environment management plan · m/s. c. v. c. mining company cluster environment management plan 1-1...
TRANSCRIPT
M/s. C. V. C. Mining Company Cluster Environment Management Plan
Team Labs and Consultants1-1
ENVIRONMENT MANAGEMENT PLAN
1.0 IntroductionThis report discusses the management plan for mitigation/abatement of adverse
environmental impacts and enhancement of beneficial impacts due to mining. The EMP has
been designed within the framework of various legislative and regulatory requirements on
environmental and socio-economic aspects.
M/s. C. V. C. Mining Company proposes to conduct semi mechanized underground method
mining for Mica, Quartz and Feldspar in an area of 4.33 Acres or 1.752 Ha located in Survey
No. 109, 110 & 111, Talupuru Village, Sydapuram Mandal, SPSR Nellore District, Andhra
Pradesh. In principle grant of quarry lease of extension of time notice was issued by the
Department of Mines and Geology, Government of Andhra Pradesh vide Notice No.
21290/R3-1/2016 dated 01.10.2018. Mining Plan was approved Deputy Director of Mines and
Geology, Guntur vide Letter No. 3355/MP/Quartz/NLR/2018 dated 16.10.2018. Proposed
production of Mica @ 375.95 TPA, Quartz @ 198 TPA and Feldspar @ 990 TPA. Capital cost
proposed for the mining will be approximately Rs. 40 Lakhs. As per the ADMG letter, the total
cluster of area within 500m surrounding from the ml boundary is 25.357 ha.
M/s. C. V. C. Mining Company is conscious of his environmental responsibility towards the
society in minimizing the pollution load due to this project and accordingly decided to carry
out the Environment Management Plan. The objective of preparing environment
management plan is to delineate effective measures to control and to mitigate the
environmental pollution. This report presents the environment management plan, detailing
the environmentally sound technology and the measures needed to contain and mitigate the
anticipated environmental impacts due to the project.
1.1 Uses of mineral
Quartz containing 99% plus Silica is used in glass industry. This is also used in electrical
industry for making semi conductors. Feldspar is mainly used for ceramic and isolators
manufacturing units. Mica is used in paints as a pigment extender and also helps to brighten
the tone of colored pigments and also used in the electrical industry the same as thermal
insulation, and electrical insulators in electronic equipment.
1.2 Mining Technology
The mining operations will be carried out by the underground mining method with semi
M/s. C. V. C. Mining Company Cluster Environment Management Plan
Team Labs and Consultants1-2
mechanized by adopting of drilling and blasting with help of jack hammers. The accessing to
the mine through the existing shaft and the winzes will be made at a spacing of 15-30m to
explore the ore body and level interval between two adjacent levels will be 6-8m.
1.3 Cluster Details
Reason for submission of the present project and background information:
The MoEF & CC through its legislation has issued a notification No. SO 141(E) dated 15.1.2016
through which it issued cluster guidelines for the purpose of obtaining Prior Environmental
Clearance for the Mines. As per that SO every mine shall obtain prior EC for its operations
and also EC for the entire cluster incase it falls in the definition of cluster. Accordingly the
present cluster falls under purview of definition of cluster as per the SO. Hence the present
EMP for the whole cluster is being prepared. As per the S. O. 2269 (E) notification dated
01.07.2016 and the ADMG letter, the total cluster of area within 500m surrounding from the
ml boundary is 25.357 ha. The details of Cluster projects as per Mining Plan are given below.
a. Details of mine leases within 500m radiusS.
No.Name of themine lease Location of the Mine Leases Extent,
haMine Lease
and Date EC and mine status
1 M/s. C. V. C.Mining Company
Survey No. 109, 110 & 111, TalupuruVillage, Sydapuram Mandal, SPSRNellore District
1.752 LOI01.10.2018 Applied for EC
2 M/s. C. V. C.Mining Company
Survey No. 101, Talupuru Village,Sydapuram Mandal, SPSR NelloreDistrict
10.117Executed
on06.08.1986
NA, Non-working fromexecution time -due to
lack of EC
3 M/s. VeenusMining Company
Survey No. 143/B, 144, 147/2 & 147/3,Tummala Talupuru Village, SydapuramMandal, SPSR Nellore District
6.90Executed
on07.07.1980
NA, Non-working fromSep 2013-due to lack of
EC
4 M/s. VeenusMining Company
Survey No. 143/B, 147/2P & 147/1,Tummala Talupuru Village, SydapuramMandal, SPSR Nellore District
6.588Executed
on29.12.1996
NA, Non-working fromSep 2011-due to lack of
ECTotal Area 25.357
b. Area utilized for miningS. No. Name of the mine lease Total Extent, ha Area to be excavated, ha
1 M/s. C. V. C. Mining Company 1.752 0.132 M/s. C. V. C. Mining Company 10.117 5.63 M/s. Veenus Mining Company 6.9 3.54 M/s. Veenus Mining Company 6.588 4
Total Area 11.869 5.73
M/s. C. V. C. Mining Company Cluster Environment Management Plan
Team Labs and Consultants1-3
c. Total Reserves and Life of the Mine in the ClusterS.
No. Name Area, ha ProductionTPA Reserves T Life of Mine,
Years1 M/s. C. V. C. Mining Company 1.752 13940 101650 72 M/s. C. V. C. Mining Company 10.117 30937 820826 273 M/s. Veenus Mining Company 6.9 14028 428970 314 M/s. Veenus Mining Company 6.588 14000 420000 30
Total Area 11.869 44877 922476 34
d. Details of Production and Wastage for the plan periodS.
No. Name Production for PlanPeriod, Ton
Wastage for PlanPeriod, Ton
DumpArea, ha
1 M/s. C. V. C. Mining Company 5305 2856.7 0.8732 M/s. C. V. C. Mining Company 52000 28000 2.53 M/s. Veenus Mining Company 27468 21582 1.14 M/s. Veenus Mining Company 27000 20000 1
e. Details of Water Requirement
Name of the Mine Extent(ha)
Water RequirementKLD
DomesticWater KLD
WasteWater KLD
M/s. C. V. C. Mining Company 1.752 5.9 3.0 0.6M/s. C. V. C. Mining Company 10.117 12.2 1.7 1.4M/s. Veenus Mining Company 6.9 8.5 1.5 1.2M/s. Veenus Mining Company 6.588 8.5 1.5 1.2
f. Details of TransportationName Extent (ha) Production TPA No. of Trips per day
M/s. C. V. C. Mining Company 1.752 13940 1.0M/s. C. V. C. Mining Company 10.117 30937 3.0M/s. Veenus Mining Company 6.9 14028 1M/s. Veenus Mining Company 6.588 14000 1
1.4 Mine Location
The mine lease area falls in the Survey of India topo sheet no. 57 N/11 with the co-ordinates
of Latitude 14°17'54.74"N and Longitude 79°41'30.20"E with a elevation of 50 m. The nearest
village is Tummalatalupuru located at a distance of 60m from the ML area in SE direction.
