Monthly Environmental Report August 2013

ii August 2013 Causeway Upgrade Project Monthly Environmental Report v2.docx

Document history and status

Revision Date issued Written By Reviewed by Approved by Revision Status

A 17.09.2013 K Stevens E Collins / S Kane / B Dunbar

For REVIEW

B 18.09.13 K Stevens M Evans FOR APPROVAL

C 19.09.13 K Stevens M Evans M Evans FINAL

D 14.10.13 K Stevens K Stevens FINAL with revised App D

Distribution of copies

Revision Purpose Issued to

A For review E Collins/B Dunbar/S Kane

B For approval/release Mark Evans

C FINAL Auckland Council

D FINAL reissued Auckland Council

Printed: 16/10/2013 09:16

Last saved: 16/10/2013 09:16

File name: K:\EN Environment\EN51 Construction\04 Council Reporting\Monthly Report\2013 06 Report\June 2013 Causeway Upgrade Project Monthly Environmental ReportECverA.docx

Author: Kevin Stevens

Environmental Manager: Michael Cassidy

Name of organisation: Causeway Alliance

Name of project: SH16 Causeway Upgrade Project

Document version: Revision D

6 August 2013 Causeway Upgrade Project Monthly Environmental Report v2.docx

Contents 1.0 INTRODUCTION 7

1.1 PURPOSE OF THE REPORT 7

2.0 OVERVIEW of ACTIVITIES UNDERTAKEN 7

2.1 Environmental 7

2.2 Communications and Stakeholder Management 7

2.3 Key Stakeholder Milestones 7

2.4 Construction 8

3.0 MEETINGS, INSPECTIONS & EVENTS 8

4.0 ENVIRONMENTAL MONITORING 8

4.1 EARTHWORKS COMPLIANCE 8

4.2 CONSTRUCTION NOISE & VIBRATION 8

4.3 AIR QUALITY 9

4.4 CONTAMINATED SOIL 9

4.5 EROSION AND SEDIMENT CONTROL 9

4.6 ARCHAEOLOGICAL 9

4.7 COASTAL MONITORING 9

4.8 MARINE MONITORING 9

4.9 ECOLOGICAL 10

5.0 CORRESPONDENCE ON CONSENT CONDITIONS AND PLANS 10

6.0 WORKS PROPOSED FOR SEPTEMBER 2013 10

Appendix A: SH16 Causeway Alliance Construction Zone Plan

Appendix B: SH16 Causeway Alliance 3 Month Construction Programme

Appendix C: SH16 Causeway Summary Construction Programme

Appendix D: SH16 Causeway Imported and Exported Material Summary

7 August 2013 Causeway Upgrade Project Monthly Environmental Report v2.docx

1.0 INTRODUCTION

1.1 PURPOSE OF THE REPORT

To provide Auckland Council with a monthly overview of construction progress and compliance activity on the SH16 Causeway Upgrade project.

This report describes and details activities during the month of August 2013.

2.0 OVERVIEW of ACTIVITIES UNDERTAKEN

2.1 Environmental

Regular contact is continuing with Auckland Council compliance team.

Review of draft Urban Design and Landscape Plan by Auckland Council and Auckland Transport staff.

2.2 Communications and Stakeholder Management

The next quarterly Community Liaison Group (CLG) meeting was held on 13 August 2013 at Pringle Park Bowling Club in Te Atatu and attended by 30 members. The presentation and minutes are available on the project web page: http://www.nzta.govt.nz/network/projects/project.html?ID=208

A further meeting was held on 26 August 2013 with CLG members to identify potential environmental mitigation opportunities which could be considered as an additional ‘legacy’ of the project. These ideas will be considered by the Project Alliance Board and a response will be provided to the next CLG meeting in November. The CLG Environmental Mitigation meeting minutes are also on the project’s web page.

2.3 Key Stakeholder Milestones

• Produced fortnightly Causeway News project updates to stakeholders, project neighbours and wider community

• Working Liaison Group meeting held on 21 August • Presented to Auckland Council staff at Auckland Central Library on the NZ Transport

Agency’s Western Ring Route projects • Met with Forest & Bird members to review floating bird roosts proposed south of

Causeway Bridge. • Presented to Bus and Coach Association on bus lane closures and options to mitigate bus

delays • Responses received to the STEM assessment from Te Atatu Pony Club and local schools

on the reuse of hardwood timber for projects (non-heritage projects). • Met with Te Atatu primary school principals to progress environmental legacy project

concepts

8 August 2013 Causeway Upgrade Project Monthly Environmental Report v2.docx

Three calls to the project’s freephone number were received during the period. Positive feedback and no complaints were received from residents, local or regional stakeholders.

