ATLAS + NA62

DIRK MERGELKUHL

Dirk MERGELKUHL| SU pendant LS1 day| 07.11.2012| EDMS 1250936| page 2

Quoi (quelles activités prévues pendant le LS1)

• The main works for ATLAS are measurements for: Opening of detector

Update of infrastructure (3D + levelling)

Muon EEL installation on A-side

Muon EES installation on A-side

Pixel detector and beampipe (VI) extraction

Pixel works in SR1 (surface)

Muon chambers in sector 13

Update of infrastructure (3D + levelling)

Installation of Pixel, IBL and new VI

Detector closing

Experience shows that the non-planned activities can be substantial

• In parallel the analysis and reports for above mentioned works

Dirk MERGELKUHL| SU pendant LS1 day| 07.11.2012| EDMS 1250936| page 3

Comment (quelles sont les procédures ?)

• In general as previous installation works but modifications to adapt to the actual situation in the cavern are expected.

Update of SU infrastructure will be done as previously but AT401 replaces TC2002

Detector opening and closing measurements as in previous Technical Stops

For EEL and EES installation equivalent to C-side in TS 2011/12

Muon in sector 13 as installation of Muon barrel in 2004-2007

Works for Pixel and VI replacement partly as for initial installation or as for scale one mock-up in building 180. Some details need still to be defined!

Dirk MERGELKUHL| SU pendant LS1 day| 07.11.2012| EDMS 1250936| page 4

Matériel

• Mainly identical as use for the construction and last Technical Stops including most of the tooling.

• The AT401 should replace TC2002 as often as necessary (or possible) to gain in precision or time following the need.

• Waiting for offers for AT401 prism supports from main workshop

• Instruments: TC2002, NA2, D2x, AT401

• Software: Carnet4000, PCTOPO32, AICON 3D Studio, Spatial Analyzer

Dirk MERGELKUHL| SU pendant LS1 day| 07.11.2012| EDMS 1250936| page 5

Quand (planning des activités)

• Our planning has to follow mainly the ATLAS planning:Opening process 41.06 days Thu 07.02.2013Thu 14.03.2013UX15 opened for access 0 days Mon 11.02.2013Mon 11.02.2013Side A 40.06 days Thu 07.02.2013Wed 13.03.2013

-          5 days Measurement of geometrical network (update) Mon 11.02.2013Fri 15.02.2013-          Measurement of TAS-A before opening of detector (reference for VI and for closure) Mon 11.02.2013Mon 11.02.2013

Removing of TAS survey device 1 hr Mon 11.02.2013Mon 11.02.2013-          Measurement of TAS-C before opening of detector (reference for VI and for closure) Mon 11.02.2013Mon 11.02.2013

Removing of TAS survey device 1 hr Mon 11.02.2013Mon 11.02.2013Survey of monobloc A -1 Wed 13.02.2013Wed 13.02.2013Survey of monobloc C -1 Wed 13.02.2013Wed 13.02.2013EE installation side A 63.5 days Thu 14.02.2013Tue 23.04.2013Survey of monobloc C -2 Fri 15.02.2013Fri 15.02.2013

-          4 days Stability of ground Mon 18.02.2013Thu 28.02.2013Survey of monobloc A -2 Tue 19.02.2013Tue 19.02.2013EEL installation 30.33 days Tue 19.02.2013Tue 19.03.2013Survey S15 Tue 19.02.2013Tue 19.02.2013Survey S1 Mon 25.02.2013Mon 25.02.2013

-          Installation of T2 for EBA opening (beampipe) Tue 26.02.2013Tue 26.02.2013-          Installation of T2 for EBC opening (beampipe) Wed 27.02.2013Wed 27.02.2013-          3 days network for VI measurement Wed 20.02.2013Fri 22.02.2013

VI-A survey Fri 01.03.2013Mon 04.03.2013VI-C survey Fri 01.03.2013Fri 01.03.2013Survey S1 Mon 04.03.2013Mon 04.03.2013

-          2 days Stability of feet Tue 05.03.2013Wed 06.03.2013Survey S9 Thu 07.03.2013Fri 08.03.2013Survey S7 Fri 08.03.2013Fri 08.03.2013Survey S9 Mon 11.03.2013Tue 12.03.2013Survey S7 4 Tue 12.03.2013Wed 13.03.2013EES side A 25.21 days Mon 18.03.2013Wed 17.04.2013

