organisation mgmt - nicmar ncp-21
TRANSCRIPT
-
7/28/2019 Organisation Mgmt - NICMAR NCP-21
1/19
NICMAR- SODE
PGP-CM - MODULE NO: 01
ASSIGNMENT
MANAGEMENT IN
ORGANISATIONS
COURSE CODE: NCP 21
PREPARED & SUBMITTED BY:
NAME: M.S.MADHURI
REG NO: 212-06-11-10652-2141
-
7/28/2019 Organisation Mgmt - NICMAR NCP-21
2/19
2
CONTENTS:
(I) Introduction 03(II) Scope of work 04(III) Organization chart 09(IV) Justification to organization chart 10(V) Functions 11(VI) Authority of personnel 17(VII) Recommendations 19(VIII)Conclusion 19(IX) Bibliography 19
-
7/28/2019 Organisation Mgmt - NICMAR NCP-21
3/19
3
MANAGEMENT IN ORGANISATIONS
INTRODUCTION:
A project is made up of a group of interrelated work activities constrained bya specific scope, budget, and schedule to deliver capital assets needed to
achieve the strategic goals of the company.
For any project to initiate, develop, achieve targets and finish in a systematic
manner, personnel is required to plan, schedule, lead, monitor execution till
completion or in briefMANAGE the project. This personnel is the PROJECT
MANAGER.
The project manager needs to see to the following before commencement and
also during execution of the work:
I-
PlanningII- Cost managementIII- Time managementIV- Quality management.
PLANNING:
Develop and manage the management plan with measurable goals andobjectives.
Organize and lead project team by implementing project controls, definingroles and responsibilities and developing communication protocols.
Identification of unique site conditions and their impact on constructionsequencing and operations.
Develop contract administration and documentation procedures. Identify elements of project design and construction that are likely to give
rise to dispute and claims and develop strategies to dissolve the same.
COST MANAGEMENT:
The Project in charge must interpret and integrate conceptual budgetprepared by the planning section and assess impacts on the project cost.
Develop a project budget taking into consideration project objectives, costconstraints and material procurement strategies.
Develop cash flow schedule based on project progress schedule. Determine impact of external economic factors on the project cost and methods of
funding the project in crisis.
-
7/28/2019 Organisation Mgmt - NICMAR NCP-21
4/19
4
Must determine the man-hour/cost forecasting productivity studies, impactanalysis, efficiency studies etc.
TIME MANAGEMENT:
Develop project scheduling requirements and systems. Monitor project milestones and schedule calculations to determine relative
percentage for work progress.
Developing and managing Critical Path schedules. Analysis of concurrent delays, comprehensive and non-comprehensive delays. Perform impact analysis on known or potential construction changes. Review acquisition plans and drawings to verify probability of constructability
within stipulated established performance period.
QUALITY MANAGEMENT:
Preparation of a quality management plan and selection and leading the qualitymanagement team (QA/QC) to perform as per plan.
Monitoring conformance of works to contract documents during constructionphase.
Determination of materials that require testing and assess performance resultsrelative to project quality objectives.
Ensuring adequate level of details in drawings to achieve desired level of quality. Monitor risk management and preparation and implementation of safety plans.
SCOPE OF THE GIVEN PROJECT
The project manager, for effective planning, scheduling and controlling the project
shall firstly undertake the feasibility studies of the project and develop the estimated
cost of the project. Based on this and the total stipulated duration of the project, the
project manager will deploy staff, mobilize required machinery and workers, and
procure materials required at the site.
1. Undertake feasibility studies:Taking into consideration the details of the project comprising construction
of 10 bungalows, 20 apartments in 5 buildings, 100 dwellings for white
collared workers, 300 dwellings for blue collared workers, a market and an
entertainment complex, the following analysis has been generated.
-
7/28/2019 Organisation Mgmt - NICMAR NCP-21
5/19
5
Assumptions: 1) Land cost not taken into consideration.
2) Material consumption and rates considered as per CPWD and DSR-
2009
3) Finishing viz. floor/wall tiles/ dado etc not taken into consideration.
