design consideration of gas turbine
TRANSCRIPT
-
7/29/2019 Design Consideration Of Gas Turbine
1/155
DISCUSSION ONGAS TURBINE DESIGN
CONSIDERATION
Completed by :Mohammad Ibnul Hossain
Executive Engineer (Operation)Tongi 80(105) MW GT Power Station
Bangladesh Power Development BoardE-mail : [email protected]
-
7/29/2019 Design Consideration Of Gas Turbine
2/155
Efficiency
Reliability
Thermal consideration
Corrosion
Wear
FrictionUtility
Cost
Safety
Weight
Noise
Strength
Shape
Size
Flexibility
Cost
Control
Stiffness
Surface Finish
Environment
Maintenance
Volume
-
7/29/2019 Design Consideration Of Gas Turbine
3/155
The Brayton CycleThe Brayton cycle consists of two adiabatic work transfers and twoconstant pressure heat transfer heat processes .
From State 1 to State 2 the gas undergoes an isentropic,adiabatic compression. This process increases the temperature,
pressure, and density of the gas.
T= 15C
T= 1268C
T= 1110C
T= 365C
-
7/29/2019 Design Consideration Of Gas Turbine
4/155
Static pressure(Ps )The force per unit area exerted on the walls of a container by astationary fluid. tire pressure
Impact pressure (Pi) is the force per unit area exerted by fluids in motionthe pressureexerted on one's hand held outside a moving cars window
Pt = Ps + PiPart (a) illustrates the measurement of static pressure. Static pressure will not take intoaccount the velocity of the air.
Part (b) illustrates the measurement of total pressure, which accounts forboth static pressure and the pressure due to the moving fluid (impact pressure).
-
7/29/2019 Design Consideration Of Gas Turbine
5/155
Here { E + or }
v (velocity) Eg P & T pressure and temperature.Here , v ( small inlet to a larger outlet ) (Pi)
Here , { E + or } , So , Pt
As , Pt = Ps + Pi , So , Ps
Pt Ps
So , Pt , so T ( Charls and Boyls Law)
-
7/29/2019 Design Consideration Of Gas Turbine
6/155
DIVERGENT DUCT :
-
7/29/2019 Design Consideration Of Gas Turbine
7/155
DIVERGENT DUCT :
Velocity
Pressure
Temperature
-
7/29/2019 Design Consideration Of Gas Turbine
8/155
BLADE VANE
Axial flow compressor,P current stage > P previous stage [ incrementally]What a single stage of compressor consistsof ?A set of rotor blades attached to a rotatingdisk . Flow area between rotor blade isslightly divergent .
followed by stator vanes attached to astationary ring.Flow area between compressor vanes is alsodivergent than blade .What is done by the blade ?
convert mechanical energy into gaseousenergy. ( Here , energy is added) .What happens?Pi So Pt and
slight Ps for divergence
Pt
Ps
v
-
7/29/2019 Design Consideration Of Gas Turbine
9/155
What is done in Stator Vane ?
slow the air divergent duct shape,
BLADE VANE
Here { E + or }
v (velocity) Eg P & T pressure and
temperature.
Here , v ( small inlet to a larger outlet )
(Pi)
Here , { E + or } ,
So , Pt
As , Pt = Ps + Pi ,
So ,
Pt Ps
Pt
Ps
v
-
7/29/2019 Design Consideration Of Gas Turbine
10/155
Variable Inlet Guide Vane
IGV
-
7/29/2019 Design Consideration Of Gas Turbine
11/155
-
7/29/2019 Design Consideration Of Gas Turbine
12/155
Condition IGV opening
Startup - 2850 34
2850- Loading 57
Loading increases >> exhausttemperature increase
IGV opening increase
At Base Load to keep the
exhaust temp. from 570 C84
At Peak Load to keep the
exhaust temp. not beyond to C + C
84
-
7/29/2019 Design Consideration Of Gas Turbine
13/155
Compressor
-
7/29/2019 Design Consideration Of Gas Turbine
14/155
inlet guide vanes,The axial-flow compressor section
consists of the compressor rotor and the
inclosing casing.the 17 stages of rotor and stator blading,
the exit guide vanes.
Compressor
-
7/29/2019 Design Consideration Of Gas Turbine
15/155
Variable Inlet Guide Vanes
(IGVs)IGVs are used to control the airflow
through the compressor, in turn controllingthe airflow through the entire machine.