Nearest town is Gudur located at a distance of 22 Km from the ML area in SE direction.
Nearest railway station is at Manubolu at a distance of 20.8 km from the lease area in SE
direction. Nellore to Rapur main road is passing at a distance of 3.0 km in North direction.
Duggunta to Kalichedu road is passing at a distance of 0.15 km in NE direction. Cart Road is
M/s. C. V. C. Mining Company Cluster Environment Management Plan
Team Labs and Consultants1-4
available from the main road to the ML area. Tummalatalupuru RF is at a distance of 0.8 km
in West direction. Munagapadu RF is at a distance of 4.0 km in SW direction. Turimerla RF is
at a distance of 3.6 km in SE direction. Vutukur RF is at a distance of 6.0 km in SE direction.
Chaganam RF is at a distance of 6.3 km in South direction. Krishnareddipalle RF is at a
distance of 8.1 km in SW direction. Tatipalli RF is at a distance of 6.8 km in SW direction. Potu
Konda RF is at a distance of 9.8km in SW direction. Gonunarayanapalem RF is at a distance of
9.6 km in SW direction. Vepinapi RF is at a distance of 9.3km in SW direction. Duggunta RF is
at a distance of 3.5 km in North direction. Podalakur RF is at a distance of 4.2 km in North
direction. Vavintaparti RF is at a distance of 6.2 km in NW direction. Mogalluru RF is at a
distance of 7.7 km in NW direction. Pulikollu RF is at a distance of 8.9 km in NW direction.
Biradavolu Extension RF is at a distance of 9.6 km in NE direction. Kandleru River is flowing at
a distance of 3.5 km in North direction. Seasonal Paideru Kaluva is passing at a distance of 4.0
km in North direction. Penner River is flowing at a distance of 2.8 km in South direction.
Seasonal Griddalur Kaluva is passing at a distance of 8.7 km in SE direction. Seasonal Maleru
River is flowing at a distance of 8.7 km in SE direction. Telugu Ganga Canal is passing at a
distance of 7.5 km in SW direction. There is no state/national boundary, national park,
wildlife/bird sanctuary and critically polluted areas within 10km radius from the quarry lease
area. Mine lease location map is presented in figure 1.1. Details of the mine lease area are
presented in table 1.1. The lease area is bounded by following Geo Co- Ordinates
Latitude, N Longitude, E14°17'54.8" 79°41'25.5"14°17'56.3" 79°41'25.7"14°17'55.4" 79°41'31.8"14°17'56.5" 79°41'32.1"14°17'55.8" 79°41'33.9"14°17'55.2" 79°41'33.9"14°17'54.8" 79°41'33.6"14°17'54.8" 79°41'34.4"14°17'53.3" 79°41'33.6"14°17'53.5" 79°41'33.1"14°17'52.6" 79°41'32.4"14°17'53.4" 79°41'31.1"14°17'54.3" 79°41'29.2"14°17'53.1" 79°41'28.9"
M/s. C. V. C. Mining Company Cluster Environment Management Plan
Team Labs and Consultants1-5
Table 1.1 Details of the Mine Lease area
State & District Mandal Village Sy. No. Area in ha OwnershipAndhra Pradesh& SPSR Nellore Sydapuram Talupuru 109, 110 & 111 1.752 Patta Land
1.5 Land use pattern of the lease area
The quarry lease area is part of agricultural land with gentle slope due NNE.
Table 1.2 Land use pattern in lease areaS. No Purpose Extent (ha)
1 Area for quarrying 0.132 Dump Area 0.8733 Infrastructure 0.014 Road 0.0845 Mineral Storage 0.0286 Green belt 0.0757 Vacant 0.552
Total 1.752
M/s. C. V. C. Mining Company Cluster Environment Management Plan
Team Labs and Consultants1-6
Figure 1.1 Mine lease Location Map of M/s. C. V. C. Mining Company
Figure 1.2 Mine lease boundary map of M/s. C. V. C. Mining Company
M/s. C. V. C. Mining Company Cluster Environment Management Plan
Team Labs and Consultants1-7
M/s. C. V. C. Mining Company Cluster Environment Management Plan
Team Labs and Consultants1-8
2.0 Topography
The quarry lease area is part of agricultural land with gentle slope due NNE.
3.0 Regional Geology
The Nellore Mica belt is about 110 Km long from Vinjamoor in the North to Ozili in the South.
The width of Mica belt varies from 10 Km to 30 Km and the depth of Pegmatite varies from 10
to 350m (As per the information collected from the existing underground mines of Mica). The
dips of Pegmatite lenses are 45° to 80° towards West. This Nellore Mica belt is divided into 6
zones as detailed below
Nellore Mica Belt
1 Northern Pennar on the North most portion2 Tatipatri - Prabhugiripatnam3 Podalakur - Talupuru4 Kalichedu5 Utukur - Sydapuram6 Chennur – Kadivedu on the south most portion
The mining lease applied area is in the 3rd zone namely Podalakur-Talupuru. The granites and
pegmatite have intruded into schists of Kandra Volcanics, which contain Quartz, Biotite and
Hornblende Schists. Under favorable conditions, Muscovite books of commercial grades have
formed by intrusion of pegmatite into schists. Hundreds of Mica Mines were worked in the
Nellore Mica belt. The available information is Rubby Mica was found in 4th & 5th Zones and
green mica was found in other zones.
4.0 Geology of the area
A pegmatite lense is outcropping in the mining lease applied area. The dimension of the
pegmatite on surface is 25m wide and 50 m long. The country rocks is hornblende biotite
schist exists along the western margin of the pegmatite trending in NNE.
