ceesp electrical energy project management 9 human resources

52
7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 1/52 Electrical Energy Conversion and Power Systems Universidad de Oviedo ELECTRICAL ENERGY PROJECT MANAGEMENT Part 9 – Human Resources Lecturer: José Ángel Díaz Álvarez

Upload: abraham-fernandez

Post on 14-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 1/52

Electrical EnergyConversion andPower Systems

Universidadde Oviedo

ELECTRICAL ENERGYPROJECT MANAGEMENT

Part 9 – Human Resources

Lecturer: José Ángel Díaz Álvarez

Page 2: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 2/52

9. Human Resources

In the Project Management world

Brands

CompaniesFame

Prestige

 

2

do not secure results. People do.

Clients do not only hire companies, they want to secure

good teams too. E.g. Tender processes.

Page 3: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 3/52

9. Human Resources

Human Resources are the BEST actives in a company, agood project team and a good HR management are a key

to success.

It is needed to:

3

• get the best new resources

and

maximize the performance of the existing ones

Page 4: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 4/52

9. Human Resources

Human resources management process include:

HUMAN RESOURCES PLANNING

 

4

PROJECT TEAM ACQUISITION

PROJECT TEAM DEVELOPMENT

PROJECT TEAM MANAGEMENT

Page 5: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 5/52

9. Human Resources

Human resources management process include:

HUMAN RESOURCES PLANNING

 

5

PROJECT TEAM ACQUISITION

PROJECT TEAM DEVELOPMENT

PROJECT TEAM MANAGEMENT

Page 6: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 6/52

9.1 Human Resources Planning

Identify and document project roles, responsibilities andreporting structure.

Create the Staff Management Plan

6

For Human Resources planning it must be taken intoaccount:

• Organizational structure of the company

• Technical interfaces• Interpersonal interfaces

• Logistics

Page 7: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 7/52

9.1 Human Resources Planning

Tools and techniques used for Human Resourcesplanning:

• Organization charts and role description

7

MatrixHierarchical Text

Oriented

Page 8: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 8/52

9.1 Human Resources Planning

8Hierarchical

Page 9: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 9/52

9.1 Human Resources Planning

9Matrix (RACI)

Page 10: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 10/52

9.1 Human Resources Planning

Role_______________________________________________________________________________________________________________________

Responsibilities___________________________________________

______________________________________________________________

______________________________________________________________

____________________________________________________________________________________________________________________________

______________________________________________________________

______________________________________________________________

10

______________________________________________________________

Authority:________________________________________________________________________________________________________________

______________________________________________________________

______________________________________________________________

______________________________________________________________

______________________________________________________________

______________________________________________________________

______________________________________________________________

Text oriented

Page 11: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 11/52

9.1 Human Resources Planning

As the result of the HR Planning we get:

Roles and Responsibilities Roles

Authority

Responsibility

11

Competence

• Project Organization Chart

• Staff Management Plan Staff Adquisition

Timetable: Resource Histogram

Page 12: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 12/52

9.1 Human Resources Planning

12

When the resource demand exceeds the maximum available, it is

needed a RESOURCE BALANCING STRATEGY 

Page 13: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 13/52

9. Human Resources

Human resources management process include:

HUMAN RESOURCES PLANNING

 

13

PROJECT TEAM ACQUISITION

PROJECT TEAM DEVELOPMENT

PROJECT TEAM MANAGEMENT

Page 14: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 14/52

9.2 Project Team Acquisition

Project Team Acquisition is the process to get the humanresources needed to complete the project

The Project Management Team can have control over theselected team members or not

14

For Project Team Acquisition it must be taken into account:

• Environmental factors of the Company

• Organizational processes

• Roles and responsibilities

• Project organization chart

• Staff Management Plan

Page 15: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 15/52

9.2 Project Team Acquisition

Project Team Acquisition is the process to get the humanresources needed to complete the project

The Project Management Team can have control over theselected team members or not

15

For Project Team Acquisition it must be taken into account:

• Environmental factors of the Company

• Organizational processes

• Roles and responsibilities

• Project organization chart

• Staff Management Plan

Availability: Who and When?