2.4 Construction

• Alwyn Ave - no progress on earthworks for creating access to Whau Bridge (south-west side) due to wet weather.

• Whau River bridge (north-east side) - working platform for ground improvements and vibro cement column installation underway

• Rosebank Domain – vegetation clearing continuing ahead of powerline relocation

• Zone 1 Causeway (North Traherne Island) – continue installing drainage layer, wick drains, ground monitoring instrumentation, relocation of shell bank and works in advance of coastal marine occupation

• South Traherne Island – clearing of vegetation alongside shared path

• Great North Road Interchange (GNRI) to SH16 westbound on-ramp – mangrove clearing and earthworks continuing ahead of coastal marine occupation.

• Trial embankment – removal of concrete block in coastal marine area.

3.0 MEETINGS, INSPECTIONS & EVENTS

1 August 2013 - Earthworks Compliance Inspection (Auckland Council / Causeway Alliance)

6 August 2013 - Coastal works Compliance (Auckland Council / Causeway Alliance)

15 August 2013 - Earthworks Compliance Inspection (Auckland Council / Causeway Alliance)

29 August 2013 - Earthworks Compliance Inspection (Auckland Council / Causeway Alliance)

4.0 ENVIRONMENTAL MONITORING

4.1 EARTHWORKS COMPLIANCE

Earthworks Compliance Inspections completed by Auckland Council officers on the 1, 15 and 29 August 2013 all recorded compliance scores of 1 (Full Compliance).

4.2 CONSTRUCTION NOISE & VIBRATION

No Site Specific Noise Management Plans were submitted or approved in August.

No noise monitoring was undertaken during August.

9 August 2013 Causeway Upgrade Project Monthly Environmental Report v2.docx

4.3 AIR QUALITY

No air quality complaints or issues were received during the period.

Causeway Alliance Daily Site Reports did not indicate any air quality issues.

4.4 CONTAMINATED SOIL

An import/export fill strategy has been finalised, implemented and will be submitted to Council in September. Tests on exported material were completed during the period at GNRI, Causeway and West (Whau River), resulting in classifications of managed soil, contaminated soil and clean fill being identified.

A summary of imported material sources and exported material disposal locations, classifications and quantities at various site locations during August is included in Appendix D.

4.5 EROSION AND SEDIMENT CONTROL

CESCP No. 11 for Southern Traherne Island was approved 22 August.

Two amendments to CESCP No. 8 for Whau Bridge access were approved on 2 and 22 August.

CESCP No. 10 is for the Rosebank Domain access road and relates to works which require a new resource consent application, and this has yet to be submitted to Council.

4.6 ARCHAEOLOGICAL

Inspections of archaeological sites and regular monitoring were completed during the period at the GNRI westbound ramp site (adjacent to Oakley Creek). This included middens and a concrete building and related works from a Waitemata County Council quarry (dating back to 1920/1930s).

4.7 COASTAL MONITORING

A coastal monitoring inspection was completed by Auckland Council on 6 August and recorded a compliance score of 1 (Full Compliance).

4.8 MARINE MONITORING

No marine monitoring was undertaken during the period.

The six monthly construction phase marine monitoring programme will commence during the 2013/2014 summer.

10 August 2013 Causeway Upgrade Project Monthly Environmental Report v2.docx

Five intertidal beach profile baseline section surveys were completed on the north side of the Causeway.

Two intertidal profile baseline section surveys were completed on the south side of the Rosebank Domain access road.

The existing channel profiles in the Oakley Inlet, opposite side slope protection works, are being surveyed.

4.9 ECOLOGICAL

Ongoing inspection for Significant and Valued vegetation was undertaken during the period at GNRI, Traherne Island North and South, between Whau River bridge (north-eastern corner) and Patiki off-ramp and at the Rosebank Domain.

There was accidental clearance and disturbance of a small area of vegetation on the western side of south Traherne Island, beyond the designation boundary, during the site clearance operation. A letter, investigation and detailed plan reporting the extent of this incident and proposed mitigation will be provided in September.

Pre-clearance inspections for reptiles/lizards were undertaken at the Rosebank Domain site during the period.

Monthly assessment of avian roosting locations was undertaken in Zone 3 (Harbourview-Orangihina).

Planning continues for the installation of two temporary bird roost sites (floating pontoons) south of Causeway Bridge.

A draft Animal Pest Management Plan is prepared and is being reviewed prior to submission to Council. This covers the pest control required by BOI Condition A.6.