5.0 Details of Exploration
The area is previously worked by the previous applicant. One inclined shaft, one vertical shafts
were driven in North and Southern parts with to entry drives from levels at 12m, 18m, 25m,
37m and 46m were made to reach 5 levels at RL 188m, RL 182m, RL 175m, 163m and RL 154m.
The major concentration was made to extract the mica mineral only during that period and
feldspar zone was not tapped. A large dump of Mica pegmatite is existing in the area over an
extent of 8731 m2 with 2 to 2.25 m height. Total volume = 8731 X 2 = 17462 m3. Now, it is fresh
mine and we are waiting for statutory clearances from concerned departments.
M/s. C. V. C. Mining Company Cluster Environment Management Plan
Team Labs and Consultants1-9
6.0 Estimation of Reserves
The estimation of Mica, Quartz & Feldspar reserves is made by using the cross sectional
method the ore body. One cross section X-X1 was drawn perpendicular to the strike direction
of the formation to estimate the reserves. The ore zone is established upto 46m BGL and
probable resources are measured to the depth of 18m below the proved reserves. The bulk
density considered as 2.5 t/cum and recovery is taken as 10% of Quartz, 50% of Feldspar and
5% of Mica mineral. Geological Reserves calculation was given below in Table 1.3.
Table 1.3 Reserves Estimation
Section CategorySectional
Area(m2)
Sectionalinfluence
(m)
Volume(m3)
SpecificGravity
VolumeTons
Feldspar@ 50%Tons
Quartz@ 10%Tons
Mica@05%tons
Waste@ 35%Tons
X-X1Proved 1593 36 57348 2.5 143370 71685 14337 7168.5 50179.5
Probable 1230.61 36 44302 2.5 110754.9 55377.5 11075.5 5537.7 38764.2TOTAL 101650 254124.9 127062 254124.9 127062.5 25412.5
6.1 Mineable Reserves & Anticipated Life of the MineDescription Quantity Tons
Total Reserves 254124.9Pegmatite reserves blocked in pillar compartments 152474.94Reserves available 101649.96Annual Production 1564.5Life of the Mine: Mineable Reserves/Annual Production = 101649.96/1564.5 64.97 or 65Years
7.0 Mining Method
The mining operations will be carried out by the underground mining method with semi
mechanized by adopting of drilling and blasting with help of jack hammers. The accessing to
the mine through the existing shaft and the winzes will be made at a spacing of 15-30m to
explore the ore body and level interval between two adjacent levels will be 6-8m. In this
underground mining methods are as follows:
Entry into the deposits is by two inclined shafts along apatite vein at 60O from the
horizontal and with x – section of 2.5m x 2.2 m.
Drives cross cuts and winzes of 2.2 m x 2.0m cross section are developed to block the
mineral.
10 HP electrical winch and bucket of 0.6 tons capacities are used for hoisting the broken
material from the underground mine faces.
M/s. C. V. C. Mining Company Cluster Environment Management Plan
Team Labs and Consultants1-10
Material broken from the mine faces is moved to the hoist chamber through manually
pushed tubs on rails laid on the drive floors.
Wooden props are used to support local loose patches.
Cap lamps will be used by the workers
Underground layouts are as follows:
The method of mining is underground mining method. There are old workings up to a depth
of 52 m. One vertical shaft is available at South upto 52 m depth and a inclined shaft in South
side with two inlets are present. The present workings have established the presence of
pegmatite. Several cross cuts which are proposed to confirm width of pegmatite and content
of minerals are planned. Thus by the end of five years, the pegmatite will be explored
/exploited up to 52m depth and width will be established. Inclined Shaft will be extended
upto 125 m RL (95 m).
System of Drilling & Blasting:
The pegmatite and schist are hard and compact rocks. Excavation is done by drilling and
blasting. The cross sections of vertical shaft is 2.5 m. Diameter, that of winze is 2.2 m and that
of level drives and cross cuts is 2.2/2 m. The number of holes required for shaft, winze and
levels are 42, 42, 48, 54 & 64 respectively. Model Burn cut design for underground drilling and
blasting this formula is followed in the small mines viz Mica pegmatite which are of 2.2 m
(Height) and 2m(Width) with proportionate measurements and drill hole length will be 0.75m
each with 32mm dia. The alternate holes are charged with explosives the sequence of delay
occurs from centered 4 holes and the surrounding are fires with few seconds/ milli seconds
delay. The drilled holes are blasted by using slurry explosives and short delay detonators to
control vibrations. All precautions prescribed under MMR 1961 will be followed. The average
quantity of explosives used as 2 Tons /1 Kg of explosive. The requirement of explosive for
shaft sinking is 9 Kgs for 1 m progress, winzes is 7 Kgs for 1m progress and 5 Kgs for 1m
progress in levels. The total requirement of explosives for total annual volume of 1980 MT,
development work is calculated for five years
Mine support:
The Hanging Wall and Foot Wall consist of Hornblende schist’s and pegmatite itself is strong.
Normally supports are not required. When kaolin is present, the pegmatite becomes soft and
M/s. C. V. C. Mining Company Cluster Environment Management Plan
Team Labs and Consultants1-11
friable. That portion of mine work will be supported by post and bar method. The supporting
material is timber for temporary support and steel for permanent support.
Underground transportation:
Mica (Scrap and books) will be handpicked from the blasted material in the mine and carried
on head loads to the surface for dressing in Mica Shed. The rest of the broken rock will be
loaded manually into half ton capacity level tubs and trammied on rails to the shaft bottom
from where, the material is lifted by hoist to the surface and emptied into level tubs, for
further coarse of action i.e. sorting and sizing etc
Mine ventilation:
30000 m3/min capacity ventilation plan will be installed as forcing fan at surface at the mouth
of man way with proper construction. The air is forced through man way and the return air
will be through the vertical shaft which is second outlet. Necessary ventilation stopping will
be constructed at required places so that short circuiting of air is not allowed. The air will be
forced so that every person employed in the mine will be supplied 6 m3 for minute, as well as
dilute all the gases generated in the mine to permissible limits.