4) Cost of designing and preparation of drawings and Architects haveNOT been considered.
Bungalows 2000 sft each 10 nos
Item Rate Unit Qty Amount
Excavation 200 Cum 3900 780000
Concrete works 7000 Cum 1100 7700000
Reinf Steel 51000 MT 135 6885000
Brickwork 3100 Cum 1200 3720000 All Plastering 175 Sqm 10500 1837500
All Painting 90 Sqm 10500 945000
Sanitary and
plumbing Lump sum 164006
Doors/
Windows/ Grills Lump sum 109338
Electrical
fixtures Lump sum 54669
Misc Lump sum 221955
TOTAL 22417468
Apartments1300 sft each
20nos- in 5
bldgs
Item Rate Unit Qty Amount
Excavation 200 Cum 4230 846000
Concrete works 7000 Cum 1520 10640000
Reinf Steel 51000 MT 180 9180000
Brickwork 3100 Cum 1550 4805000
All Plastering 175 Sqm 14500 2537500 All Painting 90 Sqm 14500 1305000
Sanitary and
plumbing Lump sum 219851
Doors/
Windows/ Grills Lump sum 146568
Electrical Lump sum 73284
-
7/28/2019 Organisation Mgmt - NICMAR NCP-21
6/19
6
fixtures
Misc Lump sum 297532
TOTAL 30050735
Dwellings 800 sft each 100 nos
Item Rate Unit Qty Amount
Excavation 200 Cum 26050 5210000
Concrete works 7000 Cum 4000 28000000
Reinf Steel 51000 MT 480 24480000
Brickwork 3100 Cum 4800 14880000
All Plastering 175 Sqm 44900 7857500
All Painting 90 Sqm 44900 4041000
Sanitary and
plumbing Lump sum 633514
Doors/
Windows/ Grills Lump sum 422343
Electrical
fixtures Lump sum 211171
Misc Lump sum 857355
TOTAL 86592883
Dwellings 650 sft each 300 nos
Item Rate Unit Qty Amount
Excavation 200 Cum 54000 10800000
Concrete works 7000 Cum 10600 74200000
Reinf Steel 51000 MT 1275 65025000
Brickwork 3100 Cum 11850 36735000
All Plastering 175 Sqm 109550 19171250
All Painting 90 Sqm 109550 9859500
Sanitary and
plumbing Lump sum 1618431
Doors/
Windows/ Grills Lump sum 1078954
Electrical
fixtures Lump sum 539477
Misc Lump sum 2190276
TOTAL 221217888
-
7/28/2019 Organisation Mgmt - NICMAR NCP-21
7/19
7
Entertainment
complex 28000 sft 1 no
Item Rate Unit Qty Amount
Excavation 200 Cum 15000 3000000
Concrete works 7000 Cum 5500 38500000 Reinf Steel 51000 MT 600 30600000
Brickwork 3100 Cum 1600 4960000
All Plastering 175 Sqm 15000 2625000
All Painting 90 Sqm 15000 1350000
Sanitary and
plumbing Lump sum 607763
Doors/
Windows/ Grills Lump sum 405175
Electrical
fixtures Lump sum 810350 Misc Lump sum 828583
TOTAL 83686871
Market 100 sft 20 nos shops
Item Rate Unit Qty Amount
Excavation 200 Cum 400 80000
Concrete works 7000 Cum 180 1260000
Reinf Steel 51000 MT 25 1275000
Brickwork 3100 Cum 130 403000
All Plastering 175 Sqm 1200 210000
All Painting 90 Sqm 1200 108000
Sanitary and
plumbing Lump sum 25000
Doors/
Windows/ Grills Lump sum 40000
Electrical
fixtures Lump sum 13344
Misc Lump sum 22193
TOTAL 3436537
Area
development 300000 sft 1 no
Item
Rate in
Rupees Unit Qty Amount
-
7/28/2019 Organisation Mgmt - NICMAR NCP-21
8/19
8
Surface Dressing 4 Sft 200000 800000
Concrete works 7000 Cum 4000 28000000
Reinf Steel 51000 MT 400 20400000
Turf 100 Sft 65000 6500000
Electrical/Lamps Lump sum 338800
Misc Lump sum 552388
TOTAL 55791188
Total Estimated value = 503193570.00 INR
Total Estimated time required = 30 months
Hence Average turnover required per month = 16773119.00 INR
Considering that the turnover per annum must be @ 80 lakhs INR per main staffdeployed, the company must have 26 main staff members under companys roll
and the rest be recruited as supervisors locally.
