TRANSCRIPT

Page 1: Battery Energy Storage System Presentation

Battery Energy Storage System Presentation

Approved by the Board of Genex Power Limited

Page 2: Battery Energy Storage System Presentation

2

• 100MW of operating assets

• 250MW in construction

• 470MW of pipeline assets 50MW Jemalong Solar Project (Operating)

KIDSTON CLEAN ENERGY HUB

BOULDERCOMBE BATTERY PROJECT (BBP)

50MW Large-Scale Battery Energy Storage System (Development)

50MW Kidston Solar Project (Operating)

250MW Kidston Pumped StorageHydro Project (Construction)

150MW Kidston Wind Project (Development)

Up to 270MW Kidston Stage Two Solar Project (Feasibility)

JEMALONG SOLAR PROJECT (JSP)

Genex | Clean Energy, On Demand

Diverse renewable energybase

Portfolio of renewable energy generation and storage projects

Revenue substantially underpinned by long-term contracts

7 October 2021

Page 3: Battery Energy Storage System Presentation

Delivering a portfolio of renewable energy generation and storage projects

3Genex | Clean Energy, On Demand

Renewable Energy Generation Energy StorageChallenges of intermittent renewable energy:

• Oversupply of power in prime generation conditions (irradiation and wind)

• Leading to volatile pricing

• Decreasing system stability

• Solar not available in peak demand times

The benefits of batteries:

• Stores energy for use in peak time

• Balances out the pricing dynamic

• Quick release of power when required

• Increase system stability

Genex PowerGenex’s diverse portfolio of renewable energy generation and storage projects provides:

• Increased renewable energy availability to the grid

• The ability to optimise energy sales revenue

• Enables shareholder value accretion as the NEM transitions

• Maximise power prices received from energy sales

7 October 2021

Page 4: Battery Energy Storage System Presentation

4Genex | Clean Energy, On Demand

Renewable energy is expected to increase to 83% of NEM total power supply in 2055

Large-scale storage will maximise renewable energy availability (particularly solar)

Growing penetration of renewable generation underpins the business case for storage

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

2022

2023

2024

2025

2026

2027

2028

2029

2030

2031

2032

2033

2034

2035

2036

2037

2038

2039

2040

2041

2042

2043

2044

2045

2046

2047

2048

2049

2050

2051

2052

2053

2054

2055

% o

f pow

er g

ener

atio

n

Generation capacity forecast for NEM

Solar Wind Coal

Renewable energy growthThe need for storage

7 October 2021

Source: Genex estimates

Page 5: Battery Energy Storage System Presentation

Evolving energy market – the need for storage

5

Growth of intermittent wind and solar creating volatility in the market

Need for low-cost, large-scale storage to facilitate high penetration of renewables and maintain reliability requirements

5 minute settlement from 1 October likely to increase price volatility

Large-scale batteries can respond to the market in undera second

Genex is addressing the need for energy storage via:

250MW Kidston Pumped Storage Hydro Project; and

50MW Bouldercombe Battery Project.

Paid to Charge / Paid to DischargeQLD Retail Electricity Price

Genex | Clean Energy, On Demand

$(60.00)

$(40.00)

$(20.00)

$-

$20.00

$40.00

$60.00

$80.00

$100.00

$120.00

12:3

0:00

1:30

:00

2:30

:00

3:30

:00

4:30

:00

5:30

:00

6:30

:00

7:30

:00

8:30

:00

9:30

:00

10:3

0:00

11:3

0:00

12:3

0:00

13:3

0:00

14:3

0:00

15:3

0:00

16:3

0:00

17:3

0:00

18:3

0:00

19:3

0:00

20:3

0:00

21:3

0:00

22:3

0:00

23:3

0:00

$/M

Wh

Queensland Electricity Prices - 11 September 2021

7 October 2021

Source: AEMO

Page 6: Battery Energy Storage System Presentation

Allows for further deployment of intermittent generation (wind & solar)

Ability to provide much needed system strength services

Batteries can take advantage of low spot prices and excess renewable energy supply when charging

