Long-Term Plan Update. Source Control Projects Non-ECP Basins (ESP Basins) Carlos Adorisio, PE, SFWMD June 1, 2006. BASINS TRIBUTARY TO THE EVERGLADES. Long-Term Plan Update. Introduction - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Long-Term Plan Update

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Long-Term Plan UpdateLong-Term Plan Update

Source Control Projects

Non-ECP Basins

(ESP Basins)

Carlos Adorisio, PE, SFWMD

June 1, 2006

Page 2: Long-Term Plan Update

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

BASINS TRIBUTARY TO THE EVERGLADES

Page 3: Long-Term Plan Update

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Long-Term Plan UpdateLong-Term Plan Update

Introduction In general, the recommended strategy in the

Non-ECP basins is to rely upon source controls and full integration with CERP to achieve water quality standards.

In addition to the Non-ECP Permit requirements, Part 3 of the LTP (Pre-2006 Strategies, ESP Basins) defines supplemental strategies and approaches for water quality improvement in discharges from the Non-ECP Basins.

Page 4: Long-Term Plan Update

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Source ControlsSource ControlsNon-ECP BasinsNon-ECP Basins

Objectives are to be carried out using an integrated approach balancing four distinct elements:

Regional

Initiatives

Local BMP

Initiatives

Outreach

Voluntary

BMPs

Source

Controls

Page 5: Long-Term Plan Update

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Source ControlsSource ControlsNon-ECP BasinsNon-ECP Basins

Source Controls Cooperative agreements - monitoring and

implementation of BMPs On-going and/or proposed local capital

improvement projects Non-structural BMPs:

New permit requirement and/or modification to address water quality concerns

Operational changes Public outreach - ESP Public Outreach Plan

Page 6: Long-Term Plan Update

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Long-Term Plan UpdateLong-Term Plan Update

Non-ECP strategies funded under LTP (FYs 04-06) Source controls

BMP development and implementation: C-11 West and VOW

BMP Grant program: Feeder Canal Additional analyses

Ensure no impacts to flood protection: NSID and NNRC

Water quality improvement measures: C-11 West

Page 7: Long-Term Plan Update

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

The Broward Everglades The Broward Everglades Working Group (BEWG)Working Group (BEWG)

Background - In response to a request from Broward County EPD, LTP recognizes that reduction of phosphorus through source controls (i.e., urban BMPs) is of highest priority to achieve compliance with the phosphorus criterion.

LTP Project Description - The SFWMD will assist Broward County in coordinating a county-wide working group to develop a comprehensive pollution prevention plan with specific water quality goals.

Page 8: Long-Term Plan Update

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

BEWGBEWGAccomplishmentsAccomplishments

Stakeholders participated in the identification of various pollution reduction options, with each agency determining where they could contribute.

Each party presented an overview of activities underway and to be undertaken in support of the Working Group’s objectives and Everglades Restoration.

Activities and commitments of each stakeholder group were compiled as part of C-11 West Basin Pollution Reduction Action Plan (April 2006 Final Report).

Page 9: Long-Term Plan Update

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

BEWG Final ReportBEWG Final Report

http://www.broward.org/waterresources/c_11_pollution_actionplan.pdf

Page 10: Long-Term Plan Update

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

BEWGBEWGNext StepsNext Steps

Maintain momentum through frequent updates with participants, assist partners with implementation, and revise strategy as necessary

Measure progress through water quality monitoring

Continue partnership between Broward County & SFWMD to develop pollution reduction action plans for the NSID and NNRC basins and to expand outreach and technical support

Page 11: Long-Term Plan Update

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

C-11 W BasinC-11 W BasinSource ControlsSource Controls

TP range: 16-19 ppb (average: 17 ppb)SFWMD:

$2 million to cost share local capital improvement projects

SBDD and ITDD to modify permits Stringent requirement for new development

CBWCD Outreach: presentations at local elementary schools

Page 12: Long-Term Plan Update

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

C-11 W Basin - LTPC-11 W Basin - LTP

Project Manager: Tjerk van Veen

LTP Project Description: Assist local communities in

developing, evaluating and implementing source controls

Perform feasibility analysis and conceptual design of water quality improvement measures for consideration in the Broward County WPA project

Page 13: Long-Term Plan Update

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

C-11 W Basin - LTPC-11 W Basin - LTP

Project Status

Nursery BMP Grant Program - $360,000 since April 2005

Public Outreach – Website, Educational Videos

Completed contract for preliminary design of Western C-11 Impoundment modifications to reduce phosphorus loads Final Report (May 12, 2006):

http://www.sfwmd.gov/org/erd/longtermplan/documents.shtml

Page 14: Long-Term Plan Update

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

C-11 W Basin - LTPC-11 W Basin - LTP

Work planned for remainder of FY 06Start 2nd year of C-11 West Nursery BMP

Grant programContinue public outreach activities

Page 15: Long-Term Plan Update

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

NSID BasinNSID BasinSource ControlsSource Controls

TP range: 16-29 ppb (average: 18 ppb)Operational changes implemented by NSID:

Reduced discharges into WCA-2A Inter-basin transfers of stormwater

New development - include additional storage and water quality treatment

Renewal of permits every 5 years

Page 16: Long-Term Plan Update

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

NSID Basin - LTPNSID Basin - LTP

Project Manager: Jonathan Madden

LTP Project Description: Perform a hydraulic

evaluation to determine: Impacts to the Hillsboro

Canal Provide additional

surface water storage

Page 17: Long-Term Plan Update

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

NSID Basin - LTPNSID Basin - LTP

Project StatusHydraulic analysis has been completedFinal Report (November 14, 2005):

http://www.sfwmd.gov/org/erd/longtermplan/documents.shtml

Page 18: Long-Term Plan Update

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

NSID Basin - LTPNSID Basin - LTP

Work planned for remainder of FY 06Review alternatives on how to proceed

based on findings of studyDevelop pollution reduction action plan

through BEWGMonitor and assist in implementation of

source controls

Page 19: Long-Term Plan Update

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

NNRC BasinNNRC Basin Source Controls Source Controls

TP range: 13-16 ppb (average: 15 ppb)Operational changes:

SFWMD (G-123) OPWCD

BDD’s Landscape contractor - BMPs for Turf and Landscape

PAID - program to improve swalesRenewal of permits every 5 years

Page 20: Long-Term Plan Update

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

NNRC Basin - LTPNNRC Basin - LTP

Project Manager: Jonathan Madden

LTP Project Description: Perform flood impact

analysis to ensure basin’s current level of flood protection is maintained if the use of structure G-123 is discontinued

Page 21: Long-Term Plan Update

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

NNRC Basin - LTPNNRC Basin - LTP

Project StatusFlood impact analysis has been completedFinal Report (September 2005):

http://www.sfwmd.gov/org/erd/longtermplan/documents.shtml

Page 22: Long-Term Plan Update

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

NNRC Basin - LTPNNRC Basin - LTP

Work planned for remainder of FY 06Review alternatives on how to proceed

based on findings of flood impact analysis Develop pollution reduction action plan

through BEWGMonitor and assist in implementation of

source controls

Page 23: Long-Term Plan Update

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Village of Wellington Village of Wellington Acme Basin B Source ControlsAcme Basin B Source Controls

TP range: 90-170 ppb (average: 119 ppb) Water quality treatment marsh “Equine Race

Track Lake Expansion” Ordinances:

livestock waste storage and hauling application of low P fertilizer compliance staff

SFWMD – Basin B: Stringent permit requirement compliance and enforcement activities

Page 24: Long-Term Plan Update

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Village of Wellington Village of Wellington Acme Basin B - LTPAcme Basin B - LTP

Project Manager: Jonathan Madden

LTP Project Description: Assist Village of Wellington

in developing, evaluating and implementing source controls

Page 25: Long-Term Plan Update

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Village of Wellington Village of Wellington Acme Basin B - LTPAcme Basin B - LTP

Project StatusFinalizing FY06 cost-share agreement with

VOW to develop, evaluate, and implement additional BMPs

Page 26: Long-Term Plan Update

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Village of Wellington Village of Wellington Acme Basin B - LTPAcme Basin B - LTP

Work planned for remainder of FY 06 Assist VOW in developing BMP Implementation

Plan Locate and remove nutrient rich sediment from canal

system GIS database for BMP ordinance compliance

Additional Public Outreach Update & distribute BMP flyers Local educational videos for television

Page 27: Long-Term Plan Update

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Feeder Canal BasinFeeder Canal BasinSource ControlsSource Controls

TP range: 76-177 ppb (average: 98 ppb)Optimize upstream monitoring networkCoordinate with Seminole Tribe Optimize BMPs to comply with water quality

requirementsEnsure new developments comply with

water quality requirements

Page 28: Long-Term Plan Update

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Feeder Canal Basin - LTPFeeder Canal Basin - LTP

Project Manager: Hongying Zhao

LTP Project Description: Develop and implement

a voluntary BMP program in the West Feeder Canal Sub-basin

Wingate Mill Canal

Page 29: Long-Term Plan Update

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Feeder Canal Basin - LTPFeeder Canal Basin - LTP

Project Status Approximately $580,000 awarded to projects in

Feeder Canal Basin

Work planned for remainder of FY 06 Continue to monitor implementation of funded

BMP projects

Page 30: Long-Term Plan Update

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

LTP and Non-ECP PermitLTP and Non-ECP Permit

Other activities planned for remainder of FY06 LTP updates/revisions being considered based on:

Studies’ findings Revised CERP Project Schedules Updated basin flow & TP load estimates

Revised LTP funding recommendations for FYs 2007-2010 (currently LTP only allocates funds for Non-ECP projects in FYs 2004-2006)

Coordinating development of TBELs for Non-ECP permit compliance with FDEP

Page 31: Long-Term Plan Update

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Everglades Protection Area Tributary BasinsLong-Term Plan for Achieving Water Quality Goals

Additional InformationAdditional Information

Chapter 3: Phosphorus Controls for the Basins Tributary to the Everglades Protection Area

http://www.sfwmd.gov/sfer/