Page 1: Use of Progressive Elaboration in EGIS Program Planning

Use of Progressive Elaboration in EGIS Program Planning

Brandon Pfleckl GIS Program Manager PWCSA

Page 2: Use of Progressive Elaboration in EGIS Program Planning

Summary ó Enterprise-wide GIS (EGIS) Program Planning can be

a daunting task full of questions and fear of where and how to start. Then, once you start, how do you stay on track? ó Understanding the concepts of proper program

management can save significant time and energy over the life-cycle of building your EGIS program.

Page 3: Use of Progressive Elaboration in EGIS Program Planning

Summary ó We’ll explore three major processes involved in

program planning; ó Establishment of a program vision ó Development of a program of projects that seek to

achieve your vision ó Process of project planning and project execution on the

program scale

Page 4: Use of Progressive Elaboration in EGIS Program Planning
Page 5: Use of Progressive Elaboration in EGIS Program Planning

• A project represents a single level of effort and usually has a well-defined scope of work including detailed requirements, executables and schedule. With projects you generally know what needs to be accomplished and have a clear path forward. Programs tend to have a much greater level of uncertainty.

• Generally speaking, a program is a set of related projects organized to accomplish a common vision. Programs span much longer time-frames and represent numerous levels of efforts (numerous projects). Each project in a program should represent a building block used to construct your program vision.

Programs versus Projects

Page 6: Use of Progressive Elaboration in EGIS Program Planning

• Progressive elaboration allows projects in the short-term to be planned in detail, but mid to long-term projects will have only generally defined scopes. As short-term projects are completed more information will become available concerning available resources and organizational priorities.

• Detailed planning efforts will then “progress” to the next projects in line. • Regardless of path shifts, progressive elaboration allows you to keep your

direction heading towards your vision.

Progressive Elaboration

Page 7: Use of Progressive Elaboration in EGIS Program Planning

Progressive Elaboration in Program Planning – Conceptual Analogy:

• Let’s look a look at the process of planning a family vacation to the beach as a good analogy of the process involved within program planning and progressive elaboration.

• You will be able to apply the concepts directly to your EGIS program to help reach success.

Page 8: Use of Progressive Elaboration in EGIS Program Planning

Develop high-level vision • Development of a high-level vision should be done early in any process you

undertake so you have an understanding of what you are trying to achieve and all actions moving forward are aimed at achieving your vision.

FAMILY-FRIENDLY DININGHOTEL ON THE BEACH

FAMILY-FRIENDLY BEACH / ACTIVITIES

VACATION IN LATE SUMMER

Page 9: Use of Progressive Elaboration in EGIS Program Planning

Develop high-level vision • Use your very general understanding of what you want to accomplish as a

discussion framework moving forward and add a greater level of detail to your vision..

BEACH WITHIN DRIVING DISTANCE

FAMILY-FRIENDLY DINING

- WITHIN WALKING DISTANCE FROM HOTEL

HOTEL ON THE BEACH

-MUST HAVE A POOL

FAMILY-FRIENDLY BEACH / ACTIVITIES

- PARASAILING- SEA-KAYAKING

VACATION IN LATE SUMMER

- MID-LATE AUGUST

High-level Vision

Page 10: Use of Progressive Elaboration in EGIS Program Planning

Refine high-level vision to include specific details

• Defining your high-level vision is an enormously important step which lays the foundation for more detailed planning efforts moving forward.

• There is a lot to plan and coordinate. You want to execute your tasks in the most efficient way and with clear direction or you will waste time.

• Specific details must be added to your vision before you can begin.

· SPECIFIC BEACH DETERMINED· SPECIFIC HOTEL DETERMINED· LIST OF SPECIFIC RESTAURNATS

DETERMINED· ACTIVITY VENDORS DETERMINED

SPECIFIC VISION

DETERMINE BEACHES WITH PARASAILING AND SEA-KAYAKING

ACTIVITIES

DETERMINE HOTELS WITH AVAILABILITY IN

MID-LATE AUGUST

WORK WITH FAMILY (STAKEHOLDERS) TO MAKE SELECTIONS

DETERMINE ALL BEACHES WITHIN

DRIVING DISTANCE

DETERMINE FAMILY FRIENDLY BEACHES

DETERMINE HOTELS WITH A POOL

DETERMINE HOTELS WITH FAMILY-FRIENDLY DINING

WITHIN WALKING DISTANCE

Page 11: Use of Progressive Elaboration in EGIS Program Planning

Identify necessary projects to achieve your vision and their dependencies

• What will allow for you to accomplish your specific vision? • What decisions must be made? The answers to these questions will identify

the projects you need to execute to achieve your vision.

