our annual report for web

Upload: gianluca-tonolo

Post on 06-Apr-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/2/2019 OUR Annual Report for Web

    1/69

  • 8/2/2019 OUR Annual Report for Web

    2/692 Ofce of Utilities Regulation / Annual Report & Financial Statements 2010 - 11

    A n n u A l R e p o R t 2 0 1 0 - 2 0 1 1

    Organisation Chart

    Mission Statement

    Introduction & Objectives

    Director Generals Statement

    SECTOR REPORTS

    Consumer & Public Affairs

    Electricity

    Telecommunications

    Water & Sewerage

    Transportation

    Administration/Human Resources

    Key Performance Indicators (KPI)

    Outlook and Work Programme for Fiscal 2011/2012

    FINANCIAL STATEMENTS Year ended March 31, 2011

    Index

    Independent Auditors Report to the Members

    FINANCIAL STATEMENTS

    Statement of Comprehensive Income

    Statement of Financial Position

    Statement of Change in Reserves

    Statement of Cash Flows

    Notes to the Financial Statements

    SUPPLEMENTARY INFORMATION

    Statement of Income

    Schedule of Expenses

    2

    3

    4

    5

    10

    12

    17

    24

    26

    26

    27

    29

    31

    32

    35

    36

    37

    38

    39-66

    67

    68

    contents

  • 8/2/2019 OUR Annual Report for Web

    3/693 Ofce of Utilities Regulation / Annual Report & Financial Statements 2010 - 11

    organisationchart

  • 8/2/2019 OUR Annual Report for Web

    4/69

    To contribute to national development by creating

    an environment for the ecient delivery of utility

    services to the customers whilst ensuring that

    service providers have the opportunity to make a

    reasonable return on investment.

    MISSION STATEMENT

    Ofce of Utilities Regulation / Annual Report & Financial Statements 2010 - 11 3

  • 8/2/2019 OUR Annual Report for Web

    5/69

    INTRODUCTIONThe Oce of Utilities Regulation Act of 1995established the Oce of Utilities Regulation(the Oce/OUR) as a body corporate.Under the Act, the OUR is charged with theresponsibility of regulating the provision ofutility services in the following sectors:

    Electricity

    Telecommunications

    Water & Sewerage

    Public transportation by road, railand ferry

    OBJECTIVES To ensure that consumers of utility

    services enjoy an acceptable qualityof service at reasonable cost.

    To establish and maintain transparent,consistent and objective rules for theregulation of utility service providers.

    To promote the long-term ecientprovision of utility services for

    national development consistent withGovernment policy.

    To provide an avenue of appeal forconsumers who have grievances withthe utility service providers.

    To work with other related agenciesin the promotion of a sustainableenvironment.

    To act independently and impartially.

    THE OFFICEThe Director General and Deputy DirectorsGeneral comprise The Oce. The DirectorGeneral is appointed by the GovernorGeneral and the Deputy Directors Generalare appointed by the Prime Minister.

    This, the Fourteenth report of the Oce,will inform Parliament and the country atlarge of the regulatory activities of the OURfor the calendar year 2010 and its nancialoperations for the scal year April 1, 2010 toMarch 31, 2011.

    Ofce of Utilities Regulation / Annual Report & Financial Statements 2010 - 115

  • 8/2/2019 OUR Annual Report for Web

    6/696

    A n n u A l R e p o R t 2 0 1 0 - 2 0 1 1

    Ofce of Utilities Regulation / Annual Report & Financial Statements 2010 - 11

    The Annual Report is an opportunity to give an account

    to our stakeholders by providing an assessment of

    what has been achieved, the current priorities, the

    challenges ahead and the plans in place to meet them.

    The report also intends to provide information to allow

    a discerning public to make a judgement about therelevance and value of the work that the OUR seeks to

    accomplish.

    The OUR has been selected, based on its advanced

    strategic preparation, as one of the initial twelve (12)

    entities to be accorded full devolution. This will put

    the OUR in a better position to assume signicant

    control over its nancial and human resources and be

    accountable for agreed objectives.

    Even before the decision to grant devolution, theOUR had developed strategic plans to dismantle

    professional silos that required the technical sta being

    assigned and working primarily according to sectors.

    An emphasis of the OURs approach going forward, is

    to deploy professionals seamlessly across the various

    utility sectors over which the Oce exercises its remit.

    We committed last year to ensuring that the OUR

    acts in tandem with its mission statement. Within this

    context six mission critical objectives were established

    viz:

    1. Lowering utility costs (particularly electricity)

    and improving competitiveness:

    The process for achieving this objective is nowunderway. The tender process to procure 480

    megawatts of generating capacity weighted in favour

    of natural gas, commenced during the year. At the

    time of preparation of this report the OUR was in the

    process of commissioning evaluation of competitive

    bids for this capacity. It is worth noting that this is

    the rst time in decades that the power sector has

    embarked on a planned and timely expansion and a

    retirement schedule. Commissioning more ecient

    generation capacity is of course only one critical part

    of the equation for lowering electricity generation

    costs.

    It is equally important to focus on the procurement

    of fuel which represents about 65% of the cost of

    electricity and is a direct pass through to customers. To

    this end, the OUR has highlighted to the government

    the need to put in place a mechanism for regulatory

    oversight of the procurement of fuel and its pricing. It

    is envisaged that this will cover:

    competitive sourcing, access

    to scarce infrastructure

    (docking, loading and

    storage) and determination

    of appropriate indexation

    mechanisms for reference

    prices/freight, insurance

    and ocean losses. The OUR

    also takes the position that

    a review of the Common

    External Tari as it applies

    to fuel prices is desirable

    dirctor nrlssttmnt

    ... the OUR has

    highlighted to thegovernment the

    need to put in place

    a mechanism for

    regulatory oversight

    of the procurement of

    fuel and its pricing.

  • 8/2/2019 OUR Annual Report for Web

    7/697 Ofce of Utilities Regulation / Annual Report & Financial Statements 2010 - 11

    A n n u A l R e p o R t 2 0 1 0 - 2 0 1 1

    as its removal would see an immediate reduction in

    electricity rates.

    2.Modernizing the countrys utility

    infrastructure and ensuring greater

    availability of services at economic rates:

    The OURs eort in this regard is on-going. Last year

    we reported on the initiative taken to speed up the

    deployment of smart meters in the electricity sector

    by the earmarking of a special fund in the electricity

    tari for this purpose. It is anticipated that smartmeters and ultimately the development of a smart grid

    will inter alia: allow for better control of losses, enable

    easier switching by customers, enhance customers

    ability to monitor and adjust consumption, reduce

    theft and improve information ows to customers as

    well as receive accurate actual readings and bills. A

    recent publication by the European Regulatory Group

    for Electricity and Gas noted that Due to the fact that

    smart meters are included in the IT-Infrastructure of the

    network operator, there exists a high potential for process

    optimization and savings in operational costs. Using the

    synergies could also lead to further benets.

    We are also of the view that the use of Smart Meters

    is one of the critical indicators of the growing

    phenomenon of utilities convergence which

    is further revolutionizing how services are

    received and costs allocated to the public.

    In this regard the OUR has indicated that

    the call in some quarters to separate

    telecommunications regulation from

    electricity is not only likely to increase

    the total cost of regulation and weaken

    regulatory capacity but is also counter tothe emerging trend with regard to utilities

    convergence. This is manifested by such

    phenomenon as the delivery of broadband

    over the copper line and the use of common

    billing and network security systems for

    utilities, as well as the development of

    smart grids that would allow integration of renewables

    into the supply system.

    3. Speeding up the turnaround time for

    decision making:

    The impending move to de-concentration of authority

    and the utilization of the necessary IT tools will assist

    in this area. The de-concentration of authority will

    eliminate the long delays often encountered in

    operationalizing decisions because of the need to

    obtain administrative approval from the Ministry ofFinance and or the Cabinet Oce. For its part, the

    improved IT infrastructure will allow sta real time

    internal access to data thereby reducing turnaround

    time for projects and instantaneous responses to

    requests for information and statistics. The OUR is also

    constantly reviewing its own internal processes with a

    view to reducing the time taken to make and enforce

    decisions and to secure redress for the public.

    4. Serving as a central repository for easily

    accessible information to inform all utility

    related decisions and stakeholders:

    Assistance provided by the Inter-American

    Development Bank (IDB) has been pivotal to

    the attainment of this objective. The process

    to engage consultants to provide

    recommendations, training and assist

    with procurement and installation of

    relevant hardware and software took

    place during the year. Training has

    begun, some hardware and software

    have been acquired and the process of

    building and conguring the network is

    underway. The OUR intends to appoint

    a highly qualied Chief Information

    Ocer/Director IT to develop and

    manage the relational database. It is

    anticipated that the OUR will be able to

    transition to this database within the

    next period.

    ... to separatetelecommunications

    regulation from

    electricity is not onlylikely to increase

    the total cost of

    regulation andweaken regulatory

    capacity but is

    also counter to theemerging trend with

    regard to utilities

    convergence.