5.0 CORRESPONDENCE ON CONSENT CONDITIONS AND PLANS

Letter dated 12 August from Council approving the lighting plan for the Te Atatu Road Contractor’s Yard.

Letter dated 29 August from Council approving the layout plan submitted for Construction Yard 2 in Rosebank Domain.

6.0 WORKS PROPOSED FOR SEPTEMBER 2013

Refer Appendix B for three Month Construction Programme and Appendix C for SH16 Causeway Upgrade Project Summary Programme.

11 August 2013 Causeway Upgrade Project Monthly Environmental Report v2.docx

Zone 1 Causeway - continue installing the working platform, drainage blanket, wick drains, coffer dam and reclamation in the coastal area on north Traherne Island. Establish access and working platform on south Traherne Island.

Zone 2 / Zone 3 – Access track from Alwyn Ave to Whau River Bridge (south-west) to commence after lizard relocation and environmental controls installed. Continue installing ground improvements at abutment on the north- east side of Whau River Bridge.

Zone 5 - Installing the coffer dam, rock revetment on Oakley Creek bends and earthworks to widen the embankment in the vicinity of Oakley Creek at Great North Road Interchange Area.

The environmental focus for September will continue to be on inspections prior to and during vegetation removal and ground clearance to ensure ecological and archaeological stand over requirements are met. The establishment and monitoring of sediment and erosion controls will also continue.

Appendix A: SH16 Causeway Alliance Construction Zone Plan

mdalvi
Text Box

Appendix B: SH16 Causeway Alliance 3 Month Construction Programme

8/07/2013 SH16 CA 90‐Day Work Starts Plan 130701 FINAL.xlsx

SH16 CAUSEWAY ALLIANCE90 DAY "WORK STARTS" PLANThis 90‐Day plan is to be read in conjunction with the Project Summary Programme.

. All Management Plans Complete ‐ 1/7 . Pavements Design IFC ‐ 23/8

. Road Barriers IFC Complete . SW Drainage Design Approved ‐ 29/8

l d / b i l i l i /

. . . AND BEYOND90‐DAY MILESTONESAREA

01‐Jul‐13 05‐Aug‐13 16‐Sep‐13 23‐Sep‐13 30‐Sep‐13

de

07‐Oct‐13 14‐Oct‐1312‐Aug‐1308‐Jul‐13 15‐Jul‐13 22‐Jul‐13 29‐Jul‐13 19‐Aug‐13 26‐Aug‐13 02‐Sep‐13 09‐Sep‐13

K:\CS Construction and Programme\CS04 Programmes\90‐Day Plan\90‐Day Plan July to Sept 2013\SH16 CA 90‐Day Work Starts Plan 130701 FINAL.xlsx Author: Glenn Houpapa 1 of 1

. KRAs Implemented ‐ 22/7 . Substantial Design Completion ‐ 28/8. Commence Steel Barrier Installation ‐ 15/7 . IFC for Area West GI's

. Close Hopetoun St Office ‐ 30/8 . 100% All Cost Codes FCTC

. Winter Marine Monitoring Commences ‐ 1/7 . Winter Marine Monitoring Completed ‐ 31/8

. Stability Berm Remedial Methodology Application ‐ 16/9

. Enabling works complete for Area 3 handover ‐ 5/7 . Divert Share Path, GNR WB to Causeway Br ‐ 5/8 . Commence temp EB off ramp 23/9. Enabling works complete for Area 1 handover ‐ 12/8 . Commence earthowrks to Area 2 ‐ 12/9

. Commence fingers / coffer dams ‐ 19/8

. Traherne Is Instrumentation Installed ‐ 20/7 . 1200‐2100 Zone 1 GI Package IFC ‐ 15/8 . Rosebank culvert embankment designation approved‐ 26/9

. Wick Drain Installation Commences ‐ 29/7E 1

GNRI

Project W

id

. Commence Area 3EB widening 7/10

C l t Wi k D i. Wick Drain Installation Commences   29/7

. Remove existing trial embankment ‐ 5/8 . Commence Embankment Fill 16/9

. Yard 2 Established ‐ 12/8 . Consent for Raceway RW Approved ‐ 1/10

. North East Access to WRB Complete ‐ 8/7 . Commence works to Raceway Channel ‐ 12/8

. TTM to EB shoulder WRB Complete ‐ 7/8 . Alwyn Ave Access: WRB SW Complete ‐ 30/8. Raceway Powerlines relocated ‐ 29/7 . South Eastern Access established WRB ‐ 10/9