• Let’s look at one of those questions, travel. You’ve decided to drive to the

beach but there are several dependencies to making sure you get to where you want to go on-time, safely, and reliably. Your travel project is comprised of several tasks:

• Develop travel route • Prepare vehicle for travel • Travel to destination

Page 12: Use of Progressive Elaboration in EGIS Program Planning

Identify necessary projects to achieve your vision and their dependencies

DEVELOP TRAVEL ROUTE

TIME

PREPARE VEHICLE TRAVEL TO DESTINATIONTRAVEL PROJECT

START

REACH DESTINATION

INPU

T / C

HA

NG

E

INPU

T / C

HA

NG

E

INPU

T / C

HA

NG

E

Page 13: Use of Progressive Elaboration in EGIS Program Planning

Identify necessary projects to achieve your vision and their dependencies

DEVELOP TRAVEL ROUTE

TIME

PREPARE VEHICLE TRAVEL TO DESTINATIONSTART

TRAVEL PROJECT

REACH DESTINATION

INP

UT

/ CH

AN

GE

INP

UT

/ CH

AN

GE

INP

UT

/ CH

AN

GE

CHECK WEATHER FORCASTS

START PACKING PROJECT

LIST ITEM NEEDS RELATED TO ACTIVITES

LIST MEDICATIONS NEEDED

PACK

CHECK-IN TO HOTEL

START “GET SETTLED”

PROJECT

UNPACK

PICK RESTAURANT FOR DINNER

Page 14: Use of Progressive Elaboration in EGIS Program Planning

Perform short and long-term planning using progressive elaboration

• Detailed planning can only be done well in the short-term.

• While you need to have a good idea of the projects that are necessary to reach

your vision, you can only plan projects in detail where detailed information exists.

• Over time your priorities, resources and the environment in which you are working will change. This is where progressive elaboration becomes such a useful tool.

Page 15: Use of Progressive Elaboration in EGIS Program Planning

LONG TERMMEDIUM TERM

DEVELOP TRAVEL ROUTE

SHORT TERM

TRAVEL TO DESTINATION

TRAVEL PROJECT

START

REACH DESTINATION

INP

UT

/ C

HA

NG

E

INP

UT

/ C

HA

NG

E

Stop at Joe’s Quickie Mart for gas and

snacks

Take RT 87 to interstate 95

Start Disney movie for children

Take Rt 55 to 87

Check GPS unit for traffice and adjust

route

Talk to family about next

required rest-stop

Check GPS unit for traffice and adjust

route

Talk to family about next

required rest-stop

DECREASING LEVEL OF UNDERSTANDING / DECREASING LEVEL OF PLANNING DETAIL

Perform short and long-term planning using progressive elaboration

Page 16: Use of Progressive Elaboration in EGIS Program Planning

Perform short-term project execution

MEDIUM TERM

DEVELOP TRAVEL ROUTE

SHORT TERM

TRAVEL TO DESTINATION

TRAVEL PROJECT

START

REACH DESTINATION

INP

UT

/ CH

AN

GE

INP

UT

/ CH

AN

GE

Stop at Joe’s Quickie Mart for gas and

snacks

RT 87 to HWY 95

Start Disney movie for children

RT 55 to RT 87Check GPS unit for traffice and adjust

route

Talk to family about next

required rest-stop

DECREASING LEVEL OF UNDERSTANDING / DECREASING LEVEL OF PLANNING DETAIL

COMPLETED TASKS

HWY 95 to RT 1

Stop at State Rest-Stop

Stop for gas and food

Page 17: Use of Progressive Elaboration in EGIS Program Planning

Case Study Review of the Prince William County Service Authority’s EGIS Program Development Process:

Page 18: Use of Progressive Elaboration in EGIS Program Planning

Background: Prince William County Service Authority (PWCSA) – Enterprise GIS Transition Project

Had been using Autodesk CAD technology for last 10 years: •Basic mapping capabilities •Limited analytics •No system integration •Isolated (Silo) Departmental Processes and Analysis

The Prince William County Service Authority is a wastewater and water utility serving the second largest county in Virginia.

Page 19: Use of Progressive Elaboration in EGIS Program Planning

GIS Vision - Become a GIS-Centric Organization § Reduce silos of information § Integrate GIS with other systems and enable advanced asset analysis § Visualize, access and analyze information from all departments in a spatial context

- Operations & Maintenance - Customer Service - SCADA - Finance - Laboratory

§ Utilize GIS to improve internal workflows across all departments § Provide faster, more accurate and efficient services to its external and internal customers

Page 20: Use of Progressive Elaboration in EGIS Program Planning

Develop high-level vision • “become nationally recognized as a steward of the environment and a premier

provider of clean water and superior service by achieving excellence in our partnerships, our work culture, and our business practices.”