  • 8/2/2019 OUR Annual Report for Web

    8/698

    A n n u A l R e p o R t 2 0 1 0 - 2 0 1 1

    Ofce of Utilities Regulation / Annual Report & Financial Statements 2010 - 11

    5. Improving efciency and effectiveness

    through a comprehensive monitoring

    system:

    A Utility Monitoring Division has been established and

    staed. While its role and functions are still evolving,

    the Division has identied several priority areas

    across the regulated sectors. These include intensive

    regulatory oversight of a multi-billion dollar eciency

    improvement programme in the water sector and a

    multimillion US dollar energy eciency improvement

    programme for JPSCo. In collaboration with theRegulation and Policy Division, arrangements for the

    development and publication of a number of standard

    data reports on the regulated utilities are at various

    stages of completion. Indeed quarterly data reports

    for the telecommunications sector are already a part

    of the reporting regime and those for electricity and

    water should come on stream in the next scal year.

    6. Delivering tangible benets to

    consumers and easing social disaffection:

    The OUR continues its drive to increase the awareness

    of and the consumers participation in the Guaranteed

    Standards scheme. The scheme represents an agreed

    minimum level of service to be provided by a utility

    to the consumer. The Oce continues to monitor the

    number of breaches committed by the utilities and

    ensures that the consumers are given the requisite

    compensation where a claim is led. Compensation

    to the consumer is also

    accomplished using an

    automatic mechanism

    for some of the

    guaranteed standards.

    This was introduced for

    the NWC in 2008 and the

    JPS in 2010.

    The Oce also

    recognises that the

    continued engagement

    of its stakeholders is

    critical to its decision making process. The traditional

    means of consultation with our stakeholders such

    as media workshops and public fora are still being

    employed. However, we will have more in- depth

    consultations and exchange of ideas on an on-going

    basis with industry and sector leaders.

    RENEABLE ENERY

    The OUR is cognisant of the limitations of

    renewables for a country such as Jamaica, given

    such considerations as high initial investment costs,

    limited capacity to oer subsidies, the nascence of

    the various technologies and in some instances their

    unsuitability as base load capacity. Even so, increasing

    the contribution of the renewables as a portion of

    the countrys power capacity is a vital objective

    given the need for diversication, reduced fossil

    fuel dependency, savings on foreign exchange and

    protection of the environment. In this regard the OUR

    notes with some satisfaction that during the year, theJPS commissioned its wind turbines at Munro College

    and completed signicant work on its proposed hydro

    plant at Maggotty, both in St. Elizabeth.

    Wigton has also concluded an agreement with JPS

    for the commissioning of its fourteen megawatt (14

    MW) wind farm. This cleared the way for the Oce to

    recommend to the Minister of Energy and Mining the

    issuance of a license for the facility. Wigton has also

    submitted a new request to the Oce for a license for

    an additional four megawatt (4MW) plant.

    The development of a policy on net billing on which

    there has been extensive consultation during the

    year is far advanced. The OUR anticipates that the

    promulgation of such a policy with a standard oer

    contract for capacity below 100 kW will provide a llip

    to persons or entities wishing to invest in renewables

    for small capacities.

    The Oce continues

    to monitor the

    number of breachescommitted by the

    utilities and ensures

    that the consumersare given the requisite

    compensation where

    a claim is led.

  • 8/2/2019 OUR Annual Report for Web

    9/699 Ofce of Utilities Regulation / Annual Report & Financial Statements 2010 - 11

    A n n u A l R e p o R t 2 0 1 0 - 2 0 1 1

    The matter of the OURs Declaration of the Avoided

    Cost of Generation has been the subject of some

    misunderstanding. It is therefore important to

    underscore that the calculation of avoided cost is a

    technical exercise and the tari that is established

    by that process is not in and of itself a tool for the

    encouragement of renewables. Ultimately, what

    determines the level of renewables is policy backed

    by legislation and a determination of what level of

    subsidy and or incentive is appropriate to attain the

    desired target for renewables as a percentage of

    total electricity supply. In this regard, we continueto encourage the government to move beyond the

    statement of a policy for the promulgation of the

    statutory framework to ensure attainment of the

    desired levels of investment.

    Natural as Project

    Although not falling directly within its remit, the OUR

    was called upon to provide advice, recommendations

    and expert assistance to the government with respect

    to the introduction of Natural Gas into Jamaicas

    energy supply mix. There will be a requirement tobuild new Infrastructure to facilitate the transition to

    Natural Gas as a main source of fuel for the generation

    of power using combined cycle technology. However,

    before natural gas can be introduced into the countrys

    energy supply mix, an appropriate natural gas policy,

    legislation and regulatory framework must be put in

    place. The Oce has been active in providing advice

    on the statutory and regulatory framework that is

    required for facilitating investment in the construction

    of natural gas facilities and the

    integration of natural gas as a major

    source in the countrys fuel mix. Inpreparation to regulate a Natural

    Gas Sector, the OUR has already

    begun to expose and train its sta

    with respect to issues in Natural Gas

    regulation and has also begun to

    develop the appropriate links and

    networks with international bodies

    and regulatory agencies involved

    in this industry. In fact I am a member of National

    Association of Regulatory Utility Commissioners

    (NARUC) Committee on Natural Gas.

    Management Accountability Framework

    The priorities outlined above are also reected in

    the Management Accountability Framework to

    which the OUR is committed as part of the Public

    Sector Transformation initiative. The policies and

    programmes, objectives, indices and deliverables set

    out in the Management Accountability Frameworkwill, in the next reporting period and beyond, be

    the benchmark for assessing the OURs performance.

    Among the major commitments set out in the

    Framework document are:

    The attainment of a raft of legislative changes

    aimed at accelerating the speed with which

    matters are addressed, mandating minimum

    quality standards, enhanced enforcement

    powers and options, set timelines for tasks and

    increased reporting against established targets

    and indices.

    Provisions for assessing and measuring customer

    satisfaction, for on-going and constructive

    engagement of stakeholders including the

    development of a citizens charter and the

    adoption of measures and mechanisms to enhance

    both internal and external accountability;

    Specic measures to enhance the development

    and orientation of the sta and the OUR toward

    delivering better regulation in the public

    interest and value for money in terms of the

    regulatory budget;

    Greater focus on risk management to ensure

    the sustainability of the OUR, its adaptability to

    contingency and its eectiveness in mitigating

    the adverse eects of imponderables in the

    regulated sectors.

    ... an appropriatenatural gas

    policy, legislationand regulatory

    framework must be

    put in place.

  • 8/2/2019 OUR Annual Report for Web

    10/6910

    A n n u A l R e p o R t 2 0 1 0 - 2 0 1 1

    Ofce of Utilities Regulation / Annual Report & Financial Statements 2010 - 11

    Zia Mian

    Director enral

    Notably, as part of the commitment to ensuring

    accountability, the OUR has followed through on

    its promise to establish an Audit Committee. That

    Committee is up and running and has already

    provided several recommendations for improving

    operations. Specic arrangements were also made

    for an internal audit function during the year and

    the Policy and Procedures Manual which addresses

    both internal and external elements of the Oces

    operations is under review. The updated manual

    will be in place by the end of the next reporting

    period. The OUR has also embarked on obtaining ISOcertication to establish procedures to deliver high

    quality service to all stakeholders.

    Im also pleased to be serving as Chairman of

    the Organisation of Caribbean Utility Regulators

    (OOCUR) and as 1st Vice Chair of the Commonwealth

    Telecommunications Organisation (CTO). In the

    capacity as Chairman of OOCUR, it was my pleasure

    to have hosted the Organisations 8th annual

    conference as well as a council meeting and general

    assembly in Ocho Rios, St. Ann in November. The

    three-day conference saw a number of regional andinternational participants and was ocially opened

    by the Deputy Prime Minister Dr. the Honourable

    Kenneth Baugh. Feedback from participants

    indicated that the conference was successful.

    CONCLUSION

    I remain convinced that

    no matter the challenges

    and uncertainties of the

    regulatory environment,

    the regulator must

    maintain as its primary

    focus, enhancing and

    protecting the public

    interest. In the medium

    to long term, thetrue measure of this is

    reected in: on-going utility

    investments (expected to be over US$ 1.2 billion),

    utility markets that are dynamic and innovative,

    expanded services to customers and the delivery

    of these at lower economic cost and with better

    customer service. The OUR is committed to these

    objectives and I rmly believe that the institution

    has the orientation and the personnel to deliver

    on this mandate. I also anticipate that those who

    have the ability to inuence our resources and to

    create and facilitate an environment conducive tothe delivery of our mandate will provide us with the

    requisite support and necessary tools. I look forward

    to another successful year.

    ... the regulatormust maintain as

    its primary focus,enhancing and

    protecting the

    public interest.

  • 8/2/2019 OUR Annual Report for Web

    11/6911 Ofce of Utilities Regulation / Annual Report & Financial Statements 2010 - 11

    A n n u A l R e p o R t 2 0 1 0 - 2 0 1 1

    CONSUMER & PUBLIC AFFAIRS

    The Consumer and Public Aairs (CPA) Division, in

    keeping with its mandate, continued its eorts at

    ensuring that the interests of utility consumers were

    adequately protected throughout the year. The Public

    Aairs arm of the division continued its aggressive

    public education programme through its media

    information sharing sessions, mass media productions

    and remained active in developing and maintaining

    relationships among stakeholder groups.