-          Measurement of EES12 before final adjustment-          Measurement of EES10 before final adjustment-          Measurement of EES08 before final adjustment-          Measurement of EES06 before final adjustment-          Measurement of EES14 before final adjustment-          Measurement of EES16 before final adjustment-          Measurement of EES02 before final adjustment-          Measurement of EES04 before final adjustment

Dirk MERGELKUHL| SU pendant LS1 day| 07.11.2012| EDMS 1250936| page 6

Quand (planning des activités)

• Our planning has to follow mainly the ATLAS planning:

Rails installation & survey Wed 27.03.2013Wed 27.03.2013Survey and adjustment ID rotation stage Thu 28.03.2013Thu 28.03.2013Survey and adjustment of Pit table Thu 28.03.2013Fri 29.03.2013Survey and adjustment of DST Mon 01.04.2013Tue 02.04.2013

-          Measurement of TX1STF-A (at beginning) Wed 03.04.2013Wed 03.04.2013-          Measurement of TX1STF-C (at beginning) Thu 04.04.2013Thu 04.04.2013-          4 hours Maintenance of HLS system Fri 05.04.2013Fri 05.04.2013-          Measurement of maximum of BOL/BOS/BML/BMS/BIL/BIS chambers

New chambers sector 13 220.75 days Fri 01.03.2013Mon 02.12.2013-          Adjustment of Muon brackets/rails BOS Sector 13 A-          Adjustment of Muon brackets/rails BOS Sector 13 C-          Adjustment of Muon brackets/rails BME Sector 13 A-          Adjustment of Muon brackets/rails BME Sector 13 C-          Adjustment of chamber BOS Sector 13 A-          Adjustment of chamber BOS Sector 13 C-          Adjustment of chamber BME Sector 13 A-          Adjustment of chamber BME Sector 13 C-          Installation of automatic HLS control system in trench C- Installation and calibration of BCAM system

Installation of new positioning system 20 days Mon 27.01.2014Wed 19.02.2014-          4 days Stability of ground (before VI and Pixel installation)-          5 days Measurement of geometrical network (update before VI and Pixel installation)-          3 days local network for VI and Pixel installation

Pixel Installation 14.63 days Fri 21.03.2014Wed 09.04.2014Align DST to PST Wed 26.03.2014Wed 26.03.2014Package Injection & Transfer to PST Fri 28.03.2014Wed 02.04.2014

Dirk MERGELKUHL| SU pendant LS1 day| 07.11.2012| EDMS 1250936| page 7

Quand (planning des activités)

• Our planning has to follow mainly the ATLAS planning:Close EBA and JD-A 9.63 days Fri 18.07.2014Wed 30.07.2014

-          Installation of T2 for EBA closure (beampipe) Mon 28.07.2014Mon 28.07.2014EBA survey Mon 28.07.2014Mon 28.07.2014Survey JD-A + decision Wed 30.07.2014Wed 30.07.2014Fixed point survey Thu 31.07.2014Thu 31.07.2014Survey ECT-A + decision Fri 01.08.2014Mon 04.08.2014

-          Installation of T2 for EBC closure (beampipe) Fri 01.08.2014Fri 01.08.2014EBC survey Fri 01.08.2014Mon 04.08.2014

-          Survey of Monobloc-A during closure operation (without load of JFC1-3)Survey of VT-A Tue 12.08.2014Tue 12.08.2014

-          Survey of VJ-A Tue 12.08.2014Tue 12.08.2014-          Survey of LUCID-A-          Survey of Monobloc-A during closure operation (with load of JFC1-3)

Survey JD-C + decision Wed 27.08.2014Wed 27.08.2014-          Survey of VA-C fixed point during closure operation

Survey ECT-C + decision Thu 04.09.2014Fri 05.09.2014-          Survey of Monobloc-C during closure operation (without load of JFC1-3)

