data_centers - design consideration(1).pdf

56
John Jones, M.B.A. Vice President for Information Technology Indiana Wesleyan University Design Considerations When Planning a New Data Center Eric Sank, P.E., RCDD Design Collaborative, Inc.

Upload: fazilarahman

Post on 17-Feb-2016

14 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Data_Centers - Design Consideration(1).pdf

John Jones, M.B.A. Vice President for Information Technology

Indiana Wesleyan University

Design Considerations When Planning a New Data Center

Eric Sank, P.E., RCDD Design Collaborative, Inc.

Page 2: Data_Centers - Design Consideration(1).pdf

•History of the IWU Data Center •Challenges •Charge •Frustration •Partnership

Data Center Design – a Case Study.

Page 3: Data_Centers - Design Consideration(1).pdf

Understand your needs.

•Present Equipment + Growth •Racks •Layout •Misc. Equipment

Page 4: Data_Centers - Design Consideration(1).pdf

Location, location, location...

•Security •Access to fiber/copper •Accessibility •No Foreign Services •Visibility

Page 5: Data_Centers - Design Consideration(1).pdf

Reliability

•How Critical are Processes •Uptime Institute

•www.uptimeinstitute.org •Tier Classification

Page 6: Data_Centers - Design Consideration(1).pdf

Tier 1 •Single Path cooling & electrical

•No redundancy

•99.671% availability (28 hours/year)

Reliability – Tier Classification

Page 7: Data_Centers - Design Consideration(1).pdf

Reliability – Tier Classification

Tier 2 •Single Path cooling & electrical

•Redundant capacity, single path

•Raised floor, UPS, engine generator

•99.741% availability (22 hours/year)

Page 8: Data_Centers - Design Consideration(1).pdf

Reliability – Tier Classification

Tier 3 •Active & Passive delivery paths

•Redundant Capacity

•Concurrently maintainable9

•99.982% availability (1.6 hours/year)

Page 9: Data_Centers - Design Consideration(1).pdf

Reliability – Tier Classification

Page 10: Data_Centers - Design Consideration(1).pdf

Reliability – Tier Classification

Tier 4 •Dual active delivery paths

•N+1 redundancy

•Concurrently maintainable

•99.995% availability (.4 hours/year)

•Clean out your desk!

Page 11: Data_Centers - Design Consideration(1).pdf

Power Distribution

•Design Considerations •Rules of Thumb

Page 12: Data_Centers - Design Consideration(1).pdf

Power Distribution

Design Considerations •Does electrical service have adequate capacity?

•Need at least one feed from building utility

service.

•Distribution type panel on output of transfer

switch

Page 13: Data_Centers - Design Consideration(1).pdf

Rules of Thumb •200-400 watts/sq f.t total electrical load for

data center including A/C

•Cost is dependent on distance from service.

Power Distribution

Page 14: Data_Centers - Design Consideration(1).pdf

Emergency Generator

•Design Considerations •Rules of Thumb

Page 15: Data_Centers - Design Consideration(1).pdf

Emergency Generator

Design Considerations •Powers A/C, UPS, lights & other critical equip.

•Fuel choice – natural gas vs. diesel

•Transfer switch – programmed transition

•Indoor vs. Outdoor

•Accessories – heater, charger, etc

Page 16: Data_Centers - Design Consideration(1).pdf

Emergency Generator

Rules of Thumb •Size the generator 2-3 times the KW of

UPS/equipment load.

•Estimate $250-$300/KW for installed price

Page 17: Data_Centers - Design Consideration(1).pdf

UPS (Uninterruptible Power Supply)

...brown can’t do this for you.

Page 18: Data_Centers - Design Consideration(1).pdf

...brown can’t do this for you.

UPS (Uninterruptible Power Supply)

•Design Considerations •Rules of Thumb

Page 19: Data_Centers - Design Consideration(1).pdf

UPS

Design Considerations •Required watts.

•Actual vs. rated loads

•Availability – N, N+1, 2N

•Single Unit vs multiple, rack mounted UPS

•Dual Conversion vs. standby

•Location

•Battery type, time, weight

•Bypass – static and wrap-around

•Flywheel Technology

•Limit battery recharge when on generator

Page 20: Data_Centers - Design Consideration(1).pdf

UPS

Rules of Thumb •70-100 watts/s.f. for standard equipment

layout. Can go up to 200-300 watts/s.f.

•5-7 years life for maintenance –free batteries

and 10-14 years for lead-acid batteries.

•$500-$800 per KW.