    Appeals

    For the 2010 calendar year, the division accepted

    for investigation, one hundred and thirty-nine

    (139) new appeals. In addition to the new appeals,

    one hundred and twenty-two (122) appeals which

    remained unresolved in 2009 were carried forward to

    2010 bringing the total number of appeals requiring

    attention during the year to two hundred and sixty-

    one (261).

    Of the 139 new appeals, 89 (64%) were related to

    services provided by the Jamaica Public Service

    Company (JPSCo) while 50 (36%) were related to

    services provided by the National Water Commission

    (NWC). No appeals relating to services provided by the

    telecommunications companies were received.

    Resolution of Appeals

    Of the 261 appeals that were investigated in 2010, 184

    (70%) were resolved/closed as at December 31, 2010.

    Of those resolved, 44 (24%) were resolved in favour

    of the customer while 134 (73%) were resolved in the

    utilities favour. The remaining 6 (3%) included matters

    that were mutually resolved between the customers

    and the service providers and those that the OUR

    closed as a result of customers failure to provide the

    required information to facilitate the review.

    Predominant Concerns

    Similar to previous years, billing related matters

    continued to be the main cause of appeal to the OUR

    during 2010. Concerns regarding

    billing accounted for 77% of

    total appeals received.

    As it relates to JPSCos

    services, the matter of

    billing adjustment was the

    predominant basis for appealsto the OUR. These adjustments

    were applied based on

    allegations by JPSCo that there

    was evidence of irregularity

    at the premises. Some of these

    alleged irregularities included illegal abstraction

    (bypass etc.) and meter tampering. Investigations of

    these concerns revealed that an irregularity existed at

    some of the premises and the customer knowingly or

    unknowingly beneted.

    In regard to the NWC, the primary concern was high

    consumption charges particularly during the period in

    which the island was aected by drought conditions.

    This situation once again brought to the fore

    customers concern that air collects in the pipelines

    during periods of prolonged water lock-os and

    results in the meter recording an inated consumption

    when supply is restored. In an eort to address the

    concern, a meeting was held with representatives of

    the Bureau of Standards Jamaica (BSJ) and the OUR.

    At the meeting, the BSJ advised that it was aware of

    a study on this subject that was being undertaken by

    the NWC. The OUR requested a copy of the document

    but it had not been received at the time of writing.

    The NWC has however indicated that it has placed air

    release valves at specic points along its distribution

    pipelines to mitigate against this occurrence.

    While no appeals were accepted in relation to the

    telecommunications service providers, there was

    concern in relation to perceived unfair billing practices

    and the quality of service oered by those providers.

    ... billing related

    matters continued

    to be the main

    cause of appeal

    to the OUR during

    2010.

  • 8/2/2019 OUR Annual Report for Web

    12/6912

    A n n u A l R e p o R t 2 0 1 0 - 2 0 1 1

    Ofce of Utilities Regulation / Annual Report & Financial Statements 2010 - 11

    Credits and Compensation

    As a result of the

    OURs intervention, an

    amount of $6.3 million

    was secured for utility

    customers in 2010. This

    amount was primarily

    due to a reduction in the

    debit adjustments that

    were applied to customers

    accounts where accounts wereback-billed.

    Utility Report on the uaranteed Standards

    The NWC and the JPSCo continue to show high

    incidences of breaches under the Guaranteed

    Standards scheme. In the report from JPSCo, regarding

    its performance under the

    scheme for the year 2010, the

    company indicated that it

    committed approximately

    83,000 breaches attracting

    a potential compensation of

    approximately $140-million.

    Of this amount only

    approximately $9-million

    was credited for breaches

    based on claims submitted

    by customers and for those

    specic breaches to which

    automatic compensation applies.

    In the case of the NWC, the company indicated that

    it committed approximately 30,000 breaches in the

    same period, attracting potential compensationof approximately $58-million. Credits to accounts

    however only totalled approximately $600,000 and

    were primarily as a result of automatic credits where

    applicable as claims submitted for other breaches

    continue to be low.

    Public Education

    The OUR continued its aggressive public education

    programme throughout 2010 and provided accurate,

    relevant and timely information to stakeholders.

    The programme of activities included the hosting

    of a successful media gathering in April 2010. The

    event was organized to provide media practitioners

    with information on the revised thrust of the OUR

    (specically to focus on appeals), outline new initiatives

    as well as to discuss various regulatory matters.

    The public education programme also focused on the

    delivery of messages through mass media productions.

    These productions included the ve minute radio

    programme Inside the OUR; the introduction of

    time signal messages as well as newspaper strip

    advertisements. During the year, the frequency of

    the newsletter publication The Regulator increased

    from twice yearly to four times per year.

    While a strategic decision was taken to suspend Parish

    Day activities during the reporting period, the OURs

    interactions with its largest stakeholder group, utility

    consumers, were maintained through participationin several activities organized by church/community

    groups and other private organizations.

    Utility Monitoring Division

    Ocially staed and launched in October 2010, the

    Utility Monitoring Division of the OUR has primary

    responsibility for ascertaining whether the regulated

    entities are compliant with Oce Directives, relevant

    pieces of legislation, license conditions and tari

    requirements. Its activities are also structured to

    provide the Oce with on-going assessment ofits regulatory eectiveness. The Division carefully

    monitors and assesses key utility projects and quality

    standards to determine whether established targets

    are met, and submits recommendations to the

    Oce on the approach to be taken in addressing

    issues that have arisen or are likely to arise. The

    Division ensures that all decisions include measurable

    ... an amount of$6.3 million was

    secured for utility

    customers in 2010.

    The NWC and the

    JPSCo continue

    to show highincidences of

    breaches underthe Guaranteed

    Standards scheme.

  • 8/2/2019 OUR Annual Report for Web

    13/6913 Ofce of Utilities Regulation / Annual Report & Financial Statements 2010 - 11

    A n n u A l R e p o R t 2 0 1 0 - 2 0 1 1

    indices for assessing success

    and reect regulatory

    impact assessment. It

    is also responsible for

    commissioning regular

    Regulatory Impact

    Assessments (RIAs) regarding

    the improvement in

    eciency and compliance

    with agreed service, quality

    and investment targets.

    The following are the general

    activities of the Division:

    monitor utility projects through progress

    reports etc.;

    monitor service standards through reporting

    and customer feedback surveys etc.;

    produce regular Regulatory Impact

    Assessments;

    conduct periodic audits of specic functions

    of the utilities; prepare policy papers and recommendations

    to the Oce;

    maintain communication with service

    providers on actions/strategies with

    respect to projects and other regulatory

    undertakings.

    Since inception, the Division has been actively

    involved in the monitoring of the multi-billion dollar

    NWC K-Factor Fund. It has recommended to the Oce,

    its no objection to requests from the NWC to make

    withdrawals from the K-Factor Fund as well as requests

    for new projects to be included in the K-Factor

    programme.

    The Division also monitors the cash inows and

    outows and the progress of existing projects. It will

    also monitor the Electricity Eciency Improvement

    Fund (EEIF), the rules for which are expected to be

    published early in 2011.

    ELECTRICITY

    OverviewIt was a historic and active year for the electricity sector.

    The OUR which is charged with the responsibilityof ensuring the Least Cost Expansion Plan (LCEP)

    approach to the addition of generation capacity, and

    guided by the governments energy policy, began a

    process for the procurement of 480 megawatts (MW)

    of new generation capacity.

    With regard to

    renewable energy,

    the Petroleum

    Corporation of

    Jamaica (PCJ), byMinisterial Directive,

    has exclusivity on

    the development of

    renewables and in a

    number of instances

    holds the right to

    the information

    that is required

    for the immediate

    exploitation of such

    resources. The PCJs

    exclusivity in this regard, has restricted the OURsability to request proposals for new generating

    capacity using renewable energy sources.

    This arrangement is further compounded by a conict

    of interest in light of the PCJs interest in participating

    as a competitor in the generation market. The

    urgent need to have this matter addressed has been

    The Division

    ensures that all

    decisions includemeasurable indices

    for assessing

    success and reectregulatory impact

    assessment.

    PCJs exclusivity

    in this regard, has

    restricted the OURsability to request

    proposals for newgenerating capacityusing renewable

    energy sources...

    such exclusivity isinconsistent withthe

    new energy policy.

  • 8/2/2019 OUR Annual Report for Web

    14/6914

    A n n u A l R e p o R t 2 0 1 0 - 2 0 1 1

    Ofce of Utilities Regulation / Annual Report & Financial Statements 2010 - 11

    communicated by the OUR to the political executive,

    as such exclusivity is inconsistent with the new energy

    policy.

    In regard to wind and hydro power as renewable

    energy sources, the OUR maintains its position that

    there is need for further studies over an extended

    period on the variability of wind speeds and river

    ows.