8.0 Extent of Mechanization
The machinery/equipment proposed for the applied area as followsTable 1.5 List of Machinery
S. No. Name of the Machinery No’s1 Compressor (310cfm FAD capacity – 8 to 10kg/cms pressure) 1
2 Jack hammers (25 to 30kgs weight to operate with 6 to 7kgs/cm2 pressure of compressorair
5
3 Drill steels 150
4
Underground transport Hoist one ton capacity 1 ½ tubs to run on rails 12 20 kgs/m rails lines & crossing 5 tons 20mm steel wire rope 120 mt
5
Pumping 20 HP – 10m head electric pump 1 10 HP- 30m head electric pump 1 Compressed air roto pump 2
6 Ventilation – 30000 cft/m ventilation fan 17 Lighting – 10kva step down transformer 440v to 110 v 1
8Miscellaneous G.I. Sheets 5 Tons
M/s. C. V. C. Mining Company Cluster Environment Management Plan
Team Labs and Consultants1-12
Structural , Head Gear & others 5 Tons G. I. Pipes (3” dia, 2” dia, 1” dia) 3 Tons Mining Tools (Spares, Crow Bars, Fans) 1 Tons
9.0 Employment Potential
The following personnel have been deployed for undertaking mining operations in the subject
area.
Table 1.6 Employment potentialS. No. Designation Quantity No’s
1 Mining Manager/Supervisor 12 Mining Engineer 13 Mine Foreman 14 Mine Mate 15 Blaster 16 Mine surveyor 17 Electrical Supervisor 18 Geologist 19 Hoist Operator 1
10 Maintain Staff 211 Skilled workers 3012 Unskilled workers 2013 Mica supervisor 114 Watch man 4
Total 6610.0 Year wise development and production
1st Year: It is proposed to link the two shafts from hanging wall side in the west of pegmatite
zone to eastern boundary crossing the inclined shaft to previous year’s workings with single
drive (2.2 m (H) x 2m (W)) drive top (2m (H)) over a length of 58m (L) along south boundary of
the pegmatite body between section lines, with 2 cross cuts (2.2 m (H) x 2m (W)) of lengths of
17m+17m advances in North direction. At the same time, 1 Winze/Vertical Shink (3m (H) x 2m
(W)) x 2.1 will be driven down to reach the 3 year development cum production level and
excavating 1045Tons of rock mass from which 522.5 tons (50%) of Feldspar, 104.5 tons (10%)
of Quartz and 52 tons (5%) of Mica recovery and remaining will be as waste @365.8 Tons
(35%).
2nd year: It is proposed to link the two shafts from hanging wall side in the west of pegmatite
zone to eastern boundary crossing the inclined shaft to previous year’s workings with single
drive (2.2m (H) x 2m (W)) drive top 2m (H) over a length of 68m (L) in west of the pegmatite
M/s. C. V. C. Mining Company Cluster Environment Management Plan
Team Labs and Consultants1-13
body between section lines, these 2 drives will be connected by 2 cross cuts (2.2m (H) x 2m
(W)) of lengths of 18 + 18 m. At the same time, 1 Winze / Vertical Shink (6m (H) x 2m (W)) 2.2
m will be driven down to reach the 3rd year development cum production level excavating 1210
Tons of rock mass from which 605 tons (50%) of Feldspar, 121 tons (10%) of Quartz and 60.5
tons (5%) of Mica recovery and remaining will be as waste @ 423.5 Tons (35%).
3rd Year: It is proposed to link the two shafts from hanging wall side in the west of pegmatite
zone to eastern boundary crossing the inclined shaft to previous year’s workings with single
drive (2.2m (H) x 2m (W)) drive top 2m (H) over a length of 67m+54m (L) in East and West of
the pegmatite body between section lines, these 2 drives will be connected by 2 cross cuts
(2.2m (H) x 2m (W)) of lengths of 18 + 18 m. At the same time, 1 Winze / Vertical Shink (6m
(H) x 2m (W)) 2.2 m will be driven down to reach the 3rd year development cum production level
and excavating 1958 Tons of rock mass from which 979 tons (50%) of Feldspar, 195.8 tons
(10%) of Quartz and 97.9 tons (5%) of Mica recovery and remaining will be as waste @ 685.3
Tons (35%). The Inclined shaft will be further extended to a length of 12m due SW with (2.5m
(H)x2.2m (W)).
4th Year: It is proposed to link the two shafts from hanging wall side in the west of pegmatite
zone to eastern boundary crossing the inclined shaft to previous year’s workings with 2 drives
(2.2m(H)x2m(W)), drive top 2m(H) over a length of 68m+57m(L) in East and west of the
pegmatite body between section lines, these 2 drives will be connected by 2 cross cuts (2.2 m
(H)x2m(W)) of lengths of 18+18 m. At the same time, 1 Winze/Vertical Shink (6m (H)x2m(W))
2.2m will be driven down to reach the 5th year development cum production level and
excavating 1980 Tons of rock mass from which 990 tons (50%) of Feldspar, 198 tons (10%) of
Quartz and 99 tons (5%) of Mica recovery and remaining will be as waste @ 693 Tons (35%).
The Inclined shaft will be further extended to a length of 13m due SW with (2.5m (H)x 2.2m
(W)).
5th Year: It is proposed to link the two shafts from hanging wall side in the west of pegmatite
zone to eastern boundary crossing the inclined shaft to previous year’s workings with 2 drives (
2.2 m (H)x 2m (W)) drive top 2m (H) over a length of 67m+55m (L) in East and west of the
pegmatite body between section lines, these 2 drives will be connected by 2 cross cuts (2.2m (H)x
2m (W)) of lengths of 18+18 m. At the same time, 1 Winze/Vertical Shink (6m (H) x 2m (W)) 2.2m
will be driven down to reach the next year development cum production level and excavating
M/s. C. V. C. Mining Company Cluster Environment Management Plan
Team Labs and Consultants1-14
1969 Tons of rock mass from which 984.5 tons (50%) of Feldspar, 196.9 tons (10%) of Quartz
and 98.45 tons (5%) of Mica recovery will be achieved. About 2856.7 tons intercalated waste
will be generated which would be dumped on the proposed dump over the west portion of
the proposed QL area. The top soil generated will be utilized for plantation purpose. The
detailed calculations and year wise development quantities are given below
Table 1.4 Year Wise Production for Feldspar, Quartz and Mica
Year Volume(m3)
TonnageFactor
VolumeTons
Feldspar @50% Tons
Quartz @10% Tons
Mica @5% tons
Waste @35% Tons
I Year 418 2.5 1045 522.5 104.5 52.3 365.8II Year 484 2.5 1210 605.0 121.0 60.5 423.5III Year 783.2 2.5 1958 979.0 195.8 97.9 685.3IV Year 792 2.5 1980 990.0 198.0 99.0 693.0V Year 787.6 2.5 1969 984.5 196.9 98.5 689.2Total 22208 8162 4081 816.2 408.1 2856.7
Re-handling of waste dump for Scrap Mica segregation @3% recovery.
