long-term system assessment project update
DESCRIPTION
Long-Term System Assessment Project Update. Warren Lasher Manager, System Assessment. Purpose. To Inform Near-Term Planning with Potential Solutions that Meet Long-Range System Needs Intent is not to select new circuits to recommend - PowerPoint PPT PresentationTRANSCRIPT
December 15, 2008Regional Planning Group
Long-Term System AssessmentProject Update
Warren LasherManager, System Assessment
Regional Planning GroupDecember 15, 2008 2
Purpose
To Inform Near-Term Planning with Potential Solutions that Meet Long-Range System Needs
• Intent is not to select new circuits to recommend
• Rather, the intent is to provide a selection of alternatives through scenario analysis that can be considered when developing solutions for near-term congestion or reliability needs
Regional Planning GroupDecember 15, 2008 3
Specific Focus
The focus of this study is to look for:
Long-Lead-Time Projects – projects that may require 5 or more years to bring on-line
Large Projects – projects that both solve short-term issues but also meet long-term system needs.
Regional Planning GroupDecember 15, 2008 4
Scope
Study Year: 2018All generation currently on-line (and expected to
maintain operation) plus all units with signed IAs as of 7/1/2008
Base Case will include the CREZ Scenario 2 (selected by PUCT on 7/17/08)
Generation Expansion – by scenarioGas price – by scenarioEmissions allowance prices – by scenarioA report will be submitted to PUCT by end of 2008Analysis will continue next year
Regional Planning GroupDecember 15, 2008 5
Methodology
Study Consists of Two Components1. Evaluation of Regional System Needs
– A/C contingency steady-state analysis – SC-UC Model Development
2. Evaluation of Economic Projects
Regional Planning GroupDecember 15, 2008 6
A/C Contingency Analysis
Evaluated Five Areas• Northeast Region• Houston• South-Central• Valley
Using different local generation dispatches, evaluated the reliability needs of these areas under increasing amounts of import
Looked for thermal limit and voltage violations under contingency, primarily on the 345-kV network
Did not evaluate transient stability limits
Regional Planning GroupDecember 15, 2008 7
A/C Contingency Analysis
Under peak load conditions, generation availability was reduced by up to 2,800 MW to determine import constraints (resulting in a net import of 2,550 MW)
Example: Northeast Region
Regional Planning GroupDecember 15, 2008 8
A/C Contingency Analysis
Example: Houston RegionUnder peak load conditions, generation availability was reduced by up to 1,100 MW to determine import constraints (resulting in a net import of 6,760 MW)
Regional Planning GroupDecember 15, 2008 9
A/C Contingency Analysis
Example: South-Central RegionUnder peak load conditions, generation availability was reduced by up to 1,900 MW to determine import constraints
Regional Planning GroupDecember 15, 2008 10
A/C Contingency Analysis
Example: Valley RegionUnder peak load conditions, generation availability was reduced by up to 1,000 MW to determine import constraints (resulting in an import of 2,700 MW)
Regional Planning GroupDecember 15, 2008 11
A/C Contingency Analysis
Results:• No reliability need for additional import capacity
in the Northeast and South-Central Regionso At high levels of unavailable generation, import
restrictions are noted in these areas
• A new import pathway into Houston will be required by the summer peak season of 2018
• Current connections to the Valley region appear to be adequate although imports over existing interconnections with CFE may be required
Regional Planning GroupDecember 15, 2008 12
SC-UC Analysis
In order to build a 2018 model for economic analysis, small load-serving projects had to be added to the SCUC base-case model• Projects required to reliably serve load• Analyzing 8,760 hours using DC loadflows
These projects are not in the base-case, which is built off of the last year of the latest 5-Year Plan
In areas where several of these projects were required, a more cost-effective solution might be to build one larger (345-kV) project, rather than several smaller 138-kV upgrades
Regional Planning GroupDecember 15, 2008 13
SC-UC Analysis
Based on this analysis, four areas were selected for further analysis:• Houston Import• Western Williamson County• West of Waco• North of Dallas (Cooke and Grayson County)
In addition, these areas were reviewed for reliability needs:• Brenham Area• Columbus Area
Regional Planning GroupDecember 15, 2008 14
Options for Houston Import
The following options were evaluated for new pathways into the Houston area:• Fayette to Zenith• Salem to Zenith• Lufkin to Canal• Hillje to Parish, O’Brien or Zenith
Choice may depend on future base-load generation additions
Options further evaluated in the analysis of economic projects
Regional Planning GroupDecember 15, 2008 15
North Dallas Area
Area around Cooke and Grayson Counties (north of Dallas near the Oklahoma border)
Load growth may stress existing 138-kV service345-kV Option: Tap into the CREZ line connecting
Oklaunion and West Krum, and build a new 345-kV right-of-way to the Valley substation. Potential new 345-kV substations at the Payne and Valley View substations with 345-kV/138-kV autos.
Regional Planning GroupDecember 15, 2008 16
West Waco Area
Area west of Waco, in McLennan, Coryell, and Bosque County
Again, limited 345-kV service in this area345-kV Option: New 345-kV right of way from
Comanche Peak, south to the new Newton substation included in the CREZ plan. This would allow a new connection(s) into this area from the west. This option provided significant economic benefits if additional nuclear generation is developed at Comanche Peak.