    Procurement of 480M of enerating Capacity

    on a Build, Own & Operate (BOO) Basis

    The OUR has the responsibility for overseeing the

    procurement process for additional electricity

    generating capacity. In this regard, a Request for

    Proposal (RFP) for the supply of up to 480 MW of

    Base-Load Generating Capacity on a Build, Own and

    Operate (BOO) basis was sent out to the industry on

    December 13, 2010. Prospective applicants oering

    cogeneration solutions were aquired to submit their

    proposals for consideration. As part of this solicitation,

    alternative proposals would also be considered.

    Based on the 2010 indicative Generation ExpansionPlan, a block of 480MW is required over the next six

    (6) years. This is required to be commissioned in two

    tranches: 360MW by January 2014 and the remaining

    120MW by January 2016.

    The Ministry of Energy and Mining (MEM) in its

    National Energy Policy 2009 2030 identied fuel

    diversication as one of its main objectives. The policy

    states that as part of the diversication strategy,

    natural gas will, in the short to medium term, be the

    fuel of choice for the generation of electricity and the

    production of Alumina. This was factored into the RFP,which indicated that bids conforming to the energy

    policy would receive a premium in the evaluation

    process. The OUR has determined that the indicative

    all-in avoided cost of electricity is US$0.1005/kWh and

    this cost reects the long run generation cost that is

    expected from the bids.

    Commissioning of the JPSCo 3M ind Farm at

    Munro, St. Elizabeth, October 13, 2010.

    The Jamaica Public Service Company Ltd. (JPSCo) was

    successful in two of its three responses to the OURs

    March 25, 2008 Request for Proposals for the supply

    of Electricity from Renewable Energy Based Power

    Generation Facilities on a Build, Own and Operate

    (BOO) Basis.

    The three proposals submitted by JPSCo were the

    Munro Wind Farm 3MW, the Maggotty Hydro

    6.3MW and the Great River Hydro 8MW projects. Thesuccessful projects were the Munro Wind Farm and

    the Maggotty Hydro. Of these two, the Munro Wind

    Farm was the rst to be constructed and is the second

    wind farm in operation in Jamaica.

    round Breaking for JEPs 65.5 M Plant

    The Oce on the 7th May 2008, issued a Request for

    Proposal (RFP) for the Procurement of 60 MW of new

    capacity. Jamaica Energy Partners Ltd (JEP) was the

    successful bidder.

    JEP sought and obtained approval from the OUR to

    make available an additional 5.5 MW of capacity above

    the 60 MW requested in the RFP. This request to provide

    additional capacity was approved in accordance with

    the Government of Jamaicas Procurement Guidelines.

    The ground breaking ceremony for the 65.5 MW power

    plant was held on December 2, 2010. The facility which

    is called West Kingston Power Partners is a subsidiary

    of the Jamaica Energy Partners and will be located at

    Industrial Terrace in West Kingston.

    igton indfarmII PPA and Price Determination

    Wigton Windfarm Limited (WWFL) is a company duly

    incorporated under the laws of Jamaica and whose

    principal shareholder is the Petroleum Corporation of

    Jamaica.

  • 8/2/2019 OUR Annual Report for Web

    15/6915 Ofce of Utilities Regulation / Annual Report & Financial Statements 2010 - 11

    A n n u A l R e p o R t 2 0 1 0 - 2 0 1 1

    WWFL has proposed to sell energy to the grid from the

    new project, Wigton WindfarmII with capacity totalling

    14.98 MW. The facility is being designed to achieve an

    average annual capacity factor of approximately 35%

    (representing an average annual capacity of 5MW). A

    Power Purchase Agreement (PPA) is being nalised

    between Wigton and the Jamaica Public Service

    Company Limited (JPSCo).

    WWFL requested a review of the Energy Payment Rate

    which was contracted under the Power Interchange

    Agreement (PIA) between itself and the JPSCo in 2010.In its application to the OUR, WWFL requested a review

    of the rate per kilowatt hour based on the avoided

    cost plus 15%. WWFLs request was in keeping with the

    October 2009 National Energy Policy which states that

    Jamaica would ...Introduce incentives, where feasible,

    and a plan of action for implementation to foster the

    development of wind, solar and renewable technologies.

    This will require the review by the regulatory authority

    of existing renewable power generators to aord them

    such incentives that may be available, to encourage the

    sustainable development of the sector.

    Standard Oer Contract for Net Billing

    The Standard Oer Contract (SOC) is geared towards

    assisting Jamaica to meet its renewable energy

    supply targets by providing an opportunity for small

    electricity generators to provide energy to the grid

    through a standard pricing regime and a streamlined

    process.

    This initiative will help the Government of Jamaicas

    stated Energy Policy objective of having 15% of total

    energy generation coming from renewable sources by

    2015. It will also widen competition in the generation

    market since it will facilitate householders and others

    involved in self-generation to sell their excess power

    to the grid.

    The SOC will be a legal document required to be signed

    by the small power supplier [with excess energy sales

    from renewable technology with capacity up to 100kW]

    and JPSCo. The SOC will outline a predetermined

    price structure and a well-dened interconnection

    arrangement. The SOC will also include the eective

    date and terms of all ownership, insurance, operating

    and maintenance agreements. Additionally, it will

    specify the pricing formula for energy, schedule, or a

    combination of the two for determining net billing.

    The OUR will convene public meetings as part of the

    consultation process on the SOC.

    The promulgation of rules to govern the

    Electricity Eciency Improvement Fund

    Arising out of the Jamaica Public Service Company

    Limiteds (JPSCo) 2009 Tari Submission, the Oce

    approved the establishment of the Electricity Eciency

    Improvement Fund (EEIF). The purpose of the Fund

    is to augment JPSCos proposed capital, operation

    and maintenance expenditure of US$45M on system

    loss reduction initiatives over the ve-year price cap

    period 2009-2014. To this end, the amount of US 0.4 c/

    kWh approximately US$13M annually, is expected to

    go into the EEIF from the electricity taris specically

    for Advanced Metering Infrastructure and other loss

    reduction technologies.

    Following on consultations with the JPSCo, the Oce

    issued a Determination on the Rules of Procedure.

    These Rules of Procedure set out the principles,

    parameters and processes to govern the operation

    and administration of the EEIF.

    JPSCo Annual Adjustment

    The Oce is required to undertake an annual reviewof JPSCos performance under the existing price cap

    regime and approve adjustments as provided for in

    the Plan as it relates to movements in ination and

    exchange rates. Accordingly, the OUR approved the

    annual adjustment to the JPSCo tari which resulted in

    an average eective increase of 1.70% on customers

    bills.

  • 8/2/2019 OUR Annual Report for Web

    16/6916

    A n n u A l R e p o R t 2 0 1 0 - 2 0 1 1

    Ofce of Utilities Regulation / Annual Report & Financial Statements 2010 - 11

    eneration & Metering Code

    The Generation and Metering Codes establish

    the guiding principles, operating procedures and

    technical standards governing the operation of the

    Jamaican power generation system. The nal draft of

    the document is now being reviewed with a view to

    nalizing it in 2011.

    Transmission & Distribution Code

    The purpose of Transmission and Distribution Codes

    is to permit the development, maintenance and

    operation of an ecient, coordinated transmission

    and distribution system in Jamaica. This is tied to the

    Generation Codes and will be completed within the

    same timeframe.

    JPSCo Appeal to the Tribunal Z Factor Claim for

    Reclassication Exercise

    By a Notice of Appeal dated April 1, 2010, the JPSCo

    challenged the OURs Determination on its Z-Factor

    Claim for Reclassication costs. The Determination

    Notice which was issued one month earlier denied

    JPSCos claim for approximately J$4.3 billion to be

    recovered under the Z- Factor on the grounds that it

    failed to satisfy the criteria specied in the Licence for

    Z-factor adjustments.

    The Claim was in relation to compensation to workers

    following a reclassication exercise. The company

    disagreed with the outcome of the exercise and in

    particular the amount to be paid to the workers.

    After several court battles the JPSCo lost its bid at the

    Appeal Court to have the award quashed.

    The case (Z Factor Claim) was presented to the

    Electricity Tribunal in November 2010. The Tribunal is

    expected to publish its ruling in 2011.

    Demand Forecast

    As part of the Least Cost Expansion Plan (LCEP), the

    demand forecast was derived as a primary input

    into the determination of electricity supply required

    to meet consumer demand at the least cost. The

    projected energy requirement for Jamaicas Electricity

    System was developed for the period 2010 through

    2030. Consequent on this assessment, system

    net energy requirements and peak demand were

    projected to increase respectively at a compounded

    annual growth rate of 4.0 and 3.80 percent over

    the next twenty years. This nding does not dier

    signicantly from the previous projections in 2003and 2004 (by the JPSCo and OUR respectively) when

    net energy requirements were projected to increase

    at a rate of 4.6 percent and net peak demand at 4.5

    percent.