The existing waste dump will be re-handled phase-wise on sight. The waste will be manually
segregated to extract the mica and leaving the 97% waste.
Year Area m2 Heightm
Volumem3 T.F Volume
TonsRecovery@3% tons
Leftover Waste@97% tons
1 1766 2 3532 2.5 8830 264.9 8565.12 1766 2 3532 2.5 8830 264.9 8565.13 1614 2 3228 2.5 8070 242.1 7827.94 1735 2 3470 2.5 8675 260.25 8414.755 1850 2 3700 2.5 9250 277.5 8972.5
Total 43655 1309.65 42345.3511.0 Drilling & Blasting
The pegmatite and schist are hard and compact rocks. Excavation is done by drilling and
blasting and the cross sections of vertical shaft is 2.5m diameter, that of winze is 2.2m and
that of level drives and cross cuts is 2.2/2m. The number of holes required for shaft, winze
and levels are 42, 42, 48, 54 & 64 respectively. Model Burn cut design for underground
drilling and blasting this formula is followed in the small mines viz Mica pegmatite which are
height of 2.2m and width of 2m with proportionate measurements and drill holes length will
be 0.75m each with diameter of 32mm. The alternate holes are charged with explosives and
the sequence of delay occurs from centered 4 holes and the surrounding are fired with few
M/s. C. V. C. Mining Company Cluster Environment Management Plan
Team Labs and Consultants1-15
seconds/milli seconds delay. The drilled holes are blasted by using slurry explosives and short
delay detonators to control vibrations. All precautions prescribed under MMR 1961 will be
followed. The average quantity of explosives used as 2Tons/1 Kg of explosive. The
requirement of explosive for shaft sinking is 9 Kgs for 1m progress, winzes is 7 Kgs for 1m
progress and 5 Kgs for 1m progress in levels. The total requirement of explosives for annual
production of 1980 MT, development work is calculated for five years
Inclined shaft/winzes/V. Shink =64m x 7kgs = 448kgs
Levels =494m x 5kgs=2470kgs
Cross cuts =178m x 7kgs = 1246kgs
Total Requirement = 4464kgs
Allowing for losses on miss fire etc 10% is taken over and above this. The total requirement is
4580.4 Kgs.
The average yearly requirement: 916.08 Kgs
The Lessee will apply for licensed Explosive Magazine. The required explosive will be drawn
from that magazine. Alternatively engages a licensed blasting contractor for carrying out the
drilling and blasting (which practice is in vogue in small mines in the area).
9.1 Drilling & blasting safety
Adequate competent persons will be provided to make the blasting operation completely
safe.
Vibration will be managed by delayed blasting pattern, proper stemming and control
charge per hole.
Adequate sirens and signal boards will be given in addition to posting guards at strategic
points.
All terms and conditions laid down in the license shall be compiled
No dangerous/inflammable articles shall be taken by the personnel employed for blasting.
12.0 Use of Mineral
Mica:
Mica is having high insulation property. One mill thick Ruby Mica can stop 10000 volts. The
mica will not deform even at very high temperature. This is an important requirement for
space machinery. Most of the mica produced in India is exported to developed countries. Scrap
M/s. C. V. C. Mining Company Cluster Environment Management Plan
Team Labs and Consultants1-16
Mica is utilized in forming various products like Micanite Sheet, Mica Tapes & Mica powder.
They are used in electronic machinery. Green Mica is present in the mining lease applied area.
Feldspar:
Feldspar containing 12% + Alumina is used in Ceramic Industry and Sanitary Ware. Electric
Ceramic Insulators for over head lines are made from Feldspars. This is used in India and
export demand is available.
Quartz
This is used in Glass Industry. High quality quartz is used to make semi conductors which are
essential for electronic industry. The demand is available for Quartz in India and outside.
13.0 Water requirement
Water requirement of 5.9 KLD is mainly for drinking purpose, domestic purpose, green belt
maintaining and for sprinkling on Mine haulage roads the water shall be drawn from nearby
village. The domestic waste water shall be sent to septic tank followed by soak pit. The water
requirement is presented in table 1.7.
Table 1.7 Water RequirementS. No. Water Usage Quantity KLD
1 Wet drilling operation 1.02 Water sprinkling on haul roads and for waste dump 1.33 Domestic Water 3.04 Green Belt 0.6
Total 5.914.0 Environment Management Plan
Environmental protection is an issue that no organisation can neglect and hope to survive.
The byproducts of civilization are being dumped upon the environment to a degree that the
environment finds difficult to assimilate. The key to the success of the integrated approach to
pollution prevention and control is the management and operation of the organization.
Effective committed management delivers a successful operation. As total commitment to
the environment, not just for compliance with legal or regulatory compliance will be the
essence of environment management. Many companies have recognized the benefits of
implementing an effective environmental management system. Environmental management
plan can be effectively implemented to mitigate the pollution levels by observing the
following:
a. Pollution will be prevented or reduced at the source
M/s. C. V. C. Mining Company Cluster Environment Management Plan
Team Labs and Consultants1-17
b. Pollution that can not be prevented will be recycled in an environmentally safe manner.
c. Pollution that can not be prevented or recycled will be treated in environmentally safe
manner and
d. Disposal and other releases into the environment will be used only as a last resort and will
be conducted in an environmentally safe manner.
The proposed project is Mica, Quartz and Feldspar mine. The mine owners are aware of the
adverse impacts due to the mining activity and propose to initiate a number of measures for
the environment protection within the mine area and in the surrounding areas. The company
has a stated environmental policy of ensuring regulatory compliance with respect to the
statutory laws and regulations and those periodically issued by the Ministry of Environment,
GOI, New Delhi, CPCB, New Delhi and A.P Pollution Control Board, Hyderabad.