The IGVs modulate during the start-up andacceleration of the gas turbine to ratedspeed, loading & unloading of the
generator and deceleration of the gasturbine during shutdown.
-
7/29/2019 Design Consideration Of Gas Turbine
16/155
Compressor Structure
Inlet Guide Vane
-
7/29/2019 Design Consideration Of Gas Turbine
17/155
Compressor Structure
Compressor cylinder
Compressor cylinder has 3 parts:
Forward casing ;
After casing
compressor outlet casing.
-
7/29/2019 Design Consideration Of Gas Turbine
18/155
Compressor Structure
Forward casing After casing
-
7/29/2019 Design Consideration Of Gas Turbine
19/155
Discharge casing
Compressor Structure
-
7/29/2019 Design Consideration Of Gas Turbine
20/155
Compressor outlet casing
Compressor Structure
-
7/29/2019 Design Consideration Of Gas Turbine
21/155
compressor structure
Compressor vane: IGV, stationary blade and EGV (Exhaust Guide vane)
IGV
EGV
StationaryBlade
-
7/29/2019 Design Consideration Of Gas Turbine
22/155
Compressor Structure
Stationary Blade (lower half of the Cylinder )
P bl O d i O ti f th C d
-
7/29/2019 Design Consideration Of Gas Turbine
23/155
Problems Occur during Operation of the Compressor and
Its solution by design consideration
Problem :Stalling and Surging during lower speed .
Remedy :
The inlet guide vanes are incorporated . It limits the
amount of air flowing through the compressor andprevents stalling .
Provisions for bleeding air from the compressor areprovided at one or more stages. This prevent both stalling
and Surging.
-
7/29/2019 Design Consideration Of Gas Turbine
24/155
Compressor Structure
Compressor moving blade
-
7/29/2019 Design Consideration Of Gas Turbine
25/155
compressor rotor
Compressor rotor is a drumstructure with 17 impellers(including a half shaft).17impeller panels are tightly pulledby 16 long bolt pull rods to beintegrated.
Compressor Structure
-
7/29/2019 Design Consideration Of Gas Turbine
26/155
Working Principle :air is confined to the space between the
rotor and stator blading >>>>compressed instages by a series of alternate rotating(rotor) and stationary (stator) airfoil shaped
blades.
The rotor blades supply the force needed tocompress the air in each stage and the statorblades guide the air so that it enters in thefollowing rotor stage at the proper angle.
-
7/29/2019 Design Consideration Of Gas Turbine
27/155
The compressed air exits through the compressordischarge casing to the combustion chambers.
Air is extracted from the compressor for turbinecooling, for bearing sealing, and during start-up
for pulsation control.
P bl O d i O ti f th C
-
7/29/2019 Design Consideration Of Gas Turbine
28/155
Problems Occur during Operation of the Compressorand Its solution by design consideration :
Problem :
Air has the natural tendency to flow toward low-pressurezones. If air were allowed to flow "backward" into the lowerpressure zones, the efficiency of the compressor would
decrease tremendously as the energy used to increase the
pressure of the air was wasted.
Remedy :
seals are incorporated at the base of Each row of vanes to
prevent air leakage.
The tip clearances of the rotating blades are also kept at a
minimum by the use ofcoating on the inner surface of the
compressor case.
-
7/29/2019 Design Consideration Of Gas Turbine
29/155
The MS5001N and P, the MS7001A and B, and the
MS9001B are essentially the same
GROWTH OF PRESSURE RATIO OF GAS TURBINE
-
7/29/2019 Design Consideration Of Gas Turbine
30/155
What is achieved ?
Reliability
-
7/29/2019 Design Consideration Of Gas Turbine
31/155
What is achieved ?Performance
Reliability
Some Initiative to improve performance of Compressor and
-
7/29/2019 Design Consideration Of Gas Turbine
32/155
Some Initiative to improve performance of Compressor and
Implementation by design consideration ( Improving Design)
Goal :
Increase the Pressure Ratio.
Increase the Air Flow .
How It is Implemented ? Increase the Diameter of the inlet-stage. No. of stages are added.
What Result We get ?
Model - MS5000 - pressure ratio 6.78MS5001N -compressor operated at a pressure
ratio of 9.8. and Now we get more the 10 in the
frame-9 Machine.
-
7/29/2019 Design Consideration Of Gas Turbine
33/155
What is achieved ?
More Efficiency
To improve performance of Compressor and Implemented
-
7/29/2019 Design Consideration Of Gas Turbine
34/155
To improve performance of Compressor and Implemented
by design consideration ( Improving Design) :
Goal :To provide higher firing temperature at reduced loadfor regenerative-cycle and combined-cycle applications.