All machine operators shall be recruited locally on temporary basis.
2. Mobilization of Manpower and Machinery:One the estimate is prepared, the manpower and machinery are to be mobilized. The
Project In-charge in consultation with planning department shall arrive to an organization
chart to assess and deploy the required number of personnel for each department at each
level under companys roll and also arrange to recruit the balance required staff atsupervisor level locally.
The organization chart shall be as follows:
-
7/28/2019 Organisation Mgmt - NICMAR NCP-21
9/19
-
7/28/2019 Organisation Mgmt - NICMAR NCP-21
10/19
10
Machine operators (locally recruited)JUSTIFICATION OF ORGANIZATION CHART:
The above formulated organization chart shall prove to be effective in timely and
profitable execution of all works in the project provided all responsibilities of all staff arecomplied with. The requirement of the aforesaid number of staff can be justified as
follows:
(I) Administration: 1 number officer and 1 assistant are required for executingall administration works effectively. In failure of this the single staff at
administration will be over burdened with various works and will fail to
perform any with perfection.
(II) Site Execution: Owing to the estimated project cost and duration, works atdifferent phases need to be executed simultaneously. For this the presence ofexperienced senior engineer is necessary. The senior engineer shall
communicate to his subordinates who shall further pass the instructions to the
locally recruited supervisors for good communication and execution of
works.
(III) QS/Planning: At the QS and planning department a number of works need tobe executed simultaneously namely project planning and scheduling,
preparing RA Bills, reconciliation of materials, preparation and certification
of PRW & sub contractor bills, preparation of daily, weekly and monthlyreports and forwarding the same to HO etc. Hence a senior engineer is
necessarily required and a junior engineer for supporting the head. 1 number
of supervisor may be deputed for all necessary documentation,
correspondence and supportive data preparation at the department.
(IV) QA/QC: For the quality assurance and quality control an experienced officerneed to be deputed for expertise in all operations. He needs to be assisted by
a supervisor for all supportive documentation in the project.
(V) Accounts: An experienced officer shall be deputed in accounts departmentfor accuracy in all accountability and bank statements. He requires 1 number
of assistant that shall support in all works to be executed.
(VI) Stores: The stores department need to accurately maintain all inward andissuance and balance stock of materials. Depending on the magnanimity of
-
7/28/2019 Organisation Mgmt - NICMAR NCP-21
11/19
11
the project, an assistant manager with an assistant need to be deputed for all
data recordings, purchases, and maintenance of all PO, PR, MRN, MIS
records. The department shall have two supervisors to supervise materials
stocks at site and issuance of material.
(VII) R&M: The R&M department requires one strong officer having strongcommand over the workers. He need to be assisted by an assistant to ensure
proper communication with all workers effectively.
(VIII)Safety: the safety department shall necessarily have one officer with goodexperience in following safety at site. He shall be assisted by an assistant for
all training programmes of workers. The officer, assistant and supervisor
shall constantly review the site for any non compliances of safety being
practiced and shall take necessary action for correction of the same. A round
the clock compounder shall be deputed for giving all kinds of first aid at site
in event of emergency.
(IX) Mechanical: The mechanical department shall essentially be deputed with anengineer for looking to all technicality in maintenance of machinery at site.
He shall be assisted by an experienced technician for all repairs and
monitoring. Two supervisors shall be deputed for all minor daily
maintenance works for all machinery at site. All operators shall be recruited
locally.
(X) Electrical: The electrical department requires an experienced seniortechnician with an assistant for all major electrical works. They may besubordinated by a supervising assistant for other works and documentation.
(XI) EDP: the EDP department can be effectively handled by an assistant gradepersonnel. He shall regularly update all data and see to the occasional
maintenance of computer systems at site.
