marcom annual report 2013 - pianc home reports commissions 2013...marcom annual report 2013 3 water...

11
MarCom Annual Report 2013 1 The World Association for Waterborne Transport Infrastructure Maritime Navigation Commission - MarCom Association Mondiale pour des Infrastructures de Transport Maritimes et Fluviales Commission de la Navigation Maritime - MarCom MarCom Annual Report 2013 1. General Programme In 2013, MarCom continued to pay specific attention to reducing the number of ongoing Working Groups, with a special focus on finalizing those that have been active for longer. This activity has required significant efforts to Working Group Chairpersons and MarCom Mentors in the follow-up of the Working Groups, and to MarCom members in general in review tasks. With the two Terms of Reference approved during the year, the objective is to dedicate Working Groups to topics of very high interest for the PIANC Community and at the same time achieve a steady flow limiting the duration of the Working Groups whenever possible while keeping the high quality standard required to PIANC Reports and even increasing it. There was also progress in the definition of topics for new Working Groups, addressing two key issues: use of Ship-Handling simulation for channel and harbour design and design of small and medium LNG Terminals, including bunkering facilities. A significant input regarding topics for future Working Groups on Port Terminals will be derived from the ongoing WG 158 “Masterplans for the Development of Existing Ports”, already at an advanced status. Ongoing Working Groups and Terms of Reference address the most highly rated topics from the MMX questionnaire drafted during the MMX PIANC Congress in Liverpool. MarCom has been reviewing during 2013 its Action Plan in line with the ongoing revision of PIANC Strategic Plan. Mentoring of Working Groups was a key discussion topic, oriented to improve management, development and efficiency of the Working Groups and the quality of the Reports. Meetings In 2012, MarCom organised two commission meetings: Brussels, January 29 th and 30th Sendai (Japan),September 11 th and 12 th , hosted by the Japanese National Section. The meeting was combined with a technical visit to the Tsunami damaged Ports in Miyagi prefecture. MarCom membership

Upload: lyhanh

Post on 02-May-2018

221 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: MarCom Annual Report 2013 - PIANC Home reports commissions 2013...MarCom Annual Report 2013 3 Water Injection Dredging is a four-step process with the following sequence: injection

MarCom Annual Report 2013

1

The World Association for Waterborne Transport Infrastructure

Maritime Navigation Commission - MarCom

Association Mondiale pour des Infrastructures de Transport

Maritimes et Fluviales

Commission de la Navigation Maritime - MarCom

MarCom Annual Report 2013

1. General Programme In 2013, MarCom continued to pay specific attention to reducing the number of ongoing Working Groups, with a special focus on finalizing those that have been active for longer. This activity has required significant efforts to Working Group Chairpersons and MarCom Mentors in the follow-up of the Working Groups, and to MarCom members in general in review tasks. With the two Terms of Reference approved during the year, the objective is to dedicate Working Groups to topics of very high interest for the PIANC Community and at the same time achieve a steady flow limiting the duration of the Working Groups whenever possible while keeping the high quality standard required to PIANC Reports and even increasing it. There was also progress in the definition of topics for new Working Groups, addressing two key issues: use of Ship-Handling simulation for channel and harbour design and design of small and medium LNG Terminals, including bunkering facilities. A significant input regarding topics for future Working Groups on Port Terminals will be derived from the ongoing WG 158 “Masterplans for the Development of Existing Ports”, already at an advanced status. Ongoing Working Groups and Terms of Reference address the most highly rated topics from the MMX questionnaire drafted during the MMX PIANC Congress in Liverpool. MarCom has been reviewing during 2013 its Action Plan in line with the ongoing revision of PIANC Strategic Plan. Mentoring of Working Groups was a key discussion topic, oriented to improve management, development and efficiency of the Working Groups and the quality of the Reports. Meetings In 2012, MarCom organised two commission meetings:

Brussels, January 29th and 30th

Sendai (Japan),September 11th and 12th, hosted by the Japanese National Section. The meeting was combined with a technical visit to the Tsunami damaged Ports in Miyagi prefecture.

MarCom membership

Page 2: MarCom Annual Report 2013 - PIANC Home reports commissions 2013...MarCom Annual Report 2013 3 Water Injection Dredging is a four-step process with the following sequence: injection

MarCom Annual Report 2013

2

Three new National Sections are now represented in PIANC: Turkey (Mr Burak Bilgin), Poland (Mr. Maciej Gucma) and Australia (Mr. Peter Fountain and Mr. Mr. Scott Wiliam Keane). This new members increase MarCom geographic presence substantially. Mr. Mohammad Reza Allahyar replaced Mr. Ali Akbar Safaaei as representative of the National Section of Iran. At present there are 31 MarCom members, amongst them one is chairman, four are alternate members and three are Young Professionals. 2. Presentations A presentation was done by Mr. Lucien Halleux, Chairman of WG 144 “Classification of soils and rocks for the Maritime Dredging Process”. 3. Publications In 2013, two MarCom Working Group Reports were published by PIANC.