Implemented by :
The fixed inlet guide vane was replaced with a variableguide vane
-
7/29/2019 Design Consideration Of Gas Turbine
35/155
What is achieved ?Flexibility
of Operation
-
7/29/2019 Design Consideration Of Gas Turbine
36/155
.
GROWTH OF AIR FLOW OF GAS TURBINE
Lists some of the parameters of these axial compressors.
-
7/29/2019 Design Consideration Of Gas Turbine
37/155
p pBy starting with an efficient, reliable design and improving this design in agradual manner, improved overall compressor performance has been achievedwithout sacrificing reliability or mechanical integrity.
Objective of How it is done ? & How it is Figure Goal
-
7/29/2019 Design Consideration Of Gas Turbine
38/155
jDesignconsideration
incorporated ?g
Achieved
optimizingcompressor
wheel materialcharacteristics,cost, andserviceconditions
This type of constructionreduces weighs reduction ,
minimizes acceleration duringstart-up.
The disks are assembled witha number of axial tie-bolts,with the bolt-circle diameter
selected to produce adynamically stiff rotor andgood torque transmission.Weight loss+ StiffnessEnsuresV critical > V running .Axial clearance is providedbetween wheel rims to allowthermal expansion during start-up.
Weightreduction ,
stiffnessthermalconsiderationCostServicecondition
Objective of How it is done ? & How it is Figure Goal
-
7/29/2019 Design Consideration Of Gas Turbine
39/155
Objective ofDesignconsideration
How it is done ? & How it isincorporated ?
Figure GoalAchieved
Using Right
QualityMaterial inlastcompressorstage tocompensate
thetemperaturerise ,minimizethermalstress duringstart-up ,shut-down,
Higher-strength material (CrMoV)
(Chromium Molybdenum steels- 0.5 to5% Cr and 0.5 to 1.5% Mo with smalladditions of vanadium)used in the last compressor stage. high-temperature strength aftertesting stringent process controls and
ultrasonic inspection procedure.wheel life of 30 years at base load.designed for may thousands ofstarts and shut-down.Remainder of the compressor wheelsare made of three basic grades ofsteel, CrMo, NiCrMo, and NiCrMoVthe principal alloyingelements. Processing of these alloysproduces abalance of desired material
properties includingtensile strength and fracture
strength
thermal stressLife span
Objective of How it is done ? & How Figure Goal
-
7/29/2019 Design Consideration Of Gas Turbine
40/155
Designconsideration
it isincorporated ?
Achieved
Using RightQuality
Material in lastcompressorstage toproduces abalance ofdesired
materialpropertiesincludingtensilestrength andfracture
toughness.
CrMo,NiCrMo, and NiCrMoV
Materials are used .optimization of thesematerial has resultedin a 35% improvementin fracture toughness
strengthfracture
toughness.
The Brayton Cycle
-
7/29/2019 Design Consideration Of Gas Turbine
41/155
The Brayton CycleThe Brayton cycle consists of two adiabatic work transfers and twoconstant pressure heat transfer heat processes (Figure 3).
From State 2 to State 3, heat is added at constant pressure. For a gas-turbine, heat is added through a combustion process.
The combustor of a gas turbine is the device that accepts both
-
7/29/2019 Design Consideration Of Gas Turbine
42/155
The combustor of a gas turbine is the device that accepts bothhighly compressed air from the compressor and fuel from a fuelsupply so that continuous combustion can take place.
Fuel
High compressed air
This raises the temperature of the working gases to a very highlevel. This combustion must take place with a minimum ofpressure drop and emission production. The very hightemperature gases flow from the combustor to the first stage
turbine nozzles.
-
7/29/2019 Design Consideration Of Gas Turbine
43/155
Combustion Chamber Design :
Most Simple :
Fuel Injector
Impractical-f the excessive pressure loss resulting from
combust on at high velocities.Pressure loss from combustion the air velocity squared.
Velocity too high to establish stable combustion . Even
if ignited initially , the flame will be carried downstream
and cant be sustain without continuous i nition.
-
7/29/2019 Design Consideration Of Gas Turbine
44/155
Adding Baffle :
Flame stabilization zone (Eddy region)baffle
To secure flame at low velocity regionis achieved by installing baffle which will further generate
eddy region behind baffle and allow sufficient time for fuel to
completely combust.At that place, flame will stabilize and gives us continuous
ignition.