14.1 Sources of Pollution and Control Measures
The sources of pollution from the proposed activity are mainly from Mining, Drilling, Blasting
and transportation of mineral.
14.1.1 Noise Generation
The major source of noise pollution is due to drilling, machinery and Blasting. Protective
equipment to reduce the noise levels like ear muffs and other protective devices will be
provided to the staff working near noise generating sources. The greenbelt development will
also help in the reduction of noise levels outside the mine. Noise barriers in the form of trees
are provided to attenuate the noise levels. Training would be imparted to mine personnel to
generate awareness about the damaging effects of noise. Proper maintenance of the
equipment will also reduce the noise. The noise produced due to machinery operation and
vehicles are negligible.
15.0 Occupational Safety and Health
Health and safety aspects of the mine will be taken care off as per the World Bank (WB)
guidelines on open pit mining. The guidelines provide the detailed information on the aspects
that are required to be taken into account for maintaining proper health and safety issues.
The workers continuously exposed to dust will be provided with some protective devices like
dust mask to prevent respiratory disorders. The workers continuously exposed to a high noise
will be provided with ear muffs/ earplugs. Green belt in and around the mining area will be
developed to attenuate noise and dust impact. The blasting carried out in the mine area will
M/s. C. V. C. Mining Company Cluster Environment Management Plan
Team Labs and Consultants1-18
be carefully planned and executed under the supervision of a responsible officer, to avoid any
accidents. Drinking water supply for the employees will be provided by the project authority.
The standard of the drinking water will be per WHO guidelines. Periodical training programme
to inform the employees about their task, associated risk, and safe working practices will be
undertaken. Training will also include information on accident prevention, proper control and
maintenance of equipment and safe material handling practices. Proper fencing will be
provided around the mine pits and waste dump areas to prevent the accidents and cattle felt.
A regular monitoring of the Occupational Health and Safety will reduce the chances of
accidents in the mine. Records of job related accidents and illness should be maintained.
These information’s will be reviewed and evaluated to improve the effectiveness of
Environmental Health and Safety programme.
15.1 Occupational Safety and Health to Control Dust Inhalation
Dust is expected to be generated during mining and dose not effect the environment.
However while drilling, wet drilling will be practiced. It is a small scale mining activity and not
much vehicular movement is expected. Water sprinkling arrangement will be provided to
reduce the dust emissions and green belt will be developed around the pits to reduce dust
generation and noise generation. Trucks are covered with tarpaulin during transportation and
overloading of trucks will be avoided to prevent dust generation. PUC certified trucks will be
used for transportation of mineral and waste within the lease area. Greenbelt will be
developed with tall trees around the waste dump area to prevent dust emission. All the above
precautions would be adopted to prevent dust generation at site and to be dispersed in the
outside environment. However, for the safety of workers at site, engaged at the strategic
locations/dust generation points like drills, loading & unloading points dust masks would be
provided. Dust masks would prevent inhalation of RSPM thereby reducing the risk of lung
diseases and other respiratory disorders. Regular health monitoring of workers will be carried
out.
15.2 Occupational Safety and Health to Control Exposure to Noise
Blasting will be done using safety fuse using slurry explosive to reduce vibrations, and the
amount of explosive used will also be less at a time. There will not be heavy earth moving
machinery which may create some noise pollution. Thus the vibration and noise will be well
controlled within permissible limits. Trucks are kept in switch-off mode while loading and the
M/s. C. V. C. Mining Company Cluster Environment Management Plan
Team Labs and Consultants1-19
speed of the trucks are restricted to limited speed of 15-20kmph to prevent the noise
generation and safety purposes. To protect the workers from exposure to high levels of noise,
following measures would be adopted; by provision of protective devices like ear muffs/ear
plugs to workers who cannot be isolated from the source of high intensity noise, reducing the
exposure time of workers to the higher noise levels by shift management.
15.3 Control of Ground Vibrations & Fly Rocks Boulder
In this area the applicant proposes to deploy blasting with less quantity of explosives. There is
going to be hardly any impact on surroundings, as there are less blasting and intended to use
low power explosives in this mine. It is a small scale mine and only limited No. of holes are
blasted. Ground vibrations due to blasting and its impact on various mine structures, should
be studied in details when the mine becomes operational. General measures to reduce
ground vibration & fly rocks resulting from blasting are given below:
Peak particle velocity or ground vibrations for safety of nearby structures and residential
buildings should be well within 1 mm/sec;
To contain fly rocks, stemming column should not be less than the burden of the hole, and
the blasting area should be muffled;
Blasting should be carried out in the daytime, as during the night time the sound intensity
becomes higher;
Blasting should not be carried out when strong winds are blowing towards the inhabited
areas;
Each blast should be carefully planned, checked, and executed under the supervision of a
responsible officer. Blasting data/observations should be recorded; and
As per the mining plan, in order to ensure slope stabilization, controlled production blasting
shall be adopted to avoid tension cracks and back breaks. Such cracks may get filled with
water, which reduces the stability of excavated slopes and the angle of slopes.
16.0 Water Quality Management
Since there is no chemical discharge either from the mine or from the processing mine, there
will not be water pollution. The proposed mine workings will not touch the ground water
aquifer and no change in quality of water.
M/s. C. V. C. Mining Company Cluster Environment Management Plan
Team Labs and Consultants1-20
16.1 Water Resources
There are no wells or springs in the area. Mining operations will be carried on surface. Hence
there will not be adverse effect on ground water due to mining. The daily water requirement
for the mine operations would be approximately 5.9 KLD. Water sprinkling on mine haulage
roads etc shall consume 1.3 KLD. Wet drilling operations consume about 1.0 KLD. For green
belt development water consumption is about 0.6 KLD. Domestic purpose is about 3.0 KLD.
The water is to be sourced from nearby village through tankers. The generation of
wastewater from domestic sources is expected to be approximately 2.4 KLD, which will be
sent to septic tank followed by soak pit.
16.2 Water Management
Following measures will be adopted to mitigate the impact on the water resources:
The blasting activities will have to take care on the sinkholes, cracks and fissures in the site
activities.
During excavation and drilling activities effort must be taken to avoid face collapse at these
cracks and fissures.