•3 ft. maintenance clearance required in front

and possibly on the sides

Page 21: Data_Centers - Design Consideration(1).pdf

Air Conditioning

•Design Considerations •Rules of Thumb

Page 22: Data_Centers - Design Consideration(1).pdf

Air Conditioning

Design Considerations •Sawcut for Drains

•Redundancy – N+1, 2N

•Clearance Around Units (maintenance)

•Outdoor Condensing Units

•Humidity concerns

•Refrigerant preferred over chilled water

Page 23: Data_Centers - Design Consideration(1).pdf

Air Conditioning

Rules of Thumb •$800-1000 per KW of electric load. ($1600-2000 for 2N redundancy)

•Footprint up to 20 s.f. each for up to approximately 100 kw.

•18” is minimum preferred height for raised flooring.

Page 24: Data_Centers - Design Consideration(1).pdf

Fire Detection

•Design Considerations •Rules of Thumb

Page 25: Data_Centers - Design Consideration(1).pdf

Fire Detection

Design Considerations

•Standard smoke detectors vs. VESDA

•Smoke detectors not required beneath raised floor

Rules of Thumb

•Approx. $150 per device for standard fire alarm system

•Approx. $5/s.f. for VESDA

Page 26: Data_Centers - Design Consideration(1).pdf

Fire Suppression

•Design Considerations •Rules of Thumb

Page 27: Data_Centers - Design Consideration(1).pdf

Fire Suppression

Design Considerations

•Wet system acceptable – no piping in data center

•FM200 has replaced Halon as agent

Rules of Thumb

•Cost - $35,000 for 1,000 s.f. and $10,000 for each additional 1,000 s.f.

•Need space for control panel and tanks. Plan on 4 s.f. for the tank per 1,000 s.f. of data center.

Page 28: Data_Centers - Design Consideration(1).pdf

Security

•Design Considerations •Rules of Thumb

Page 29: Data_Centers - Design Consideration(1).pdf

Security

Design Considerations/Rules of Thumb •Security/Card Access

•Approximately $2,500 per door, including card reader, headend/controller, and door hardware.

Page 30: Data_Centers - Design Consideration(1).pdf

Racks

•Design Considerations •Rules of Thumb

Page 31: Data_Centers - Design Consideration(1).pdf

Rack - Enclosures

Design Considerations •Hot aisle – cold aisle lay out

•3’ min. working clearance on both front and back

•Include cable management – vertical /horizontal

•Avoid heat dams caused by cabling in rear of rack

Page 32: Data_Centers - Design Consideration(1).pdf

Rack-Enclosures

Rules of Thumb •Costs – Up to $3,500 for specialized racks

•Can include UPS, A/C, and monitoring

•Sizes – 24-32” widths, 30-44” depths

•Cable management can help air flow

Page 33: Data_Centers - Design Consideration(1).pdf

Branch Circuits, PDU’s, Strips

•Design Considerations •Rules of Thumb

Page 34: Data_Centers - Design Consideration(1).pdf

Branch Circuits, PDU’s, Strips

Design Considerations •# of servers/circuit/rack – ensure plug strips have enough plugs

•Is monitoring of load on each circuit required? Can be accomplished at panel or at plugstrip. Access info via local readout or by web server

•Branch circuit wiring typically run beneath raised floor.

•Power distribution can be built-in in some racks.

•Blade servers will require a 208 volt feed instead of 120v.

•Dual corded loads and 2N redundancy

Page 35: Data_Centers - Design Consideration(1).pdf

Branch Circuits, PDU’s, Strips

Rules of Thumb •Approx. 4-6 1U servers for each 20 amp circuit

•Approx. $350 per 20 amp circuit run from panelboard to rack

•Approx. $300 each for vertical plug strips in rack.

Page 36: Data_Centers - Design Consideration(1).pdf

Cable Trays

•Design Considerations •Rules of Thumb

Page 37: Data_Centers - Design Consideration(1).pdf

Cable Trays

Design Considerations

•Data cabling overhead – power wiring below

•Wire basket type tray or traditional steel/aluminum ladder type.

•Cabling can be integrated into racks

Rules of Thumb

•$20-$30 per lin. foot cost for basket tray (8”×4”)

•$40-$60 per lin. foot for ladder type tray.

Page 38: Data_Centers - Design Consideration(1).pdf

Monitoring

•Design Considerations

Page 39: Data_Centers - Design Consideration(1).pdf

Monitoring

Design Considerations •Provide for monitoring/annunciators on critical systems like UPS, generator, fire alarm, fire suppression, air conditioning, and batteries.

•Control panel on equipment is most cost-effective and is typically included with equipment.

•SNMP available for most equipment.

•HTML available for monitoring of most equipment

•Often the first item cut for cost savings.