. Rosebank contaminated fill consents approved ‐ 26/9

. WRB Seismic & Push‐over Analysis Resolved ‐ 5/7 . Commence Vibro Concrete Columns NE Whau ‐ 5/8 . VCCs NE Whau Complete ‐ 2/09. Temp Staging Procurement Finalised ‐ 15/07

/

ZONE

AREA

WEST

CTURE

S

. WRB south westernGI complete ‐ 4/10

. Complete Wick Drains to Traherne Island 30/9

. Reinforcing procurement completed ‐ 19/07 . Commence Temp Staging WRB ‐ 6/9. Alwyn Ave Demolition Complete ‐ 22/07 . WRB IFCs 26/8ST

RUC

K:\CS Construction and Programme\CS04 Programmes\90‐Day Plan\90‐Day Plan July to Sept 2013\SH16 CA 90‐Day Work Starts Plan 130701 FINAL.xlsx Author: Glenn Houpapa 1 of 1

Appendix C: SH16 Causeway Summary Construction Programme

PreferredProponent

Consent Amendment / Approval

Marine Reserve Acts decision

ConfirmPlan B

TOCSign-off

PAAsigned

Management Plans

Finalise Design ConceptValue Engineering

Roads - Design / Check / RFC

Drainage - Design / Check / RFC

Utilities - Design / Check / RFC

Geotech - Design / Check / RFC

Structures - Design / Check / RFC

Mobilise team

Whau River Bridge - EB Stitch

Whau River Bridge - WB (Phase B - centre & east) / stitch

Median barrier replacement to approachesProcurement

Staging Staging removal EB Cycleway / footpath

TTM / early works

Median barriers / lighting

EB MSE slope / Earthworks

Patiki Rd Bridge

WB pavement Stage 1

Pavement - median

Landscaping

Install TTM EB / WB 2250-2800

EB Coffer Dams /infill / drainage blanket 2000-1260

EB Earthworks / preload

Causeway 1260-2100 Settlement

EB Remove toe / coastal protection

Stormwater EB 1260-2100

Pavement EB 1260-3050 / 3rd lane

Earthworks Central 1260-2100

Stormwater WB

Earthworks - Central 2100-3050

Median barrier / lights

Paving - Central 1260-2100

OGPA WBEnabling / staging

Causeway Bridge - EB WB substructure remedials

Causeway Bridge - Median

Area 1 - GNR-SH16 WB On-ramp 0-600m

Area 2 - GNR-SH16 WB On-ramp 600-1200m

Area 3 - SH16-GNR EB Off ramp - temp

Area 5 - access

Area 6 - SH16 EB widening

WCA - median works

Area 8 - access Area 8 SH16 gore

Shift EB traffic tonew EB lanes

15/7/2015

Relocate WB traffic northbetween old & new medians

13/1/2016

Target PracticalCompletion

3/6/2016

Alliance contingency

Westbound LanesDeliverable

22/12/2016

Design / preconstruct

Earthworks

Temporary Works etc

Drainage / Utilities

Structures

Pavement / barriers

EB widening

OGPA WB / EB

WB 2250-2800 coffer dams / infill / drainage blanket wick drains WB 2250-2800 preload WB 2250-2800 settlement Coastal protect. / pave / 3rd lane WB 1900-3050

Cycleway 650-1200

WCA access

SettlementOakley Boardwalk

Area 10 - GNR-SH16 EB On Ramp Stage 1

SH16-GNR EB Off-ramp 260-680m

Area 5 embankment only

Area 3 SH16 EB 680-1040 Settlement

Area 10 - GNR-SH16 EB On Ramp Stage 2

Wetland

WCA - Ramp 2 superstructure

Area 9 - Median / final pavements

GNRICompletion

27/9/2016

GNRI contingency

EB wick drains 2000-1040

wick drainsEB coffer dams / infill / drainage blanket 2100-2800

WB - Retaining walls

WB Earthworks Stage 1

WB Stormwater / Utilities

Ewks / Utilities On ramp / Cycleway

Median E/WMedian barrier wall RW6

Median E/W balance

Traffic to shoulders(bull run) 3400-4700

Shift traffic northto EB lanes

Zone 2 CommenceTTM install

Zones 2 & 3complete

EB 2100-2800 preload EB 2100-2800 settlement Coast protect. / SW

CFA cols - bridge abutments - West / East

WB 1260-2250 Stab. berm / fill /coastal protect/ SW /Utilities

Utilities / Cycleway 2250-3050C'way 1260-2250

Median retaining wall

Stormwater Median 2100-3050

Median barrier / lighting

Paving - Central 2100-3050

Demo/ Earthworks WB 1260-2220

Paving - WB 1260-2200

Complete SW

OGPA EB

Area 1 - Access/EarthworksWCA - works

WCA - Ramp 3 substructure WCA - Ramp 3 superstructure Area 5 pavement

WCA - substructures

Area 9 - temp works / shift EB sth

Area 9 - north

WCA - MSE wall / Ramp 2 substructure

Area 2 - WB completion

Utilitiescomplete

30/6/2015

Whau River Bridgecomplete

30/6/2015

Zone 2 east - median works (with Zone 1)