-
7/29/2019 Design Consideration Of Gas Turbine
45/155
Adding Swirl :
strong vortex is produced using swirl vanes around fuel nozzle xwill create low pressure region. Due to this pressure difference, airstarts moving towards it from radial holes around liner. With thismovement, flame start propagating up to some extent and will form arecirculation zone which stabilizes flame.
combustor air enters in the chamber through rings. and producerecirculation zone which further stabilizes flame for
complete combustion.
Dilution zone
Vortex
PrimaryZone
Swirl
http://www.bestinnovativesource.com/wp-content/uploads/2013/02/Flame-stabilization-region-created-by-swirl-vanes.jpg -
7/29/2019 Design Consideration Of Gas Turbine
46/155
So we have ,
Combustion takes place in the primary zone of the Combustor .
Primary air = of total airflow) is used to support the combustionprocess.
The remaining air, referred to as secondary or dilution air, is admitted
into the liners in a controlled manner.
-
7/29/2019 Design Consideration Of Gas Turbine
47/155
The secondary air
controls the flame pattern,cools the liner walls,
dilutes the temperature of the core gasses,
This cooling air is critical,as the flame temperature is above 1930C which is
higher than the metals in the engine can endure.
Important
-
7/29/2019 Design Consideration Of Gas Turbine
48/155
Important
fuel nozzles and combustion liners control the burning and
mixing of fuel and air under all conditions to avoid excesstemperatures reaching the turbine or combustion cases.Maximum combustion section outlet temperature (turbine
inlet temperature) in this engine is about 1070C
Ab t th t bili ti f fl
-
7/29/2019 Design Consideration Of Gas Turbine
49/155
About the stabilization of flame,
air velocity plays a vital role. To understand this effect, we will
take the help of following graph
the velocity of air range of burnable mixture
For the stabilization of flame,the size of baffle is also important.Flow velocity in the Flow velocity in the combustion chamber ismaintained below blowout limit so that combustion chamber can
support wide range of fuel to air ratios.
http://www.bestinnovativesource.com/wp-content/uploads/2013/02/Range-of-burnable-fuel-to-air-ratios-versus-combustion-chamber-gas-velocity.jpg -
7/29/2019 Design Consideration Of Gas Turbine
50/155
Combustion Chamber
Cross-
firetube
Secondary
Flamedetector
Primary
FlameDetector
-
7/29/2019 Design Consideration Of Gas Turbine
51/155
Some notable arrangements in combustionChamber:
a)Primary Flame Detector in the Chamber 1,2,3,14b)Secondary Flame Detector in the chamber 1,2,3,14c) Primary , Secondary and Tertiary Fuel Connection
clock wise direction from manifold .
-
7/29/2019 Design Consideration Of Gas Turbine
52/155
Introduction of combustion chamber structure
-
7/29/2019 Design Consideration Of Gas Turbine
53/155
-
7/29/2019 Design Consideration Of Gas Turbine
54/155
TRASTION PIECE
-
7/29/2019 Design Consideration Of Gas Turbine
55/155
-
7/29/2019 Design Consideration Of Gas Turbine
56/155
-
7/29/2019 Design Consideration Of Gas Turbine
57/155
-
7/29/2019 Design Consideration Of Gas Turbine
58/155
-
7/29/2019 Design Consideration Of Gas Turbine
59/155
-
7/29/2019 Design Consideration Of Gas Turbine
60/155
-
7/29/2019 Design Consideration Of Gas Turbine
61/155
FLOW SLEEVE
-
7/29/2019 Design Consideration Of Gas Turbine
62/155
-
7/29/2019 Design Consideration Of Gas Turbine
63/155
-
7/29/2019 Design Consideration Of Gas Turbine
64/155
-
7/29/2019 Design Consideration Of Gas Turbine
65/155
-
7/29/2019 Design Consideration Of Gas Turbine
66/155
-
7/29/2019 Design Consideration Of Gas Turbine
67/155
Cap-liner
-
7/29/2019 Design Consideration Of Gas Turbine
68/155
-
7/29/2019 Design Consideration Of Gas Turbine
69/155
-
7/29/2019 Design Consideration Of Gas Turbine
70/155
-
7/29/2019 Design Consideration Of Gas Turbine
71/155
-
7/29/2019 Design Consideration Of Gas Turbine
72/155
Primary Nozzle
-
7/29/2019 Design Consideration Of Gas Turbine
73/155
Primary Nozzle
-
7/29/2019 Design Consideration Of Gas Turbine
74/155
-
7/29/2019 Design Consideration Of Gas Turbine
