use of progressive elaboration in egis program planning
TRANSCRIPT
Use of Progressive Elaboration in EGIS Program Planning
Brandon Pfleckl GIS Program Manager PWCSA
Summary ó Enterprise-wide GIS (EGIS) Program Planning can be
a daunting task full of questions and fear of where and how to start. Then, once you start, how do you stay on track? ó Understanding the concepts of proper program
management can save significant time and energy over the life-cycle of building your EGIS program.
Summary ó We’ll explore three major processes involved in
program planning; ó Establishment of a program vision ó Development of a program of projects that seek to
achieve your vision ó Process of project planning and project execution on the
program scale
• A project represents a single level of effort and usually has a well-defined scope of work including detailed requirements, executables and schedule. With projects you generally know what needs to be accomplished and have a clear path forward. Programs tend to have a much greater level of uncertainty.
• Generally speaking, a program is a set of related projects organized to accomplish a common vision. Programs span much longer time-frames and represent numerous levels of efforts (numerous projects). Each project in a program should represent a building block used to construct your program vision.
Programs versus Projects
• Progressive elaboration allows projects in the short-term to be planned in detail, but mid to long-term projects will have only generally defined scopes. As short-term projects are completed more information will become available concerning available resources and organizational priorities.
• Detailed planning efforts will then “progress” to the next projects in line. • Regardless of path shifts, progressive elaboration allows you to keep your
direction heading towards your vision.
Progressive Elaboration
Progressive Elaboration in Program Planning – Conceptual Analogy:
• Let’s look a look at the process of planning a family vacation to the beach as a good analogy of the process involved within program planning and progressive elaboration.
• You will be able to apply the concepts directly to your EGIS program to help reach success.
Develop high-level vision • Development of a high-level vision should be done early in any process you
undertake so you have an understanding of what you are trying to achieve and all actions moving forward are aimed at achieving your vision.
FAMILY-FRIENDLY DININGHOTEL ON THE BEACH
FAMILY-FRIENDLY BEACH / ACTIVITIES
VACATION IN LATE SUMMER
Develop high-level vision • Use your very general understanding of what you want to accomplish as a
discussion framework moving forward and add a greater level of detail to your vision..
BEACH WITHIN DRIVING DISTANCE
FAMILY-FRIENDLY DINING
- WITHIN WALKING DISTANCE FROM HOTEL
HOTEL ON THE BEACH
-MUST HAVE A POOL
FAMILY-FRIENDLY BEACH / ACTIVITIES
- PARASAILING- SEA-KAYAKING
VACATION IN LATE SUMMER
- MID-LATE AUGUST
High-level Vision
Refine high-level vision to include specific details
• Defining your high-level vision is an enormously important step which lays the foundation for more detailed planning efforts moving forward.
• There is a lot to plan and coordinate. You want to execute your tasks in the most efficient way and with clear direction or you will waste time.
• Specific details must be added to your vision before you can begin.
· SPECIFIC BEACH DETERMINED· SPECIFIC HOTEL DETERMINED· LIST OF SPECIFIC RESTAURNATS
DETERMINED· ACTIVITY VENDORS DETERMINED
SPECIFIC VISION
DETERMINE BEACHES WITH PARASAILING AND SEA-KAYAKING
ACTIVITIES
DETERMINE HOTELS WITH AVAILABILITY IN
MID-LATE AUGUST
WORK WITH FAMILY (STAKEHOLDERS) TO MAKE SELECTIONS
DETERMINE ALL BEACHES WITHIN
DRIVING DISTANCE
DETERMINE FAMILY FRIENDLY BEACHES
DETERMINE HOTELS WITH A POOL
DETERMINE HOTELS WITH FAMILY-FRIENDLY DINING
WITHIN WALKING DISTANCE
Identify necessary projects to achieve your vision and their dependencies
• What will allow for you to accomplish your specific vision? • What decisions must be made? The answers to these questions will identify
the projects you need to execute to achieve your vision.
