Goran Tesevic Civil and Structural Engineer
Key Projects:1. Reconstruction of reinforced concrete highway bridge
L=12+29.50+12 m……………………………………………………......3-8
2. Reconstruction of concrete beam bridge L=8.50 m…………… .9-103. Reconstruction of concrete beam bridge L=9.0 m……………..11-144. Reconstruction of concrete beam bridge L=7.0 m……………..15-165. Reconstruction of concrete beam bridge L=7.5 m…………………176. Demolition and removal of old expansion joints and construction
of new ones…………………………………………………………….18-207. Production of reinforced T beams……………………………….........21
1. Reconstruction of reinforced concrete highway bridge L=12+29.50+12 m.
Replacement of damaged post-tensioning beam
Installation of highway safety traffic barriers
Setting load of 150 KN in order to preserve the existing deflection
Installation of a temporary support
Isolation of pre-stressed T beam New pre-stressed T beam
Replacement of damaged pre-stressed T beam
New longitudinal connection between the top of flanges
Detail during work
Repairing cracks in concrete by injecting epoxy resin
Repair and rehabilitation of cracks
2. Reconstruction of concrete beam bridge L=8.50 m
Removing of damaged precast concrete deck modules and laying reinforced concrete T beams
Concreting Installation waterproofing membranes
3. Reconstruction of concrete beam bridge L=9.0 m
Damaged precast concrete deck modules
Start removing of damaged precast concrete deck modules and new deck slab
Concreting Detail between two concrete T beams
Ready for installation waterproofing membrane A new bridge safety fence and guardrail barriers
4. Reconstruction of concrete beam bridge L=7.0 m
Expanding of bridge sidewalks
New sidewalk with a safety fence
5. Reconstruction of concrete beam bridge L=7.0 m
Expanding of bridge sidewalks New sidewalks with a safety fences
Bridge 1 Preparing for extension joint replacement
New extension joint
Bridge 2 Expansion joint during installation
Production of reinforced T beams