75/155
-
7/29/2019 Design Consideration Of Gas Turbine
76/155
Secondary and Tertiary Nozzle
-
7/29/2019 Design Consideration Of Gas Turbine
77/155
Secondary and Tertiary Nozzle
TertiaryNozzle
Tertiary
Nozzle
-
7/29/2019 Design Consideration Of Gas Turbine
78/155
-
7/29/2019 Design Consideration Of Gas Turbine
79/155
-
7/29/2019 Design Consideration Of Gas Turbine
80/155
-
7/29/2019 Design Consideration Of Gas Turbine
81/155
-
7/29/2019 Design Consideration Of Gas Turbine
82/155
-
7/29/2019 Design Consideration Of Gas Turbine
83/155
-
7/29/2019 Design Consideration Of Gas Turbine
84/155
The number of combustors
-
7/29/2019 Design Consideration Of Gas Turbine
85/155
the machine airflow by thepressure ratio Example
the MS9001E uses 14 combustors
compared to 10 on the MS7001E
becausethe 9E airflow is 1.44 times as
large To improve performance of Combustion Chamber and Implementedby design consideration ( Improving Design) :
-
7/29/2019 Design Consideration Of Gas Turbine
86/155
y g ( p g g )
Goal :
a) Improve High Temperature Strength .
b) Reduction Thermal Gradient.
In the Liner Section
Implementation :
Improvement in the liner Construction and using bettermaterial .Example :
In Model MS7001FA liner is 30% thicker and 210 mm (8.4
in.) and Using Hastelloy-X material and addition of HS-188in the aft 278 mm (11.1 in.) portion and the application of
thermal barrier coating to the internal surface.
To improve performance of Combustion Chamber and Implementedby design consideration ( Improving Design) :
-
7/29/2019 Design Consideration Of Gas Turbine
87/155
y g ( p g g )
Goal :
a) Improve High Temperature Strength .
b) Reduction Thermal Gradient.
In the Transition Piece Section
Implementation :
Improvement in the Transition Piece Construction andusing better material .Example :
Nimonic 263, was introduced into service for transition
pieces. This material is a precipitation-strengthened, nickel-base alloy with higher strength capability than Hastelloy-X.
Since the early 1980s, Thermal Barrier Coatings (TBCs) have
been applied to the transition pieces.
-
7/29/2019 Design Consideration Of Gas Turbine
88/155
What is achieved ?
ReliabilityHigh Temperature Strength
Reduction Thermal Gradient.IN LINER
andTransition Piece
To improve performance of Combustion Chamber and Implementedby design consideration ( Improving Design) :
-
7/29/2019 Design Consideration Of Gas Turbine
89/155
y g p g g
Goal :
a) Reduction of Combustion noise .
b) Reduction Wear .In the Liner Section
Implementation
Incorporating More No. Nozzle instead of One with waterInjection system.Example :
MS7001E design to accommodate six fuel nozzles
instead of one with water injection forNOx control (Discuss Later)
To improve performance of Combustion Chamber and Implementedby design consideration ( Improving Design) :
-
7/29/2019 Design Consideration Of Gas Turbine
90/155
y g p g g
Goal :
Reduction Wear .
In the Transition Piece
ImplementationTo increase the wear resistance of some transition piecesin the aft end Cobalt-base hard coatings applied by thermal
spray improve the wear life of sealing components by more
than four times.
-
7/29/2019 Design Consideration Of Gas Turbine
91/155
To improve performance of Combustion Chamber and Implementedby design consideration ( Improving Design) :
-
7/29/2019 Design Consideration Of Gas Turbine
92/155
Goal :Reliability in Ignition Process
IMPLEMENTATION :
a)Using Two sparking Plug .b)Using Two Flame Detector .
c) Using Cross Fire Tubes .
-
7/29/2019 Design Consideration Of Gas Turbine
93/155
What is achieved ?
ReliabilityIn
Ignition System
To improve performance of Combustion Chamber and Implementedby design consideration ( Improving Design) :
-
7/29/2019 Design Consideration Of Gas Turbine
94/155
Goal :Completely burn of the residual fuel.
Implementation:
By allowing air jets in the combustion chamber for properStoichiometric air fuel mixture .Combustor length must be sufficient to provide for flame
stabilization. combustion. and mixing with dilution air. The
typical value of the length-to-diameter ratio for linersranges from three to six.