Survey VJ & VT Fri 12.09.2014Fri 12.09.2014-          Survey of LUCID-C-          Survey of Monobloc-C during closure operation (with load of JFC1-3)-          Measurement of TX1STF-A (close to end)-          Measurement of TX1STF-C (close to end)-          1.5 days LArg stability measurement

Beam pipe bake-out filled with Ne) 10 days Fri 12.09.2014Thu 25.09.2014Survey of TAS (checking) Mon 06.10.2014Mon 06.10.2014Survey of TAS and adjustment Fri 10.10.2014Mon 13.10.2014Cleaning of side C 2 days Fri 24.10.2014Tue 28.10.2014

- works in SR1 for the Pixel and/or VI-          Alignment of the DST (in SR1 Dec  ‘12)-          ITT alignment (in SR1 Dec ‘12)-          Alignment of the ITT w.r.t. DST ( in SR1 Feb ’13)-          Survey of the IST w.r.t the Pixel mounts (in SR1 March ’13)-          Adjustment of the Pixel mounts (in SR1 Late ’13)-          Alignment of the DST  w.r.t. ITT ( in SR1 Late ’13)

Dirk MERGELKUHL| SU pendant LS1 day| 07.11.2012| EDMS 1250936| page 8

Par qui (quelles sont les personnes qui vont intervenir)

• Dirk MERGELKUHL

• Vitali BATUSOV (100%)

• Mikhail LYABLIN (partly)

• Additional Russian person to replace Mikhail (partly)

• Contract personnel

• Others following needs and availability

Dirk MERGELKUHL| SU pendant LS1 day| 07.11.2012| EDMS 1250936| page 9

Status de la préparation/problèmes non résolus

• Different measurements are well integrated in ATLAS planning

• Level of radiation unknown for beampipe measurements

• Targets and supports for VT beampipe still in design phase (ATLAS)

• Procedure to open UPS doors to LHC not really clear

• Full integration of AT401 including transfer to LGC and automation

• BCAM system for ATLAS closure still in design phase (ATLAS+SU)

Dirk MERGELKUHL| SU pendant LS1 day| 07.11.2012| EDMS 1250936| page 10

Quoi (quelles activités prévues pendant le LS1)

• The main works for NA62 are measurements for: GTK

STRAW 2, 3 and 4

RICH

LAV 8-12

Vac Tank 1, 2a, 2b, 3a, 3b

IRC

MUV1

Network update

Measurement of detectors before start

• In parallel the analysis and reports for above mentioned works

Dirk MERGELKUHL| SU pendant LS1 day| 07.11.2012| EDMS 1250936| page 11

Quand (planning des activités)

• Our planning has to follow the NA62 planning: Autumn 2013 MUV1 and SAC

Sep-Oct 2013 RICH Vessel installation, mirror and PMT after that

Summer/Autumn 2013 Straw 1+2, LAV9

Spring 2014 Straw 3+4, LAV10+11+12, IRC, Vac Tanks, CHOD

Summer 2014 Control and final adjustments

Time estimation ~ 4-6 month for a team + reports and analysis

To be ready for data taking September 2014Par qui (quelles sont les personnes qui vont intervenir)

• Mateusz BORUCHOWSKI

• Dirk MERGELKUHL

• Others following needs and availability

Dirk MERGELKUHL| SU pendant LS1 day| 07.11.2012| EDMS 1250936| page 12

Statut de la préparation/problèmes non résolus

• Planning less detailed than LHC experiments

• Some parts in design phase

• So far regular delays for nearly all parts

Matériel

• Mainly identical as use as before technical run.

• The AT401 could replace TC2002 if helpful for certain measurements

• Instruments: TC2002, NA2, AT401

• Software: Carnet4000, PCTOPO32, Spatial Analyzer

Dirk MERGELKUHL| SU pendant LS1 day| 07.11.2012| EDMS 1250936| page 13

Conclusion

• Works for ATLAS are well understood and prepared

• Open issues are mostly linked to beampipe replacement where some late decisions are still outstanding

• LS1 will be charged but different than a xmas-TS for these 18 months

Reports must be done in parallel

ATLAS works only partly in two shifts

• From the actual planning the simultaneous intensive periods for ATLAS+NA62 are spring 2014 and autumn 2014

From experience delays could be possible for NA62

Main concentration with very charged period at end of LS1