• Let’s look at one of those questions, travel. You’ve decided to drive to the
beach but there are several dependencies to making sure you get to where you want to go on-time, safely, and reliably. Your travel project is comprised of several tasks:
• Develop travel route • Prepare vehicle for travel • Travel to destination
Identify necessary projects to achieve your vision and their dependencies
DEVELOP TRAVEL ROUTE
TIME
PREPARE VEHICLE TRAVEL TO DESTINATIONTRAVEL PROJECT
START
REACH DESTINATION
INPU
T / C
HA
NG
E
INPU
T / C
HA
NG
E
INPU
T / C
HA
NG
E
Identify necessary projects to achieve your vision and their dependencies
DEVELOP TRAVEL ROUTE
TIME
PREPARE VEHICLE TRAVEL TO DESTINATIONSTART
TRAVEL PROJECT
REACH DESTINATION
INP
UT
/ CH
AN
GE
INP
UT
/ CH
AN
GE
INP
UT
/ CH
AN
GE
CHECK WEATHER FORCASTS
START PACKING PROJECT
LIST ITEM NEEDS RELATED TO ACTIVITES
LIST MEDICATIONS NEEDED
PACK
CHECK-IN TO HOTEL
START “GET SETTLED”
PROJECT
UNPACK
PICK RESTAURANT FOR DINNER
Perform short and long-term planning using progressive elaboration
• Detailed planning can only be done well in the short-term.
• While you need to have a good idea of the projects that are necessary to reach
your vision, you can only plan projects in detail where detailed information exists.
• Over time your priorities, resources and the environment in which you are working will change. This is where progressive elaboration becomes such a useful tool.
LONG TERMMEDIUM TERM
DEVELOP TRAVEL ROUTE
SHORT TERM
TRAVEL TO DESTINATION
TRAVEL PROJECT
START
REACH DESTINATION
INP
UT
/ C
HA
NG
E
INP
UT
/ C
HA
NG
E
Stop at Joe’s Quickie Mart for gas and
snacks
Take RT 87 to interstate 95
Start Disney movie for children
Take Rt 55 to 87
Check GPS unit for traffice and adjust
route
Talk to family about next
required rest-stop
Check GPS unit for traffice and adjust
route
Talk to family about next
required rest-stop
DECREASING LEVEL OF UNDERSTANDING / DECREASING LEVEL OF PLANNING DETAIL
Perform short and long-term planning using progressive elaboration
Perform short-term project execution
MEDIUM TERM
DEVELOP TRAVEL ROUTE
SHORT TERM
TRAVEL TO DESTINATION
TRAVEL PROJECT
START
REACH DESTINATION
INP
UT
/ CH
AN
GE
INP
UT
/ CH
AN
GE
Stop at Joe’s Quickie Mart for gas and
snacks
RT 87 to HWY 95
Start Disney movie for children
RT 55 to RT 87Check GPS unit for traffice and adjust
route
Talk to family about next
required rest-stop
DECREASING LEVEL OF UNDERSTANDING / DECREASING LEVEL OF PLANNING DETAIL
COMPLETED TASKS
HWY 95 to RT 1
Stop at State Rest-Stop
Stop for gas and food
Case Study Review of the Prince William County Service Authority’s EGIS Program Development Process:
Background: Prince William County Service Authority (PWCSA) – Enterprise GIS Transition Project
Had been using Autodesk CAD technology for last 10 years: •Basic mapping capabilities •Limited analytics •No system integration •Isolated (Silo) Departmental Processes and Analysis
The Prince William County Service Authority is a wastewater and water utility serving the second largest county in Virginia.
GIS Vision - Become a GIS-Centric Organization § Reduce silos of information § Integrate GIS with other systems and enable advanced asset analysis § Visualize, access and analyze information from all departments in a spatial context
- Operations & Maintenance - Customer Service - SCADA - Finance - Laboratory
§ Utilize GIS to improve internal workflows across all departments § Provide faster, more accurate and efficient services to its external and internal customers
Develop high-level vision • “become nationally recognized as a steward of the environment and a premier
provider of clean water and superior service by achieving excellence in our partnerships, our work culture, and our business practices.”
• The GIS is envisioned as the cornerstone of the SA integrated information technology environment.
• By coupling GIS geospatial data along with non-spatial data of other SA systems, the SA will have the ability to provide faster, more accurate and efficient services to its external customers.
• This will change GIS from another SA system into an operational requirement and a key component in the way the SA conducts business.
