Project UNDP/ GEF 00074315
Energy Efficiency in North West Russia
Methodology of ENMS implementation
in municipal sector
Urban ENMS definition
The ENMS is the complex of technical and administrative measures, which
aimed to reduce the energy consumption of municipal buildings ( schools,
hospitals, sport facilities, communal service and other public buildings):
Herewith ENMS provides:
- Analysis and monitoring of information about energy consumption for all
municipal buildings in the city
- Opportunity for CEAP development
- Constant control of consumed energy resources for each municipal building
- A rapid response for changing energy parameters, which goes from the
buildings
ENMS is a key for Energy Efficiency in scale of whole CITY
How it works ?
Let’s figure out together
Every municipal building is the main subject for ENMS
Each buildings consist of some multi level managing
structure:
1) Managing and accountant department
2) The main departments
3) Service department
How it works ?
Every municipal building is consumer of energy resources
Which resources are
consuming by buildings?
To whom buildings should pay
for energy consumption ?
How it works ?
ENERGY SUPPLY COMPANY
How it works ?
Every municipal building needs in money to cover the
expences for energy bills
Why city should cover these
expences for every municipal
buildings?
Which structure in city is
responsible for that?
How it works ?
ENERGY SUPPLY COMPANY
CITY DEPARTMENT OF HEALTH
How it works ?
There is some governmental structure in every city, which
have a following function:
Control and monitoring of
energy consumption by
municipal buildings
Responsibility for EE
activities in this cities
Modernization and repair
of buildings and their
infrastructure
CEAP development
Regional or city center
of energy efficiency
Department of Energy
and Housing and
Communal Services
Some external private
company
(as a subcontractor)
How it works ?
ENERGY SUPPLY COMPANY
CITY DEPARTMENT OF HEALTH
Department of Energy and
Housing and Communal Services
How this relation works on practice in CIS countries ?
Deputy of Mayor
Mayor
GIS, SC
How it works ?
ENERGY SUPPLY COMPANY
This type of individual
direct communication on
the monthly basis
Two way connection
might works as manual
and as in automatic
mode
Each building based on specific legislation have to be equiped
by meters
ESC form the energy bills based on information from meters
How it works ?
CITY DEPARTMENT OF HEALTH
This committiee is responsible for forecasting of
consumed energy resources by buildings
Allocation money in
depends of consumed
energy
The control of the level of consumed
energy by each buildings
Forecasting a cashflow
for prospective for
further budgeting
The data transfer - 1 time per quarter in manual mode
How it works ?
CITY DEPARTMENT OF HEALTH
Department of Energy and
Housing and Communal Services
Preparation energy balance of
the city
Preparation of energy action
plan
Preparation of program of
repair of municipal buildings
Awareness rising in terms of
efficient usage of energy for
end users
Activities of this department aimed to the realisation of EE measures in buidings
through the analysis of collected data and city energy action plan development
The data transfer - 1 time per quarter in manual mode
How the existing scheme works in
real life?
ENERGY SUPPLY COMPANY
CITY DEPARTMENT OF HEALTH
Department of Energy and
Housing and Communal ServicesDeputy of Mayor
Mayor
GIS, SSA
What are the main barriers?
• Lack of awareness and understanding situation by the city administration for the
establishment of ENMS
Lack of legislation about ENMS implementation
• The absence of unified automatic system of energy monitoring, collection and
analysis of energy consumption
• The absence of position of energy manager in Department of Energy and Housing
and Communal Services
• No interest to reduce the energy consumption in buildings
• Low level of awareness and knowledge about EE in municipal buildings
Weak technical equipment in municipal buildings (including meters)
Absence of technical feasibility for total modernization of all buildings
Absence of education on regular basis with end users ( municipal buildings)
The main key elements of ENMS
The main principle of ENMS based on 3 key elements:
Energy Monitoring System
Implementation
EMS – it’s set of equipment,
which enable metering of
energy parameters in
buildings and automatic
remote transfer these data to
the PC / The external view
reflecting through the some
soft on PC – Energy
Monitoring software
Development of administrative
documents which regulating the
work of energy manager in
existing administrative structure
Development an algorithm of
action of energy manager
Практические моменты реализации
СГУЭР бюджетного сектора
Department of Energy and Housing
and Communal Services
Energy Manager
GIS , SSA
е
Energy Monitoring Systemе
City Department of
Health
Energy Supply
Company
ее
е
Deputy of Mayor
е
The complex of this measures ensure the existing sheme by technical and
administrative links , which form the ENMS
Practical point is the simultaneous constrcuction of two types of connections
The abcense of one link will not provide the efficient operation of whole system
Master of Ceremony
The main key elements of ENMS
Energy Monitoring System
Implementation
EMS – it’s set of equipment,
which enable metering of
energy parameters in
buildings and automatic
remote transfer these data to
the PC / The external view
reflecting through the some
soft on PC – Energy
Monitoring software
Development of administrative
documents which regulating the
work of energy manager in
existing administrative structure Energy Monitoring System – it’s set
of equipment, which enable
metering of energy parameters in
buildings and automatic remote
transfer these data to the PC / The
external view reflecting through the
some soft on PC – Energy
Monitoring software
The regulating documents define the main
responsible administrative person in structure
(energy team), their responsibilities, reporting
Department of Energy and Housing
and Communal Services
Energy Manager
City Department of
Health
Deputy of Mayor
Energy Specialist in buildings
Specialist from City
Department of Health
Energy Manager
Deputy
of
Mayor
Mayor
Conduction of inventory buildings located in the municipal government . Building data collection
Collecting all data about buildings, engineering infrastructure , energy consumption
existence of energy assessment, internal building energy action plan, implemented EEM
2 step
1 step
Statistic analysis of collected dataKey performance indicators definition and calculationComparison real KPI with normative
3step
The ranking and grouping buildings based on deviation real KPI with normative and other factor (existence of energy audit passport, some implemented EEM)
Практические моменты реализации
СГУЭР бюджетного сектора
The main steps of energy manager’s methodology:
The algorithm of action define the main steps of
action of energy manager
4 step
Technical assistance in forming the list of buildings needs to be assessed in terms of energy survey
5 step
Technical assistance for the buildings to define and prepare the feasibility study for prospective EEM in terms of modernization
Preparation and implementation of training programs for end users
Практические моменты реализации
СГУЭР бюджетного сектора
The algorithm of action define the main steps of
action of energy manager
STEP 1 to STEP 5 – this is sort of micromanagement processes
6 step
Forming the total results of whole group of buildings
7 шаг
Technical assistance to define and prepare the feasibility study for whole group of buildings which planned to be renovated
Technical assistance in finance planning for prospective EE modernization including searching some source of funding
7 step
Практические моменты реализации
СГУЭР бюджетного сектора
STEP 6 to STEP 7 – this is sort of macromanagement processes
The algorithm of action define the main steps of
action of energy manager
The main responsibilities of Energy Manager:
- Daily work and coordination of ENMS
- Monitoring and control the limits of energy consumption by buildings
- Conduction of benchmarking based on the KPI;
- Technical assistance in forming the list of buildings needs to be
assessed in terms of energy survey
- Assistance in EE modernization for the buildings which have been assessed
- Awareness rising for energy team’s members ( training program on regular
basis)
- Coordination, identification and assessment of new opportunities for the EE
modernization of municipal buildings
- Development of investment programs aimed to EE modernization
Project UNDP/ GEF 00074315
Energy Efficiency in North West Russia
Thank you for your attention
Vitaly Bekker
Project manager