WG 118-2013 (Former MarCom-Incom EG) “Direct Access to Maritime Ports by adapted Inland Waterway Vessels” (Chairman Mr. Caude, France)

The Report starts with the analysis of relevant case studies in ports from Europe, U.S.A. and China, including legislation issues. Methods used to improve safe access of Inland Waterway Vessels (adapted) to Maritime Ports are addressed such as:

o Wave and wind analysis required o Determination of Environmental forces and their effects on Vessel stability o Evaluation of restricted seaworthiness of Inland Waterway Vessels in Maritime

areas, including risk analysis of the vessel o Practice

The Report finishes with a set of recommendations drafted by the Expert Group.

WG 120-2013 (Former MarCom WG 51) “Water Injection Dredging” (Chairman Mr. Smits, Belgium)

Page 3: MarCom Annual Report 2013 - PIANC Home reports commissions 2013...MarCom Annual Report 2013 3 Water Injection Dredging is a four-step process with the following sequence: injection

MarCom Annual Report 2013

3

Water Injection Dredging is a four-step process with the following sequence: injection of water (low pressure), fluidization of top sediment layers, generation of density flow over the bottom and sustainable relocation. This process has obvious environmental advantages, but it is only suitable under specific conditions regarding characteristics of the site, sediments, bathymetry and hydrodynamics. The main applications are maintenance dredging, shallows in sandy rivers, cleaning of locks, jetties, pipelines and other infrastructure and levelling of hopper tracks and trimming of slopes. In addition to the above mentioned issues, the Report addresses the theoretical analysis and physical principles on which the method is based, specific equipment, environmental conditions and monitoring of the process. Also contractual conditions are addressed because of the specific features of the process. Finally, a comprehensive set of Case Studies is shown.

WG 121 Harbour Approach Channels: completed in 2013 At the end of 2013, three additional Working Group reports are ready for publication in PIANC HQ:

WG 121 (Former MarCom WG49) “Harbour Approach Channels Design Guidelines”, that will be the successor to one of the most important former PIANC Reports, WG 30 “Approach Channels. A guide for Design”, issued in 1997.

Special publication on “Tsunami Disasters in Ports due to the Great East Japan Earthquake”

WG 135 “Design principles for Container Terminals in Small and medium Ports”

4. Progress of MarCom Working Groups The status of ongoing MarCom Working Groups can be summarized as follows.

Page 4: MarCom Annual Report 2013 - PIANC Home reports commissions 2013...MarCom Annual Report 2013 3 Water Injection Dredging is a four-step process with the following sequence: injection

MarCom Annual Report 2013

4

WG 47 « Criteria for the Selection of Breakwater Types » The Chairman of the WG has distributed to its members a draft for discussion. Once the Working Group agrees on a final text will be reviewed by MarCom members. WG 48 « Guidelines for Port Constructions related to Bow Thrusters » The Report has already been reviewed by MarCom and will be ready for publication as soon as the Final version is received from the Working Group. WG 144 « Classification of Soils and Rocks for the Maritime Dredging Process » The Final Report should be forwarded to MarCom soon for publication. A first version of the Report will be published in electronic format and, after a year during which observations from readers and experts are expected, the Final version will be drafted. WG 145 « Berthing Velocities and Fender Design » Activities are ongoing. The Working Group has gathered a lot of information. A presentation to MarCom is expected in February 2014. WG 152 « Guidelines for Cruise Terminals » The new Chairman, Mr. David Pino has started his activity in September. The WG has fully resumed its activity. WG 153 « Recommendations for the Design of Marine Oil Terminals » The Working Group is making good progress. WG 158 Masterplans for the Development of Existing Ports The Working Group progresses very well according to schedule,. A presentation to MarCom and a draft final report are expected in February 2014. WG 159 Renewable Energy for Maritime Ports The Working Group is in progress. A questionnaire has been distributed to National Sections through PIANC HQ. EG 160 (ex WG 50) « Overview of Design Codes and Guidelines for Harbour Structures » The EG has resumed activity. WG 161 Interactions between Offshore Windfarms and Maritime Navigation The Working Group has started activity. WG 162 – Recommendations for increased durability and service life of marine concrete infrastructure The Working Group is active, with a first draft report foreseen in 2014 and completion in 2015.