• The GIS is envisioned as the cornerstone of the SA integrated information technology environment.

• By coupling GIS geospatial data along with non-spatial data of other SA systems, the SA will have the ability to provide faster, more accurate and efficient services to its external customers.

• This will change GIS from another SA system into an operational requirement and a key component in the way the SA conducts business.

Page 21: Use of Progressive Elaboration in EGIS Program Planning

Develop high-level vision

Page 22: Use of Progressive Elaboration in EGIS Program Planning

Refine vision to include specific details

The GIS-Centric organizational approach was further defined to accomplish the following (partial list):

• Optimize design engineer’s time • Provide access by all SA personnel to common data across IT

systems in a spatial context • Reduce clerical costs associated with maintaining current data in multiple systems • Increase O&M field crew efficiency due to integration of mobile, GIS, and

work management • Optimize scheduling of work • Provide ability to better recognize and set priorities • Identify critical assets • Reduce crew windshield time/travel distance minimized • Provide ability to provide customers information in seconds when they

call in and improve the customer’s experience

Page 23: Use of Progressive Elaboration in EGIS Program Planning

Identify necessary projects to achieve your vision and their dependencies

To properly determine the projects needed to reach the SA’s GIS vision, the SA had to: • (1) evaluate in detail its existing workflows and data quality across all

major IT systems

• (2) determine user needs related to the specific GIS vision items, and

• (3) determine improvements in the way data was collected, stored, and integrated with GIS

Page 24: Use of Progressive Elaboration in EGIS Program Planning

Identify necessary projects to achieve your vision and their dependencies

Let’s take a look at one of the specific vision items that contains a large number of project dependencies; provide access by all SA personnel to common data across IT systems in a spatial context. • Integrate GIS with customer service system • Integrate GIS with work order management system (CMMS) • Integrate GIS with SCADA system • Integrate GIS with financial system

Page 25: Use of Progressive Elaboration in EGIS Program Planning

Identify necessary projects to achieve your vision and their dependencies

Integrate GIS with the work order management system. In order for GIS to integrate with the work order management system the following tasks had to be accomplished: • Integrate GIS with work order management system • Identify, refine, document and implement updated workflows related to data

collection and storage • Identify data discrepancies between the two systems and make corrections • Determine database linking features between the two systems and make