-
7/29/2019 Design Consideration Of Gas Turbine
95/155
What is Stoichiometric Ratio ?
The Stoichiometric ratio is the
perfect ideal fuel ratio where thechemical mixing proportion iscorrect.
When burned all fuel and air isconsumed without any excess left
over
-
7/29/2019 Design Consideration Of Gas Turbine
96/155
What is achieved ?
Fuel Economy
To improve performance of Combustion Chamber and Implementedby design consideration ( Improving Design) :
-
7/29/2019 Design Consideration Of Gas Turbine
97/155
Goal :
To remove NOx from the combustion.
What is NOx ?
NO and NO2, collectively called NOx.
Why Removal of NOx ?
It is bad for the environment and bad for the health.Must below 100 ppm in the combustion product .
Where it is produced ?
2 sources of NOx emissions .1. NOx is generated by the fixation of atmospheric nitrogen in the
flame. This is called thermal NOx.2. Other NOx are also generated by the conversion of a fraction of
any nitrogen chemically bound in the fuel (called fuel-bound
nitrogen or FBN).
Thermal NOx
-
7/29/2019 Design Consideration Of Gas Turbine
98/155
Is an exponential function of the (T)
temperature of the flame a linear function of time (t)
To Minimize the NOx we have to designthe combustion chamber
Where
The combustion temperature must belowthe NOx producing Temp.
And
The combustion process takes lesser time .
The combustion chamber Which is used for dln system
-
7/29/2019 Design Consideration Of Gas Turbine
99/155
The combustion chamber Which is used for dln system
-
7/29/2019 Design Consideration Of Gas Turbine
100/155
-
7/29/2019 Design Consideration Of Gas Turbine
101/155
What is achieved ?
EnvironmentFriendly
Machine
Some Design Factors must be done in designing combustion chamber
-
7/29/2019 Design Consideration Of Gas Turbine
102/155
Wobbe Number :
Wobbe Number is an indicator of the characteristics and stability of
the combustion process.
Here , LHV Lower Heating Value of fuel ,Sp. GR Specific GravityTamb Ambient Temperature
the wobbe Number can cause the Flame to burn closer to the liner.
Decreasing the wobbe Number can cause pulsations in the
combustor.
Some Design Factors must be done in designing combustion chamber
-
7/29/2019 Design Consideration Of Gas Turbine
103/155
:
Pressure drop.
100 fps (30mps), 4%
80fps (24mps), 2.5%:
70fps (21 mps), 2%:
50fps (15mps), 1%.
Some Design Factors must be done in designing combustion chamber
-
7/29/2019 Design Consideration Of Gas Turbine
104/155
The heat-release the fuel-to-air ratio
The heat-release the combustor pressure.
The heat-release = ( Combustor capacity)
The Brayton Cycle
From State 3 to State 4 the gas passes through an adiabaticisentropic turbine which decreases the temperature and pressure of
the gas
Static pressure(Ps )The force per unit area exerted on the walls of a container by astationary fluid. tire pressure
-
7/29/2019 Design Consideration Of Gas Turbine
105/155
Impact pressure (Pi) is the force per unit area exerted by fluids in motionthe pressureexerted on one's hand held outside a moving cars window
Pt = Ps + PiPart (a) illustrates the measurement of static pressure. Static pressure will not take intoaccount the velocity of the air.
Part (b) illustrates the measurement of total pressure, which accounts forboth static pressure and the pressure due to the moving fluid (impact pressure).
Convergent Duct
-
7/29/2019 Design Consideration Of Gas Turbine
106/155
Velocity
Pressure
Temperature
-
7/29/2019 Design Consideration Of Gas Turbine
107/155
Pt PiA static pressure decrease is seen as air flows through a convergent duct and goesthrough expansion. A temperature drop is associated with any expansion process.
Here { E + or }
Here , v (large inlet to a smaller outlet )
(Pi)
Here , { E + or } So , Pt
As , Pt = Ps + Pi So , Ps
Axial flow compressor,P current stage > P previous stage [ incrementally]
-
7/29/2019 Design Consideration Of Gas Turbine
108/155
BLADE VANE
What a single stage of compressor consistsof ?A set of rotor blades attached to a rotating
disk . Flow area between rotor blade isslightly divergent .
followed by stator vanes attached to a
stationary ring.Flow area between compressor vanes is alsodivergent than blade .What is done by the blade ?
convert mechanical energy into gaseousenergy. ( Here , energy is added) .What happens?Pi So Pt andslight Ps for divergence
Pt
Ps
v
Vane /Nozzle
nozzles convert the gaseous heat andpressure energy into higher velocity gas flow(Pi)
-
7/29/2019 Design Consideration Of Gas Turbine
109/155
NozzleBlade
Pt
Ps
v
Vane Blade
(Pi)
In addition to accelerating the gas,the vanes "turn" the flow to direct it into therotor blades at the optimum angle.
