Work Instruction KEUB - JPN - Execute Plan Assessment Purpose This simulation will show you the basic steps to execute plan assessment. Trigger Perform this transaction when you need to execute a plan assessment. Menu Path Use the following SAP Easy Access menu path(s) to begin this transaction: Accounting > Controlling > Profitability Analysis > Planning > Integrated planning > Transfer Cost Center Planning > KEUB - Assessment Transaction Code KEUB Tuesday, July 14, 2009 CO_KEUB_JPN_Execute Plan Assessment.udc 1/12

Upload: nguyencaohuy

Post on 03-Jan-2016

21 views

Category:

Documents


2 download

DESCRIPTION

co temple

TRANSCRIPT

Page 1: CO KEUB JPN Execute Plan Assessment

Work Instruction KEUB - JPN - Execute Plan Assessment

Purpose

This simulation will show you the basic steps to execute plan assessment.

Trigger

Perform this transaction when you need to execute a plan assessment.

Menu Path

Use the following SAP Easy Access menu path(s) to begin this transaction:

Accounting > Controlling > Profitability Analysis > Planning > Integrated planning > Transfer Cost Center Planning > KEUB - Assessment

Transaction Code

KEUB

Tuesday, July 14, 2009 CO_KEUB_JPN_Execute Plan Assessment.udc

1/11

Page 2: CO KEUB JPN Execute Plan Assessment

Work Instruction KEUB - JPN - Execute Plan Assessment

Screen Flow

Tuesday, July 14, 2009 CO_KEUB_JPN_Execute Plan Assessment.udc

2/11

Page 3: CO KEUB JPN Execute Plan Assessment

Work Instruction KEUB - JPN - Execute Plan Assessment

Procedure

1. In SAP, start the transaction using the menu path or transaction code.

SAP Easy Access

2. Double-click the Accounting node .

3. Double-click the Controlling node .

4. Double-click the Profitability Analysis node .

5. Double-click the Planning node .

6. Double-click the Integrated Planning node .

Tuesday, July 14, 2009 CO_KEUB_JPN_Execute Plan Assessment.udc

3/11

Page 4: CO KEUB JPN Execute Plan Assessment

Work Instruction KEUB - JPN - Execute Plan Assessment

7. Double-click the Transfer Cost Center Planning/Process Planning node .

8. Double-click the KEUB - Assessment node .

Execute Plan Assessment: Initial Screen

9. Click the Period edit field .

10.

As required, complete/review the following fields:

Tuesday, July 14, 2009 CO_KEUB_JPN_Execute Plan Assessment.udc

4/11

Page 5: CO KEUB JPN Execute Plan Assessment

Work Instruction KEUB - JPN - Execute Plan Assessment

Field R/O/C Description

Period R Unit of time into which a fiscal year is subdivided. Company data can be analyzed on a particular date in each period. In accounting, a fiscal year can be subdivided into a maximum of 16 periods. The fiscal year itself is a period. Example: 005

11.

Click the Period To edit field .

12.

As required, complete/review the following fields:

Field R/O/C Description

Period To R Unit of time when the activity ends. Example: 005

13.

Click the Fiscal Year edit field .

14.

As required, complete/review the following fields:

Field R/O/C Description

Fiscal Year R Period, 12 months as a rule, for which the company is to create its inventory and balance sheet. The fiscal year can be the same as the calendar year, but does not have to be. Example: 2008

15.

Click the Cycle edit field .

16.

Click the Cycle possible entries button .

Tuesday, July 14, 2009 CO_KEUB_JPN_Execute Plan Assessment.udc

5/11

Page 6: CO KEUB JPN Execute Plan Assessment

Work Instruction KEUB - JPN - Execute Plan Assessment

Cycle (1) 18 Entries found 18 Entries found

17.

Double-click the OpCo ID01 item .

Tuesday, July 14, 2009 CO_KEUB_JPN_Execute Plan Assessment.udc

6/11

Page 7: CO KEUB JPN Execute Plan Assessment

Work Instruction KEUB - JPN - Execute Plan Assessment

Execute Plan Assessment: Initial Screen

18.

Click the Test Run check box .

Tuesday, July 14, 2009 CO_KEUB_JPN_Execute Plan Assessment.udc

7/11

Page 8: CO KEUB JPN Execute Plan Assessment

Work Instruction KEUB - JPN - Execute Plan Assessment

Execute Plan Assessment: Initial Screen

19.

Click the Execute button .

Tuesday, July 14, 2009 CO_KEUB_JPN_Execute Plan Assessment.udc

8/11

Page 9: CO KEUB JPN Execute Plan Assessment

Work Instruction KEUB - JPN - Execute Plan Assessment

Execute Plan Assessment: Initial Screen

20.

Click the Exit button .

Tuesday, July 14, 2009 CO_KEUB_JPN_Execute Plan Assessment.udc

9/11

Page 10: CO KEUB JPN Execute Plan Assessment

Work Instruction KEUB - JPN - Execute Plan Assessment

Result

You have successfully executed a plan assessment.

Tuesday, July 14, 2009 CO_KEUB_JPN_Execute Plan Assessment.udc

10/11

Page 11: CO KEUB JPN Execute Plan Assessment

Work Instruction KEUB - JPN - Execute Plan Assessment

Scenario

Instructions In this simulation you are required to:

Execute plan assessment.

Required Data

This section provides the field data required to complete this exercise. Refer to this data sheet as necessary while performing the exercise.

Field Value

Period 005

Period To 005

Fiscal Year 2008

Cycle ID5401

Tuesday, July 14, 2009 CO_KEUB_JPN_Execute Plan Assessment.udc