Develop high-level vision
Refine vision to include specific details
The GIS-Centric organizational approach was further defined to accomplish the following (partial list):
• Optimize design engineer’s time • Provide access by all SA personnel to common data across IT
systems in a spatial context • Reduce clerical costs associated with maintaining current data in multiple systems • Increase O&M field crew efficiency due to integration of mobile, GIS, and
work management • Optimize scheduling of work • Provide ability to better recognize and set priorities • Identify critical assets • Reduce crew windshield time/travel distance minimized • Provide ability to provide customers information in seconds when they
call in and improve the customer’s experience
Identify necessary projects to achieve your vision and their dependencies
To properly determine the projects needed to reach the SA’s GIS vision, the SA had to: • (1) evaluate in detail its existing workflows and data quality across all
major IT systems
• (2) determine user needs related to the specific GIS vision items, and
• (3) determine improvements in the way data was collected, stored, and integrated with GIS
Identify necessary projects to achieve your vision and their dependencies
Let’s take a look at one of the specific vision items that contains a large number of project dependencies; provide access by all SA personnel to common data across IT systems in a spatial context. • Integrate GIS with customer service system • Integrate GIS with work order management system (CMMS) • Integrate GIS with SCADA system • Integrate GIS with financial system
Identify necessary projects to achieve your vision and their dependencies
Integrate GIS with the work order management system. In order for GIS to integrate with the work order management system the following tasks had to be accomplished: • Integrate GIS with work order management system • Identify, refine, document and implement updated workflows related to data
collection and storage • Identify data discrepancies between the two systems and make corrections • Determine database linking features between the two systems and make
adjustments to one or both database schemas
Identify necessary projects to achieve your vision and their dependencies
TIME
INTEGRATE GIS & WORK ORDER SYSTEM
UPDATE DATABASE SCHEMAS IMPLEMENT UPDATED WORKFLOWS
CORRECT DATA DISCREPANCIES
START INTEGRATION of GIS with CMMS
Identify necessary projects to achieve your vision and their dependencies
START
EGIS Dependency Diagram GIS Program Projects
Early Start Duration Early Finish
Late Start Slack Late Finish
Service Outage Tool
Early Start Duration Early Finish
Late Start Slack Late Finish
Key Asset Outage Identification
Early Start Duration Early Finish
Late Start Slack Late Finish
Missing Elements/Asset Review Tool
Utility Network Analysis Toolset
Early Start Duration Early Finish
Late Start Slack Late Finish
LIMS Related GIS Layer Development
Early Start Duration Early Finish
Late Start Slack Late Finish
LIMS Data Workshop Discussion
Early Start Duration Early Finish
Late Start Slack Late Finish
Determine LIMS Stakeholders
Early Start Duration Early Finish
Late Start Slack Late Finish
Integration of GIS with LIMS
LIMS System Development or App Purchase
Early Start Duration Early Finish
Late Start Slack Late Finish
LIMS Data Analysis/Reporting Tools Development
LIMS Integration with GIS and Data Analysis
EF = 10 / LF = 121 / Duration = 10
Early Start Duration Early Finish
Late Start Slack Late Finish
Integration of W/S Models with SCADA
Early Start Duration Early Finish
Late Start Slack Late Finish
Integrate GIS/SDE with SCADA System
Early Start Duration Early Finish
Late Start Slack Late Finish
Create and Populate GIS SCADA Layers
Early Start Duration Early Finish
Late Start Slack Late Finish
SCADA Integration WorkshopsCompletion of
SCADA Upgrade Project
Early Start Duration Early Finish
Late Start Slack Late Finish
Develop SCADA Data Analysis Toolset
Completed SCADA GIS Data Analysis Toolset
Early Start Duration Early Finish
Late Start Slack Late Finish
Finalize CAD Data Submittal Standards
Early Start Duration Early Finish
