Former DuPont Barksdale Works Project Update
October 5, 2004
DuPont Corporate Remediation Group
Great Lakes Visitors Center
October 5, 2004 Former DuPont Barksdale Works Project Update
2
Purpose of Presentation
Provide an update on the alternative water supply project.
Provide update on additional project work conducted since the July 2004 public meeting and remaining work for 2004.
October 5, 2004 Former DuPont Barksdale Works Project Update
3
Presenters
Brad Nave– Project Director, DuPont Corporate Remediation
Group (CRG)
Alternative Water Supply Project
October 5, 2004 Former DuPont Barksdale Works Project Update
5
Pipeline Construction UpdateAlternative Water Supply
Construction started first week of August 2004. Approximately 46,100 feet of main (ductile iron pipe
and HDPE) and service lateral (copper line to homes) was specified in the design.
To date, approximately 50% of the pipeline (based on lineal footage) has been constructed.
– Approximately 70% of the total main (~32,400 ft.) has been constructed.
– Approximately 19% of the total service lateral length (~13,700) has been constructed.
October 5, 2004 Former DuPont Barksdale Works Project Update
6
Pipeline Construction UpdateAlternative Water Supply
Bjork R
d
Wedal Rd Wedal Rd
Engoe RdEngoe Rd
On
dossago
n Rd
Nevers Rd
Wannebo Rd
Main completed
Main to be completed
October 5, 2004 Former DuPont Barksdale Works Project Update
7
&V&V &V
&V&V &V &V
&V&V &V
&V &V &V
&V
&V&V&V&V&V&V
&V&V
&V&V
&V
&V
&V
&V
&V &V&V
&V&V&V&V&V &V
&V&V
&V&V&V
&V&V
&V
&V
Bjo
rk Rd
29450N29600N 29890N
30900N30110N
73150BJ
30240N
30300N
30380N
30810N
30700N30490N
30600N
72480H72470H72450H
72420H72410H
72370H72330H
72520H
72920H72910H
72860H
72790H
72730H72700H
72040H
73500H
73300BC73280H73250H
&V Fire Call NumberParcel Boundary
Parcels Included in Municipal Water Supply AgreementRoads
LEGEND
Lateral Services Completed to date
October 5, 2004 Former DuPont Barksdale Works Project Update
8
October 5, 2004 Former DuPont Barksdale Works Project Update
9
October 5, 2004 Former DuPont Barksdale Works Project Update
10
October 5, 2004 Former DuPont Barksdale Works Project Update
11
October 5, 2004 Former DuPont Barksdale Works Project Update
12
October 5, 2004 Former DuPont Barksdale Works Project Update
13
October 5, 2004 Former DuPont Barksdale Works Project Update
14
Pipeline Construction UpdateAlternative Water Supply
Near term schedule:– Anticipate completion of ductile iron pipe
installation north of Nolander Road within a week.– Main will be reduced to 4-inch south of Nolander
to end of pipeline (just north of Boyd’s creek) and in Birch Grove.
– Multiple crews will be assigned to lateral line construction.
– Continue restoration of: Roadways and culverts. Shoulders and ditches (grading and seeding). Private properties.
October 5, 2004 Former DuPont Barksdale Works Project Update
15
Pipeline Construction UpdateAlternative Water Supply
Birch Grove Schedule:– Anticipate within the next two weeks that
construction will begin and should take approximately 5 to 10 days, depending on subsurface conditions.
– Due to limited space, vehicular traffic will be restricted during main line construction.
October 5, 2004 Former DuPont Barksdale Works Project Update
16
Pipeline Construction UpdateAlternative Water Supply
Construction completion targeted for end of calendar year 2004, assuming:
– No regulatory delays.– Outstanding contractor performance (construction and
safety).– Favorable weather.– No unforeseen or unmanageable technical issues.
A few private properties will likely have to be fully restored (final grading and seeding) in 2005, due to weather issues.
Wetlands issues at three properties have yet to be resolved; therefore, these lateral lines may be completed in 2005.
Other Barksdale Site Work
October 5, 2004 Former DuPont Barksdale Works Project Update
18
Residential Monitoring
April 2004 sampling results transmitted to WDNR in August.
Annual change-out of carbon cylinders has been completed.
Eighty-two homes sampled at the end of August.– Preliminary results indicate no new detections of
site-related compounds. Carbon filters continue to be effective.
– Report of results pending.
October 5, 2004 Former DuPont Barksdale Works Project Update
19
Site Investigation
Construction of new monitoring wells (10) will be completed this week.
Additional groundwater sampling to be conducted in 4Q2004.
Anticipate preliminary results in December 2004.
October 5, 2004 Former DuPont Barksdale Works Project Update
20
Miscellaneous Site Work
Continuing work with Adventus to evaluate a new generation of soil amendments to reduce concentrations of nitroaromatic/nitramine compounds in soil.– Generation 3 product uses nano-scale zero valent
iron. Continuing Georgia Tech research on
destruction of TNT. Small repair on stream diversion to be
undertaken during the 4th quarter.
October 5, 2004 Former DuPont Barksdale Works Project Update
21
Home Value Protection Program
Three homes purchased to date. Two have been resold.
72410 Highway 13 – purchased on June 29th
– Home is in poor condition.– Structural and moisture issues exist.– Interior mold issues exist.– DuPont is currently soliciting bids for removal of
the structure. Program will remain in effect until six months
after alternative water is available.
October 5, 2004 Former DuPont Barksdale Works Project Update
22
Questions or comments?