FUNCTIONS:
PROJECT MANAGER and DEPUTY PROJECT MANAGER:
The project manager shall ensure TIMELY DELIVERY of targets by frequentlymonitoring construction programs and ensuring that there is not more than 10%
delay in progress as per the program.
-
7/28/2019 Organisation Mgmt - NICMAR NCP-21
12/19
12
He is responsible to inspect Non conformity of work done by going through thereports and shall not allow more than 10 Non Conformity reports in 3 months.
Shall ensure zero accidents to workers at site by reviewing and taking aptmeasures for 100% safe man hours.
Shall monitor and health and environment to ensure not more than 2% workmenfall ill due to unhygienic work conditions.
Shall ensure 100% that construction materials at site are stacker in propermanner and unwanted debris are removed regularly and effectively.
ADMINISTRATION DEPARTMENT:
The administration department is responsible to record the attendance of all staffand get it signed by the project in charge on daily basis.
The department shall also check for uninformed absentees, and prolongedabsenteeism of any staff and report the same to the project in charge/projectmanager.
The administration officer shall check for all external affairs of the company atthat particular site namely, management of transportation, accommodation,
canteen/mess functioning, issuance of ID cards to all labour after verification,
The department will be responsible for obtaining all labour licenses. Shall maintain all insurance policies like C.A.R Policies, workmen
Compensation policy, cash on transit and fidelity.
Shall look to providing accommodation and basic amenities like clean water,electricity for all workmen.
Providing accommodation and conveyance to all staff and seeing to theirwelfare.
He shall comply to keep a record of the details of all staff members at that siteand report to the head office in non conformity of any.
Shall be responsible to make all arrangements for Executives of the companyduring review visits.
ACCOUNTS DEPARTMENT:
The accounts department must responsibly account for every rupee spent fromthe companys account.
Must prepare salary statements for all employees. Must check the cash flows, dues, and pending liabilities and report the same to
the project in charge.
-
7/28/2019 Organisation Mgmt - NICMAR NCP-21
13/19
13
The accounts officer shall report to the project manager for all transactions andtake approval for each transaction.
He shall be responsible for accuracy in tallying the net available cash at handwith the book balance.
Shall be responsible for calculating TDS and advance recoveries for all subcontractors and PRWs during the payments of bills.
Shall reconcile Bank statements and report the same to the project manager. Shall be responsible for updating all ledgers and sub ledgers on daily basis. Shall account for pending funds and budgeted expenses to the project manager in
consultation with the QS department.
RESOURCE & MOBILITY (R&M) DEPARTMENT:
The R&M in charge shall be responsible for mobilization of workers. They shall account for the NMR Labour deployed at site for various purposes
after approval of project manager.
Shall be responsible to deal with all qualms of workers and discuss the samewith project manager to arrive to a decision.
Shall be responsible for welfare activities of the workers. Shall check for effectiveness in work of labour deployed and shall also account
for idle time of labour.
EDP DEPARTMENT:
The EDP department in charge/ staff shall be responsible for recording all dataand processing the same. He shall follow up with the head office management by
producing all data regularly.
Shall be responsible for the hardware & software maintenance of all computersystems being used at site.
In event of minor repair of any computer system, he shall in consultation withthe project manager get the same done otherwise for major issues shall report to
the concerned HOD at the head office.
Shall regularly update a back up for all data stored as a preventive measure incase of sudden failures.
-
7/28/2019 Organisation Mgmt - NICMAR NCP-21
14/19
14
QS / PLANNING:
The in charge has to ensure time management for delivery of resources bymonitoring material procurement, and manpower mobilization as per need of the
project schedule.
Distribution of drawings, and execution schedule to all site execution staff andrecording regular feedback to progress.
Monitoring sequence of construction as per schedule. Timely delivery of RA Bills by ensuring accurate measurements of all executed
works, authorization of joint records and timely approvals for required items
from client.
Analysis, and approval of PRW rates, sub-contractors work orders issuance, andmonitoring timely preparation of bills for the same.
Monitoring zero cost of the project and reporting the same to the project incharge.