Page 5: MarCom Annual Report 2013 - PIANC Home reports commissions 2013...MarCom Annual Report 2013 3 Water Injection Dredging is a four-step process with the following sequence: injection

MarCom Annual Report 2013

5

WG 164 Upgrade of Port Terminals by increasing dredged depth As there is no candidate to chair the Working Group, the kickoff meeting will be organized by MarCom Chairman and Secretary and try to start the activity anmd select a Chairperson. WG 165 - Design and Maintenance of Container Terminal Pavements The WG is active. A first draft report is expected by the end of 2014. WG 167 Design of combined terminals for Ro-Ro and Ro-Pax vessels The Chairman was designated in September 2013 and the Group is ready to start. 5. New Working Groups ExCom approved the following two Terms of Reference in 2013:

WG 171- “Ship Handling Simulation Dedicated to Channel and Harbour Design” The evolution of the size, variety, manoeuvring capacity and behaviour of ships as well as the improvements and developments in available tools support the need to set a new Working Group that will update the Report of Working Group 20 from 1992. The Working Group Report will provide guidelines and recommendations on best practice in the application of Ship handling Simulation to verify the design of approach channels to harbours and terminals and the manoeuvring areas within harbours as well as to check safe manoeuvres beforehand.

WG 172- “Design of small and medium LNG terminals including bunkering facilities”

The potential of use of LNG as an alternative fuel for ships is now a relevant issue due to recent IMO regulations and as part of the debate on improving the environmental performance of shipping. Nowadays, most LNG operations are concentrated in large dedicated terminals but, among other needs, bunkering with LNG requires investment on appropriate infrastructure and this fact increases the demand of guidelines and recommendations for the design of small and medium LNG terminals and even potential integration of those in multipurpose terminals. The Working Group will investigate jetties and berths, land installations, marine transfer arms for loading and unloading, technical requirements and design, safety aspects and risk assessment. The final product will be a set of recommendations and guidelines for design and operation of small and medium LNG terminals including bunkering facilities.

6. Progress of Joint Working Groups / Expert Groups MarCom has correspondent Members in the following joint or other Commission’s Working Groups:

- PTG “Permanent Task Group on Climate Change” - EnviCom “Working with nature”

Page 6: MarCom Annual Report 2013 - PIANC Home reports commissions 2013...MarCom Annual Report 2013 3 Water Injection Dredging is a four-step process with the following sequence: injection

MarCom Annual Report 2013

6

- EnviCom WG 136 “Sustainable Maritime navigation” - InCom WG 140 “Semi-probabilistic design concept for inland hydraulic structures”: Mr.

Fernagu, chairman of EG 160 - RecCom WG 147 “Guidelines for facilitation and integration among recreational,

fishery and commercial navigation”: Mr. Ferrante - EnviCom WG 150 “Green ports, a practical guide for a sustainable seaport”: Mr.

Ferrante - InCom WG 155 “Ship behaviour in Locks and Lock approaches”: Mr. Hunter 7. Special Activities PIANC-MarCom Seminar in Japan 2013 After the September MarCom meeting and Technical visit, several MarCom members participated actively in the PIANC-MarCom Seminar in Japan 2013, organized by the National Section of Japan. The Seminar was preceded by a visit to the Port of Tokyo and its Museum, including some of the sites for the venue of the 2020 Olympic Games. 8. MarCom Technical Visit Last September 12th PIANC National Section of Japan hosted a visit to the ports in Miyagi Prefecture that were severely damaged by the Tsunami. MarCom visited several sites, accompanied by Mr. Koichi Sase, from Tokohu Regional Development Bureau, organization from the Ministry of Land, Infrastructure, Transport and Tourism in charge of the reconstruction programme of the region. The visit included Onagawa Port, Ishinomaki fishery port, with presentations by the Fisheries Infrastructure Department of the Ministry of Agriculture, Fishing and Fisheries, and finally the Sendai-Shiogama Port with an impressive overview of the reconstruction of the port terminals. MarCom had the opportunity to know on site the huge extent of the damage caused by the Great East Japan Earthquake and Tsunami and to appreciate the real complexity of the reconstruction process that involved impressive efforts in engineering, planning, management, cooperation and stakeholder involvement, which have been the tools for success in this outstanding challenge. MarCom wishes to thank the host of the September meeting, the PIANC National Section of Japan, specially the President of the National Section Dr.Sunohara and MarCom member Mr. Higuchi, as well as the Authorities that presented the different sites during the technical visit.