adjustments to one or both database schemas

Page 26: Use of Progressive Elaboration in EGIS Program Planning

Identify necessary projects to achieve your vision and their dependencies

TIME

INTEGRATE GIS & WORK ORDER SYSTEM

UPDATE DATABASE SCHEMAS IMPLEMENT UPDATED WORKFLOWS

CORRECT DATA DISCREPANCIES

START INTEGRATION of GIS with CMMS

Page 27: Use of Progressive Elaboration in EGIS Program Planning

Identify necessary projects to achieve your vision and their dependencies

START

EGIS Dependency Diagram GIS Program Projects

Early Start Duration Early Finish

Late Start Slack Late Finish

Service Outage Tool

Early Start Duration Early Finish

Late Start Slack Late Finish

Key Asset Outage Identification

Early Start Duration Early Finish

Late Start Slack Late Finish

Missing Elements/Asset Review Tool

Utility Network Analysis Toolset

Early Start Duration Early Finish

Late Start Slack Late Finish

LIMS Related GIS Layer Development

Early Start Duration Early Finish

Late Start Slack Late Finish

LIMS Data Workshop Discussion

Early Start Duration Early Finish

Late Start Slack Late Finish

Determine LIMS Stakeholders

Early Start Duration Early Finish

Late Start Slack Late Finish

Integration of GIS with LIMS

LIMS System Development or App Purchase

Early Start Duration Early Finish

Late Start Slack Late Finish

LIMS Data Analysis/Reporting Tools Development

LIMS Integration with GIS and Data Analysis

EF = 10 / LF = 121 / Duration = 10

Early Start Duration Early Finish

Late Start Slack Late Finish

Integration of W/S Models with SCADA

Early Start Duration Early Finish

Late Start Slack Late Finish

Integrate GIS/SDE with SCADA System

Early Start Duration Early Finish

Late Start Slack Late Finish

Create and Populate GIS SCADA Layers

Early Start Duration Early Finish

Late Start Slack Late Finish

SCADA Integration WorkshopsCompletion of

SCADA Upgrade Project

Early Start Duration Early Finish

Late Start Slack Late Finish

Develop SCADA Data Analysis Toolset

Completed SCADA GIS Data Analysis Toolset

Early Start Duration Early Finish

Late Start Slack Late Finish

Finalize CAD Data Submittal Standards

Early Start Duration Early Finish

Late Start Slack Late Finish

Develop and Implement GIS Data Submittal Standards

Early Start Duration Early Finish

Late Start Slack Late Finish

Develop Data Loading Model

Early Start Duration Early Finish

Late Start Slack Late Finish

Auto GIS Data Population Tools:Auto-ID Tool

Auto TO/FROM ToolTopology Checks

Early Start Duration Early Finish

Late Start Slack Late Finish

Update GIS Production Workflows

GIS Production Improvements

Early Start Duration Early Finish

Late Start Slack Late Finish

GIS Production Tool Review and Evaluation

Customer Service Data Analysis Toolset

Customer Service Internet Web Portal

Customer Service Advanced GIS Web Portal

EF = 13 / LF = 121 / Duration = 13

EF = 8 / LF = 121 / Duration = 8

EF = 10 / LF = 121 / Duration = 10

Asset Management Data Analysis Toolset

Fully Integrated Advanced GIS Web Portal

Highly Configured GIS Production Tools & Workflow (Data Quality and Efficiency Focus)

PWCSA GIS Vision

High Quality Reliable GIS Database

Early Start Duration Early Finish

Late Start Slack Late Finish

Chlorine Data Tool Development

Early Start Duration Early Finish

Late Start Slack Late Finish

Link from Oracle to GIS

Early Start Duration Early Finish

Late Start Slack Late Finish

Transition of Data Application to Oracle Environment

Early Start Duration Early Finish

Late Start Slack Late Finish

ROI Analysis Chlorine Data Analysis and Mapping System

Early Start Duration Early Finish

Late Start Slack Late Finish

Integration of W/S Models with SDE

Early Start Duration Early Finish

Late Start Slack Late Finish

‘Smart’ Fire Flow Tool

Early Start Duration Early Finish

Late Start Slack Late Finish

Water Age Tracking/Visualization Tool

Early Start Duration Early Finish

Late Start Slack Late Finish

Water Usage Forecasting Tool (Per Home Detail)