Late Start Slack Late Finish
Develop and Implement GIS Data Submittal Standards
Early Start Duration Early Finish
Late Start Slack Late Finish
Develop Data Loading Model
Early Start Duration Early Finish
Late Start Slack Late Finish
Auto GIS Data Population Tools:Auto-ID Tool
Auto TO/FROM ToolTopology Checks
Early Start Duration Early Finish
Late Start Slack Late Finish
Update GIS Production Workflows
GIS Production Improvements
Early Start Duration Early Finish
Late Start Slack Late Finish
GIS Production Tool Review and Evaluation
Customer Service Data Analysis Toolset
Customer Service Internet Web Portal
Customer Service Advanced GIS Web Portal
EF = 13 / LF = 121 / Duration = 13
EF = 8 / LF = 121 / Duration = 8
EF = 10 / LF = 121 / Duration = 10
Asset Management Data Analysis Toolset
Fully Integrated Advanced GIS Web Portal
Highly Configured GIS Production Tools & Workflow (Data Quality and Efficiency Focus)
PWCSA GIS Vision
High Quality Reliable GIS Database
Early Start Duration Early Finish
Late Start Slack Late Finish
Chlorine Data Tool Development
Early Start Duration Early Finish
Late Start Slack Late Finish
Link from Oracle to GIS
Early Start Duration Early Finish
Late Start Slack Late Finish
Transition of Data Application to Oracle Environment
Early Start Duration Early Finish
Late Start Slack Late Finish
ROI Analysis Chlorine Data Analysis and Mapping System
Early Start Duration Early Finish
Late Start Slack Late Finish
Integration of W/S Models with SDE
Early Start Duration Early Finish
Late Start Slack Late Finish
‘Smart’ Fire Flow Tool
Early Start Duration Early Finish
Late Start Slack Late Finish
Water Age Tracking/Visualization Tool
Early Start Duration Early Finish
Late Start Slack Late Finish
Water Usage Forecasting Tool (Per Home Detail)
Early Start Duration Early Finish
Late Start Slack Late Finish
GWP Model Visualization Tools
Water / Sewer Model GIS Analysis and Planning Toolset
Early Start Duration Early Finish
Late Start Slack Late Finish
Chlorine Data Analysis Tools
Early Start Duration Early Finish
Late Start Slack Late Finish
User Workshop Discussion
Early Start Duration Early Finish
Late Start Slack Late Finish
Re-engineering Select Queires
Early Start Duration Early Finish
Late Start Slack Late Finish
Transition Previously Developed Changes from DEV to PROD
Early Start Duration Early Finish
Late Start Slack Late Finish
Test Web Portal Updates
Portal User Tool Fine-Tuning and Database Optimization
Early Start Duration Early Finish
Late Start Slack Late Finish
Develop Updated Documentation
Early Start Duration Early Finish
Late Start Slack Late Finish
Perform Roll-out and Traning
EF = 15 / LF = 121 / Duration = 15
ES = 0 / LS = 106 / Slack = 107
Early Start Duration Early Finish
Late Start Slack Late Finish
Clone SA140 App Server to SA147
Early Start Duration Early Finish
Late Start Slack Late Finish
Clone SA141 Web Server to SA148
Early Start Duration Early Finish
Late Start Slack Late Finish
Connect SA147 to Oracle Environment
GIS Development Environment Finalization
EF = 15 / LF = 121 / Duration = 15
EF = 15 / LF = 121 / Duration = 15
ES = 0 / LS = 106 / Slack = 107
Early Start Duration Early Finish
Late Start Slack Late Finish
Uninstall ARcSDE from DEV ENV
Early Start Duration Early Finish
Late Start Slack Late Finish
Reinstall ArcSDE with 10.1 for Oracle 11G
Early Start Duration Early Finish
Late Start Slack Late Finish
Set-up GIS Group SDE Connections
ArcGIS 10.1 Upgrade
Early Start Duration Early Finish
Late Start Slack Late Finish
Perform Testing
Early Start Duration Early Finish
Late Start Slack Late Finish
Transition DEV to PROD
Early Start Duration Early Finish
Late Start Slack Late Finish
Perform all steps again for original PROD ENV
Early Start Duration Early Finish
Late Start Slack Late Finish
Point SDE to Oracle 11G and Test
Oracle 11G Upgrade
Early Start Duration Early Finish
Late Start Slack Late Finish
Reconfigure TEST portal with 11G Server environment
Early Start Duration Early Finish
Late Start Slack Late Finish
Develop SA140 with ArcSDE 10.1 and point to Oracle 11G
Early Start Duration Early Finish
Late Start Slack Late Finish
Test and Transition Web Portal to DEV