Staging WB

Whau River Bridge WB - Establish west access Staging / WRB WB (West end) / remove staging

Early works Traherne Island

Critical

OGPA EB / WB

Site Office Establishment

Cycleway 3900-4700

Whau River Bridge EB - east / west access / Grd improvements

Job NoDate

Drawn

Programme No Rev No

No Revision App Date 101 H

4265/12/12

CWBSH16 CAUSEWAY

SUMMARY PROGRAMME A Draft 2

DESIGN / CONSENTS

APPROVALS

ROSEBANK PENINSULA

Z2 - CH 3060-4400

WHAU RIVER BRIDGE

Z3 - CH 4400-4950

CAUSEWAY

Z1 - CH 1200-3060

SH16 / GREAT NORTH

ROAD INTERCHANGE

Z5 - CH 100-1200

KEY

F Revision F 26/4

G Revision G / Design 85% 5/7

H Zone 2 / Zone 3 reviced 30/8

Status Updateas at 30 August 2013

WHAU RIVER BRIDGE

RAMP 2

RAMP 3

RAM

P 1

RAMP 4

GREAT NORTH ROADINTERCHANGE

OAKLEY CREEK

BOARDWALK

RW1 Barrier Wall830-1075

CAUSEWAY

BRIDGE

RW2 Barrier Wall2275-2740

ROSEBANKON / OFF RAMPS

ROSEBANK DOMAIN

RW6 L - shaped Median Wall

4170-4425

RW5 (MSE slope)

PATIKI ROADON-RAMP BRIDGE

PATIKION RAMP

PATIKIOFF RAMP

RW7 (Stone Strong Wall)3545-3615

RW3 (Stone Strong Wall)3060-3160

RW4

(MSE

Slo

pe)

3330

-340

0

Appendix D: SH16 Causeway Imported and Exported Material Summary

SH16 Causeway Upgrade - Imported and Exported Material Summary August 2013 v2

Aug-13 Export Causeway Zone 1B Topsoil / Organics

Cleanfill NA Ridge Road Quarry 56

Aug-13 Export Causeway Zone 1B Topsoil / Organics

Cleanfill NAPuketutu Island Fulton Hogan

950

Aug-13 Export GNRI GNRI Area 1 Topsoil-Managed

Managed NA Greenmount Landfill 523

Aug-13 Export GNRI GNRI Area 1 Topsoil-Contaminated

Contaminated NA Hampton Downs Landfill 439

Aug-13 Export GNRI GNRI Area 1 and Area 2 Topsoil Cleanfill NA Puketutu Island Fulton Hogan 576

Aug-13 Export West Zone 3 Clean Fill Cleanfill NA Yard (and then disposed of to Greenmount)

100

Aug-13 Export West Zone 3 Clean Fill Cleanfill NA Zone 2 1000Aug-13 Import Causeway Zone 1B Drainage Blanket Woodhill Sand Cleanfill Woodhill Quarry NA 1533

Aug-13 Import Causeway Zone 1B Coffer Dam Revetment Rock Cleanfill Pukekawa Quarry

n/a 105

Aug-13 Import Causeway Zone 1B Haul Road Gap 65 Non Spec Cleanfill Brookby Quarry n/a 716

Aug-13 Import Causeway Zone 1B Working Platform GAP 100 Cleanfill Brookby Quarry NA 3582

Aug-13 Import GNRI GNRI Area 1 D50.320 Cleanfill Pukekawa Quarry

GNRI-area 2 212

Aug-13 Import GNRI GNRI Area 1 Drainage metal Cleanfill Te Atatu yard GNRI-area 1 200

Aug-13 Import GNRI GNRI Area 1 Type B ROP (SPR)

Cleanfill Brookby Quarry GNRI-area 1 8775

Aug-13 Import GNRI GNRI Area 2 GAP 100 Cleanfill Brookby Quarry GNRI-area 2 1262

Disposal Facility Volume(Tonnes)

Soil Classification

Source of Imported Fill

Month Moved

Import / Export

Zone Area/Source Material Material Type