Early Start Duration Early Finish

Late Start Slack Late Finish

GWP Model Visualization Tools

Water / Sewer Model GIS Analysis and Planning Toolset

Early Start Duration Early Finish

Late Start Slack Late Finish

Chlorine Data Analysis Tools

Early Start Duration Early Finish

Late Start Slack Late Finish

User Workshop Discussion

Early Start Duration Early Finish

Late Start Slack Late Finish

Re-engineering Select Queires

Early Start Duration Early Finish

Late Start Slack Late Finish

Transition Previously Developed Changes from DEV to PROD

Early Start Duration Early Finish

Late Start Slack Late Finish

Test Web Portal Updates

Portal User Tool Fine-Tuning and Database Optimization

Early Start Duration Early Finish

Late Start Slack Late Finish

Develop Updated Documentation

Early Start Duration Early Finish

Late Start Slack Late Finish

Perform Roll-out and Traning

EF = 15 / LF = 121 / Duration = 15

ES = 0 / LS = 106 / Slack = 107

Early Start Duration Early Finish

Late Start Slack Late Finish

Clone SA140 App Server to SA147

Early Start Duration Early Finish

Late Start Slack Late Finish

Clone SA141 Web Server to SA148

Early Start Duration Early Finish

Late Start Slack Late Finish

Connect SA147 to Oracle Environment

GIS Development Environment Finalization

EF = 15 / LF = 121 / Duration = 15

EF = 15 / LF = 121 / Duration = 15

ES = 0 / LS = 106 / Slack = 107

Early Start Duration Early Finish

Late Start Slack Late Finish

Uninstall ARcSDE from DEV ENV

Early Start Duration Early Finish

Late Start Slack Late Finish

Reinstall ArcSDE with 10.1 for Oracle 11G

Early Start Duration Early Finish

Late Start Slack Late Finish

Set-up GIS Group SDE Connections

ArcGIS 10.1 Upgrade

Early Start Duration Early Finish

Late Start Slack Late Finish

Perform Testing

Early Start Duration Early Finish

Late Start Slack Late Finish

Transition DEV to PROD

Early Start Duration Early Finish

Late Start Slack Late Finish

Perform all steps again for original PROD ENV

Early Start Duration Early Finish

Late Start Slack Late Finish

Point SDE to Oracle 11G and Test

Oracle 11G Upgrade

Early Start Duration Early Finish

Late Start Slack Late Finish

Reconfigure TEST portal with 11G Server environment

Early Start Duration Early Finish

Late Start Slack Late Finish

Develop SA140 with ArcSDE 10.1 and point to Oracle 11G

Early Start Duration Early Finish

Late Start Slack Late Finish

Test and Transition Web Portal to DEV

Early Start Duration Early Finish

Late Start Slack Late Finish

Test and Transition SA140 to SDE DEV

Early Start Duration Early Finish

Late Start Slack Late Finish

Perform Testing

Early Start Duration Early Finish

Late Start Slack Late Finish

User Workshop Discussion

Early Start Duration Early Finish

Late Start Slack Late Finish

Requirements Gathering and Reporting

Early Start Duration Early Finish

Late Start Slack Late Finish

I&I Web Portal DEV

Customized User Group GIS Web Portals

Early Start Duration Early Finish

Late Start Slack Late Finish

Develop Updated Documentation

Early Start Duration Early Finish

Late Start Slack Late Finish

Perform Roll-out and Traning

Early Start Duration Early Finish

Late Start Slack Late Finish

Engineering Planning GIS Web Portal DEV

Early Start Duration Early Finish

Late Start Slack Late Finish

Customer Service Web Portal DEV

Early Start Duration Early Finish

Late Start Slack Late Finish

Dispatch GIS Web Portal DEV

Early Start Duration Early Finish

Late Start Slack Late Finish

Field Services GIS Web Portal DEV

Early Start Duration Early Finish

Late Start Slack Late Finish

C&D GIS Web Portal DEV

Early Start Duration Early Finish

Late Start Slack Late Finish

GENERAL GIS Web Portal DEV

Early Start Duration Early Finish

Late Start Slack Late Finish

Test Geometric Network

Early Start Duration Early Finish

Late Start Slack Late Finish

Develop Geometric Network

Early Start Duration Early Finish

Late Start Slack Late Finish

Plan Geometric Network

Early Start Duration Early Finish

Late Start Slack Late Finish

Implement in PROD Environment

Early Start Duration Early Finish

Late Start Slack Late Finish

Train GIS Group on GeoNet use

Geometric Network

Early Start Duration Early Finish

Late Start Slack Late Finish

Run Topology Rules and Identify issues

Early Start Duration Early Finish

Late Start Slack Late Finish

Develop Topology Rules

Early Start Duration Early Finish

Late Start Slack Late Finish

Plan Topology Rules & Corrections

Early Start Duration Early Finish

Late Start Slack Late Finish

Train GIS Group Staff

Early Start Duration Early Finish

Late Start Slack Late Finish

Perform Corrections and Test

Topological Data Corrections

Early Start Duration Early Finish

Late Start Slack Late Finish

Plan Utility Network Tools

Early Start Duration Early Finish

Late Start Slack Late Finish

Utility Network Tools Workshops

Early Start Duration Early Finish

Late Start Slack Late Finish

Workshop Discussion of CL DB and App needs

Early Start Duration Early Finish

Late Start Slack Late Finish

Workshop Interviews: what EPA reporting reqs exist

Early Start Duration Early Finish

Late Start Slack Late Finish

Review of LIMS-style software options: should we develop or buy

DEPENDANCYPlanning and Execution of SCADA

Implementation Project

Early Start Duration Early Finish

Late Start Slack Late Finish

Program Workflow Development

Early Start Duration Early Finish

Late Start Slack Late Finish

Stakeholder Workshops

Early Start Duration Early Finish

Late Start Slack Late Finish

GPS Stakeholder Identification

Early Start Duration Early Finish

Late Start Slack Late Finish

GPS Application DevelopmentStakeholder Feedback

and Resource Allocation

Early Start Duration Early Finish

Late Start Slack Late Finish

User Training and Rollout

GPS Program Development

Early Start Duration Early Finish

Late Start Slack Late Finish

Pilot Project Planning (ENG)

Early Start Duration Early Finish

Late Start Slack Late Finish

Pilot Execution and Reporting

DEPENDANCYStakeholder Resources shall play a significant

role. Currently, additional GIS Group resources are not available for significant data

collection

Early Start Duration Early Finish

Late Start Slack Late Finish

Update Production Procedures

Early Start Duration Early Finish

Late Start Slack Late Finish

Place Holder for OTHER tools

Early Start Duration Early Finish

Late Start Slack Late Finish

Testing

Early Start Duration Early Finish

Late Start Slack Late Finish

Rollout and Training

Early Start Duration Early Finish

Late Start Slack Late Finish

Program Workflow Development

Early Start Duration Early Finish

Late Start Slack Late Finish

GPS Application DevelopmentStakeholder Feedback and Resource

Allocation

Early Start Duration Early Finish

Late Start Slack Late Finish

User Training and Rollout

Early Start Duration Early Finish

Late Start Slack Late Finish

Pilot Project Planning (CUSTOMER SERVICE

Early Start Duration Early Finish

Late Start Slack Late Finish

Pilot Execution and ReportingEarly Start Duration Early

Finish

Late Start Slack Late Finish

Program Workflow Development

Early Start Duration Early Finish

Late Start Slack Late Finish

GPS Application Development

Stakeholder Feedback and Resource

Allocation

Early Start Duration Early Finish

Late Start Slack Late Finish

User Training and Rollout

Early Start Duration Early Finish

Late Start Slack Late Finish

Pilot Project Planning (OPERATIONS AND MAINT)