Early Start Duration Early Finish
Late Start Slack Late Finish
Test and Transition SA140 to SDE DEV
Early Start Duration Early Finish
Late Start Slack Late Finish
Perform Testing
Early Start Duration Early Finish
Late Start Slack Late Finish
User Workshop Discussion
Early Start Duration Early Finish
Late Start Slack Late Finish
Requirements Gathering and Reporting
Early Start Duration Early Finish
Late Start Slack Late Finish
I&I Web Portal DEV
Customized User Group GIS Web Portals
Early Start Duration Early Finish
Late Start Slack Late Finish
Develop Updated Documentation
Early Start Duration Early Finish
Late Start Slack Late Finish
Perform Roll-out and Traning
Early Start Duration Early Finish
Late Start Slack Late Finish
Engineering Planning GIS Web Portal DEV
Early Start Duration Early Finish
Late Start Slack Late Finish
Customer Service Web Portal DEV
Early Start Duration Early Finish
Late Start Slack Late Finish
Dispatch GIS Web Portal DEV
Early Start Duration Early Finish
Late Start Slack Late Finish
Field Services GIS Web Portal DEV
Early Start Duration Early Finish
Late Start Slack Late Finish
C&D GIS Web Portal DEV
Early Start Duration Early Finish
Late Start Slack Late Finish
GENERAL GIS Web Portal DEV
Early Start Duration Early Finish
Late Start Slack Late Finish
Test Geometric Network
Early Start Duration Early Finish
Late Start Slack Late Finish
Develop Geometric Network
Early Start Duration Early Finish
Late Start Slack Late Finish
Plan Geometric Network
Early Start Duration Early Finish
Late Start Slack Late Finish
Implement in PROD Environment
Early Start Duration Early Finish
Late Start Slack Late Finish
Train GIS Group on GeoNet use
Geometric Network
Early Start Duration Early Finish
Late Start Slack Late Finish
Run Topology Rules and Identify issues
Early Start Duration Early Finish
Late Start Slack Late Finish
Develop Topology Rules
Early Start Duration Early Finish
Late Start Slack Late Finish
Plan Topology Rules & Corrections
Early Start Duration Early Finish
Late Start Slack Late Finish
Train GIS Group Staff
Early Start Duration Early Finish
Late Start Slack Late Finish
Perform Corrections and Test
Topological Data Corrections
Early Start Duration Early Finish
Late Start Slack Late Finish
Plan Utility Network Tools
Early Start Duration Early Finish
Late Start Slack Late Finish
Utility Network Tools Workshops
Early Start Duration Early Finish
Late Start Slack Late Finish
Workshop Discussion of CL DB and App needs
Early Start Duration Early Finish
Late Start Slack Late Finish
Workshop Interviews: what EPA reporting reqs exist
Early Start Duration Early Finish
Late Start Slack Late Finish
Review of LIMS-style software options: should we develop or buy
DEPENDANCYPlanning and Execution of SCADA
Implementation Project
Early Start Duration Early Finish
Late Start Slack Late Finish
Program Workflow Development
Early Start Duration Early Finish
Late Start Slack Late Finish
Stakeholder Workshops
Early Start Duration Early Finish
Late Start Slack Late Finish
GPS Stakeholder Identification
Early Start Duration Early Finish
Late Start Slack Late Finish
GPS Application DevelopmentStakeholder Feedback
and Resource Allocation
Early Start Duration Early Finish
Late Start Slack Late Finish
User Training and Rollout
GPS Program Development
Early Start Duration Early Finish
Late Start Slack Late Finish
Pilot Project Planning (ENG)
Early Start Duration Early Finish
Late Start Slack Late Finish
Pilot Execution and Reporting
DEPENDANCYStakeholder Resources shall play a significant
role. Currently, additional GIS Group resources are not available for significant data
collection
Early Start Duration Early Finish
Late Start Slack Late Finish
Update Production Procedures
Early Start Duration Early Finish
Late Start Slack Late Finish
Place Holder for OTHER tools
Early Start Duration Early Finish
Late Start Slack Late Finish
Testing
Early Start Duration Early Finish
Late Start Slack Late Finish
Rollout and Training
Early Start Duration Early Finish
Late Start Slack Late Finish
Program Workflow Development
Early Start Duration Early Finish
Late Start Slack Late Finish
GPS Application DevelopmentStakeholder Feedback and Resource