Batteries can store low cost renewable energy to support peak demand events

The benefits of large-scale storage

Rapid construction and deployment flexibility

Significant technology advancement and decreasing capital costs

Batteries can provide premium peaking service to meet high periods of demand

Advanced technology – ability to react to market signals in milliseconds

Genex | Clean Energy, On Demand 67 October 2021

Page 7: Battery Energy Storage System Presentation

7

Site: Dalrymple (2018)Supplier: ABB & SamsungCapacity: 8MW/30MWh

Genex | Clean Energy, On Demand

Site: Hornsdale (2017)Supplier: TeslaCapacity: 100MW/129MWh

Site: Ballarat (2018)Supplier: Fluence Capacity: 52MW/25MWh

Site: Lake Bonney (2018)Supplier: TeslaCapacity: 52MW/25MWh

Site: Gannawarra (2018)Supplier : TeslaCapacity: 30MW/30MWh

Genex set to leverage the strong arbitrage business case due to growing solar generation in the electricity market

Currently no large-scale batteries generating in the Queensland market

Batteries have the ability to operate in all 9 markets (energy market + 8 FCAS markets)

BESS have the capability to address system security issues caused by rapid deployment of intermittent generation

Australian’s operationallarge-scale battery landscape

7 October 2021

Page 8: Battery Energy Storage System Presentation

Australia’sbattery growth

8Genex | Clean Energy, On Demand

There is a requirement for significant BESS battery roll out along the east coast of Australia

Approximately 123GWh of capacity needed by 2040

The only operating BESS’s in Australia are located in SA and VIC

Batteries inserted into renewable energy zones fill the gaps in dispatchable supply allowing renewable generation to be used more effectively

Source: AEMO

7 October 2021

-

10

20

30

40

50

NSW SA QLD VIC

GWh

(tho

usan

ds)

Required BESS by 2040

0

50

100

150

200

250

NSW SA QLD VIC

MW

h

Current Operating BESS

Source: Genex estimates

Page 9: Battery Energy Storage System Presentation

9Genex | Clean Energy, On Demand

Large-scale batteries & 5-minute settlement

Milliseconds Seconds Minutes Hours

Batteries Hydro Gas Coal

5-minute market

✓ The introduction of the 5 minute pricing market in the NEM rewards the rapid provision of power into the grid

✓ Historically pricing was on a 30 minute basis (average of 6 by 5 minute intervals)

✓ Recent change has distinct 5 minute pricing blocks

✓ The ability to rapidly enter (and withdraw) power will provide the power source with better ability to capture peak discharge prices (and take advantage of trough prices to recharge)

✓ Battery technology, with the ability to discharge power in millisecond and pumped hydro (seconds) are well positioned to benefit from the change in market dynamics

-50

0

50

100

150

200

250

12:0

0:00

AM

1:00

:00

AM

2:00

:00

AM

3:00

:00

AM

4:00

:00

AM

5:00

:00

AM

6:00

:00

AM

7:00

:00

AM

8:00

:00

AM

9:00

:00

AM

10:0

0:00

AM

11:0

0:00

AM

12:0

0:00

PM

1:00

:00

PM

2:00

:00

PM

3:00

:00

PM

4:00

:00

PM

5:00

:00

PM

6:00

:00

PM

7:00

:00

PM

8:00

:00

PM

9:00

:00

PM

10:0

0:00

PM

11:0

0:00

PM

$/M

Wh

Spot Price ($/MWh)

Time interval

Discharge price ($/MWh)

1:00pm to 3.00pm

Charge price ($/MWh)

8:00am to 12.00pm

Total Cycle Price

($/MWh)

30min 196 -22 218

5min 263 -175 438

Discharge

Charge

QLD Wholesale Electricity Price – September 2021

5 minute settlement impact on pricing (1MW/1MWh)

Source: AEMO https://aemo.com.au/en/energy-systems/electricity/national-electricity-market-nem/data-nem/data-dashboard-nem

Notes to table: stylist representation of a charge and discharge cycle (energy only market)

7 October 2021

Page 10: Battery Energy Storage System Presentation

Example: sudden increase in wind velocity

NEM frequency rises >50Hz

Battery rapidly charges to increase demand, frequency falls back to 50Hz

10Genex | Clean Energy, On Demand

Large-scale batteries & the FCAS market

✓ Frequency Control Ancillary Services (FCAS) are a group of services that help maintain the NEM at a stable frequency of 50Hz

✓ Short term imbalances between supply and demand can cause frequency instability, which can ultimately lead to system failure and blackouts

✓ The intermittent nature of renewables increases potential instability

✓ Historically coal fired power stations provided FCAS given their size and considerable inertia