Early Start Duration Early Finish

Late Start Slack Late Finish

Pilot Execution and Reporting

Early Start Duration Early Finish

Late Start Slack Late Finish

HRMP Workshops

Early Start Duration Early Finish

Late Start Slack Late Finish

Map Corrections Task

Early Start Duration Early Finish

Late Start Slack Late Finish

C&D Task

Early Start Duration Early Finish

Late Start Slack Late Finish

CIP Task

Early Start Duration Early Finish

Late Start Slack Late Finish

Chris Brown’s Documents Task

Incorporation of Historical Records into GIS Database

Early Start Duration Early Finish

Late Start Slack Late Finish

O&M Locator Room

Early Start Duration Early Finish

Late Start Slack Late Finish

Mapping Boxes

Early Start Duration Early Finish

Late Start Slack Late Finish

Engineering Scanning

Early Start Duration Early Finish

Late Start Slack Late Finish

HRMP Planning

Early Start 120 HRS Early Finish

Late Start Slack Late Finish

GIS Production work

Early Start 120 HRS Early Finish

Late Start Slack Late Finish

GIS Production work

Early Start 120 HRS Early Finish

Late Start Slack Late Finish

GIS Production work

Early Start 120 HRS Early Finish

Late Start Slack Late Finish

GIS Production work

Early Start 120 HRS Early Finish

Late Start Slack Late Finish

GIS Production work

Early Start 120 HRS Early Finish

Late Start Slack Late Finish

GIS Production work

Early Start Duration Early Finish

Late Start Slack Late Finish

Transition of Existing Marker Documents to new System

Early Start Duration Early Finish

Late Start Slack Late Finish

Workflow Adjustment Planning and Execution for New Documents

Early Start Duration Early Finish

Late Start Slack Late Finish

Markers/Document Management Workshop Discussions and Planning

Advanced Document Access Capabilities

EF = 18 / LF = 121 / Duration = 18

ES = 0 / LS = 103 / Slack = 103

DEPENDANCYMoving forward would require an

organizational transition to an enterprise level document management system similar to

“Share Point,” which can tag documents with coordinates for spatial tracking. Otherwise, current system is as good as is reasonable

Early Start Duration Early Finish

Late Start Slack Late Finish

Identify Finance Stakeholders

Early Start Duration Early Finish

Late Start Slack Late Finish

Determine Finance-GIS Integration Requirements

Early Start Duration Early Finish

Late Start Slack Late Finish

Perform In-Depth Review of Finance System/DB

Early Start Duration Early Finish

Late Start Slack Late Finish

Create GIS/Finance GIS Layers

Finance GIS Analysis Toolset

Early Start Duration Early Finish

Late Start Slack Late Finish

Integrate Finance with GISEarly Start Duration Early

Finish

Late Start Slack Late Finish

Finance Customer Connection Fee Calculator

Early Start Duration Early Finish

Late Start Slack Late Finish

Finance Depreciation Analysis Tool

Early Start Duration Early Finish

Late Start Slack Late Finish

‘Other’ Finance Tools

EF = 15 / LF = 121 / Duration = 15DEPENDANCYSelection of a new Finance system shall play a major role in the planning and execution of this

project

Early Start Duration Early Finish

Late Start Slack Late Finish

Develop Facility Analysis Tools

Early Start Duration Early Finish

Late Start Slack Late Finish

Perform GIS/Facility Integration

Early Start Duration Early Finish

Late Start Slack Late Finish

Create Additional Facility GIS Layers

Early Start Duration Early Finish

Late Start Slack Late Finish

Facility Information Workshops

Transition Facility Workflows and Data

into CMMS

Facility GIS Access and Analysis

EF = 7 / LF = 121 / Duration = 7DEPENDANCY

Choice of new CMMS will play a major role: City Works has built-in integrations, Maximo