Allocation
Early Start Duration Early Finish
Late Start Slack Late Finish
User Training and Rollout
Early Start Duration Early Finish
Late Start Slack Late Finish
Pilot Project Planning (CUSTOMER SERVICE
Early Start Duration Early Finish
Late Start Slack Late Finish
Pilot Execution and ReportingEarly Start Duration Early
Finish
Late Start Slack Late Finish
Program Workflow Development
Early Start Duration Early Finish
Late Start Slack Late Finish
GPS Application Development
Stakeholder Feedback and Resource
Allocation
Early Start Duration Early Finish
Late Start Slack Late Finish
User Training and Rollout
Early Start Duration Early Finish
Late Start Slack Late Finish
Pilot Project Planning (OPERATIONS AND MAINT)
Early Start Duration Early Finish
Late Start Slack Late Finish
Pilot Execution and Reporting
Early Start Duration Early Finish
Late Start Slack Late Finish
HRMP Workshops
Early Start Duration Early Finish
Late Start Slack Late Finish
Map Corrections Task
Early Start Duration Early Finish
Late Start Slack Late Finish
C&D Task
Early Start Duration Early Finish
Late Start Slack Late Finish
CIP Task
Early Start Duration Early Finish
Late Start Slack Late Finish
Chris Brown’s Documents Task
Incorporation of Historical Records into GIS Database
Early Start Duration Early Finish
Late Start Slack Late Finish
O&M Locator Room
Early Start Duration Early Finish
Late Start Slack Late Finish
Mapping Boxes
Early Start Duration Early Finish
Late Start Slack Late Finish
Engineering Scanning
Early Start Duration Early Finish
Late Start Slack Late Finish
HRMP Planning
Early Start 120 HRS Early Finish
Late Start Slack Late Finish
GIS Production work
Early Start 120 HRS Early Finish
Late Start Slack Late Finish
GIS Production work
Early Start 120 HRS Early Finish
Late Start Slack Late Finish
GIS Production work
Early Start 120 HRS Early Finish
Late Start Slack Late Finish
GIS Production work
Early Start 120 HRS Early Finish
Late Start Slack Late Finish
GIS Production work
Early Start 120 HRS Early Finish
Late Start Slack Late Finish
GIS Production work
Early Start Duration Early Finish
Late Start Slack Late Finish
Transition of Existing Marker Documents to new System
Early Start Duration Early Finish
Late Start Slack Late Finish
Workflow Adjustment Planning and Execution for New Documents
Early Start Duration Early Finish
Late Start Slack Late Finish
Markers/Document Management Workshop Discussions and Planning
Advanced Document Access Capabilities
EF = 18 / LF = 121 / Duration = 18
ES = 0 / LS = 103 / Slack = 103
DEPENDANCYMoving forward would require an
organizational transition to an enterprise level document management system similar to
“Share Point,” which can tag documents with coordinates for spatial tracking. Otherwise, current system is as good as is reasonable
Early Start Duration Early Finish
Late Start Slack Late Finish
Identify Finance Stakeholders
Early Start Duration Early Finish
Late Start Slack Late Finish
Determine Finance-GIS Integration Requirements
Early Start Duration Early Finish
Late Start Slack Late Finish
Perform In-Depth Review of Finance System/DB
Early Start Duration Early Finish
Late Start Slack Late Finish
Create GIS/Finance GIS Layers
Finance GIS Analysis Toolset
Early Start Duration Early Finish
Late Start Slack Late Finish
Integrate Finance with GISEarly Start Duration Early
Finish
Late Start Slack Late Finish
Finance Customer Connection Fee Calculator
Early Start Duration Early Finish
Late Start Slack Late Finish
Finance Depreciation Analysis Tool
Early Start Duration Early Finish
Late Start Slack Late Finish
‘Other’ Finance Tools
EF = 15 / LF = 121 / Duration = 15DEPENDANCYSelection of a new Finance system shall play a major role in the planning and execution of this
project
Early Start Duration Early Finish
Late Start Slack Late Finish
Develop Facility Analysis Tools
Early Start Duration Early Finish
Late Start Slack Late Finish
Perform GIS/Facility Integration
Early Start Duration Early Finish
Late Start Slack Late Finish
Create Additional Facility GIS Layers
Early Start Duration Early Finish
Late Start Slack Late Finish
Facility Information Workshops
