former dupont barksdale works project update october 5, 2004 dupont corporate remediation group...

22
Former DuPont Barksdale Works Project Update October 5, 2004 DuPont Corporate Remediation Group Great Lakes Visitors Center

Upload: brittney-conley

Post on 03-Jan-2016

215 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Former DuPont Barksdale Works Project Update October 5, 2004 DuPont Corporate Remediation Group Great Lakes Visitors Center

Former DuPont Barksdale Works Project Update

October 5, 2004

DuPont Corporate Remediation Group

Great Lakes Visitors Center

Page 2: Former DuPont Barksdale Works Project Update October 5, 2004 DuPont Corporate Remediation Group Great Lakes Visitors Center

October 5, 2004 Former DuPont Barksdale Works Project Update

2

Purpose of Presentation

Provide an update on the alternative water supply project.

Provide update on additional project work conducted since the July 2004 public meeting and remaining work for 2004.

Page 3: Former DuPont Barksdale Works Project Update October 5, 2004 DuPont Corporate Remediation Group Great Lakes Visitors Center

October 5, 2004 Former DuPont Barksdale Works Project Update

3

Presenters

Brad Nave– Project Director, DuPont Corporate Remediation

Group (CRG)

Page 4: Former DuPont Barksdale Works Project Update October 5, 2004 DuPont Corporate Remediation Group Great Lakes Visitors Center

Alternative Water Supply Project

Page 5: Former DuPont Barksdale Works Project Update October 5, 2004 DuPont Corporate Remediation Group Great Lakes Visitors Center

October 5, 2004 Former DuPont Barksdale Works Project Update

5

Pipeline Construction UpdateAlternative Water Supply

Construction started first week of August 2004. Approximately 46,100 feet of main (ductile iron pipe

and HDPE) and service lateral (copper line to homes) was specified in the design.

To date, approximately 50% of the pipeline (based on lineal footage) has been constructed.

– Approximately 70% of the total main (~32,400 ft.) has been constructed.

– Approximately 19% of the total service lateral length (~13,700) has been constructed.

Page 6: Former DuPont Barksdale Works Project Update October 5, 2004 DuPont Corporate Remediation Group Great Lakes Visitors Center

October 5, 2004 Former DuPont Barksdale Works Project Update

6

Pipeline Construction UpdateAlternative Water Supply

Bjork R

d

Wedal Rd Wedal Rd

Engoe RdEngoe Rd

On

dossago

n Rd

Nevers Rd

Wannebo Rd

Main completed

Main to be completed

Page 7: Former DuPont Barksdale Works Project Update October 5, 2004 DuPont Corporate Remediation Group Great Lakes Visitors Center

October 5, 2004 Former DuPont Barksdale Works Project Update

7

&V&V &V

&V&V &V &V

&V&V &V

&V &V &V

&V

&V&V&V&V&V&V

&V&V

&V&V

&V

&V

&V

&V

&V &V&V

&V&V&V&V&V &V

&V&V

&V&V&V

&V&V

&V

&V

Bjo

rk Rd

29450N29600N 29890N

30900N30110N

73150BJ

30240N

30300N

30380N

30810N

30700N30490N

30600N

72480H72470H72450H

72420H72410H

72370H72330H

72520H

72920H72910H

72860H

72790H

72730H72700H

72040H

73500H

73300BC73280H73250H

&V Fire Call NumberParcel Boundary

Parcels Included in Municipal Water Supply AgreementRoads

LEGEND

Lateral Services Completed to date

Page 8: Former DuPont Barksdale Works Project Update October 5, 2004 DuPont Corporate Remediation Group Great Lakes Visitors Center

October 5, 2004 Former DuPont Barksdale Works Project Update

8

Page 9: Former DuPont Barksdale Works Project Update October 5, 2004 DuPont Corporate Remediation Group Great Lakes Visitors Center

October 5, 2004 Former DuPont Barksdale Works Project Update

9

Page 10: Former DuPont Barksdale Works Project Update October 5, 2004 DuPont Corporate Remediation Group Great Lakes Visitors Center

October 5, 2004 Former DuPont Barksdale Works Project Update

10

Page 11: Former DuPont Barksdale Works Project Update October 5, 2004 DuPont Corporate Remediation Group Great Lakes Visitors Center

October 5, 2004 Former DuPont Barksdale Works Project Update

11

Page 12: Former DuPont Barksdale Works Project Update October 5, 2004 DuPont Corporate Remediation Group Great Lakes Visitors Center