Preparation and analysis of PCE on monthly basis and informing the same forsuggestions and improvement with the deputy project manager and project
manager.
Reconciling materials used at site and reporting to deputy project manager forlosses and corresponding the same to QC In charge for effective monitoring.
SITE EXECUTION TEAM:
The in charges shall conform to the requirements of the client and ensure thestandard of quality at all times.
The site execution shall effectively mobilize workers at site for quality andquantity of work.
Wastage of materials shall be controlled effectively by all site execution staff atpar.
Shall ensure timely delivery of all works as per schedule procured fromQS/Planning Department.
Shall ensure accuracy in bill preparation for PRW. Shall inform project in charge for any discrepancy in drawings or work
feasibility to seek suggestions.
SAFETY DEPARTMENT:
The safety in charge shall monitor safe working environments to ensure all staffand workmen are issued with PPE
-
7/28/2019 Organisation Mgmt - NICMAR NCP-21
15/19
15
The officer shall ensure zero accidents at site involving workmen or staff. The officer shall occasionally conduct meetings and demonstrate methods of
safety at various stages of construction.
The department shall look into educate all workmen the importance of usingsafety gear so as to remain safe during work.
The officer shall follow up with the stores in charge and the project manager forprocurement of apt safety gear namely helmets, shoes, gloves, goggles, and
belts.
The officer shall suggest to the project manager for locally recruiting acompounderto give first aid at site.
A high degree of housekeeping must be ensured. All potential hazards are identified , assessed and eliminated. Safe accessibility is ensured for all workmen & staff. Safety during working at heights. Safe electrical installations at site for construction. Safety during welding operations. By providing Personal Protective equipment. Periodical testing of all equipment as per statutory requirements. Use of environment friendly construction process. Proper & safe storage of Hazardous and / or toxic substances. Controlling spillage / discharge and disposition of waste or other materials. Welfare measures. All persons deployed at site shall be knowledgeable of and comply with
environmental laws, rules & regulations.
Daily safety meetings (Tool box meetings) Proper training to staff & workmen to carry out assigned job safely. Inspections & Audits- To carry out regular safety inspections & Audits. Proper workmen compensation, insurance, registration. Arranging all Safety Health and Environment permits before commencement of
works. (Earthwork, Hot work, height work, blastings etc)
By submitting timely checklists on SHE activities. By displaying caution boards, details of available emergency services etc
QA/QC DEPARTMENT:
The QA/QC in charge shall check for accuracy in calibration of testingequipment and devices.
-
7/28/2019 Organisation Mgmt - NICMAR NCP-21
16/19
16
Shall monitor the execution at site to be in conformity with the standards as percontract.
Shall ensure that 100% of works at site are under the scrutiny of the QC/QAdepartment through quality inspection, observation and product realization.
The department shall take up preventive actions to prevent realization of materialfailure after execution so as to ensure cost effectiveness to the project.
STORES:
The stores in charge shall follow up with the planning in charge for timelyprocurement of materials.
Shall be responsible for the protection & safe custody of materials and check forstacking. Stocking and accounting for each item procured as per standards.
Shall monitor keep a track of shelf life of items so as to ensure consumption ofitems with early expiry date first and hence reduction in wastage.
Shall regularly follow up with the suppliers for timely delivery of materials atsite as and when required.
Shall physically verify materials at site along with QS department for effectivereconciliation of materials.
ELECTRICAL DEPARTMENT:
The electrical department shall be responsible for all electrical connections,electrification and repair and maintenance of electrical appliances at site.
The department shall provide necessary electricity, lighting, cables and socketswherever necessary at site for all construction procedures.
Shall regularly check for all exposed cables at site and replace the same forsafety.
Shall indent for any electrical wires, testers or other equipment required at sitewith project managers approval.
MECHANICAL DEPARTMENT:
The mechanical department in charge shall be the authorized for executing allmaintenance and accountability of all machines at site.
Shall note for the break down of each machinery and time taken for repair of thesame.
-
7/28/2019 Organisation Mgmt - NICMAR NCP-21
17/19
17
He shall assign to procure the required spare parts for the repairs. In event of major break downs he shall report to the project manager and also
follow up at head office for the same.