Transition Facility Workflows and Data
into CMMS
Facility GIS Access and Analysis
EF = 7 / LF = 121 / Duration = 7DEPENDANCY
Choice of new CMMS will play a major role: City Works has built-in integrations, Maximo
and Hansen require much development on DB side
Early Start Duration Early Finish
Late Start Slack Late Finish
Scan Facility Manuals and add as Markers
Early Start Duration Early Finish
Late Start Slack Late Finish
CS Stakeholder and Requirements GatheringEarly Start Duration Early Finish
Late Start Slack Late Finish
Review and Update of CS Database
Early Start Duration Early Finish
Late Start Slack Late Finish
ROI Analysis for CS Apps
Early Start Duration Early Finish
Late Start Slack Late Finish
CS Internet Portal Workshop Discussion and Planning
Early Start Duration Early Finish
Late Start Slack Late Finish
Customer. Call Mapping Integration with GIS
Early Start Duration Early Finish
Late Start Slack Late Finish
Meter Location Info in GIS Web Portal
Early Start Duration Early Finish
Late Start Slack Late Finish
Advanced CS attribute Viewing in GWP
Early Start Duration Early Finish
Late Start Slack Late Finish
Illegal Connection Tool/Study
Early Start Duration Early Finish
Late Start Slack Late Finish
CS Internet Portal for Customer Use
Early Start Duration Early Finish
Late Start Slack Late Finish
Create Dynamic Link Between GIS and CS Consumption Data
Early Start Duration Early Finish
Late Start Slack Late Finish
Missing Customer Tool/Study
Early Start Duration Early Finish
Late Start Slack Late Finish
Water Conservation Tool/Study
Early Start Duration Early Finish
Late Start Slack Late Finish
Commercial Mischarges Tool/Study
Early Start Duration Early Finish
Late Start Slack Late Finish
Potential Leaks Tool/Study
Early Start Duration Early Finish
Late Start Slack Late Finish
Engineering Development GIS Web Portal DEV
Early Start Duration Early Finish
Late Start Slack Late Finish
Conrad’s Notebooks
Early Start 120 HRS Early Finish
Late Start Slack Late Finish
GIS Production work
Early Start Duration Early Finish
Late Start Slack Late Finish
Microfilm Appcards
Early Start 120 HRS Early Finish
Late Start Slack Late Finish
GIS Production work
Early Start Duration Early Finish
Late Start Slack Late Finish
R&A SL1
Early Start Duration Early Finish
Late Start Slack Late Finish
R&A SL2
Early Start Duration Early Finish
Late Start Slack Late Finish
R&A SL3
Early Start Duration Early Finish
Late Start Slack Late Finish
R&A SL4
Early Start Duration Early Finish
Late Start Slack Late Finish
R&A SL5
Early Start Duration Early Finish
Late Start Slack Late Finish
R&A SL6
Early Start Duration Early Finish
Late Start Slack Late Finish
R&A SL7
Early Start Duration Early Finish
Late Start Slack Late Finish
R&A SL8
Early Start Duration Early Finish
Late Start Slack Late Finish
R&A SL9
Early Start Duration Early Finish
Late Start Slack Late Finish
R&A SL10
Early Start Duration Early Finish
Late Start Slack Late Finish
R&A SL11
Early Start Duration Early Finish
Late Start Slack Late Finish
R&A SL12
Early Start Duration Early Finish
Late Start Slack Late Finish
R&A SL13
Early Start Duration Early Finish
Late Start Slack Late Finish
R&A SL14
Early Start Duration Early Finish
Late Start Slack Late Finish
W/SMD SL1
Early Start Duration Early Finish
Late Start Slack Late Finish
W/SMD SL2
Early Start Duration Early Finish
Late Start Slack Late Finish
W/SMD SL4
Early Start Duration Early Finish
Late Start Slack Late Finish
W/SMD SL5
Early Start Duration Early Finish
Late Start Slack Late Finish
W/SMD SL6
Early Start Duration Early Finish
Late Start Slack Late Finish
W/SMD SL7
Early Start Duration Early Finish
Late Start Slack Late Finish
W/SMD SL8
Early Start Duration Early Finish
Late Start Slack Late Finish
W/SMD SL9
Early Start Duration Early Finish
Late Start Slack Late Finish
W/SMD SL10
Early Start Duration Early Finish
Late Start Slack Late Finish
W/SMD SL11
Early Start Duration Early Finish
Late Start Slack Late Finish
W/SMD SL12
Early Start Duration Early Finish
Late Start Slack Late Finish
W/SMD SL13
Early Start Duration Early Finish
Late Start Slack Late Finish
W/SMD SL14
Early Start Duration Early Finish