October 5, 2004 Former DuPont Barksdale Works Project Update

12

Page 13: Former DuPont Barksdale Works Project Update October 5, 2004 DuPont Corporate Remediation Group Great Lakes Visitors Center

October 5, 2004 Former DuPont Barksdale Works Project Update

13

Page 14: Former DuPont Barksdale Works Project Update October 5, 2004 DuPont Corporate Remediation Group Great Lakes Visitors Center

October 5, 2004 Former DuPont Barksdale Works Project Update

14

Pipeline Construction UpdateAlternative Water Supply

Near term schedule:– Anticipate completion of ductile iron pipe

installation north of Nolander Road within a week.– Main will be reduced to 4-inch south of Nolander

to end of pipeline (just north of Boyd’s creek) and in Birch Grove.

– Multiple crews will be assigned to lateral line construction.

– Continue restoration of: Roadways and culverts. Shoulders and ditches (grading and seeding). Private properties.

Page 15: Former DuPont Barksdale Works Project Update October 5, 2004 DuPont Corporate Remediation Group Great Lakes Visitors Center

October 5, 2004 Former DuPont Barksdale Works Project Update

15

Pipeline Construction UpdateAlternative Water Supply

Birch Grove Schedule:– Anticipate within the next two weeks that

construction will begin and should take approximately 5 to 10 days, depending on subsurface conditions.

– Due to limited space, vehicular traffic will be restricted during main line construction.

Page 16: Former DuPont Barksdale Works Project Update October 5, 2004 DuPont Corporate Remediation Group Great Lakes Visitors Center

October 5, 2004 Former DuPont Barksdale Works Project Update

16

Pipeline Construction UpdateAlternative Water Supply

Construction completion targeted for end of calendar year 2004, assuming:

– No regulatory delays.– Outstanding contractor performance (construction and

safety).– Favorable weather.– No unforeseen or unmanageable technical issues.

A few private properties will likely have to be fully restored (final grading and seeding) in 2005, due to weather issues.

Wetlands issues at three properties have yet to be resolved; therefore, these lateral lines may be completed in 2005.

Page 17: Former DuPont Barksdale Works Project Update October 5, 2004 DuPont Corporate Remediation Group Great Lakes Visitors Center

Other Barksdale Site Work

Page 18: Former DuPont Barksdale Works Project Update October 5, 2004 DuPont Corporate Remediation Group Great Lakes Visitors Center

October 5, 2004 Former DuPont Barksdale Works Project Update

18

Residential Monitoring

April 2004 sampling results transmitted to WDNR in August.

Annual change-out of carbon cylinders has been completed.

Eighty-two homes sampled at the end of August.– Preliminary results indicate no new detections of

site-related compounds. Carbon filters continue to be effective.

– Report of results pending.

Page 19: Former DuPont Barksdale Works Project Update October 5, 2004 DuPont Corporate Remediation Group Great Lakes Visitors Center

October 5, 2004 Former DuPont Barksdale Works Project Update

19

Site Investigation

Construction of new monitoring wells (10) will be completed this week.

Additional groundwater sampling to be conducted in 4Q2004.

Anticipate preliminary results in December 2004.

Page 20: Former DuPont Barksdale Works Project Update October 5, 2004 DuPont Corporate Remediation Group Great Lakes Visitors Center

October 5, 2004 Former DuPont Barksdale Works Project Update

20

Miscellaneous Site Work

Continuing work with Adventus to evaluate a new generation of soil amendments to reduce concentrations of nitroaromatic/nitramine compounds in soil.– Generation 3 product uses nano-scale zero valent

iron. Continuing Georgia Tech research on

destruction of TNT. Small repair on stream diversion to be

undertaken during the 4th quarter.

Page 21: Former DuPont Barksdale Works Project Update October 5, 2004 DuPont Corporate Remediation Group Great Lakes Visitors Center

October 5, 2004 Former DuPont Barksdale Works Project Update

21

Home Value Protection Program

Three homes purchased to date. Two have been resold.

72410 Highway 13 – purchased on June 29th

– Home is in poor condition.– Structural and moisture issues exist.– Interior mold issues exist.– DuPont is currently soliciting bids for removal of

the structure. Program will remain in effect until six months

after alternative water is available.

Page 22: Former DuPont Barksdale Works Project Update October 5, 2004 DuPont Corporate Remediation Group Great Lakes Visitors Center

October 5, 2004 Former DuPont Barksdale Works Project Update

22

Questions or comments?