    Figure 1: Net system peak (M) 1982 - 2030

    1982 1984 1986 1988 1990 1992 1994 1996 1998 2000 2002 2004 2006 2008 2010 2012 2014 2016 2018 2020 2022 2024 2026 2028 2030

    200.0

    400.0

    600.0

    800.0

    1,000.0

    1,200.0

    1,400.0

    1,600.0

    0

  • 8/2/2019 OUR Annual Report for Web

    17/6917 Ofce of Utilities Regulation / Annual Report & Financial Statements 2010 - 11

    A n n u A l R e p o R t 2 0 1 0 - 2 0 1 1

    The demand forecast sought to dene

    electricity consumption as a function

    of the growth in the average number

    of customers and growth in the level

    of average use per customer. Load

    research data was also used to project

    peak demand (see gure 1) and net

    generation (see gure 2) needed to

    facilitate the assessment of the additional

    net generating capacity required (480

    MW by 2016) and more generally over the

    forecast period.

    Table 1:

    *Forecast

    Figure 2: Net eneration (Mh) 1982 - 2030

    1982 1985 1988 1991 1994 1997 2000 2003 2006 2009 2012 2015 2018 2021 2024 2027 2030

    1000000

    2000000

    3000000

    4000000

    5000000

    6000000

    7000000

    8000000

    9000000

    10000000

    0

    1982 1985 1988 1991 1994 1997 2000 2003 2006 2009

    350000

    700000

    1050000

    1400000

    1750000

    2100000

    2450000

    2800000

    3150000

    0

    Energyin(M

    wh)

    Figure 3: ELECTRICITY DEMAND BY RATE CLASS 1982 2009

    The analysis was based on several assumptions and a range of potential drivers of long term electricity demand,

    including but not limited to the demand for Jamaican goods, growth in population and employment. These were

    ascribed to the broad areas of economic activity (measured by GDP), demographics, electricity prices (and demand

    responsiveness) and energy intensities (determined by the type of electricity end use and technology).

  • 8/2/2019 OUR Annual Report for Web

    18/6918

    A n n u A l R e p o R t 2 0 1 0 - 2 0 1 1

    Ofce of Utilities Regulation / Annual Report & Financial Statements 2010 - 11

    Electricity Consumption

    Figure 3 indicates electricity demand over the period

    1982-2009 as inuenced by energy sales mainly from

    the residential (Rate 10) and general power (Rate 40)

    service classes.

    Total base energy sales were forecasted at

    3,231,373MWh by 2010. Similarly, this was attributedmainly to energy sales in the Rate 10 (1,133,078 MWh)

    and Rate 40 (705,873 MWh) service classes (see Table

    1).

    Number of Customers

    Table 2 shows that the number of JPSCo customers

    has increased steadily over the years 1982 to 2009,

    having grown by 160%. The majority of customers

    are residential (R10) followed by the general service

    classes (R20 & R40) which together accounted for 90%

    of total customers (excluding street light) by the close

    of 2009. This attributive share has not quite changed

    since 1982 when the combined share was 89.10%. The

    number of customers was projected to be 649, 481 at

    the close of 2010.

    TELECOMMUNICATIONS

    In an environment characterised by litigation, it has

    become even more critical for the new Information

    Table 2.

    *Forecast

  • 8/2/2019 OUR Annual Report for Web

    19/6919 Ofce of Utilities Regulation / Annual Report & Financial Statements 2010 - 11

    A n n u A l R e p o R t 2 0 1 0 - 2 0 1 1

    and Communications Technology Policy to be

    implemented.

    The current environment

    also emphasizes the

    urgent need to revisit

    the legislative and

    regulatory framework

    for the sector. This

    is evidenced by the

    numerous disputes

    regarding accessto limited facilities,

    i n t e r c o n n e c t i o n

    charges and other

    interconnection issues

    which resulted in lawsuits and counter suits among

    the major providers. Additionally, with convergence

    gaining momentum, it becomes increasingly important

    for the legislative and regulatory framework to move

    in tandem with such developments, and in so doing,

    ensure the strengthening of

    the regulators enforcement

    powers.

    The OURs operation in the

    sector has been met with

    varying levels of success,

    headlined by the Oces

    successful defence against

    Digicels appeal to the

    Tribunal in the matter of

    Assessment of Dominance

    in Mobile Call Termination.

    This ruling allows the OUR

    to direct dominant providersto issue a Reference Interconnect Oer (RIO) which will

    set out the terms and conditions of interconnections.

    The OUR will then have the responsibility to approve

    interconnection rates for the sector.

    Notwithstanding the need to revisit the legislative

    instruments governing the telecommunications

    sector, it continues to perform relatively well delivering

    more innovative packages with increased access to

    cutting edge technology. Combined data for fixed and

    mobile lines indicate that the country continues to enjoy

    well over 100% teledensity attributed mainly to persons

    owning more than one mobile instrument. Despite the

    foregoing, there are still persons lacking access either

    by virtue of economics or geographical remoteness.

    Developments in the telecommunications sector

    included;

    Publication of the Estimate of the WeightedAverage Cost of Capital

    The call for and receipt of Reference

    Interconnection Oers from all carriers

    Competitive Safeguard Rules

    Submarine Cable Legislation/Regulations/

    Guidelines

    Estimate of the eighted Average Cost of Capital

    (ACC) for Jamaican Telecommunications Carriers

    The consultative process to estimate the weighted

    average cost of capital (WACC) began on May 9, 2008with the issuing of the rst Consultation Document.

    As a result of the need to broaden the scope of the

    consultation, a second consultative document was

    issued on August 31, 2009.

    The process was quite extensive and involved

    analysing various nancial techniques. Additionally,

    there were requests from stakeholders for extensions

    for submission of comments which were granted.

    Following comments from stakeholders, the OUR

    issued a Determination Notice on December 9, 2010.

    The document presents the study of the cost of capital

    for the business of providing xed line and mobile

    telecommunications service. The Oce, among other

    things, determined it will estimate a separate WACC for

    xed line and mobile networks. The cost of capital will

    be used in any future rate making process undertaken

    by the OUR.

    ... it has become

    even more critical for

    the new Informationand Communications

    Technology Policy to

    be implemented.

    ... data for xed and

    mobile lines indicate

    that the countrycontinues to enjoy well

    over 100% teledensity

    attributed mainlyto persons owning

    more than one mobile

    instrument.

  • 8/2/2019 OUR Annual Report for Web

    20/6920

    A n n u A l R e p o R t 2 0 1 0 - 2 0 1 1

    Ofce of Utilities Regulation / Annual Report & Financial Statements 2010 - 11

    Reference Interconnection Oer (RIO-6)

    This document sets out the terms and conditions

    under which LIME will allow other operators to

    interconnect with its xed line network. The timetable

    for completing this exercise was adversely aected

    by delays in the provision of critical information and

    requests from stakeholders for an extension of the

    period for comments. The consultation document

    is currently being prepared and is scheduled to be

    published in 2011.

    Review and Harmonisation of Mobile RIOs

    Following on the ruling of the Telecommunication Appeals

    Tribunal, which upheld the OURs decision that all

    mobile operators are dominant for the termination

    of calls on their own network, the OUR in accordance

    with the provisions of the Telecommunications Act

    instructed all mobile operators to submit their RIO and

    supporting documentation to the OUR by September

    1, 2010 for review and approval.The RIO sets out the

    terms and conditions under which mobile operators

    will allow other carriers to interconnect with theirnetwork. The harmonisation of the 3 mobile RIOs is

    scheduled to commence at the start of the second

    quarter of 2011 to create a single mobile RIO.

    Competitive Safeguards Rules

    The Oce, in September 2007, published a

    Determination Notice on rules for the voice market.

    These rules are deemed necessary to promote fair and

    non-discriminatory access to restricted facilities and

    reduce the incidences of anti-competitive behaviour

    within telecommunications markets. Subsequent tothis Determination Notice, C&WJ (now LIME) submitted

    an application for reconsideration of these rules. A

    decision in this regard should be published in 2011.

    Submarine Cable Legislation/ Regulations/

    uidelines

    This activity addresses the need to ensure that there is

    competitive access to submarine cable facilities as well

    as the need to protect submarine cables in Jamaican

    waters. The exercise which is being funded by the

    United States Trade and Development Agency (USTDA)

    is slated for completion by June, 2011. Activities

    undertaken in regard to this project include the review

    of submarine cable, cable station and backhaul access

    licensing in Singapore and other countries to assesshow these regulations can be applied to Jamaicas

    situation. Other activities to be undertaken include

    interviews with carriers and other key players for input

    on how regulations can be developed that would

    lead to fair competition in Jamaicas international

    telecommunications market.

    Quality of Service Rules for the

    Telecommunications Sector

    In keeping with its statutory responsibility to ensure

    quality of service to consumers, the OUR with

    assistance from the Inter-American Development Bank

    (IDB), commissioned consultants in November 2009 to

    review mobile quality of service and to develop quality

    of service standards for providers.