Late Start Slack Late Finish
W/SMD SL3
Early Start Duration Early Finish
Late Start Slack Late Finish
Workshop – Eng Model Planning
Early Start Duration Early Finish
Late Start Slack Late Finish
Expert Model Review/Planning
Completed GIS Data for Modeling
Completed County-Wide Water/Sewer Model
ES = 0 / LS = 0 / Slack = 0
Early Start Duration Early Finish
Late Start Slack Late Finish
R&A SL1
Early Start Duration Early Finish
Late Start Slack Late Finish
R&A SL2
Early Start Duration Early Finish
Late Start Slack Late Finish
R&A SL3
Early Start Duration Early Finish
Late Start Slack Late Finish
R&A SL4
Early Start Duration Early Finish
Late Start Slack Late Finish
R&A SL5
Early Start Duration Early Finish
Late Start Slack Late Finish
R&A SL6
Early Start Duration Early Finish
Late Start Slack Late Finish
R&A SL7
Early Start Duration Early Finish
Late Start Slack Late Finish
R&A SL8
Early Start Duration Early Finish
Late Start Slack Late Finish
R&A SL9
Early Start Duration Early Finish
Late Start Slack Late Finish
R&A SL10
Early Start Duration Early Finish
Late Start Slack Late Finish
R&A SL11
Early Start Duration Early Finish
Late Start Slack Late Finish
R&A SL12
Early Start Duration Early Finish
Late Start Slack Late Finish
R&A SL13
Early Start Duration Early Finish
Late Start Slack Late Finish
R&A SL14
Early Start Duration Early Finish
Late Start Slack Late Finish
W/SMD SL1
Early Start Duration Early Finish
Late Start Slack Late Finish
W/SMD SL2
Early Start Duration Early Finish
Late Start Slack Late Finish
W/SMD SL4
Early Start Duration Early Finish
Late Start Slack Late Finish
W/SMD SL5
Early Start Duration Early Finish
Late Start Slack Late Finish
W/SMD SL6
Early Start Duration Early Finish
Late Start Slack Late Finish
W/SMD SL7
Early Start Duration Early Finish
Late Start Slack Late Finish
W/SMD SL8
Early Start Duration Early Finish
Late Start Slack Late Finish
W/SMD SL9
Early Start Duration Early Finish
Late Start Slack Late Finish
W/SMD SL10
Early Start Duration Early Finish
Late Start Slack Late Finish
W/SMD SL11
Early Start Duration Early Finish
Late Start Slack Late Finish
W/SMD SL12
Early Start Duration Early Finish
Late Start Slack Late Finish
W/SMD SL13
Early Start Duration Early Finish
Late Start Slack Late Finish
W/SMD SL14
Early Start Duration Early Finish
Late Start Slack Late Finish
W/SMD SL3
Early Start Duration Early Finish
Late Start Slack Late Finish
R&A SL13
Early Start Duration Early Finish
Late Start Slack Late Finish
R&A SL14
Early Start Duration Early Finish
Late Start Slack Late Finish
W/SMD SL13
Early Start Duration Early Finish
Late Start Slack Late Finish
W/SMD SL14
1 YR 2 YR 3 YR 4 YR 5 YR
Perform short and long-term planning using progressive elaboration • Through use of progressive elaboration, only those projects needing completion in
the early phase of the EGIS program (the short-term) were planned in detail.
TIME
INTEGRATE GIS & WORK ORDER SYSTEM
UPDATE DATABASE SCHEMAS IMPLEMENT UPDATED WORKFLOWS
CORRECT DATA DISCREPANCIES
START INTEGRATION OF GIS WITH
CMMS
DOCUMENT SYSTEM
DISCREPANCIES
DOCUMENT UPDATED
WORKFLOWS
IMPLEMENT NEW WORKFLOWS
DEVELOP NEW WORKFLOW PROCEDURES
CORRECT DISCREPANCIES IN GIS
CORRECT DISCREPANCIES IN WORK ORDER SYSTEM
IDENTIFY DATABASE
LINKING FEATURES
UPDATE GIS DB SCHEMA
UPDATE WORK ORDER DB SCHEMA
Perform short-term project execution
Key Ideas to Consider • Program planning starts at the high-level and progressively adds detail (top-down
approach).
• Each project is like a brick used to construct your program. Like building a house, you must pay careful attention to where each brick is placed (when it is completed) to ensure you progress as efficiently as possible.
• The vision is the guiding light that must be continually kept in mind or you can easily get off track.
• While there should be only one complete vision for your EGIS program the path to get there should bend and shift to accommodate change.
• Be flexible in your approach and plan for change – build opportunities to plan for change into your EGIS program planning approach through use of progressive elaboration and steadily watch as your EGIS vision becomes a reality.
Questions