CMS Upgrade Week and Workshop Draft LS1 Schedule Technical Coordination Parallel Session November 2011, FNAL 09/11/2011 [email protected] 1

Upload: kuri

Post on 08-Feb-2016

37 views

Category:

Documents


0 download

DESCRIPTION

CMS Upgrade Week and Workshop. Draft LS1 Schedule. Technical Coordination Parallel Session November 2011, FNAL. Assumptions. Working time 8h/day, 5 days a week No work during the CERN Xmas holidays Start Date Nov 17 th 2012 Duration 20 to 24 months Key objectives - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Draft LS1 Schedule

[email protected] 1

CMS Upgrade Week and Workshop

Draft LS1 Schedule

Technical Coordination Parallel SessionNovember 2011, FNAL

09/11/2011

Page 2: Draft LS1 Schedule

[email protected] 2

Assumptions

Working time8h/day, 5 days a weekNo work during the CERN Xmas holidays

Start DateNov 17th 2012

Duration20 to 24 months

Key objectivesInstall TK seal to allow for cold operationInstall and bake-out new Beam PipeInstall YE4, ME4/2, RE4Perform maintenance/upgrade on DT/HO09/11/2011

Page 3: Draft LS1 Schedule

[email protected] 3

Top Level Draft Schedule

09/11/2011

Page 4: Draft LS1 Schedule

[email protected] 409/11/2011

Page 5: Draft LS1 Schedule

[email protected] 5

Task #2 – Bring CMS to full open Config→Start configuration

→End configuration

A

G

• Time period: 19 Nov 12 – 12 Dec 12• Duration estimated from previous opening operations: 18d• Bringing beam pipe to 1Bar included• Could be interleaved with partial removal of Beam Pipe

09/11/2011

Page 6: Draft LS1 Schedule

[email protected] 609/11/2011

Page 7: Draft LS1 Schedule

[email protected] 7

Task #3→Configuration on both ends

G

• Time period: 13 Dec 12 – 14 Feb 13• Duration: 36d• Includes:

• Remove of the whole CMS beam pipe• Install Light Weight platform• Install PIX table• Remove BCM1• Remove PIX• Maintain RPC/CSC on YE1s• Remove PIX table• Install Surkov Frame

09/11/2011

Page 8: Draft LS1 Schedule

[email protected] 809/11/2011

Page 9: Draft LS1 Schedule

[email protected] 9

Tasks #4 & 5→Configuration both ends

G

• Time period: 15 Feb 13 – 11 Apr 13• Duration: 40d• Includes:

• Install TK seal + partial commissioning• Remove ME1/1 chambers• Start refurbishing ME1/1 chambers in SX5• Fine tune End Cap position to allow for upgrade of

YE3s cooling infrastructure (for ME4/2 and RE4)• Remove Light Weight platform

09/11/2011

Page 10: Draft LS1 Schedule

[email protected] 1009/11/2011

Page 11: Draft LS1 Schedule

[email protected] 11

Tasks # 6,7,8 and 9→Configuration +Z end →Configuration -Z end

E

• Includes:• Install ME42: 30d• Move to EC open config.• Reinstall ME1/1• Install RE4 services• Maintain EC systems• Access to Vac Tank through ladder like access

• Includes:• Install YE-4: 6 weeks• Work on YB0 for HO, DT,

RPC: 54d• Modify YBs configuration• Work on YB1/2 for HO, DT,

RPC• Access to Vac Tank through

ladder like system

Time period: 12 Apr 13 – 18 Jul 13

09/11/2011

G

Page 12: Draft LS1 Schedule

[email protected] 1209/11/2011

Task # 7

Once sequence is agreed upon, each task will be broken down in finer details

Page 13: Draft LS1 Schedule

[email protected] 1309/11/2011

Page 14: Draft LS1 Schedule

[email protected] 14

• Includes:• Install YE-4: 6 weeks• Work on YB0 for HO, DT,

RPC: 54d• Modify YBs configuration• Work on YB1/2 for HO, DT,

RPC• Access to Vac Tank through

ladder like system• Install fwd part of BP• Restore full open config.

Tasks # 10,11 and 12→Configuration +Z end →Configuration -Z end

• Includes:• Install RE4 services• Maintain EC systems

(change EC configuration as needed)

• Access to Vac Tank through ladder like access• Install fwd part of BP• Restore full open config.

