LDEO IIC 2010-11 Summary of year’s activities Forsyth/Wiens Recoveries Cascadia Construction and TRM Deployment (testing) – Staffing Upcoming plans/schedule Cascadia deep deployment (2011) Mariana deployment (2012) Chile deployment (2012) Cascadia recoveries/turnaround (2012) Development Completed/ongoing projects Future projects

Upload: bisa

Post on 14-Jan-2016

45 views

Category:

Documents


3 download

DESCRIPTION

LDEO IIC 2010-11. Summary of year’s activities Forsyth/Wiens Recoveries Cascadia Construction and TRM Deployment (testing) Staffing Upcoming plans/schedule Cascadia deep deployment (2011) Mariana deployment (2012) Chile deployment (2012) Cascadia recoveries/turnaround (2012) Development - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: LDEO IIC 2010-11

LDEO IIC 2010-11

• Summary of year’s activities– Forsyth/Wiens Recoveries– Cascadia Construction and TRM Deployment (testing)– Staffing

• Upcoming plans/schedule– Cascadia deep deployment (2011)– Mariana deployment (2012)– Chile deployment (2012)– Cascadia recoveries/turnaround (2012)

• Development– Completed/ongoing projects– Future projects

Page 2: LDEO IIC 2010-11

Forsyth Recoveries (S of Shatsky)

Site Depth, m Acoustics Release Data

14 6002 Good No release

12 5788 Good 1 wt dropped after ~2h 244/370

9 5933 Good 1 wt dropped after ~2h 150/370

8 6007 Good Normal release 372/372

5 5994 None

2 5752 None

Faulty burnwires: Sites 9, 12, 14?

Sites 2, 5: implosion or early release ?

Page 3: LDEO IIC 2010-11

Wiens Lau Recoveries

• 21 of 22 recovered• 13 had OBMs

• OK performance,• Some bad channels

• Depth restriction 5000 m• No low-pressure leaks

Page 4: LDEO IIC 2010-11

Inventories (instruments and people)

• ~29 standard OBS (5 TCs; 24 L4s)• 30 (20 TRM; 10 standard) in Cascadia fleet (considerable overlap in design)

• People: 3 core, 5 peak– Engineer Gassier– Engineer Koczynski– Technician Oletu– Technicians Stolzmann, Brusa

Page 5: LDEO IIC 2010-11

Cascadia Construction/Deployment

2 test cruises in LI Sound (battery issues; instrument survived 3’ drop)Corrosion test in LI sound

Made decision early 2011 to add popup buoys

Construction:

Possible TRM delays became apparent ~ April/May

Steel supplier/coater overwhelmed (19 tons in 900 pcs)

Estimated 5+ instruments ready for deployment cruise

10 standard Cascadia OBSs on track for October 2011

Page 6: LDEO IIC 2010-11

New standard OBS

Page 7: LDEO IIC 2010-11

TRM OBS

Page 8: LDEO IIC 2010-11

Cascadia Deployment

15 delivered for cruise

Page 9: LDEO IIC 2010-11

TRM Deployment Cruise July, 2011

15 deployed9 with popups

Heave challenges

1 TRM fell

1 tilted

1 recovered

Some had temperaturesensors

Major fishing collaboration

Page 10: LDEO IIC 2010-11

TRM Recovery

Page 11: LDEO IIC 2010-11

2011-12 Activities

• Cascadia Standard deployment, October 2011• Mariana experiment (Wiens) Jan/Feb 2011

– 10 standard OBSs– 5 moored instruments– Temperature sensors ?

• Chile experiment (Trehu) April/May 2011– 10 standard OBSs– Flowmeters

• Cascadia Recoveries/Turnaround [All summer…]

Page 12: LDEO IIC 2010-11

Completed Development

• Switched to Trillium Compact leveling system in Al tube

• TRMs developed and built• OBS dataloggers redesigned: batteries separated• APG dataloggers incorporated into OBSs• TRM deployment/recovery approaches

Page 13: LDEO IIC 2010-11

2011-12 Development Directions

• New FPGA for APG logger• Atomic clocks• TRM tweaks• Mariana moored instruments• Adding SIO flowmeters to standard OBSs • Incorporate broadband sensor• New OBS datalogger• Deep OBS

Page 14: LDEO IIC 2010-11

Issues

• Confidence has increased (5 years)• But… recognize need to consolidate.

• Last year, working flat-out. May be false economy given per-instrument and data costs.

• Data: Backlog is critical problem. First Forsyth

experiment site to DMC yesterday.