Page 7: MarCom Annual Report 2013 - PIANC Home reports commissions 2013...MarCom Annual Report 2013 3 Water Injection Dredging is a four-step process with the following sequence: injection

MarCom Annual Report 2013

7

Page 8: MarCom Annual Report 2013 - PIANC Home reports commissions 2013...MarCom Annual Report 2013 3 Water Injection Dredging is a four-step process with the following sequence: injection

MarCom Annual Report 2013

8

Page 9: MarCom Annual Report 2013 - PIANC Home reports commissions 2013...MarCom Annual Report 2013 3 Water Injection Dredging is a four-step process with the following sequence: injection

MarCom Annual Report 2013

9

Annex 1.- List of Members of MarCom – December, 2013

Chairman

Mr. Francisco Esteban Lefler

Director of Innovation and

Technology

Technical Services

FCC Citizen Services

Avenida del Camino de Santiago 40

Building 2 3rd Floor

28050 Madrid. España

Spain

Phone : +34 91 757 30 54

Fax: +34 915 273 47

Mob : +34 639 199 713

e-mail : [email protected]

www.fccco.es

www.fcc.es

Secretary

Mr. Dominique Etienne

Centre d’Etudes Techniques Maritimes

et Fluviales

2 boulevard Gambetta

BP 60039

F-60321 Compiègne Cedex

France

phone: +33 3 44 92 60 16

fax : +33 3 44 20 60 75

mob : +33 63 37 46 61

e-mail:

dominique.etienne@developpement-

durable.gouv.fr

Member:

Mr. H.F. Burcharth

Professor Dr. Techn.

Dep. of Civil Eng.

Aalborg University

Sohngaardsholmvej 57

DK-9000 Aalborg

Denmark

phone: +45 9635 8482

fax: +45 9814 2555

e-mail: [email protected]

Member

Mr. Arjan van der Weck

Royal Boskalis

Westminster/Hydronamic

Rosmolenweg 22

Postbus 209

Papendrecht

3350 AE

The Netherlands

phone: +31 (0)78 69 69 837

cell : +31 (0)6 516 14 898

fax:+31 78 69 69 555

e-mail: [email protected]

Member

Mr. P.D. Hunter

HR Wallingford

Howbery Park

Wallingford

Oxon, OX10 8BA

United Kingdom

phone : +44 1491 82 2353

mob. : +44 7774 620694

fax : +44 1491 832233

e-mail : [email protected]

Member

Mr. Andrea Ferrante

Ministry of Infrastructure and Transport

Via Nomentana 2

00161 Roma

Italy

phone: +39 0 6 44125242

fax : +39 0 6 44267270

e-mail: [email protected]

Member

Mr. Tore Lundestad

Port Director

Borg Haven IKS

Port Authority of Fredrikstad and

Sarpsborg

Øraveien 27

NO-1630 Gamle Fredrikstad

Norway

phone: +47 69 35 89 01

fax: +47 69 35 89 20

mobile: +47 91 11 72 02

e-mail: tore.lundestad@borg-

havn.no

www.borg-havn.no

Member

Mr. Luc Van Damme

OZConsult

Ganzenstraat 44

B-8000 Brugge

Belgium

phone: +32 50 331907

mobile: +32 475 559907

e-mail: [email protected]

Member

Mr. F.M.J. van de Laar

IAPH Europe

Spreenwendaal 6

2914 KK Nieuwerkerk IJssel

The Netherlands

phone: +31 180 323399

fax: +31 180318569

e-mail : [email protected]

Member

Mr. Veikko Saukkonen

Port of Helsinki

P.O. Box 800

FIN-00099 Helsinki

Finland

phone: +358 9 310 33673

fax : +358 9 310 33627

mobile +358 50302 9041

e-mail:

[email protected]

Member:

Mr. Kjell Karlsson

Director of Port Infrasructure

Port of Stockholm

P.O. Box 27314

SE-102 54 Stockholm

Sweden

phone: +46 8 670 2600/20

fax : +46 8 670 2606

mobile: +46 70 770 2620

e-mail:

[email protected]

Member:

Mr. Stefan Hauser

Federal Ministry of Transport, Building and

Urban Development

Location Bonn

Referat WS 11

Inland and Coastal Waterways

P.O. Box 20 01 00

D-53170 Bonn

Germany

phone: +49 228 300 4212

fax : +49 228 300 807 4212

e-mail: [email protected]

Page 10: MarCom Annual Report 2013 - PIANC Home reports commissions 2013...MarCom Annual Report 2013 3 Water Injection Dredging is a four-step process with the following sequence: injection

MarCom Annual Report 2013

10

Member:

Mr. Yoshiaki Higuchi

Corporate Officer, Oriental

Consultants Co.,Ltd.