Capacity: What competences?Experience: Similar works? Well done?

Interests: People interested in the project?

Cost: How much to pay?

Page 16: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 16/52

9.2 Project Team Acquisition

Project Team Acquisition is the process to get the humanresources needed to complete the project

The Project Management Team can have control over theselected team members or not

16

For Project Team Acquisition it must be taken into account:

• Environmental factors of the Company

• Organizational processes

• Roles and responsibilities

• Project organization chart

• Staff Management Plan

Internal procedures for staff assignment 

HHRR Department cooperation Hiring

Page 17: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 17/52

9.2 Project Team Acquisition

Tools and techniques used for Project Team Acquisition :

• Previous assignment

• Negotiation

Experience in similar projects

Tender Process

Pre-assignment

With functional managers

17

• Acquisition

• Virtual teams

Other project directors (sharing, relay…)Not enough resources in house

Team members that do not meet face to face (VC,e-mail). It allows:

Create teams with people from different geographies

Bring in the experience of an expert that lives away

Create teams with people working in different time zones

Included disabled people

Reduce or eliminate travel expenses

COMMS. PLANNING IS KEY FOR VIRTUAL TEAMS!

Page 18: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 18/52

9.2 Project Team Acquisition

As the result of the Project Team Acquisition we get:

• Project Staff AssignmentAppropriate people chosen

• Resources Availability

18

 

Time availability of team members (to dedicate to the project)

• Staff Management Plan (Updates)Dynamic updating, from feedback or other situations:

Retiring Promotions

Medical leaves

Page 19: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 19/52

9. Human Resources

Human resources management process include:

HUMAN RESOURCES PLANNING

 

19

PROJECT TEAM ACQUISITION

PROJECT TEAM DEVELOPMENT

PROJECT TEAM MANAGEMENT

Page 20: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 20/52

9.3 Project Team Development

Project Team Development improves the competences andinteraction of team members, in order to improve the projectperformance

The targets are:

 

20

• mprove eam mem ers a es

• Improve the team as a group

For Project Team Development it must be taken into account:

• Project Staff Assignment• Resources Availability

• Staff Management Plan

Page 21: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 21/52

9.3 Project Team Development

Project Team Development improves the competences andinteraction of team members, in order to improve the projectperformance

The targets are:

 

21

• mprove eam mem ers a es

• Improve the team as a group

For Project Team Development it must be taken into account:

• Project Staff Assignment• Resources Availability

• Staff Management Plan

List of team members needed in order to start the development 

Page 22: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 22/52

9.3 Project Team Development

Project Team Development improves the competences andinteraction of team members, in order to improve the projectperformance

The targets are:

 

22

• mprove eam mem ers a es

• Improve the team as a group

For Project Team Development it must be taken into account:

• Project Staff Assignment• Resources Availability

• Staff Management PlanWhen the team members can participate in team development activities

Page 23: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 23/52

9.3 Project Team Development

Project Team Development improves the competences andinteraction of team members, in order to improve the projectperformance

The targets are:

 

23

• mprove eam mem ers a es

• Improve the team as a group

For Project Team Development it must be taken into account:

• Project Staff Assignment• Resources Availability

• Staff Management Plan

Identifies strategies and training plan to develop the project team

Continuous assessment as the project progresses

Page 24: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 24/52

9.3 Project Team Development

Tools and techniques used for Project Team Development:

• General Management Abilities• Training

• Team Development Activities

 

24

Basic Rules• Relocation

• Recognition and Rewarding

Page 25: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 25/52

9.3 Project Team Development

Tools and techniques used for Project Team Development:

• General Management Abilities• Training

• Team Development Activities

 

Interpersonal abilities, very important for team development:

 

25

Basic Rules• Relocation

• Recognition and Rewarding

, ,

Valuable actives to manage the project team

Reduce problems and improve cooperation

Page 26: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 26/52

9.3 Project Team Development

Tools and techniques used for Project Team Development:

• General Management Abilities• Training

• Team Development Activities

 