All correspondence related to the manufacturers shall be the mechanicaldepartment in charges responsibility.
Shall report to the QS department for run time of all machines namely hydras,excavators, dozers, dumpers, tractors, trailers, Batching plants, vibrator needles,
concrete pumps etc on daily basis.
AUTHORITIES OF PERSONNEL:
Various responsibilities and authorities have to be assigned to the respective staff
members for proper functioning of the organization.
Project In-Charge/Project Manager:
The project in charge shall coordinate with the planning depar5tment for preparingvarious planning schedules and forward the same for timely approval. The project
in charge is authorized for making any recommendations to the planning
department.
He shall recommend finalizing the deployment of staff and manpower inconsultation with the planning department.
Shall take decisions in finalizing the materials and to take action for procurement. The project in charge (here PROJECT MANAGER) shall be the authorized
representative to deal with client / consultant.
The authority to take all decisions pertaining to execution and completion of theproject and exercising control over various departments at site is exclusively of the
PROJECT IN CHARGE (here the project manager).
He shall pass necessary instructions for implementation of plans and takecorrective measures wherever required.
All decisions pertaining to temporary infrastructure development, labour welfare,termination of sub contractor work orders/suppliers, PRW are authorized to the
project manager.
-
7/28/2019 Organisation Mgmt - NICMAR NCP-21
18/19
18
Site In-charge:
The site in charge or the senior engineer in this case is responsible to receive alldrawings, monthly planning schedules, and targets from the QS and Planning
department and discuss with the project in charge for compliance.
The site in charge is authorized to assign and allocate various duties to hissubordinates and to PRWs.
He shall instruct his subordinate for effective implementation of quality plan. He must ensure the recording of daily progress of his site for effective monitoring
and further planning.
He shall be responsible to coordinate with client for day to day progress of work atsite and report to the project manager for any non conformity of the same.
QC/QA In-charge The QC officer shall see to formulating the inspection and test plans, QC formats
for various items as per the specifications and circulating to concerned
departments.
He shall be responsible to prepare and conduct various necessary tests on materialsas per requirements.
Observation of all works at site and reporting to the project manager for any nonconformities.
Shall be responsible to implement all quality management systems formulated bythe project manager and planning in charge.
Shall conduct field tests like cube test, proctors density test and SchmidtsRebound hammer (NDT) test for assurance of quality.
Site In-charge:
The site in charge or the senior engineer in this case is responsible to receive alldrawings, monthly planning schedules, and targets from the QS and Planning
department and discuss with the project in charge for compliance.
The site in charge is authorized to assign and allocate various duties to hissubordinates and to PRWs.
He shall instruct his subordinate for effective implementation of quality plan. He must ensure the recording of daily progress of his site for effective monitoring
and further planning.
He shall be responsible to coordinate with client for day to day progress of work atsite and report to the project manager for any non conformity of the same.
-
7/28/2019 Organisation Mgmt - NICMAR NCP-21
19/19
19
RECOMMENDATIONS:
The most effective way of project execution is :
The Project manager must have total command over all aspects of an organization. He must effectively monitor all departments and shall see to the coordination
between the departments.
Shall maintain good relationship with his staff so as to get maximum output fromthe employees.
He shall have his exclusive strategies of management so that he can achieve alltargets with employee work satisfaction at the same time.
The easiest way to manage is by keeping the organization and procedurestransparent to all staff and workers and by constantly informing the Executivelevel management of all developments at site.
CONCLUSION:The construction industry remains largely manpower intensive industry. It
exhibits some unique conditions calling for experienced, smart, intelligent
and unique management approach the success or failure of any construction
industry largely depends on the quality and cooperation of workforce than thetechnology incorporated. Further the managers must not only focus on targets but
also attend to employee qualms as correction of this will result in employee
satisfaction and effective implementation of all schedules.
BIBLIOGRAPHY:
Handbook on construction project management-FTA
Essentials of Management Harold Koontz/ Heinz Weihrich A Guide to Construction projects- Keith Neighbour