    The project was expected to conclude in May 2010,

    but was delayed because of additional activities

    which had to be undertaken by the consultants. The

    service providers also failed to provide their responses

    within the time stipulated and this further delayed

    the project. Subsequent to overcoming the foregoing

    diculties, the Quality of Service Consultative

    Document Quality of Service Standards andGuidelines for the Telecommunications Sector was

    published on October 25, 2010. Comments on the

    document were received from the industry operators

    and the Consumer Advisory Committee on Utilities

    (CACU). The consultancy is expected to conclude

  • 8/2/2019 OUR Annual Report for Web

    21/6921 Ofce of Utilities Regulation / Annual Report & Financial Statements 2010 - 11

    A n n u A l R e p o R t 2 0 1 0 - 2 0 1 1

    Source: O.U.R

    Table 3: Distribution of Mobile Subscription &Penetration Rates (2006-2010)

    Table 4: Distribution of Fixed Line Subscription &Penetration Rates (2006-2010)

    Source: O.U.R

    in the rst half of 2011 and thereafter the draft rules

    and guidelines will be submitted to Parliament for

    armative resolution.

    Indirect Access: Two Stage Dialling (2SD)

    The Oce issued its Determination Notice on this

    matter on May 30, 2008. The Determination details

    the cost benet analysis and unfair burden test for the

    imposition of indirect access obligations via 2SD. LIME

    requested a reconsideration of the decision and a nal

    decision should be published before the start of scalyear 2011/2012.

    In 2-stage dialling a caller dials two distinct sets

    of numbers to reach the called destination. This is

    typically used by calling card providers.

    The initial number or code dialled by the caller is

    not the nal destination number, but a set of digits

    to activate or reach an intermediate service feature,

    service platform or another network, to authenticate

    the caller and/or prompt the caller (by a recorded

    voice or a second dial tone, etc.) for and receive the

    destination number and to route the call to the desired

    destination point.

    In some systems, 2-stage dialling is semi-automated

    and allows a caller to dial a concatenated digit string

    representative of the two sets of numbers and, in

    addition to producing operational eciency gains,

    gives the caller the familiar experience of single-

    number dialling.

    Mobile Service

    The mobile sector continued to reect growth in

    subscriptions up to 2010 and seminal expansion

    by December 2010. This, as subscribers to mobile

    telephone service totalled 3,182,000 (2010). Over

    the 2006 2010 periods, growth in subscription

    was highest in 2007(18%). Table 3 depicts that most

    subscribers continue to opt for the pre-paid mobileservice which maintained dominance of over 95% of

    total subscriptions over the ve year period.

    Following the trend of increases in subscription,

    mobile penetration also increased over the review

    period to stand at 109.53% and 117.83% by the close of

    2009 and 2010 respectively.

    Fixed Line Service

    Since 2007, subscriptions to xed line services as

    depicted in Table 4 have been on the decline. The mostrecent decline resulted in subscriptions moving from

    302,451 in 2009 to 263,060 by December 2010. This

    represents a fall-o in subscription of 13.02% over the

    period, and was mainly as a result of a reduction in the

    number of subscriptions for residential lines. Likewise,

    xed line penetration reected declines since 2007 to

    stand at 9.74% by the close of 2010.

  • 8/2/2019 OUR Annual Report for Web

    22/6922

    A n n u A l R e p o R t 2 0 1 0 - 2 0 1 1

    Ofce of Utilities Regulation / Annual Report & Financial Statements 2010 - 11

    Internet Service

    Subscriptions to internet services grew by 9.92%

    since 2006 to stand at 114,561 by December 2009,

    and thereafter subscriptions declined by 33.4% to

    a total of 76,300 users by December 2010. This has

    been attributed mainly to the growth in broadband

    subscriptions over the 2006 2010 periods.

    The penetration rates for internet services stood at

    2.83% by the close of 2010.

    Table 6: Number of Telecoms Licences (2000 -2010)

    Table 5: Distribution of Internet Subscription& Penetration Rates (2006-2010)

    Source: O.U.R

    Licences

    Twelve licences were issued in 2010 resulting in a total

    of 493 licences since the Telecommunications Sectors

    liberalisation in 2000 (see Table 6).

    Licence Terms:

    DC: Domestic Carrier

    DSP: Data Service ProviderDVSP: Domestic Voice Service Provider

    FTZC: Free Trade Zone Carrier

    FTZSP: Free Trade Zone Service Provider

    IC: International Carrier (Voice/Data/Transit)

    INTL. SP: International (Voice/ Data ServiceProvider)

    ISP: Internet Service Provider

  • 8/2/2019 OUR Annual Report for Web

    23/6923 Ofce of Utilities Regulation / Annual Report & Financial Statements 2010 - 11

    A n n u A l R e p o R t 2 0 1 0 - 2 0 1 1

    ISP (STVO): Internet Service P

    IVSP: International Voice ServiceProvider

    SCLC: Submarine Cable Landing Carrier

    Numbering Administration & Technical Support:

    The OUR, as the National Numbering Administrator,

    has responsibilities for the administration and

    management of telecommunications numbering

    resources used by carriers and service providers inJamaica.

    The OUR must ensure impartial and equitable access

    to these essential resources and provide advice to the

    industry on numbering issues.

    The Oce undertook the following major numbering

    activities during the period:

    Numbering Resource Utilization/Forecast

    (NRUF) Surveys

    Area Code Relief Planning Extra-Territorial use of International

    Subscription Identities

    Adoption of Alternative Emergency Numbers

    Local Number Portability

    Regime for Short Code

    Automation of Numbering Administration

    Functions

    Uniform Domestic Dialling Plan

    Numbering Resource Utilization/Forecast (NRUF)

    Surveys

    Carriers and service providers holding geographic

    and mobile telephone numbers must le Numbering

    Resource Utilization and Forecast (of demand over

    the next 5 years) reports semi-annually on or before

    February 1 for the preceding six-month reporting

    period ending on December 31, and on or before

    August 1 for the preceding six-month reporting period

    ending on June 30.

    NRUF data support forecasts of the exhaustion date

    for each area code (digits 1 through 3 of the 10-digit

    telephone number). The OUR monitors central oce

    code assignment rates and adjusts the projected

    exhaust dates if necessary.

    Area Code Relief Planning

    Area Code Relief refers to an activity that must beperformed when the Oce Codes within an area code

    are near exhaustion. Providing relief to such an area

    code normally involves assigning a new area code.

    Using the Numbering Resource Utilization and

    Forecast data and historical growth data submitted by

    carriers with their applications for additional numbers,

    the Oce estimated that the expected exhaust period

    for area code 876 is the 4th quarter of the year 2012.

    Based on the Oces preliminary notication to

    the North American Numbering Plan Administrator

    (NANPA) regarding the imminent exhaust of the 876area code, NANPA has reserved a new area code for

    Jamaica, pending formal application for its assignment.

    The Oce will publish a second planning document

    which will outline the activities of the second phase

    of the Area Code Relief Planning Process and Relief

    Implementation exercise. The new area code will cover

    the same geographic area as the existing 876 area

    code. This will require the dialling of the full 10 digits

    of a telephone number for all local calls.

    Extra-Territorial Use of International MobileSubscriber Identities

    The International Mobile Subscription Identity

    (IMSI) provides a unique international identication

    of mobile terminals/users and to enable these

    terminals/users to roam among public networks

    which oer public mobility services. The IMSI, as

  • 8/2/2019 OUR Annual Report for Web

    24/6924

    A n n u A l R e p o R t 2 0 1 0 - 2 0 1 1

    Ofce of Utilities Regulation / Annual Report & Financial Statements 2010 - 11

    provided in the International Telecommunications

    Unions Recommendation ITU-T E.212, The

    International Identication Plan for Public Networks

    and Subscriptions, is made up of a Mobile Country

    Code (MCC), a Mobile Network Code (MNC) and a

    Mobile Subscription Identication Number(MSIN),

    that is, MCC-MNC-MSIN. The combined MCC+MNC

    identies the home network of a mobile terminal/user.

    The ITU recently added Annex E to Recommendation

    ITU-T E.212, to provide for the use of the combined

    MCC+MNC in a country other than the country to

    which the MCC has been assigned by the Director of

    the ITUs Telecommunication Standardization Bureau.

    In other words, Annex E provides for cross-border or

    extraterritorial use of MCC+MNCs.

    The Oce consulted with the local industry by way of

    a Notice of Proposed Rule Making to formally adopt

    and implement the provisions of Annex E in Jamaica.

    The proposal was not opposed. The completion of the

    requisite Determination Notice was rescheduled for

    the rst quarter of the next calendar year

    Adoption of Alternative Emergency Numbers

    The Oce carried out an industry consultation on the

    implementation in Jamaica of secondary alternative

    emergency numbers (112 and/or 119) for public

    telecommunications networks. This was done in

    accordance with the International Telecommunications

    Unions Recommendation ITU-T E.161.1 (Guidelines

    to select Emergency Number for public

    telecommunications networks) which was developed

    based on recommendations made to the ITU by the

    OUR on behalf of the Government of Jamaica.

    Local Number Portability

    An external consultant was engaged to carry out

    a feasibility study and cost benet analysis on

    implementation options for Number Portability

    (NP) in Jamaica, in accordance with section 37 of the

    Telecommunications Act 2000. The consultation

    activities included a public workshop and individual

    meetings with key industry stakeholders. The project,

    which was put to international tender, was funded by

    the IDBs Multilateral Investment Fund Facility.