✓ Batteries are ideally suited to provide FCAS to the NEM given their ability to charge and discharge in milliseconds

✓ The NEM pays operators to provide FCAS services

Supply exceeds demand

50Hz

45 55

Example: sudden decrease in solar radiation

NEM frequency falls <50Hz

Battery rapidly discharges to increase supply, frequency rises back to 50Hz

Demand exceeds supply50Hz

45 55Coal retirements will reduce the supply of FCAS

Intermittent renewables will increase the demand for FCAS

7 October 2021

Page 11: Battery Energy Storage System Presentation

Bouldercombe Battery Project

50MW BESS located in Bouldercombe, Rockhampton in Queensland - adjacent to the Powerlink substation

11

✓ Genex’s first battery project

✓ Land to be secured under 30 year leasing arrangement next to Powerlink’s Bouldercombe substation

✓ Connection and Generator Performance Standard (GPS) process well advanced

✓ Funding discussions with potential lenders and strategic investor

✓ Tesla selected as the battery supplier and integrator

✓ Offtake arrangements well progressed

B O ULD ERC O MB E

Substation

B O ULD ERC O MB E

Project Site

Genex | Clean Energy, On Demand 7 October 2021

Page 12: Battery Energy Storage System Presentation

Genex | Green Energy, On Demand | Presentation 12

Tesla technologyMegapack 2.0

The Megapack is an all-in-one utility-scale energy storage system

optimised for cost and performance

• All Megapack components pre-installed and tested within a

single enclosure

• Battery architecture consists of battery modules and an

integrated liquid cooling and heating system for thermal

safety, enhanced performance and increased reliability

Each Megapack is shipped from Tesla’s Gigafactory fully-assembled and

factory tested. Above: inside the BBP Tesla Megapack 2.0

7 October 2021

Page 13: Battery Energy Storage System Presentation

Genex Power’sbattery financials

Genex’s BESS will leverage energy market arbitrage and FCAS markets to deliver strong and predictable revenue streams

13

Attractive outlook for price arbitrage in certain states with the introduction of 5-minute settlement in October 2021

Source: Genex BBP Financial Model – bank case

Genex | Clean Energy, On Demand

Minimal requirements for ongoing sustaining capital

Strong EBITDA margin of >75% expected from BBP

Operating life expected to be greater than the 20 year warranty

Life of asset revenue to average over $10m per annuum

Initial Capex of $55-$60m1 to develop the asset

7 October 20211: includes owner's costs, contingency and financing costs

FY20

24

FY20

25

FY20

26

FY20

27

FY20

28

FY20

29

FY20

30

Tota

l Net

Rev

enue

($m

)

Bouldercombe Battery Project Net Revenue

Energy Market Gross Margin FCAS Gross Margin

Page 14: Battery Energy Storage System Presentation

14Genex | Clean Energy, On Demand

Large-scale batteries & contingency events – Callide C case study

▪ On 25 May 2021, Unit 4 (405MW) at the Callide C coal-fired power station suffered a turbine fire:▪ The remaining two units at Callide also tripped (the fourth was offline)

▪ The transmission lines connecting Callide to the grid opened

▪ Capacity at nearby power stations including Gladstone, Stanwell, Yarwun and Mackay was affected

▪ The Queensland-NSW interconnector was disrupted

▪ The outage at Callide resulted in a 3,000MW shortfall▪ Nearly 500,000 homes and businesses in Queensland lost access to power

▪ Average RRP prices in Queensland escalated to $15,000 for nearly 2 hours

▪ If BBP had been operational at the time, it would have made $700k in gross margin on 25 May 2021 solely from arbitrage activities

▪ Over the period to 30 June, as prices remained volatile, the BBP would have netted a total of $3.2m from arbitrage gross margin alone, averaging some 255% of forecast daily revenues

▪ Extreme contingency events such as Callide C are unpredictable, but likely to increase in frequency as coal plant ages and retires

▪ Importantly similar events are not factored into Genex’s revenue forecasts for the BBP and therefore represent substantial upside to equity

7 October 2021

Significant events can deliver substantial profitability for batteries

Source: AEMO, Genex calculations

$0

$250

$500

$750

$1,000

$1,250

$1,500

$1,750

$2,000

$0

$2,000

$4,000

$6,000

$8,000

$10,000

$12,000

$14,000

$16,000

0:30 1:3

02:

303:

304:

305:

306:

307:

308:

309:

3010

:30

11:30

12:3

013

:30

14:3

015

:30

16:3

017

:30

18:3

019

:30

20:3

021

:30

22:3

023

:30

Qld

RRP

(A$/

MWh)

Qld RRP during Callide C event

Avg. 26-May-21 to 30-Jun-21 (RHS) 25-May-2021 (LHS)

0

100,000

200,000

300,000

400,000

500,000

25-M

ay26

-May

27-M

ay28

-May

29-M

ay30

-May

31-M

ay1-

Jun

2-Ju

n3-

Jun

4-Ju

n5-

Jun

6-Ju

n7-

Jun

8-Ju

n9-

Jun

10-J

un11-

Jun

12-J

un13

-Jun

14-J

un15

-Jun

16-J

un17

-Jun

18-J

un19

-Jun

20-J

un21

-Jun

22-J

un23

-Jun

24-J

un25

-Jun

26-J

un27

-Jun

28-J

un29

-Jun

30-J

un

A$'0

00 p

er d

ay

BBP Illustrative Arbitrage GM during Callide C event

BBP Arbitrage GM Average daily forecast GM

Page 15: Battery Energy Storage System Presentation

Energy storage roll out strategyGenex will leverage its experience in storage gained from the development of the Kidston Pumped Storage Hydro Project to achieve it’s target of 2500MWh of storage by 2025

2000MWhExpansion

2500MWh

RAPID EXECUTION

K2-Hydro

250MW/8 hour

Leverage our Relationships and financing skill set

✓ Powerlink Queensland

✓ Tesla

✓ Queensland Government

✓ ARENA

✓ NAIF

✓ CEFC

Progress Future Growth

✓ BBP 50MW/2 hour BESS

✓ 250MW/8 hour Kidston Pumped Storage Hydro Project

✓ Additional 1-2 BESS

✓ Geographic diversification

✓ Strategic partnerships

BBP

50MW/2 hourBESS

Diversified revenue streams

✓ Energy offtake

✓ FCAS

✓ Energy

✓ Network services

✓ Firming

HIGH RETURNING PROJECTS

RAPID EXECUTIONLOW RISK PROFILE STRONG CASH GENERATION

HIGH RETURNING PROJECTS

15Genex | Clean Energy, On Demand 7 October 2021

Page 16: Battery Energy Storage System Presentation

Genex diversified renewable portfolio

16

2021 2022 2023 2024 2025

50MW Bouldercombe Battery Construction Commissioning/Operation

50MW KidstonSolar Operation

50MW JemalongSolar Operation

250MW KidstonPumped Storage Hydro Construction Commissioning/Operation

150MW KidstonWind Construction OpsFeasibility & Financing

Genex | Clean Energy, On Demand 7 October 2021

Page 17: Battery Energy Storage System Presentation

Investment highlights

17

Diverse renewable energy and storage portfolio✓ 2 operating 50MW solar projects (KS1 & JSP)

✓ K2-Hydro funded and in construction

✓ Battery and wind projects in advanced stages

Proven track record of project execution✓ Successfully developed >$200m worth of projects

✓ Secured long term energy contracts providing secure cash flows

✓ Developed, financed and built KS1 and JSP on time and on budget

Strong relationships✓ Tier 1 stakeholders

Revenue stream certainty✓ 85% revenue contracted for 30 years

✓ >79% EBITDA margin

✓ Minimal sustaining capex

✓ Average annual revenue $82.5m until 2055

✓ Utility like nature of cashflow and revenue stream

350MW of power generation and storage✓ $1 billion renewable energy & storage portfolio

✓ Average interest rate of 2.96% locked in via long term hedge

Near term developmentof pipeline opportunities ✓ 200MW of near term development opportunities

• 50MW Bouldercombe Battery– construction 2022

• 150MW Kidston Wind – construction 2023

04 05 06

01 02 03

Genex | Clean Energy, On Demand 7 October 2021

Page 19: Battery Energy Storage System Presentation

Board and Management

19

Dr. Ralph Craven Non-Executive Chairman

Michael Addison Non-Executive Director

James Harding Chief Executive Officer

Simon KidstonExecutive Director

Craig FrancisChief Financial Officer

Teresa DysonNon-Executive Director

Yongqing YuNon-Executive Director

ASX code: GNX

Shares on issue: 1,069,900K

Market cap (30.09.2021): $251M

Cash (30.06.21): $45M1

Corporate snapshot

Genex | Clean Energy, On Demand

Kenichi SeshimoNon-Executive Director

10%

47%

43%

SHAREHOLDERSJ-POWER Institutions Other

Ben GuoNon-Executive Director

Arran McGhieChief Operations Officer

7 October 20211. Bonds, Deposits and Bank Guarantees are excluded

Page 20: Battery Energy Storage System Presentation

Our people, communities and the environment

20

People, Health and Safety

• Continuation of COVID-19 protocols to ensure our people and communities remain safe

