lhc collimators low level control changes
DESCRIPTION
Control system hardware upgrades Control system software changes Commissioning plan. LHC Collimators Low Level Control changes. A. Masi. Contents. 1 – Control system hardware upgrades. Added KVM for PXI remote management . Not touched !!!!. New PXI high availability chassis. - PowerPoint PPT PresentationTRANSCRIPT
A Masi, LHC Collimators Low Level Control changes
LHC Collimators Low Level Control changes
A. Masi
1. Control system hardware upgrades2. Control system software changes3. Commissioning plan
Contents
A Masi, LHC Collimators Low Level Control changes
1–Control system hardware upgrades
Old controls rack configuration New controls rack
Control cables protection system
New PXI high availability
chassis
Added KVM for PXI remote
management
Not touched !!!!
A Masi, LHC Collimators Low Level Control changes
1–Control system hardware upgrades
High Availability PXI chassis designed and manufactured for the
LHC collimators project
Redundant hot swappable power supply
Health Monitoring
card
Redundant easy replaceable fans
A Masi, LHC Collimators Low Level Control changes
1–Control system hardware upgrades
New electrical distribution chassis
A Masi, LHC Collimators Low Level Control changes
1–Control system hardware upgrades
TDI improvements• connection to the BETS • Installation of the interferometric gap measurement
system
Optical connectors
NI RDIO
HSSL Interface
Europa Crate
Redundant power-supply
Optical link cards to the BETS ready to be produced
• An additional FESA class will be added to publish and manage the interferometric gap measurement
A Masi, LHC Collimators Low Level Control changes
1–Control system hardware upgrades
LVDT Position drift due to external field
The I2PS is notaffected
- Optimized dimensions and winding parameters- Test Installation during 2012 Christmas Break- Ratiometric reading- 1 micrometer uncertainty with lower supply currents- Temperature compensation- No effect on the measured position of an external magnetic field
Possible replacement of some LVDT affected by magnetic interference problem with a new designed Ironless Inductive
Position Sensor (I2PS)
See CWG talk by A. Danisi on Sep 2013
20 I2PS including new electronic cards and collimator supports ready to be installed by end of
March• Waiting for feedback and
green light from CWG ….• What about injection
collimators ???
A Masi, LHC Collimators Low Level Control changes
2–Control system software changes
Main software changes:• MDC (Motor Drive Control) : upgraded to LabView 2011,
software architecture improved and optimized • PRS (Position Readout & Survey) : upgraded to LabView
2011, software architecture improved and optimized, integrated reading of I2PS
• DIM library : updated and added a more efficient acknowledgement mechanism
• FESA class : completely re-written in FESA 3.0
A Masi, LHC Collimators Low Level Control changes
2–Control system software changes
Impact for operation: • Added separation limits :
• PRS errors : Two new bits will be added for separation : B17 : POSITION_OUT_OF_SEPARATION B18: SEPARATION_TIMEOUT
• PRS warnings : A new bit will be added for separation : B5 : POSITION_OUT_OF_SEPARATION_WARNING
• A new allarm• Two new properties to define the Active IP:
- SeparationActiveIP : like betastar, used to select the separation value to be used- SeparationThreshold : like betastar, 4 2D arrays defining limits to be interpolated (Inner/Outer for gap upstream and downstream)
• Waiting for new telegram definition
• Some old alarms can be removed or simplified• Additional information have been added to the
postmortem buffer: - pmGapUpSeparationInnerLimit - pmGapUpSeparationOuterLimit - pmGapDownSeparationInnerLimit - pmGapDownSeparationOutererLimit - pmSeparationValue
A Masi, LHC Collimators Low Level Control changes
3. Commissioning plan
Commissioning guidelines: • As for 2008 the following steps will be followed before
making the full system fully operational:• Hardware commissioning EN-STI• Position sensors calibration EN-STI + support of the collimation team for the new
collimators • Functional tests on the entire system or system subsets EN-STI + Collimation
Team• Machine Interlocks test Collimation Team• Dry-run BE-OP
• The interlocks cables have not been touched so the re commissioning of the interlock chain is not needed
• During the commissioning a complete functional test bench will be made available to test and validate the new control software by collimation team
• The commissioning will proceed on the old collimators if the new ones are not yet installed
A Masi, LHC Collimators Low Level Control changes
3. Commissioning plan
Number of systems
Network Installation
230V power supply
R2E cabling
Control System
Installation
Systems ready for
commissioningSector
Cooldown LSector
Cooldown R
US15 4 OK In progress OK OK No 2 June 30 JuneUA23 6 + TDI OK In progress - OK No 30 June -UA27 2 OK In progress - OK No - 11 August
UJ33 7 - OK - Ok YES 11 August 15 September
USC55 4 No No No No No 22 September 28 JulyUS65 1 - In progress - OK No 28 July 5 May
TZ76 21 OK In progress In progress OK No 5 May 11 August
UA83 2 OK No - OK No 11 August -UA87 5 + TDI OK No - OK No - 2 JuneBA7 1 OK OK - OK YES - -
The commissioning plan is being defined according to the installation status and the dates of the cool down
A Masi, LHC Collimators Low Level Control changes
3. Commissioning plan
Some preliminary dates:
• Beginning of March deployment of the new software images and FESA class on all the systems in the tunnel. The hardware commissioning starts …
• Mid of March Test bench on the new BPM collimator available for collimation team
• End of August the entire system will be again operational including the new collimators