Page 40: Data_Centers - Design Consideration(1).pdf

Raised Floor

•Design Considerations •Rules of Thumb

Page 41: Data_Centers - Design Consideration(1).pdf

Raised Floor

Design Considerations •Adequate space for wiring and air flow. 18” is minimum

•Include grounding of pedestals.

•Ramp will be required for ADA. 1:12 slope means an 18’ ramp is required for 18” raised floor

•Consider depressed slab so ramp is not required

•NEC requires removal of abandoned cable when doing any renovations.

•Include 20% perforated tiles for air distribution in front of racks.

Page 42: Data_Centers - Design Consideration(1).pdf

Raised Floor

Rules of Thumb •Approx. $25/s.f. + $5-$10,000 for ramp

Page 43: Data_Centers - Design Consideration(1).pdf

General Construction

•Design Considerations •Rules of Thumb •Fees/Permits/Gen. Items

Page 44: Data_Centers - Design Consideration(1).pdf

General Construction

Rules of Thumb •Data center should a have vapor barrier for humidity control.

•What level of security is needed? CMU vs. Stud/Drywall

•Ancillary Spaces Needed? •Staff workstations

•Storage

•Rooms for UPS, Fire suppression, etc

Page 45: Data_Centers - Design Consideration(1).pdf

General Construction

Rules of Thumb •Approximately $150 per s.f. for new construction of the ancillary spaces (outside of data center)

•Approximately $40-$80 s.f. for remodeling existing spaces – new floors, ceilings, lights, etc

Page 46: Data_Centers - Design Consideration(1).pdf

General Construction

Fees/Permits/General Items •If replacing an existing data center, include costs for move/changeover to new location

•Arch/Engr fees – 8-12% of construction costs.

•General Conditions: Mobilization, fees, permits, utilities – by general contractor – 5-10% of construction costs.

•Contingency: include costs for unforeseen conditions. 10% for cost estimates and 3-5% after bidding.

Page 47: Data_Centers - Design Consideration(1).pdf

Bidding – A Case Study

•Existing conditions •Program •Location •Costs

Page 48: Data_Centers - Design Consideration(1).pdf

Bidding – A Case Study

•Existing conditions •Program •Location •Costs

Page 49: Data_Centers - Design Consideration(1).pdf

Bidding - Costs

- Total Costs

Page 50: Data_Centers - Design Consideration(1).pdf

Bidding - Costs

- Total Costs

Electrical Costs

•200 KW Generator $48,000

•Data center PDU’s, branch circuits $ 5,650

•Cable Tray $ 1,300

•Misc. elect costs – lights, outlets, fire alarm $27,350

•80 KW UPS (alternate) $40,600

•Total Electrical $82,300

•$/sq ft Data Center $137/sq ft

•$/sq ft Entire Project $ 62/sq ft.

Page 51: Data_Centers - Design Consideration(1).pdf

Bidding - Costs

- Total Costs

Mechanical Costs

•(2) A/C units, 77 KW capacity each - $128,000

•Sprinklers - $ 3,000

•Misc. piping, - $ 9,500

•Total Mechanical - $132,260

•$/sq ft Data Center - $220 /sq ft.

•$/sq ft Entire Project - $ 99 /sq ft.

Page 52: Data_Centers - Design Consideration(1).pdf

Bidding - Costs

- Total Costs

General Construction Costs

•Raised floor – 600 sq ft. $21,000

•Walls, doors, flooring, ceilings - $23,000

•Total General Trades - $44,000

•$ /sq ft Data Center - $73 /sq ft

•$ /sq ft Entire Project - $33 /sq ft

Page 53: Data_Centers - Design Consideration(1).pdf

Bidding - Costs

- Total Costs

Miscellaneous Costs

•Equipment Racks - $5,000.00 allowance to be purchased direct by IWU.

•Card Access - $2,500.00 allowance for 1 card reader to be purchased direct by owner

Page 54: Data_Centers - Design Consideration(1).pdf

Bidding - Costs

- Total Costs

Overhead/Fees/Contingency Costs

•Construction management fees - $21,500

•A/E Design Fees - $28,500

•Contingency - $ 5,800

•Printing, State Fees - $ 1,250

•Total Indirect Costs - $57,050

•$ /sq ft Data Center - $95 /sq ft

•$/sq ft Entire Project - $43 /sq ft.

Page 55: Data_Centers - Design Consideration(1).pdf

Bidding - Costs

- Total Costs

Total Construction Costs

•Electrical $ 83,000

•Mechanical $132,260

•General Construction $ 44,000

•Misc. Equipment $ 7,500

•Overhead/Fees/Contingency $ 57,050

•Total $323,810

•$/sq ft data center $540 /sq ft

•$/sq ft total project $243 /sq ft

Page 56: Data_Centers - Design Consideration(1).pdf

Thank you!