Regional Planning GroupDecember 15, 2008 17
Western Williamson County
Load growth around Leander up to Lampasas will require several 138-kV upgrades
Flow is generally from 345-kV lines in the east and southeast
Potential solution:• New 345-kV substation at Lampasas,
connecting to the CREZ line from Gillespie to Newton
• Upgrade the 138-kV circuits from Lampasas to Burnet13
• New 138-kV right-of-way from Burnet13 to Leander
Regional Planning GroupDecember 15, 2008 18
Other Areas
The Brenham area is generally served radially from the Fayette to the Salem substations. Options were evaluated to provide network service for the Salem substation, including new right-of-way from Salem to Zenith, or from Salem to Sandow. These solutions were generally not cost-effective.
There is congestion in the Columbus area due to flows on the 69-kV system. One possible solution would be to convert some of the 69-kV circuits to 138-kV. This solution appears to be effective in eliminating congestion in the base-case, but with added base-load generation to the south (such as new nuclear units at STP or Victoria), a better solution may be to break the 69-kV system, reinforce the two ends and add reactive support.
Regional Planning GroupDecember 15, 2008 19
Economic Analysis
Using Scenario Analysis, evaluate projects that increase system efficiency under potential future conditions. Scenarios include:• Additional Nuclear Generation (3 units, 6 units)• Natural Gas Prices ($7, $11, $15/MMBtu) with
Coal Gasification/IGCC• Carbon Constraints (Up to $100/ton)• Changes in Load Shape (Plug-In Hybrids, Energy
Storage)• Additional Renewable Generation (Wind, Solar)
Regional Planning GroupDecember 15, 2008 20
Economic Analysis – Generation Expansion
Bus-bar analysis shows type of generation options that will be most cost-effective.
Bus-Bar Cost Of Generation Alternatives
0
50
100
150
200
250
300
0 10 20 30 40 50 60 70 80 90 100
Capacity Factor
To
tal (
Bu
s-B
ar)
Co
st
($/M
Wh
)
Coal IGCC IGCC + Sq Adv CC Adv CT Nuc Wind Solar Thermal PV
Coal Price : $1.5/MMBtu
Nuclear Price: $0.75/MMBtu
Biomass: $0.5/MMBtu
Carbon Cost: $0/Ton
REC Price: $5/MWh
Gas Price: $11/MMBtu
Generation development will be driven by profit expectations.
Regional Planning GroupDecember 15, 2008 21
Economic Analysis – Generation Expansion
Impact of Carbon Tax shown on this chart.Bus-Bar Cost Of Generation Alternatives
0
50
100
150
200
250
300
0 10 20 30 40 50 60 70 80 90 100
Capacity Factor
To
tal (
Bu
s-B
ar)
Co
st
($/M
Wh
)
Coal IGCC IGCC + Sq Adv CC Adv CT Nuc Wind Solar Thermal PV
Coal Price : $1.5/MMBtu
Nuclear Price: $0.75/MMBtu
Biomass: $0.5/MMBtu
Carbon Cost: $50/Ton
REC Price: $5/MWh
Gas Price: $7/MMBtu
Regional Planning GroupDecember 15, 2008 22
Economic Analysis – Generation ExpansionERCOT system has a significant amount of intermediate generation
Net Load Duration Curve - 2018Load Minus 18,456 MW of Wind Generation
-10,000
0
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
90,000
0.00% 10.00% 20.00% 30.00% 40.00% 50.00% 60.00% 70.00% 80.00% 90.00% 100.00%
Percentage of Hours
Ho
url
y L
oad
(M
W)
Load Duration Must Run Nuclear Coal CC Base Load Max
Gas Price: $11/MMBtu
Base Load Max Capacity = 40009 MW
Regional Planning GroupDecember 15, 2008 23
Economic Analysis – Generation Expansion
At gas prices of $11/MMBtu or $15/MMBtu, additional base-load generation will likely be profitable.
Additional generation expansion, to meet 12.5% target reserve margin, will likely come from quick-start combustion turbines or very flexible combined-cycle plants.
Hourly marginal cost unit-commitment models will often underestimate the benefits from quick-start combustion turbines• Ancillary services (Non-spin)• Short-term price spikes
Regional Planning GroupDecember 15, 2008 24
Economic Analysis – General Observations
Evaluating two levels of nuclear and coal (IGCC) expansion indicates that economic projects were generally not cost-effective unless they were specifically designed for scenario generation expansion (except in certain scenarios)
Backbone projects (such as 765-kV Navarro to Hillje, and Fayette to Zenith) were generally not cost-effective unless new generation was directly connected to the backbone
Carbon constraints did not significantly alter the locations of system congestion, although they change the congestion costs and likely generation expansion options
Regional Planning GroupDecember 15, 2008 25
Economic Analysis – General Observations
No large projects in ERCOT between Dallas and Houston were found that were economically justified due to presence of CREZ wind. Import pathway into Houston from the west was cost-effective.
Analysis of up to 2,000 MW of solar generation in the McCamey area indicates limited increase in curtailment to wind or solar projects
Analysis of conventional Compressed Air Energy Storage indicates that 2,000 MW of CAES capacity can increase wind generation by 830 GWh (reducing wind generation curtailment by 1%); production costs reduced by $10 million
Regional Planning GroupDecember 15, 2008 26
Conclusions
Reliability analysis indicates a need for additional import pathway into Houston area by 2018. Selection of most cost-effective solution will likely depend on generation expansion.
Options have been presented for additional reliability projects north of Dallas, near Waco, and north of Austin
Scenario analysis indicates that cost-effectiveness of economic projects depends heavily on locations of future generation development
Long-term analysis will continue in the new year:• CREZ implementation• > 10 year analysis
Regional Planning GroupDecember 15, 2008 27
Questions?