public mtg at_brentwood final
TRANSCRIPT
AgendaWelcome and please sign in
MSD mission
Project Clear defined– Clear priorities
– Clear communications
– Clear water
Deer Creek Tunnel
Question and Answers2
MSD MissionProtect the public’s health and the natural environment through effective wastewater and stormwater management strategies
3
Welcome to Project Clear
Schedule driven by consent decree with US EPA
23-years in total (started in 2012)
Project Clear is about three central goals: Clear Priorities, Clear Communications and Clear Water.
4
Clear PrioritiesOverflows and Backups Being Addressed
Separate Sewer Areas
– Get the Rain Out – Stormwater Disconnects
– Public System Rehab and Upgrades
– Treatment Plant Enhancements
Combined Sewer Areas
– Gray/Green Infrastructure (Rainscaping)
– Cityshed5
Clear Communications
Stakeholders Engaged Early in Program
Communities are Vital Partners
Synergies Identified and Developed
Website and Social Media Leveraged
Transparent Communications Key
8
Clear Water – Deer Creek Watershed
10
**REPLACE NAME AND MAP WITH YOUR NEIGHBORHOOD.DELETE THIS MESSAGE.
Greg Exhibit
Deer Creek Tunnel Project Timeline
Phase I Phase II Phase III
Preliminary Design and
Geotech Investigation
Final Design, Construction Bid
and ROW Acquisition Documents
Construction of the
Project
Estimated Time: 60+ monthsEstimated Time: 18 months Estimated Time: 18 months
Land Acquisition BeginsWe Are Here
12
Borings
Why are they necessary?
– Tunnel Design
• Verify elevation of strong rock
• Set the depth for tunnel and shaft design
– Identify any geological issues
14
Borings
How are they performed?
– Schedule
• Work day based on each city’s regulations
• 1-2 weeks at each site (4-6 months duration)
– Not a blasting operation, very little disturbance
16
Deer Creek Tunnel Project Timeline
Phase I Phase II Phase III
Preliminary Design and
Geotech Investigation
Final Design, Construction Bid
and ROW Acquisition Documents
Construction of the
Project
Estimated Time: 60+ monthsEstimated Time: 18 months Estimated Time: 18 months
Land Acquisition BeginsWe Are Here
22
Thank you!
23
www.ProjectClearSTL.org
@ProjectClear-Deer Creek
Project Clear-Deer Creek
MSD Project Manager: Jeff Smith(314) [email protected]
Parsons Project Manager: Ed Sweet(314) [email protected]