santa rita jail going off the grid
DESCRIPTION
Santa Rita Jail Going off the Grid. Alameda County/RESCO CCAEA Meeting February 5, 2010. The Energy Program Team. Established in 1987 GSA/TSD 1 Program Manager 1 Project Manager 2 Electrician/Construction Coordinators Project and Cost Savings Oriented Minimum 10% IRR. Accomplishments. - PowerPoint PPT PresentationTRANSCRIPT
Santa Rita JailSanta Rita Jail Going off the GridGoing off the Grid
Alameda County/RESCO Alameda County/RESCO CCAEA MeetingCCAEA Meeting
February 5, 2010February 5, 2010
The Energy Program TeamThe Energy Program Team
Established in 1987GSA/TSD
1 Program Manager 1 Project Manager 2 Electrician/Construction
Coordinators Project and Cost Savings
Oriented Minimum 10% IRR
AccomplishmentsAccomplishments
$ Total Energy Saving Capital Projects Value = $50 M
$ Total Energy Incentives and Refunds = $28 M
$ Current Annual Utility Budget = $11.5 M
$ Current Annual Energy Cost Avoidance = $7.5 M
Energy Program: 1987-2010Energy Program: 1987-2010
Juvenile Justice Center LEED Gold 2007
Results
SSaanta Rita Jail, Dublin, CAnta Rita Jail, Dublin, CA
Construction 1984-1989 Occupied Space:
1 million sqft.
Peak Electrical Load: 3.2
mW (8/00) 18 Housing Units 4300 inmates 513 Sheriff’s Dept. staff 80 GSA staff
SSaanta Rita Jailnta Rita Jail
2007 Utility Cost Electricity: $ 980,000 Natural Gas: $ 900,000 Water: $ 860,000 Sewage: $ 540,000 Total: $ 3,280,000
(35% of GSA’s Utility Costs)
Fluorescent Lighting and Fluorescent Lighting and Exhaust Fan Motor Retrofit (1995) Exhaust Fan Motor Retrofit (1995)
9,000 Efficient Light Fixtures Retrofitted 600 Energy Efficient Motors Replaced
Largest Rooftop Solar Power Systemon a Government Facility (2002)
$450K Annual Energy Cost Savings, 10% of Energy Used from the Sun
The Chilled Water Plant RetrofitThe Chilled Water Plant Retrofit
Cool Roof ApplicationCool Roof Application
First MegaWatt Class Fuel Cell First MegaWatt Class Fuel Cell Cogeneration Plant (2006)Cogeneration Plant (2006)
Santa Rita Jail Integrated Energy & Santa Rita Jail Integrated Energy & Water Efficiency Project (2009):Water Efficiency Project (2009):
Hot Water Boiler Plant Renovations
Four High Efficiency Boiler 2 Domestic Hot Water Heat Exchangers
Santa Rita Jail:Santa Rita Jail: Reduced Hot Water Temperature
54 New Hot Water Coils 52 New Hot Water Expansion Compensators
Santa Rita Jail:Santa Rita Jail: Lighting Retrofit
Gym before retrofit Gym after retrofit
Retrofitted • 9000 Florescent Lighting Fixtures
Replaced • 250 HID with Fluorescent Fixtures
Permanently Delamped • 7000 Fluorescent Lamps
Santa Rita Jail:Santa Rita Jail: Water Efficiency Retrofit
Retrofitted • 1400 Inmate Flush Valves • 1400 Inmate Lavatory Valves • 150 Inmate Showers Valves
Replaced • 160 Staff/Public Toilets • 30 Staff/Public Urinals• 210 Staff/Public Sink Aerators• 30 Staff Showerheads• 8 Smart Irrigation Controllers
Santa Rita Jail:Santa Rita Jail: Laundry Water and Heat Reclamation
Santa Rita Jail:Santa Rita Jail: Cooling Tower Water Treatment
Santa Rita Jail Santa Rita Jail Energy & Water Efficiency ProjectsEnergy & Water Efficiency Projects
(1993 – 2009)(1993 – 2009)
Results $1.7M in Yearly Electrical Cost
Savings: 65% Reduction
$285K in Natural Gas Cost Savings: 40% Reduction
$540K in Water/Sewage Cost Savings: 50% Reductions
Santa Rita Jail:Santa Rita Jail: Day Room Induction Lighting Retrofit
(Feb 2010)
250W/400W Existing Metal Halidebefore retrofit
120W Retrofitted Induction after retrofit
Retrofit• 864 Lighting Fixtures
Savings • 243 kW Demand Reduction•1.7M kWh Energy Reduction
Santa Rita Jail: Santa Rita Jail: SmartGrid (2010)
22
Project PartnersProject Partners
Alameda County, California - Santa Rita Jail
Chevron Energy Solutions
And…
Existing 1.2MW
Solar PV
Existing 1.0MW
Fuel Cell
SRJ Smart Grid Project
New 12kW Wind Power
New Solar Thermal
New 2MW Battery
Smart Grid
• True system integration of renewable and clean distributed energy resources
• Superior Utilization and Control of renewable and clean distributed energy resources
• Improved local utility grid stability, and demand response
• Improved local power quality and reliability
• Off-grid Island capability
• Energy price arbitrage capability
• Demand Response Capabilities
Project Goals
Facility Energy Efficiency MeasuresReduction
of DHWEnergy Load
25
System Design – Load ImpactsSystem Design – Load Impacts Cloudy Spring Day – Solar Output UnevenCloudy Spring Day – Solar Output Uneven
0
500
1000
1500
2000
2500
3000
3500
0 3 6 9 12 15 18 21
Hour of Day
Ele
ctri
c P
ow
er (
kW)
x
Battery Charging
Battery Discharging
Photovoltaics
Net PG&E Meter Load
Fuel Cell
Santa Rita JailSanta Rita JailSmart Grid ProjectSmart Grid Project
Total Project Cost: $12,100,000
Funding: DOE Grant: $ 6,200,000 RESCO Grant: $ 1,980,000 PG&E Incentive $ 3,000,000 Chevron ES Share: $ 120,000 PG&E Share: $ 350,000 County Share: $ 450,000