As the mass of the high velocity gas flows
across the turbine blades, the gaseous energyis converted to mechanical energy.
Velocity, temperature, and pressure of the gas
are sacrificed in order to rotate the turbine togenerate shaft power
f b
-
7/29/2019 Design Consideration Of Gas Turbine
110/155
Types of Gas Turbine :
1.Impulse
2.Reaction
-
7/29/2019 Design Consideration Of Gas Turbine
111/155
P1 P2
V1 V2
Here ,P1 > P2
v1> v2Velocity-v, pressure-P
-
7/29/2019 Design Consideration Of Gas Turbine
112/155
If Pressure decreases
Velocity increases
Kinetic Energy increases
RMP increases
-
7/29/2019 Design Consideration Of Gas Turbine
113/155
Change in pressure is done :
1) By Convergent Nozzle .
2) By Convergent Blade.
-
7/29/2019 Design Consideration Of Gas Turbine
114/155
In Turbine ( Gas or Steam) :
has ConvergentNozzle system and uniform blade
system .Reaction Turbine has Convergent
Blade system and uniform nozzle
system
Impulse Turbine nozzle and blading
arrangement
-
7/29/2019 Design Consideration Of Gas Turbine
115/155
arrangement
Conver-gent
Guidevan
Here :
P1 >P2V2> V1
Moving BladeFixed Blade
ConstantArea
MovingBlade
P1P2
V1 V2
Impulse Turbine in Action
-
7/29/2019 Design Consideration Of Gas Turbine
116/155
Impulse Turbine in Action
-
7/29/2019 Design Consideration Of Gas Turbine
117/155
Impulse Turbine in Action
-
7/29/2019 Design Consideration Of Gas Turbine
118/155
Impulse Turbine in Action
-
7/29/2019 Design Consideration Of Gas Turbine
119/155
-
7/29/2019 Design Consideration Of Gas Turbine
120/155
Impulse Turbine in Action
-
7/29/2019 Design Consideration Of Gas Turbine
121/155
Impulse Turbine in Action
-
7/29/2019 Design Consideration Of Gas Turbine
122/155
Impulse Turbine in Action
-
7/29/2019 Design Consideration Of Gas Turbine
123/155
-
7/29/2019 Design Consideration Of Gas Turbine
124/155
Impulse Turbine in Action
-
7/29/2019 Design Consideration Of Gas Turbine
125/155
Impulse Turbine in Action
-
7/29/2019 Design Consideration Of Gas Turbine
126/155
-
7/29/2019 Design Consideration Of Gas Turbine
127/155
Reaction Turbine nozzle and blading arrangement
-
7/29/2019 Design Consideration Of Gas Turbine
128/155
ConstantAreaGuidevane
Conver-gentNozzle
Here
P1 > P2V2> V1
Fixed BladeMovingBlade
P1
P2
V1 V2
Reaction Turbine in Action
-
7/29/2019 Design Consideration Of Gas Turbine
129/155
Reaction Turbine in Action
-
7/29/2019 Design Consideration Of Gas Turbine
130/155
Reaction Turbine in Action
-
7/29/2019 Design Consideration Of Gas Turbine
131/155
Reaction Turbine in Action
-
7/29/2019 Design Consideration Of Gas Turbine
132/155
Reaction Turbine in Action
-
7/29/2019 Design Consideration Of Gas Turbine
133/155
Reaction Turbine in Action
-
7/29/2019 Design Consideration Of Gas Turbine
134/155
A reaction turbine is moved by two main
-
7/29/2019 Design Consideration Of Gas Turbine
135/155
A reaction turbine is moved by two mainforces:
1. There is expansion of steam is there ,pressure is decreasing so there isincrease in kinetic energy by increasingvelocity .
2. the push or impulse of the gasimpinging upon the blades
-
7/29/2019 Design Consideration Of Gas Turbine
136/155
Impulse Turbine create large
amounts of Tangential thrust
Reaction turbines create largeamounts of axial thrust, and so
require the use
So the combination of impulse
-
7/29/2019 Design Consideration Of Gas Turbine
137/155
So the combination of impulse -
reaction turbineis widely used .