• Commitment to managing risk and driving safety leadership through our organisation and ensuring our contractors implement best practice

• Strong focus on diversity and indigenous engagement within our workforce

Environment

• Strict focus on minimising disturbance

• Commitment to conserving and protecting the environments we operate in

• K2-Hydro converting disturbed mine site to sustainable energy generation

• 2 million tonnes CO2 abatement by 2025

Community

• Focus on job creation in our local communities

• At Jemalong, 151 jobs were created, 68% were local, 22% were women and 11% were Indigenous

• Indigenous Engagement Strategy to promote Indigenous employment and procurement for K2-Hydro

• 800 jobs created at Kidston and along the transmission route

Genex | Clean Energy, On Demand 7 October 2021

Page 21: Battery Energy Storage System Presentation

DisclaimerThis document has been prepared by Genex Power Limited (“Genex” or “Company”) for the purpose of providing a company and technical overview to interested analysts/investors. None of Genex, nor any of its related bodies corporate, their respective directors, partners, employees or advisers or any other person (“Relevant Parties”) makes any representations or warranty to, or takes responsibility for, the accuracy, reliability or completeness of the information contained in this document to the recipient of this document (“Recipient”) and nothing contained in it is or may be relied upon as, a promise or representation, whether as to the past or future.

The information in this document does not purport to be complete nor does it contain all the information that would be required in a disclosure statement or prospectus prepared in accordance with the Corporations Act 2001 (Commonwealth). It should be read in conjunction with Genex’s other periodic releases.

This document is not a recommendation to acquire Genex shares and has been prepared without taking into account the objectives, financial situation or needs of individuals. Before making an investment decision prospective investors should consider the appropriateness of the information having regard to their own objectives, financial situation and needs and seek appropriate advice, including financial, legal and taxation advice appropriate to their jurisdiction. Except to the extent prohibited by law, the Relevant Parties disclaim all liability that may otherwise arise due to any of this information being inaccurate or incomplete. By obtaining this document, the Recipient releases the Relevant Parties from liability to the Recipient for any loss or damage that it may suffer or incur arising directly or indirectly out of or in connection with any use of or reliance on any of this information, whether such liability arises in contract, tort (including negligence) or otherwise.

This document contains certain “forward‐looking statements”. The words “forecast”, “estimate”, “like”, “anticipate”, “project”, “opinion”, “should”, “could”, “may”, “target” and other similar expressions are intended to identify forward looking statements. Indications of, and guidance on, future earnings and financial position and performance are also forward‐looking statements. You are cautioned not to place undue reliance on forward looking statements. Although due care and attention has been used in the preparation of forward looking statements, such statements, opinions and estimates are based on assumptions and contingencies that are subject to change without notice, as are statements about market and industry trends, which are based on interpretations of current market conditions. Forward looking statements including projections, guidance on future earnings and estimates are provided as a general guide only and should not be relied upon as an indication or guarantee of future performance.

Recipients of the document must make their own independent investigations, consideration and evaluation. By accepting this document, the Recipient agrees that if it proceeds further with its investigations, consideration or evaluation of investing in the Company it will make and rely solely upon its own investigations and inquiries and will not in any way rely upon this document.

This document is not and should not be considered to form any offer or an invitation to acquire Genex shares or any other financial products, and neither this document nor any of its contents will form the basis of any contract or commitment. In particular, this document does not constitute any part of any offer to sell, or the solicitation of an offer to buy, any securities in the United States or to, or for the account or benefit of any “US person” as defined in Regulation S under the US Securities Act of 1993 (“Securities Act”). Genex shares have not been, and will not be, registered under the Securities Act or the securities laws of any state or other jurisdiction of the United States, and may not be offered or sold in the United States or to any US person without being so registered.

21Genex | Clean Energy, On Demand 7 October 2021