    The results of the study which are contained in the

    consultants Final Report will form the basis of a public/

    industry consultation and subsequent rule making.

    The Number Portability rules which will govern the

    implementation of number portability in Jamaica are

    subject to armative resolution of Parliament.

    It is envisaged thatsubsequent to an Oce

    decision the actual NP

    implementation exercise

    will require at least

    one year for successful

    execution.

    Regime for Short Code

    The industry consultation

    for the development

    and implementation of

    a numbering scheme using

    numbers which are shorter than the regular telephone

    number (common short codes) for the provisioning of

    a broad range of existing and future services via text

    messaging was rescheduled to the second quarter of

    2011 to facilitate work on Local Number Portability.

    Automation of Numbering Administration

    Functions

    After several attempts the Oce secured the requisite

    consultancy services to automate specied aspects

    of the Numbering Administration function by way of

    web-based applications.

    Numbering Administration involves the development

    and management of the National Telecommunications

    Numbering Scheme, which is a national resource, to

    ensure the availability of and fair and equitable access

    to telecommunications numbers. These numbers are

    ... Number

    Portability rules

    which will govern the

    implementation of

    number portability

    in Jamaica are

    subject to armative

    resolution ofParliament.

  • 8/2/2019 OUR Annual Report for Web

    25/6925 Ofce of Utilities Regulation / Annual Report & Financial Statements 2010 - 11

    A n n u A l R e p o R t 2 0 1 0 - 2 0 1 1

    Table 7: Production and Consumption Datafor Potable ater 2009 -2010

    used by network operators and service providers to

    oer telecommunications services to their customers

    and by networks to initiate, route and charge for calls.

    The work which commenced on October 25, 2010 has

    progressed according to schedule, with a completion

    date of March 25, 2011. The project is being funded by

    the IDBs Multilateral Investment Fund Facility.

    Uniform Domestic Dialling Plan (UDDP)

    The Uniform Domestic Dialling Plan (UDDP) which was

    established by the Oce to provide dialling parity for

    all customers, for all domestic calls, remains before the

    Telecommunications Appeals Tribunal. A hearing is

    expected in early 2011.

    Dialling parity means the ability of an end-user to use

    an equal number of digits to access a particular public

    telecommunications service, regardless of which public

    telecommunications services supplier the end-user

    chooses.

    ATER AND SEERAE

    ater Production and Consumption

    Total water produced by the National Water

    Commission (NWC) during the calendar year 2010 was

    62 billion gallons as against 67 billion gallons in 2009.

    Of this amount, billed

    consumption for the

    year was reported as

    18 billion gallons. Thelarge disparity between

    water production and

    consumption indicates

    that the NWC has a high

    percentage of Non-

    Revenue Water (NRW). At

    the end of the calendar year 2010, the NWC reported

    NRW as being 71%. The Oce has set a target for the

    NWC to reduce its NRW to at most 55% within a three

    year period. The Commission is striving to achieve this

    target through its K-factor programme.

    National ater Commission K-Factor Fund

    Signicant progress was made during the last quarter of

    the 2010 calendar year in regularising the operations of

    the K-Factor fund. The primary objective of the fund is

    to reduce non-revenue water through the replacementof mains and other activities, and the rehabilitation

    of some sewerage facilities. The regularisation

    of operations arose from the establishment of a

    Memorandum of Understanding (MOU) between the

    OUR and the NWC in October 2010. The objective of

    the MOU is to maintain the integrity of the fund. The

    OUR has also developed specic Rules and Procedures,

    as specied by the 2008 Tari Determination, to ensure

    the ecient and eective administration of the fund. It

    is expected that these Rules and Procedures will come

    into force in early 2011.

    As at December 31, 2010, a total of forty seven (47)

    projects were approved by the OUR for funding under

    the K-Factor programme at an estimated cost of J$11.7B.

    Based on the latest data available, approximately

    J$1.22B has been expended on the various projects.

    The large disparity

    between waterproduction andconsumption

    indicates that theNWC has a highpercentage of Non-Revenue Water.

  • 8/2/2019 OUR Annual Report for Web

    26/6926

    A n n u A l R e p o R t 2 0 1 0 - 2 0 1 1

    Ofce of Utilities Regulation / Annual Report & Financial Statements 2010 - 11

    NCs Request for K-Factor Collections to be based

    on Actual Collection rate

    The Determination Notice of April 2008 on NWCs

    rates stated that the Commission shall account for the

    deemed K-factor cash inow calculated on the basis of

    95% of K-factor billing.

    The NWC submitted a letter to the OUR on October 20,

    2010 requesting that the Oce adjusts the deemed

    K-factor collection rate from 95% to reect the actual

    collection rate of the NWC for the applicable month.

    The Commission argued that given the current

    environment within which it operates, it is unable to

    consistently achieve such a high collection rate.

    The Oce will provide the Commission with a response

    before the end of the rst quarter of 2011.

    Small Private and Commercial Potable ater and

    Sewerage Service Providers

    There are currently, six (6) licensed small water providers

    in Jamaica. They are as follows:

    Four Rivers Development Company

    Runaway Bay Water Company

    Dairy Spring Limited

    Can Cara Development Company

    Dynamic Environmental

    Management Limited

    Hampstead Benevolent Society

    Of these small water providers, only two (2) are

    licensed sewerage service providers namely, Can Cara

    Development Company and Dynamic Environmental

    Management Limited. In addition to these two

    companies, Rose Hall Utilities Company also has a

    sewerage service licence but does not have a licence

    for potable water. The company however obtained a

    licence from the National Environment and Planning

    Agency (NEPA) for the provision of water for irrigation

    purposes.

    Runaway Bay ater Company

    The Runaway Bay Water Company (RBWC) had an

    annual Price Adjustment Mechanism applied to its

    rates for the year 2010/2011. This is in keeping with the

    Determination Notice issued by the Oce where the

    RBWC rate adjustments are tied to that of the NWC.

    Rose Hall Utilities Company Limited

    Rose Hall Utilities Company Limited (RHUCL) is a

    licensed sewerage service provider located in RoseHall St. James. The company applied to the Oce for

    an increase of its sewerage rates and also requested

    that the Oce consider the possibility of developing a

    methodology to price re-claimed water.

    The OUR is currently consulting with the National

    Environment and Planning Agency (NEPA) and the

    Ministry of Health to determine how the selling of

    reclaimed water can be accommodated.

    ** Note that the latest NWC expenditure report on the K-Factor programme is up to the period ending October 2010.

    Table 8: K-Factor Project Approvals & Expenditure (Summary)

    May 2008 - Oct 2010**

  • 8/2/2019 OUR Annual Report for Web

    27/6927 Ofce of Utilities Regulation / Annual Report & Financial Statements 2010 - 11

    A n n u A l R e p o R t 2 0 1 0 - 2 0 1 1

    Irrigation ater

    The National Irrigation Commission (NIC) developed

    the National Irrigation Development Plan (NIDP) in an

    eort to improve the eciency of water provisioning

    to its various schemes. Additionally, the NIDP also

    serves to foster the independence of these schemes

    to enable them to eventually become Water User

    Associations. In 2010 the NIC made an application to

    the Oce for a rate to be charged to the customers of

    the Hounslow scheme. The application was examined

    and a Determination was issued on October 19, 2010. That Determination also included the imposition of

    Guaranteed Standards similar to those applied to the

    other irrigation schemes.

    Sewage Treatment

    The NWC remains the main operator of sewage

    treatment facilities. The major challenge facing the NWC

    is the modernisation of some of its older facilities to

    meet the requirements of the National Environmental

    and Planning Agency (NEPA).

    The NWC has started the rehabilitation work onsome of these facilities using funds from the K-factor

    programme.

    TRANSPORTATION

    The Oces main activity in the

    transportation sector remains one of

    providing advice to the Minister of

    Transport for the setting of bus and taxi

    fares. The legislation to bring the transport

    sector under the OURs regulatory remit is

    still pending.

    There were however no major activities in

    the transportation sector which required the

    OURs attention for the calendar year 2010.

    ADMINISTRATION/HUMAN RESOURCES

    The OUR reported a number of vacancies at the end

    of 2009/2010 and lamented its inability to ll these

    positions. Thankfully, despite the continued constraint

    on its ability to make competitive oers, the OUR was

    able to attract a number of new professionals during

    the review period and was also able to retain the

    complement with which it started the year. This has

    served to strengthen the team and it is hoped thatsome exibility will be allowed in the upcoming year to

    ensure that the organisation is able to oer the kind of

    incentives that will allow it

    to retain the skill set that

    is so critical to match

    those of the regulated

    entities and local and

    international peers with

    which it has to compete.

    With the OUR listed as

    one of the twelve publicentities to be accorded

    full devolution and

    de-concentration of

    authority, a

    considerable amount of attention

    was devoted during the year to

    preparation for this status. There were

    on-going engagements with the Public

    Sector Transformation Unit and otheragencies to develop a Management

    Accountability Framework to ensure

    transparency and accountability. This

    will become binding on the OUR as soon

    as there is sign o on devolution.

