhomeJ.cern.ch\J\jocksoft\Public\LS1

Next meeting27/03/2013892–1-D20