Sumitomo Fudosan Nishi Shinjuku

Building No.6,

3-12-1, Honnmachi, Shibuya-ku,

Tokyo, 151-0071, Japan

Japan

e-mail: [email protected]

Member:

Mr. E.D. Allen

Director of Port Engineering

Moffatt & Nichol

3780 Kilroy Airport Way

Suite 600

Long Beach

California 90806

USA

phone: +562 426 9551

fax: +562 424 7489

e-mail: [email protected]

www.moffatnichol.com

Member:

Mr. Rafael Escutia

Port Insight Consulting

Pl. Tirant lo Blanc, 3-6º-1ª

08005 - Barcelona

Spain

phone: +34 667 571 949

phone: +34 932 213 304

e-mail: [email protected]

or :

e-mail : [email protected]

Member:

Mr. Bhuvaragan Poiyaamozhi

Development Advisor (Ports)

Ministry of Shipping

R. No. 537, Transport Bhavan

Parliament Street

New Delhi 110001

India

Fax : +91 011 23 71 04 56

e-mail :

[email protected]

Member:

Dr. Adel Banawan

Associate professor

Naval Architecture and Marine

Engineering Department

Faculty of Engineering

Alexandria University

Alexandria

Egypt

phone: +20 102 593 792

fax: +203 592 1853

e-mail : [email protected]

Young Professional Belgium

Mrs Hadewych Verhaeghe

Flemish Ministry of Mobility and Public

Works

Maritime Access Division – Coastal Division

Vrijhavenstraat 3

B-8400 Ostende

Belgium

Phone : +32 (0)59 55 42 75

Mob : +32 (0)494 45 58 36

Fax : +32 (0)59 32 00 17

E-mail :

[email protected]

Alternate Member UK

Mr. Stephen Cork

Technical Director

Ports and terminal Planning

HR Wallingford

Howbery Park

Wallingford

Oxon, OX10 8BA

United Kingdom

phone: +44 1491 822296

fax: +44 1491 832233

e-mail: [email protected]

Alternate Member USA

Mr. Vahan Tanal

President

Vahan Tanal Consulting, Inc.

6 Luquer Road

Manhasset

NY 11030

USA

phone: 516.944.1717

fax: 516.944.9005

e-mail:

[email protected]

YP Com observer

Mr. Javier Almazan Palomino

Direction of Projects

Ports and Coasts

UG21

Spain

phone : 34 955602134

mobile : 34 696957916

e-mail : [email protected]

Member

Mr. Mohammad Reza Allahyar

Head of Coastal and Port

Engineering

Ports & Maritime Organization of

Iran

6th Floor, Ports and Maritime

Organization Building

Shahidi St.

Haghani Exp’way

Vanak Square

Tehran

Iran

Phone : +98 21 84932261

Fax: +98 21 84932279

e-mail : [email protected]

[email protected]

Young Professionnal Finlannd

Mr. Kim Andersson-Berlin

Arcus Ltd

Linnankatu 16

FI-20100 TURKU

Finland

Mob: +358 503 799 005

fax: +358 2233 0050

e-mail: [email protected]

Member

Dr Teak-Hee Han

Korea

email: [email protected]

Page 11: MarCom Annual Report 2013 - PIANC Home reports commissions 2013...MarCom Annual Report 2013 3 Water Injection Dredging is a four-step process with the following sequence: injection

MarCom Annual Report 2013

11

Member

Mr. Gerardo Castaño

Subdireccion de Marina Mercante

(SUBMERC)

Colombia

Phone : 2200490

e-mail : [email protected]

Alternate

CN. D. Juan Francisco Herrera

Subdireccion de Marina Mercante

(SUBMERC)

Colombia

e-mail : [email protected]

Alternate Sweden

Mr. Mattias Sandell

Technical Manager

Port of Stockholm

P.O. Box 27314

SE-102 54 Stockholm

Sweden

phone: +46 8 6702600

fax : +46 8 6702655

mobile: +46 70 7702720

e-mail:

[email protected]

Member

Mr. Burak Bilgin

Turkey

Phone: +90 212 334 4500 – (4361)

Email:

[email protected]

Member

Mr. Maciej Gucma

Center of Marine Traffic Engineering

Maritime University of Szczecin

Wally Chobrego 1/2

70-300 Szcezin

Poland

e-mail : [email protected]

Member

Mr. Peter Fountain

Industry Director Ports & Marine

AECOM

Level 21, 420 George Street

Sydney NSW 2000

Australia

e-mail: [email protected]

Alternate Australia

Mr. Scott Willian Keane

Managing Director

Keane Marine & Management

Australia

Cell Phone: +61 408558167

e-mail: [email protected]