and Hansen require much development on DB side

Early Start Duration Early Finish

Late Start Slack Late Finish

Scan Facility Manuals and add as Markers

Early Start Duration Early Finish

Late Start Slack Late Finish

CS Stakeholder and Requirements GatheringEarly Start Duration Early Finish

Late Start Slack Late Finish

Review and Update of CS Database

Early Start Duration Early Finish

Late Start Slack Late Finish

ROI Analysis for CS Apps

Early Start Duration Early Finish

Late Start Slack Late Finish

CS Internet Portal Workshop Discussion and Planning

Early Start Duration Early Finish

Late Start Slack Late Finish

Customer. Call Mapping Integration with GIS

Early Start Duration Early Finish

Late Start Slack Late Finish

Meter Location Info in GIS Web Portal

Early Start Duration Early Finish

Late Start Slack Late Finish

Advanced CS attribute Viewing in GWP

Early Start Duration Early Finish

Late Start Slack Late Finish

Illegal Connection Tool/Study

Early Start Duration Early Finish

Late Start Slack Late Finish

CS Internet Portal for Customer Use

Early Start Duration Early Finish

Late Start Slack Late Finish

Create Dynamic Link Between GIS and CS Consumption Data

Early Start Duration Early Finish

Late Start Slack Late Finish

Missing Customer Tool/Study

Early Start Duration Early Finish

Late Start Slack Late Finish

Water Conservation Tool/Study

Early Start Duration Early Finish

Late Start Slack Late Finish

Commercial Mischarges Tool/Study

Early Start Duration Early Finish

Late Start Slack Late Finish

Potential Leaks Tool/Study

Early Start Duration Early Finish

Late Start Slack Late Finish

Engineering Development GIS Web Portal DEV

Early Start Duration Early Finish

Late Start Slack Late Finish

Conrad’s Notebooks

Early Start 120 HRS Early Finish

Late Start Slack Late Finish

GIS Production work

Early Start Duration Early Finish

Late Start Slack Late Finish

Microfilm Appcards

Early Start 120 HRS Early Finish

Late Start Slack Late Finish

GIS Production work

Early Start Duration Early Finish

Late Start Slack Late Finish

R&A SL1

Early Start Duration Early Finish

Late Start Slack Late Finish

R&A SL2

Early Start Duration Early Finish

Late Start Slack Late Finish

R&A SL3

Early Start Duration Early Finish

Late Start Slack Late Finish

R&A SL4

Early Start Duration Early Finish

Late Start Slack Late Finish

R&A SL5

Early Start Duration Early Finish

Late Start Slack Late Finish

R&A SL6

Early Start Duration Early Finish

Late Start Slack Late Finish

R&A SL7

Early Start Duration Early Finish

Late Start Slack Late Finish

R&A SL8

Early Start Duration Early Finish

Late Start Slack Late Finish

R&A SL9

Early Start Duration Early Finish

Late Start Slack Late Finish

R&A SL10

Early Start Duration Early Finish

Late Start Slack Late Finish

R&A SL11

Early Start Duration Early Finish

Late Start Slack Late Finish

R&A SL12

Early Start Duration Early Finish

Late Start Slack Late Finish

R&A SL13

Early Start Duration Early Finish

Late Start Slack Late Finish

R&A SL14

Early Start Duration Early Finish

Late Start Slack Late Finish

W/SMD SL1

Early Start Duration Early Finish

Late Start Slack Late Finish

W/SMD SL2

Early Start Duration Early Finish

Late Start Slack Late Finish

W/SMD SL4

Early Start Duration Early Finish

Late Start Slack Late Finish

W/SMD SL5

Early Start Duration Early Finish

Late Start Slack Late Finish

W/SMD SL6

Early Start Duration Early Finish

Late Start Slack Late Finish

W/SMD SL7

Early Start Duration Early Finish

Late Start Slack Late Finish

W/SMD SL8

Early Start Duration Early Finish

Late Start Slack Late Finish

W/SMD SL9

Early Start Duration Early Finish

Late Start Slack Late Finish

W/SMD SL10

Early Start Duration Early Finish

Late Start Slack Late Finish

W/SMD SL11

Early Start Duration Early Finish

Late Start Slack Late Finish

W/SMD SL12

Early Start Duration Early Finish

Late Start Slack Late Finish

W/SMD SL13

Early Start Duration Early Finish

Late Start Slack Late Finish

W/SMD SL14

Early Start Duration Early Finish

Late Start Slack Late Finish

W/SMD SL3

Early Start Duration Early Finish

Late Start Slack Late Finish

Workshop – Eng Model Planning

Early Start Duration Early Finish

Late Start Slack Late Finish

Expert Model Review/Planning

Completed GIS Data for Modeling

Completed County-Wide Water/Sewer Model

