  • 7/29/2019 CEESP Project Management. Unit Two

    1/13

    Project Management

    Previous Analysis

    Lecturer: Javier Daz lvarez

    Electrical EnergyConversion andPower Systems

    Universidadde Oviedo

  • 7/29/2019 CEESP Project Management. Unit Two

    2/13

    Previous Analysis

    What do I have to think before starting a project?

    - Needs

    - Targets

    - Requirements

    - Functional

    - Technical

  • 7/29/2019 CEESP Project Management. Unit Two

    3/13

    Needs

    Some considerations:

    We have to take into account the needs of all the stakeholders. Frequently, they

    are contradictory. The direction of the company (helped by the PM if thedesignation has been done) has to balance and prioritize conflictive needs.

    It is very important to understand the differences between needs and wishes.

    Sometimes, it is important to help the customer to understand its needs and it

    could be an opportunity to increase the scope. But the target should be the

    satisfaction of the client, the increment of the scope is only a possitve

    collateral effect.

    Needs: something needed; a requirement; sometimes

    something vague

  • 7/29/2019 CEESP Project Management. Unit Two

    4/13

    Needs Project 1. Wind Farm

    We need to make a 50 MW wind farm in the following 24 months tomeet the targets of the company.

    Project 2. Substation in Oviedo

    We need to improve the quality of the electricity distribution in Oviedo.

    The key indicators of distribution quality are not as high as they should be.

    Project 3. Bridge.

    We need a bridge to increase the capacity of a road from 1.000 to

    4.000 vehicles per hour.

  • 7/29/2019 CEESP Project Management. Unit Two

    5/13

    Targets Targets should be developed as an evolution of the needs.

    They should comply with the five elements of the SMART

    model: S: Specific

    M: Measurable

    A: Agreed upon R: Realistic

    T: Time constrained

  • 7/29/2019 CEESP Project Management. Unit Two

    6/13

    Targets Project 1. Wind Farm

    Achieve the final reception, the environmental reception and the finalinscription of the wind farm in 24 months.

    Project 2. Substation in Oviedo

    Construct the substation and sign the Take Over Certificate in twelve

    months.

    Project 3. Bridge.

    Promote and construct the new bridge (4.000 vehicles per hour) in 36

    months taking into account the environmental gaps (ciconia nigra).

  • 7/29/2019 CEESP Project Management. Unit Two

    7/13

    Requirements

    Functional requirements are the needs of the customer. They

    come from the targets. The better defined targets, the betterfunctional requirements well have.

    Technical requirements are developed by the project team

    to meet with functional requirements.

  • 7/29/2019 CEESP Project Management. Unit Two

    8/13

    Exercise 2.1 Project 1. Tansmission line from nuclear power

    station 100 km from Madrid to Madrid.

    Needs, targets and requirements

    Project 2. Oil refinery in Guadalajara. Needs, targets and requirements

  • 7/29/2019 CEESP Project Management. Unit Two

    9/13

    Project selection

    Each company has its own practices

    Selection should be as much objective as possible

    Most of the times, selection is not only aquantitative issue

    Selection should be coordinated with strategictargets of the company

  • 7/29/2019 CEESP Project Management. Unit Two

    10/13

    Selection tools Profit cost ratio

    Profit/Cost

    Net Present Value

    NPV = -I0+((Fi)/(1+r)i)

  • 7/29/2019 CEESP Project Management. Unit Two

    11/13

    Selection tools (II) IRR

    Interest rate which makes NPV=0

    Payback periode

    Time to recover invested money

  • 7/29/2019 CEESP Project Management. Unit Two

    12/13

    Exercise 2.2- Calculate PCR, NPV, IRR and Payback Periode of these projects

    Project A Project B Project C Project D Project D

    Investment -6500 -6500 -6500 -10000 -10000

    Incomes year 1 4000 2500 1000 6000 2000

    Expenses year 1 -500 -500 -500 -1000 -1000

    Incomes year 2 4000 2500 1000 5000 3000

    Expenses year 2 -500 -500 -500 -1000 -1000

    Incomes year 3 2000 2500 2000 4000 4000

    Expenses year 3 -1000 -1000 -1000 -1000 -1000

    Incomes year 4 1000 2500 4000 3000 5000

    Expenses year 4 -1000 -1000 -1000 -1000 -1000

    Incomes year 5 1000 2500 4000 2000 6000

    Expenses year 5 -1000 -1000 -1000 -1000 -1000

  • 7/29/2019 CEESP Project Management. Unit Two

    13/13

    Exercise 2.2. Solution.

    Project A Project B Project C Project D Project E

    PCR 1,14 1,19 1,14 1,33 1,33

    Payback periode 2 years 3,75 years 4,5 years 2,25 years 4 years

    NPV 535,26 380,70 - 567,70 2.591,12 1.365,14

    IRR 13,33% 10,35% 5,47% 20,27% 12,01%