To prevent surface water contamination by oil/grease, leak proof containers shall be used
for storage and transportation of oil/grease. The floors of oil/grease handling area will be
kept effectively impervious.
To prevent degradation and maintain the water quality during rainy season, adequate control
measures should be adopted to check the mine run-off into the natural streams. Following
control measures are proposed to be adopted.
16.3 Catchment Area Treatment Plan
A catchment area treatment plan has been developed keeping in mind the results of the
hydrology/ hydrogeology study as well as the climate data. As there are no perennial water
sources running on or through the site, the mine water discharge is limited to the monsoon
season only. To keep water from entering the mine during this period, a garland drain will be
developed, which will bend to guide the water to the nearest natural surface drain. In terms
of water quality, good mining practices are planned, additionally the natural state of
surrounding areas, should ensure that rain water run-off from the mine does not contain any
toxic elements. As the site has no overburden or excess clay, potential discharge of sediments
is quite limited and any residual clay or limestone particles which are washed down will be
M/s. C. V. C. Mining Company Cluster Environment Management Plan
Team Labs and Consultants1-21
captured by a sump located at the lowest bench. The sump will be cleaned regularly and
discharge water monitored consistently. If required, based on monitoring, an additional catch
pit can be located at the main garland drain. The sump proposed in the bottom bench will be
designed based on the peak discharge and will be expanded over a period of time to
accommodate the increasing quantum of water discharge. The garland drain shall be
provided surrounding the mine area. Check dam and salutation pond need to be constructed
of appropriate size to arrest silt and sediment flows from soil and mineral dumps. The water
so collected should be utilised for watering the mine area, roads, green belt development etc.
The drain should be regularly desalted and maintained. The garland drain (size, gradient and
length) and sump capacity should be designed keeping 50% safety margin over and above the
peak sudden rainfall and maximum discharge in the area adjoining to natural drains. Sump
capacity should also provide adequate retention period to provide proper settling of silt
material. The surface water around the mine, and infrastructure will be regularly tested and
appropriate control measures adopted in case of any pollutant is detected above the
prescribed limits.
17.0 Waste Management and Dump area
During these five years period about 2856.7 Tons of waste will be produced. This waste will
be dumped over an area of 0.873 ha within the lease area.
18.0 Land Management
Land degradation is one of the major adverse impacts of underground mining.
19.1 Land Reclamation
No reclamation is proposed during the plan period.
19.2 Soil Conservation Measures
Top soil is not expected in this mine. To prevent soil erosion and wash-off of dump-fines from
freshly excavated benches and dumps following measures shall be adopted:
Garland drains will be provided around the mine wherever required to arrest any soil
from the mine area being carried away by the rain water;
Toe drains with suitable baffles will be provided all along the toe of the soil dumps to
arrest any soil from the dump slopes being carried away by the rain water;
Loose material slopes will be covered by mineation by making contour trenches at 2 m
interval to check soil erosion both due to wind and rain;
M/s. C. V. C. Mining Company Cluster Environment Management Plan
Team Labs and Consultants1-22
19.0 House Keeping
Proper house keeping and cleanliness will be maintained in the infrastructure facilities. Wet
mopping will be adopted to conserve water. Sign boards will be provided in the work areas
and the road and building highlighting the safety and occupational aspects.
20.0 Transport Systems
Nearest town is Gudur located at a distance of 22 Km from the ML area in SE direction.
Nearest railway station is at Manubolu at a distance of 20.8 km from the lease area in SE
direction. Nellore to Rapur main road is passing at a distance of 3.0 km in North direction.
Duggunta to Kalichedu road is passing at a distance of 0.15 km in NE direction. Cart Road is
available from the main road to the ML area. Number of truck trips will be 1 per day. When
the material is sold to the parties, it is expected to lift the minerals by their own vehicles or
hired ones from the mine. Sufficient parking facilities will be provided for vehicles loading and
unloading of material. Safety signs will be displayed inside and outside the mine to avoid road
accidents.
21.0 Environmental Greening Program
Environmental greening program is an important component of the Environment
Management Plan and is an imperative requirement for any major industrial activity, as per
the guidelines issued by the Ministry of Environment and forests, Govt. of India.
Conceptualization, design and implementation of the proposed activity, taking into account
the specific requirement of the proposed mining activity and the site conditions are
presented. During this plan period about 150 saplings of local plants will be planted over an
area of 0.075 ha in the lease area. A thorny fencing shall provide to guard the trees from the
cows and goats, necessary manpower shall be arranged for vigilance. The environmental
greening program as designed comprises the location and development of a shelterbelt and
Afforestation in about 0.075 Ha. The shelterbelt will contain species, which act as
windbreakers so that the environment within the mine is contained; the planting of different
species in rows is envisaged in general in the greenbelt.
22.0 Socio-economic Environment
The project provides an opportunity for the local people to get employment directly or
indirectly and helps in the upliftment of the socioeconomic status of the area. The proposed
project would generate an employment of 66. The management will involve in social activities
M/s. C. V. C. Mining Company Cluster Environment Management Plan
Team Labs and Consultants1-23
of stakeholders/surrounding community by planning the betterment of neighboring social
conditions through awareness and welfare programs to ensure an improved relation, useful in
the long run. Many of the beneficiaries of such programs will include own employees as well.
The goodwill of the local populace can never be ignored. It is proposed to supply drinking
water and medical facilities to the villagers. The channels employed may vary either through
direct contact or by means of local organizations. Another important facet of social
environment identified by the project proponents is a green appearance; hence the
management will develop a green belt towards aesthetic beautification as the same is
necessary to be considered as a responsible, social neighbour.
23.0 Disaster Planning
The complete mining operation will be carried out under direction of qualified mines manager
and superior mining personnel, following the directions of Directorate General of Mines
Safety (DGMS) and officers of Indian Bureau of Mines. Code of practice of different
operations will be formulated to maintain of high standard of safety. Work persons have been
given vocational training and further the standing will be continued to new entrants.
Moreover mining staff would be sent to refresher courses from time to time to keep them
abreast of the regulations. However following natural/ industrial hazards may occur during
normal operation
Cross Cuts, Drivers & Winzes maintained at underground face.