ES = 0 / LS = 0 / Slack = 0

Early Start Duration Early Finish

Late Start Slack Late Finish

R&A SL1

Early Start Duration Early Finish

Late Start Slack Late Finish

R&A SL2

Early Start Duration Early Finish

Late Start Slack Late Finish

R&A SL3

Early Start Duration Early Finish

Late Start Slack Late Finish

R&A SL4

Early Start Duration Early Finish

Late Start Slack Late Finish

R&A SL5

Early Start Duration Early Finish

Late Start Slack Late Finish

R&A SL6

Early Start Duration Early Finish

Late Start Slack Late Finish

R&A SL7

Early Start Duration Early Finish

Late Start Slack Late Finish

R&A SL8

Early Start Duration Early Finish

Late Start Slack Late Finish

R&A SL9

Early Start Duration Early Finish

Late Start Slack Late Finish

R&A SL10

Early Start Duration Early Finish

Late Start Slack Late Finish

R&A SL11

Early Start Duration Early Finish

Late Start Slack Late Finish

R&A SL12

Early Start Duration Early Finish

Late Start Slack Late Finish

R&A SL13

Early Start Duration Early Finish

Late Start Slack Late Finish

R&A SL14

Early Start Duration Early Finish

Late Start Slack Late Finish

W/SMD SL1

Early Start Duration Early Finish

Late Start Slack Late Finish

W/SMD SL2

Early Start Duration Early Finish

Late Start Slack Late Finish

W/SMD SL4

Early Start Duration Early Finish

Late Start Slack Late Finish

W/SMD SL5

Early Start Duration Early Finish

Late Start Slack Late Finish

W/SMD SL6

Early Start Duration Early Finish

Late Start Slack Late Finish

W/SMD SL7

Early Start Duration Early Finish

Late Start Slack Late Finish

W/SMD SL8

Early Start Duration Early Finish

Late Start Slack Late Finish

W/SMD SL9

Early Start Duration Early Finish

Late Start Slack Late Finish

W/SMD SL10

Early Start Duration Early Finish

Late Start Slack Late Finish

W/SMD SL11

Early Start Duration Early Finish

Late Start Slack Late Finish

W/SMD SL12

Early Start Duration Early Finish

Late Start Slack Late Finish

W/SMD SL13

Early Start Duration Early Finish

Late Start Slack Late Finish

W/SMD SL14

Early Start Duration Early Finish

Late Start Slack Late Finish

W/SMD SL3

Early Start Duration Early Finish

Late Start Slack Late Finish

R&A SL13

Early Start Duration Early Finish

Late Start Slack Late Finish

R&A SL14

Early Start Duration Early Finish

Late Start Slack Late Finish

W/SMD SL13

Early Start Duration Early Finish

Late Start Slack Late Finish

W/SMD SL14

1 YR 2 YR 3 YR 4 YR 5 YR

Page 28: Use of Progressive Elaboration in EGIS Program Planning

Perform short and long-term planning using progressive elaboration • Through use of progressive elaboration, only those projects needing completion in

the early phase of the EGIS program (the short-term) were planned in detail.

TIME

INTEGRATE GIS & WORK ORDER SYSTEM

UPDATE DATABASE SCHEMAS IMPLEMENT UPDATED WORKFLOWS

CORRECT DATA DISCREPANCIES

START INTEGRATION OF GIS WITH

CMMS

DOCUMENT SYSTEM

DISCREPANCIES

DOCUMENT UPDATED

WORKFLOWS

IMPLEMENT NEW WORKFLOWS

DEVELOP NEW WORKFLOW PROCEDURES

CORRECT DISCREPANCIES IN GIS

CORRECT DISCREPANCIES IN WORK ORDER SYSTEM

IDENTIFY DATABASE

LINKING FEATURES

UPDATE GIS DB SCHEMA

UPDATE WORK ORDER DB SCHEMA

Page 29: Use of Progressive Elaboration in EGIS Program Planning

Perform short-term project execution

Page 30: Use of Progressive Elaboration in EGIS Program Planning

Key Ideas to Consider • Program planning starts at the high-level and progressively adds detail (top-down

approach).

• Each project is like a brick used to construct your program. Like building a house, you must pay careful attention to where each brick is placed (when it is completed) to ensure you progress as efficiently as possible.

• The vision is the guiding light that must be continually kept in mind or you can easily get off track.

• While there should be only one complete vision for your EGIS program the path to get there should bend and shift to accommodate change.

• Be flexible in your approach and plan for change – build opportunities to plan for change into your EGIS program planning approach through use of progressive elaboration and steadily watch as your EGIS vision becomes a reality.

Page 31: Use of Progressive Elaboration in EGIS Program Planning

Questions

Contact Information:

Brandon Pfleckl

GIS Program Manager Prince William County Service Authority

703-335-8996 [email protected]