    ...it is hoped that

    some exibility

    will be allowed in

    the upcoming year

    to ensure that the

    organisation is able

    to oer the kind of

    incentives that willallow it to retain the

    skill set that is so

    critical.

    As in previous years,

    great emphasis

    was placed on

    sta training and

    development,

    funded mainly from

    the organisations

    budget.

  • 8/2/2019 OUR Annual Report for Web

    28/6928

    A n n u A l R e p o R t 2 0 1 0 - 2 0 1 1

    Ofce of Utilities Regulation / Annual Report & Financial Statements 2010 - 11

    As in previous years, great emphasis was placed on sta

    training and development, funded mainly from the

    organisations budget, but also with grants from agencies such

    as the Inter-American Development Bank, (IDB), through

    the Multi-lateral Investment Fund (MIF) Programme, as

    well as from membership benets from payments to

    the Commonwealth Telecommunications Organization,

    (CTO). Topics such as Electricity Law and Natural Gas,

    Internet Governance, Project Management, Alternate

    Dispute Resolution, Document Management, Public

    Speaking, Best Practices in Public Procurement and

    Renewable Wave Energy Technologies are some of theareas that were covered. Arrangements were also made

    during the year to provide all members of sta with

    training in the use of Microsoft Oce Suite applications.

    This reects the OURs determination to ensure that

    its sta makes the best use of the advantages that

    are aorded by Information Technology to improve

    the value and timeliness of service delivered to the

    public. In addition to these formal assemblies, monthly

    meet and learn sessions were held where, among

    other things, the general sta body was kept abreast

    of regulatory issues, by way of having authors of

    Consultative Documents making informal power-pointpresentations to peers.

    Also during the review period the OUR signed a

    Memorandum of Understanding (MOU) with the

    Nigerian Electricity Regulatory Commission (NERC).

    This will facilitate a mechanism for mutual co-operation

    between both entities.

    The tradition of information exchange with other

    regulatory agencies continued during the year. Sta

    members from the Nigerian Electricity Regulatory

    Commission and the Utilities Regulation andCompetition Authority in the Bahamas were hosted

    during the year. These visits continue to underscore the

    esteem in which the OUR is held by its regulatory peers.

    Corporate social responsibility constitutes one of

    the organisations core values. During the year,

    assistance was given to the Glenhope Place of Safety

    in the refurbishing of two dorms. The organisation also

    partnered with the Engineering Department of the

    University of Technology in providing the opportunity

    for work-integrated learning/internship for students

    pursuing studies in the engineering discipline.

    With regard to Procurement of Goods and Services,

    the Administration/HR Department continues to

    ensure that the organisation is fully compliant with the

    Governments Procurement Guidelines. Notably the

    OUR has, on more than one occasion, been commendedby the Oce of the Contractor General (OCG), for its

    consistently prompt submissions and responses to the

    requirements of that Oce.

    KEY PERFORMANCE INDICATORS KPI

    As part of eorts to enhance transparency and

    accountability the OUR has embarked on a value for

    money exercise as well as a KPI project. These initiatives

    will allow stakeholders to measure the performance ofthe OUR against set KPIs.

    Additionally regional regulators through the

    Organisation of Caribbean Utility Regulators (OOCUR)

    have agreed in principle to the need to benchmark

    individual performances.

    Some of the KPIs already agreed are acknowledgement

    of all correspondence within three (3) business

    days, publication of the Annual Report and nancial

    statements within one hundred (100) calendar days

    of the end of the nancial year, issuing a decision on atari submission within ninety (90) days and concluding

    investigations within thirty (30) business days.

    Other KPIs related to regulatory decision making,

    nances and training are being developed and it is

    expected that with the assistance of the Public Sector

    Transformation Unit (PSTU) these will be nalised and

    published in the 2011/2012 nancial year.

  • 8/2/2019 OUR Annual Report for Web

    29/6929 Ofce of Utilities Regulation / Annual Report & Financial Statements 2010 - 11

    A n n u A l R e p o R t 2 0 1 0 - 2 0 1 1

    Compensationfor

    SeniorSta(2010-2011)

    Notes:

    1

    Directexpensesofassignedmotorvehicle

    2

    MotorVehicleUpkeepAllowance

    3

    Pensionbenetonly

    4

    Clothingallowance

    5

    Healthandgrouplifeinsuranceisincludedundernon-cashbenets.

  • 8/2/2019 OUR Annual Report for Web

    30/6930

    A n n u A l R e p o R t 2 0 1 0 - 2 0 1 1

    Ofce of Utilities Regulation / Annual Report & Financial Statements 2010 - 11

    The OUR will aim to

    assist in achieving

    the Vision 2030 Plan

    by ensuring thatits regulation of

    the various utilities

    seeks to align private

    behaviour with the

    public interest.

    Outlook & ork Programmefor Fiscal 2011/12

    The outlook for 2011 will be driven by the OURs

    mandate as well as the Governments Vision 2030 Plan.

    The OUR has dened the Policies and Programmes

    objectives in the following terms:

    To establish and maintain transparent,

    consistent and objective rules and standards

    to regulate the providers of specied utilityservices while fully protecting the public

    interest;

    To enhance ecient utility operations and

    provide an enabling environment conducive

    to investments;

    Analytical capacity ensuring high quality

    policy options, programme design and

    advice to the government; and

    To align regulations, directives and

    processes with legislation

    and policy mandate.

    The OUR will aim to assist

    in achieving the Vision

    2030 Plan by ensuring

    that its regulation of the

    various utilities seeks to

    align private behaviour

    with the public interest.

    Success in achieving the

    set objectives and goals

    and accomplishing the

    programme of work isdependent however,

    on the extent to which the

    following assumptions hold true.

    Sta turnover will be kept to a minimum.

    This is critical given the elongated

    learning curve that obtains for regulatory

    professionals;

    Sta will be operating at optimal output

    throughout the period of the plan;

    Anticipated policy changes and the

    timetables for expected legislative

    enactments and amendments materialise;

    The enforcement powers of the OUR are

    enhanced;

    Such emergencies as arise will not be

    beyond the Oces ability to adapt and tooutsource;

    The regulatory environment will at the least

    not become more litigious;

    The existing institutional compliment and

    responsibilities are maintained or where

    there are amendments the institution is

    provided with the required notice and

    resources to make adjustments.

    Telecommunications

    For information, communication and tele-

    communication services, the imperative is to deploy

    broadband to benet all citizens, including those

    with disabilities and to str engthen competition in

    the various markets. Some of the more important

    objectives determined by the Oce for achievement

    within the planned p eriod are:

    Conduct a broadband baseline data survey,

    the ndings of which will inform the

    development of a new Universal Service/

    Access Policy.

    Complete work on the proposed

    automated number administration system

    for managing and allocating toll free

    numbers. This will allow for improved

    operational eciencies in number

    management and administration.

  • 8/2/2019 OUR Annual Report for Web

    31/6931 Ofce of Utilities Regulation / Annual Report & Financial Statements 2010 - 11

    A n n u A l R e p o R t 2 0 1 0 - 2 0 1 1

    Reconciliation of various mobile Reference

    Interconnection Oers (RIOs) in order to

    develop a standard RIO;

    Development of a Long Run Incremental

    Cost (LRIC) model for mobile networks to

    ensure rates are developed on a cost basis

    using competitive indices.

    Electricity

    For electricity, the objective is to lower real costswhile improving reliability, quality and eciency

    without compromising the environment. The work

    programme therefore reects the imperatives of

    procuring additional capacity at least economic cost

    and that system losses and other eciency factors are

    improved over the period. As a critical corollary, the

    OUR will continue to make representations to secure

    the competitive procurement of fuel for the sector and

    the adoption of a transparent index for reference prices.

    Within the parameters of Governments stated policy

    objectives, developments with respect to the sector

    and the existing regulatory framework, the major goals

    identied for the period are:

    Laying the basis for breaking the cycle of

    crisis addition to generation capacity with

    the procurement over the next ve years of

    some 480 MW of new generating capacity

    (replacement and additional);

    Creation and maintenance of an investment

    environment that is facilitative of

    competitive addition of least economic cost

    generation; Creating and enforcing a system of

    incentives designed to reduce electricity

    losses;

    Intensify monitoring and surveillance of all

    licencees within the electricity sector

    Building institutional capacity as a

    contingency for regulation of fuel

    procurement and of a Natural Gas sector in

    the event of its emergence.

    ater and Sewerage

    For water and sewerage, the focus is to provide access

    to aordable potable water and to sewerage services.

    An important element of this is to reduce non-revenue

    water and improve eciencies in the delivery process(by improving the infrastructure). The main goals for

    this sector are:

    Facilitating increased access to potable water

    and sewerage services in keeping with the

    objective of universal access to potable

    water;

    Fostering measurable improvements

    in service delivery with respect to the

    availability and reliability of potable water

    and sewerage services.

    Enforcement of the K Factor regime forimproving eciency of the water sector.

    Transport

    The OUR will again be seeking to have the regulatory

    framework in place to allow it to fully regulate economic

    aspects of the Transport sector. Currently, the OUR

    conducts the analysis of proposed tari changes and

    makes its recommendation to the Ministry.

    As we have not