Impulse Reaction Turbinereduces both the tangential
and axial stressTo the Rotor
Impulse Reaction Blade
-
7/29/2019 Design Consideration Of Gas Turbine
138/155
Impulse Reaction Blade
The fixed blades are set in a reversed mannercompared to the moving blades,
Schematic drawing of major components of gas turbine
-
7/29/2019 Design Consideration Of Gas Turbine
139/155
Gas TurbineAuxiliaries
Air InletSystem CompressorSection
ExhaustSystemTurbineSection
CombustionSection
AirInlet
Compressor TurbineSection
CombustionSection
ExhaustSection
-
7/29/2019 Design Consideration Of Gas Turbine
140/155
To improve performance of Turbine and Implementedby designconsideration ( Improving Design) :
Goal :
-
7/29/2019 Design Consideration Of Gas Turbine
141/155
Goal :
To improve the Higher firing temperature .How it is Implemented ?
Improved nozzle and bucket material .
The air-cooling of this hardware.
Simultaneous development in alloy corrosion and
oxidation resistance and bucket surface protection
systems have played a significant role in supportingfiring temperature increases.
-
7/29/2019 Design Consideration Of Gas Turbine
142/155
-
7/29/2019 Design Consideration Of Gas Turbine
143/155
What is achieved ?
More Efficiency
To improve performance of Turbine and Implementedby designconsideration ( Improving Design) :
Goal :
-
7/29/2019 Design Consideration Of Gas Turbine
144/155
Goal :
To make Vibration Free Bucket at all speed of theturbine and Making Thermal Isolation .How it is Implemented ?
The long-shank bucket and the bucket tip shroud is
introduced.
How it works ?
Damping is introduced near the bucket mid span .
-
7/29/2019 Design Consideration Of Gas Turbine
145/155
Damping is introduced near the bucket mid span .
The shank has a second important advantage in providing aneffective thermal isolation between the gas path and theturbine wheel dovetail.
-
7/29/2019 Design Consideration Of Gas Turbine
146/155
What is achieved ?
Reliability inOperation
ByVibration Control
Problems Occur during Operation of the Turbine and Its solution bydesign consideration :
Creep/Rupture
-
7/29/2019 Design Consideration Of Gas Turbine
147/155
Creep/Rupture
How it is overcome
-
7/29/2019 Design Consideration Of Gas Turbine
148/155
A creep strain criterion is chosen to avoid creep cracking.
Problems Occur during Operation of the Turbine and Its solution bydesign consideration :
Th l F ti
-
7/29/2019 Design Consideration Of Gas Turbine
149/155
Thermal Fatigue
It is due to the temperature gradient for the cooling of the hightemperature Component of gas turbine in both transient and steady-State operation , such as Vane in fig .
-
7/29/2019 Design Consideration Of Gas Turbine
150/155
Cant be eliminated, but their impact can bemitigated by judicious design and careful operation.
-
7/29/2019 Design Consideration Of Gas Turbine
151/155
What is achieved ?Thermal
Consideration
Problems Occur during Operation of the Turbine and Its solution bydesign consideration :
Corrosion
-
7/29/2019 Design Consideration Of Gas Turbine
152/155
Co os o
The use of Ni-base super alloys as turbine blades in an actual end-use atmosphere produces deterioration of material properties.This deterioration can result from erosion or corrosionErosion results from hard particles impinging on the turbine bladeand removing material from the blade surface.
Corrosion is described as hot corrosion and sulfidation processes.Hot corrosion is an accelerated oxidation of alloys caused by thedeposition of Na2SO4. Oxidation results from the ingestion of salts
in the engine and sulfur from the combustion of fuel.
Sulfidation corrosion is considered a form of hot corrosion in whichthe residue that contains alkaline sulfates. Corrosion causesdeterioration of blade materials and reduces component life.
Remedy :
Pl ti h i l i id diff i t ti
-
7/29/2019 Design Consideration Of Gas Turbine
153/155
Platinum-chromium-aluminide diffusion-type coatings
developedPt-Cr-Al coating
developed
Combination of IN-738 and Pt- Cr-Aldeveloped
vacuum plasma spray coatings are overlay-typecoatingsdeveloped
-
7/29/2019 Design Consideration Of Gas Turbine
154/155
What is achieved ?Corrosion
Control
-
7/29/2019 Design Consideration Of Gas Turbine
155/155
ThankYou