Working of mine as per approved plans
Provision of adequate capacity pumps for pumping out water from the underground
mining with standby arrangements
In order to take care of above hazards/disasters, the following control shall be adopted:
All safety precautions and provisions of Metalliferous Mine regulation 1961 are strictly
followed during all mining operations;
Regular maintenance and testing of all mining equipment as per manufacturers guidelines
Checking and regular maintenance of garland drains and earthen bunds to avoid any
inflow of surface water into mining area;
Entry of unauthorized persons shall be prohibited;
Fire fighting and first aid provisions in the mines office and mining Area;
Provision of all the safety appliances such as safety boots, helmets, goggles etc. would be
M/s. C. V. C. Mining Company Cluster Environment Management Plan
Team Labs and Consultants1-24
made available to the employees and regular check to ensure the use;
Training and refresher courses for all the employees working in the hazardous premises;
Working of mine as per approved plan, related amendments and other regulatory
provisions;
Cleaning of mine faces shall be done regularly;
Handling of explosives, charging and blasting shall be carried out by competent persons
only;
Provision of magazine at safe place with fencing and necessary security arrangement;
Suppression of dust on the haulage roads by providing water sprinkling.
24.0 Environment Management Cell
A Cell for Environmental Management within the mine at the project level, will take the
overall responsibility for co-ordination of the actions required for environmental
management and mitigation, and for monitoring the progress of the proposed management
plans and actions to be taken for the project. The Cell will be under the overall supervision of
the Mine Manager, and responsible for monitoring of the implementation of the various
actions which are to be executed by the agencies specified in the EMP. The Cell will be
headed by Mine Manager and the other members of the cell that will include a Horticulturist
and 1 no. of supervisor. The EMC will prepare a formal report on environmental management
and mitigation for the Environmental Engineer at the Mine, at six-monthly intervals. Reports
on any urgent or significant issues may be prepared at shorter intervals. Apart from
responsibilities listed above, the EMC will have the responsibility of the following:
Collection of water and air samples within and outside the work zone;
Analyzing the water and air samples;
Implementation of the control and protective measures;
Land reclamation and vegetation;
Co-ordination of the environment related activities;
Collection of the statistics of health of workers;
Green belt development;
Awareness and implementing safety programmes; and
Monitor the progress of implementation of EMP.
M/s. C. V. C. Mining Company Cluster Environment Management Plan
Team Labs and Consultants1-25
24.1 Post Project Monitoring
The survey of air pollution comprises of the following monitoring aspects;
a. Ambient air quality survey
b. Noise Level Monitoring
c. Water quality monitoring
Ambient air quality and noise level Monitoring will be carried out at minimum three stations,
one station within mine site and two stations nearby residential areas outside the mine.
Parameters like suspended particulate matter, sulphur dioxide, oxides of nitrogen carbon
monoxide and lead will be monitored. The frequency of monitoring is preferably once in three
months on 24 hour basis. The samples will be collected in accordance with the procedures
given by CPCB. Existing ambient air quality in the mine lease area is as follows.
24.2 Other Management Aspects
Records will be maintained for the analysis of ambient air quality and noise levels. These
records are not only required for the perusal of the Pollution Control Board authorities. The
management will maintain the records as per the hazardous waste regulations and EPA
regulations and apply for the annual consents for air and water, and renewal of authorization
for the storage of hazardous waste as per the Hazardous Waste (Handling & Management)
Rules, 1989. The records of hazardous waste manifest will be maintained. The format of the
same is enclosed in appendix. The mine shall obtain the consent for operation (CFO) as
required under section 25/26 of the Water act, 1974 and under section 21/22 of Air Act,
1981, before trial production and commissioning from the State Pollution Control Board. The
CFO will be renewed each year by the management. The mine will submit environmental
statement every year before September 30. The management ensures that it will comply with
all the directions and regulations issued by the Ministry of Environment and Forests, New
Delhi, State and Centre Pollution Control Boards. The Consent for Establishment, Consent for
Operation will be displayed in a conspicuous location for the information of the inspecting
authorities of different departments.
25.0 Cost proposed for Environmental Protection Measures
The cost estimate of environment management is presented in table 1.9.
Table 1.9 Environment Management - Cost EstimateS. Description Item Capital Recurring Remarks
M/s. C. V. C. Mining Company Cluster Environment Management Plan
Team Labs and Consultants1-26
No. cost (Rs.) cost (Rs.)
1 Air pollution
Nose masks 39600 26400 Once a week. Replaceable, andcost may increase with time
Cloth for drillers 59400 29700 Issued quarterlyGunny bags for covering thesurface of jackhammer holes 20400 13200 As and when needed, Lump
sum.Road wetting and waste dumpsettling (1/4 of wetting)-5000Ltrs tank
29400 18900Water tanker cost @ onetankers per day for 300 days
Plantation and maintenance41500 20750
Re-plant the non-survivingplants, watering and protectionfrom animals
Sub Total 190300 108950
2 Waterpollution
Construction of garland drains 45000 26000 Once only for the leaseperiod/life of mine
De-silting operations 40600 19720 Yearly and manual operationsConstruction of retaining wall 31200 15600 Cost of construction of wall
Sub Total 85600 45720
3 Noisepollution
Maintenance of machinerysuitably 180000 90000 Included in main cost
PPE's like Ear muffs 99000 49500 Once in six monthsSub Total 279000 139500
4Occupational
Safety andHealth
First aid kits - 2 No'sFire extinguishers - 2 No's 10000 5000 Once in year, replace by
conducting periodical checkupPPE's to all employees (handgloves @ Rs. 30, safety shoe @Rs. 1500 and helmet @ Rs. 100)
65000 32500Safety shoe twice in a year,helmets once in three years andhand gloves thrice in a year
Training and awarenessprograms on risk factors duringemergencies by the experts
29000 14500Once in six months and createsign boards about the risk andsafety precautions regularly
Periodical medical checkup andsupply of medicines 52800 23760 Once in a year and supply of
medicines for every three monthsSub Total 156800 75760
5 Environmentalmonitoring
Ambient air quality studies -Once in six months-2 locations - 13600
Will be done throughMoEF&CC/NABL recognised
laboratories
Water quality studies - Once ayear - 2 Locations - 3000
Noise studies-Once in sixmonths-2 Locations - 4400
Vibration studies - Once in year- 1 locations - 7800
Sub Total 0 28800Grand Total 711700 398730