F

Time period: 19 Jul 13 – 24 Oct 13

09/11/2011

Page 15: Draft LS1 Schedule

[email protected] 1509/11/2011

Page 16: Draft LS1 Schedule

[email protected] 16

Tasks #13,14 & 15→Configuration on both ends

G

• Time period: 25 Oct 13 – 20 Dec 13• Includes:

• Remove Surkov frame (end of TK seal activity)• Install Light Weight platform• Complete installation of new Beam Pipe: 5d• Bake-out new beam pipe: 31d (continuous)• Install PIX table• Perform trial insertion of new PIX mockup• Install PIX, PLT, BCM, PIX seal

• Delivery date for the new Beam Pipe is critical09/11/2011

Page 17: Draft LS1 Schedule

[email protected] 1709/11/2011

Page 18: Draft LS1 Schedule

[email protected] 18

Task #16→Configuration on both ends

• Time period: 06 Jan 14 – 14 Feb 14• Duration: 6w per end. Work in YB1/2 gap• Includes:

• Open YB2 to access IP side• Reinstall YB2/1 HO RBXs (HPDs qualified at Princeton)• Close & lock YB2s

H

09/11/2011

Page 19: Draft LS1 Schedule

[email protected] 1909/11/2011

Page 20: Draft LS1 Schedule

[email protected] 20

Task #17→Start configuration

→End configurationA

G• Time period: 17 Feb 14 – 12 Mar 14• Duration estimated from previous opening operations: 18dIncludes:

• Close and lock End Caps• Put HFs on 2 risers• Install Totem T1s• Put HFs on 4 risers

09/11/2011

Page 21: Draft LS1 Schedule

[email protected] 2109/11/2011

CMS closed 5monthsBefore end of LS1

Page 22: Draft LS1 Schedule

[email protected] 2209/11/2011

Page 23: Draft LS1 Schedule

[email protected] 23

Task #19 – Master Magnet Test

→Configuration on both endsA

• Time period: 13 Mar 14 – 19 Mar 14• Duration: 5d• Final opportunity to test the TK seal• Check magnetic behavior of YE4s• 5 months before the end of LS120 to fix a major Magnet/TK problems

09/11/2011

Page 24: Draft LS1 Schedule

[email protected] 2409/11/2011

Page 25: Draft LS1 Schedule

[email protected] 25

Tasks #21 to 26→Configuration on both ends

• Time period: 20 Mar 14 – 30 Jun 14• Includes

• Lower HFs to garages• Pull back YE4s• Install RE+4• Install ME-4/2• Install RE-4• Move HFs to beam level

• Cosmic Challenge at 0T on-going

C

09/11/2011

Page 26: Draft LS1 Schedule

[email protected] 2609/11/2011

Page 27: Draft LS1 Schedule

[email protected] 27

Tasks # 27→Configuration on both ends

• Time period: 01 Jul 14 – 04 Jul 14• Duration: 4d• Re-install CASTOR

A

09/11/2011

Page 28: Draft LS1 Schedule

[email protected] 2809/11/2011

Page 29: Draft LS1 Schedule

[email protected] 29

Tasks # 28 – Magnet Re-commissioning

→Configuration on both ends

→`

• Time period: 07 Jul 14 – 11 Jul 14• Duration: 1w

A

09/11/2011

Page 30: Draft LS1 Schedule

[email protected] 3009/11/2011

Page 31: Draft LS1 Schedule

[email protected] 31

Tasks # 29 – CRAFT→Configuration on both ends

• Time period: 14 Jul 14 – 22 Aug 14• Duration: 6w• Can take place during LHC re-commissioning

A

09/11/2011

Page 32: Draft LS1 Schedule

[email protected] 3209/11/2011

Page 33: Draft LS1 Schedule

[email protected] 33

Tasks # 30 – LS1 contingency→Contingency management

→6 weeks on the critical path: ~7.5%→Saturdays held as slack →Xmas breaks not counted

09/11/2011

Page 34: Draft LS1 Schedule

[email protected] 3409/11/2011

Page 35: Draft LS1 Schedule

[email protected] 35

Tasks # 31 – Beam Pipe pump down→Configuration on both ends

• Time period: 04 Oct 14 – 24 Oct 14• Duration: 21 continuous days

A

09/11/2011

Page 36: Draft LS1 Schedule

[email protected] 3609/11/2011With current scope, 20 month shutdown would be too short24 month shutdown would be appropriate