Activities oriented to improve team members’ competencies

26

Basic Rules• Relocation

• Recognition and Rewarding

Page 27: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 27/52

9.3 Project Team Development

Tools and techniques used for Project Team Development:

• General Management Abilities• Training

• Team Development Activities

 

27

Basic Rules• Relocation

• Recognition and Rewarding

Oriented to: Improve cohesion

Improve confidence

Improve interpersonal relationships

Especially relevant for virtual teams

Page 28: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 28/52

9.3 Project Team Development

Tools and techniques used for Project Team Development:

General Management Abilities• Training

• Team Development Activities

 

28

Basic Rules• Relocation

• Recognition and Rewarding

Establish clean expectations from the beginning of the project, reduces

misunderstandings and improves productivity

Page 29: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 29/52

9.3 Project Team Development

Tools and techniques used for Project Team Development:

General Management Abilities• Training

• Team Development Activities

 

29

Basic Rules• Relocation

• Recognition and RewardingLocate the most active team members in the same physical place, in order to

improve their team capacity.

Use planning charts, dashboards, etc.Not used for virtual teams

Page 30: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 30/52

9.3 Project Team Development

Tools and techniques used for Project Team Development:

General Management Abilities• Training

• Team Development Activities

 

30

Basic Rules• Relocation

• Recognition and RewardingPerformed as designed during the Human Resources planning phase

R&R decisions taken during the team management process throughperformance assessment 

Only to reward the desired behaviour. Justice must be perceived by all

Page 31: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 31/52

9.3 Project Team Development

As the result of the Project Team Development we get:

Team Performance AssessmentDynamic assessment after development efforts implementation

Indicator examples:

 

31

 

Improvements in competencies Less staff rotation ratio

Page 32: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 32/52

9. Human Resources

Human resources management process include:

HUMAN RESOURCES PLANNING

 

32

PROJECT TEAM ACQUISITION

PROJECT TEAM DEVELOPMENT

PROJECT TEAM MANAGEMENT

Page 33: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 33/52

9.4 Project Team Management

Project Team Management means:• Team Members Performance follow-up

• Provide feedback

• Solve conflicts

• Coordinate changes

33

Improves project performance

It is complicated in matrix team structures (doublereporting, project oriented and functional)

Generally under the responsibility of the Project Director

Page 34: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 34/52

9.4 Project Team Management

34

Matrix organization. Double reporting.

Page 35: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 35/52

9.4 Project Team Management

For Project Team Management it must be taken intoaccount:

Organization process actives• Project team assignment

• Roles and responsibilities

 

35

• Project organization chart

• Staff Management Plan

• Team Performance Assessment

• Team Performance Information

• Performance Reports

Page 36: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 36/52

9.4 Project Team Management

For Project Team Management it must be taken intoaccount:

Organization process actives• Project team assignment

• Roles and responsibilities

 

Policies, procedures and systems used in the organization

36

• Project organization chart

• Staff Management Plan

• Team Performance Assessment

• Team Performance Information

• Performance Reports

Page 37: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 37/52

9.4 Project Team Management

For Project Team Management it must be taken intoaccount:

Organization process actives• Project team assignment

• Roles and responsibilities

 

Provide a list of team members to be assessed

37

• Project organization chart

• Staff Management Plan

• Team Performance Assessment

• Team Performance Information

• Performance Reports

Page 38: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 38/52

9.4 Project Team Management

For Project Team Management it must be taken intoaccount:

Organization process actives• Project team assignment

• Roles and responsibilities

 

38

• Project organization chart

• Staff Management Plan

• Team Performance Assessment

• Team Performance Information

• Performance Reports

List used to supervise and assess the performance

Page 39: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 39/52

9.4 Project Team Management

For Project Team Management it must be taken intoaccount:

Organization process actives• Project team assignment

• Roles and responsibilities

 

39

• Project organization chart

• Staff Management Plan

• Team Performance Assessment

• Team Performance Information

• Performance Reports

Provides reporting lines picture

Page 40: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 40/52

9.4 Project Team Management

For Project Team Management it must be taken intoaccount:

Organization process actives• Project team assignment

• Roles and responsibilities

 

40

• Project organization chart

• Staff Management Plan

• Team Performance Assessment

• Team Performance Information

• Performance Reports

Informs about the period when team members work together and the

training plan

9 4 P j T M

Page 41: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 41/52

9.4 Project Team Management

For Project Team Management it must be taken intoaccount:

Organization process actives• Project team assignment

• Roles and responsibilities

 

41

• Project organization chart

• Staff Management Plan

• Team Performance Assessment

• Team Performance Information

• Performance Reports

The management team continuously assess the project team performance

Corrective actions can be taken

9 4 P j t T M t

Page 42: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 42/52

9.4 Project Team Management

For Project Team Management it must be taken intoaccount:

Organization process actives• Project team assignment

• Roles and responsibilities

 

42

• Project organization chart

• Staff Management Plan

• Team Performance Assessment

• Team Performance Information

• Performance ReportsTeam members performance is observed as they work 

9 4 Project Team Management

Page 43: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 43/52

9.4 Project Team Management

For Project Team Management it must be taken intoaccount:

• Organization process actives

• Project team assignment

• Roles and responsibilities

 

43

 

• Staff Management Plan• Team Performance Assessment

• Team Performance Information

Performance ReportsNeeded to compare against project management plan:

Time

Cost Control

Scope

9 4 Project Team Management

Page 44: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 44/52

9.4 Project Team Management

Tools and techniques used for Project Team Management :

• Observation and conversation

• Conflict Management

44

• Performance Assessment

• Polemics Register

9 4 Project Team Management

Page 45: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 45/52

9.4 Project Team Management

Tools and techniques used for Project Team Management :

• Observation and conversation

• Conflict Management

Used to keep in touch with the work and team members’ attitudes.

Behavioural observation

45

• Performance Assessment

• Polemics Register

9 4 Project Team Management

Page 46: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 46/52

9.4 Project Team Management

Tools and techniques used for Project Team Management :

• Observation and conversation

• Conflict Management

 

46

• Performance Assessment

• Polemics Register

 

Group normsCommunications planning Reduces conflict  

Role definition

Opinion differences are not necessarily negative More creativity

Better decisionsIf conflict arises Dealt in early stages

Dealt in private environment 

Direct and constructive approach

If needed, intensify actions until disciplinary

9 4 Project Team Management

Page 47: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 47/52

9.4 Project Team Management

Tools and techniques used for Project Team Management :

• Observation and conversation

• Conflict Management

47

• Performance Assessment

• Polemics Register

Must be provided as feedback to team members

360º can be chosenIt helps to clarify roles and responsibilities

structured time for stopping and feeding back 

find opened or unsolved conflicts

develop IDPs

set target for new periods

9 4 Project Team Management

Page 48: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 48/52

9.4 Project Team Management

Tools and techniques used for Project Team Management :

• Observation and conversation

• Conflict Management

48

• Performance Assessment

• Polemics Register

Documents: solution responsible/target day. Written register

9.4 Project Team Management

Page 49: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 49/52

9.4 Project Team Management

As the result of the Project Team Management we get:

• Requested changes

Staff changes might affect the rest of the project plan (e.g. scheduledelay or cost overrun) process a request

 

49

• Recommended corrective actions

Staff changes (transfer, externalize works, replace team members)Additional Training

Disciplinary actions

• Recommended preventive actionsReduce the probability to have HR conflicts

9.4 Project Team Management

Page 50: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 50/52

9.4 Project Team Management

As the result of the Project Team Management we get:

• Organization process actives (updating)

Performance assessment input

Lessons learned documentation

50

• Project Management Plan (updated)Change requests PMP updates:

Corrective actions - new roles for team members

- additional training actions

- reward decisions

- …

Questions & Answers

Page 51: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 51/52

Questions & Answers

51

Page 52: CEESP Electrical Energy Project Management 9 Human Resources

7/29/2019 CEESP Electrical Energy Project Management 9 Human Resources

http://slidepdf.com/reader/full/ceesp-electrical-energy-project-management-9-human-resources 52/52

52