ceesp project management. units six and seven

Upload: abraham-fernandez

Post on 14-Apr-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    1/90

    Project Management

    Time and Cost Management

    Lecturer: Javier Daz lvarez

    Electrical EnergyConversion andPower Systems

    Universidadde Oviedo

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    2/90

    Time & Cost Management Project Definition

    Resources estimation and asignation

    Time planning

    Base line

    Management of changes

    Evaluation

    Termination strategy

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    3/90

    What is time and cost control? Direct the progress

    Cost-Time-Progress are terms which are closely related

    Plannification process is not only finishing on time, it is also veryimportant when and how you finish.

    Decide about actions

    To reduce differences between the initial plan and reality Budget deviations management (more efficiency, productivity, external

    and internal colaboration)

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    4/90

    What is time and cost control? (II) Control results

    Through a tactical and strategical planning.

    Project is also conditioned by the organization strategy

    Resources management

    Always taking into account that resources are allways limited and it is

    not easy to change them

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    5/90

    Triple Restriction

    Time

    Scope

    Cost

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    6/90

    Triple Restriction- It contains the more clearly measurable indexes in project

    management

    - It allows us controlling the result of the project

    - Nevertheless, at times it is very difficult to define good indexes

    that measure the success or failure of the project. Sometimes,success or failure depends on the Public Relationships abilityof the project manager to interact with the stakeholders

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    7/90

    Project Lifecycle

    Concept

    Planning

    Execution

    Monitoring and Controlling

    Closing

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    8/90

    Concept (I) Gather data

    Identify needs

    Stablish Targets

    Finantial availability (basic)

    Stakeholders

    Risk level

    Strategy

    Possible team

    Estimate resources

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    9/90

    Concept (II) Identify alternatives

    Present a proposal

    Obtain approval for the next phase

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    10/90

    Planning (I) Assign core team members

    Conduct studies

    Develope scope baseline Final items

    Quality standards

    Resources Activities

    Stablish Master plan

    Budget

    Tasks definition

    Policies and procedures

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    11/90

    Planning (II) Risks evaluation

    Present a summary Obtain approval for the next phase

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    12/90

    Execution, monitoring and controlling (I) Create

    Organization

    Communications

    Motivate team

    Detail technical requirements

    Stablish: Information control systems

    Work items

    Obtain goods and services Execute work items

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    13/90

    Execution, monitoring and controlling (II) Direct / Follow / Anticipate / Control

    Scope

    Quality

    Time

    Cost

    Risks Solve problems

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    14/90

    Closing Finish work items

    Review and accept Close accountability

    Transfer product responsibility

    Evaluate project Document results

    Liberate and reallocate resources

    Reallocate project team

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    15/90

    Time and cost control documentation Project constitution document

    Scope and requirements statement

    Tasks breakdown

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    16/90

    Project Constitution Document Document signed by a high level manager/director who has

    functional authority over all resources and organizations that

    works in the project. Its approval formally initiates the project.

    A project manager is identified and assigned as early in the

    project as it is feasible, preferably while the projectconstitution document is being developed and always prior tothe start of the planning.

    It is reccommended fot the project manager to participate inthe development of the Project Constitution Document, as itprovides to the project manager with the authority to makeuse of resources to project activities.

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    17/90

    Scope & requirements statement Document that describes the project

    It can be from a high level document that describes the workto be done to a complete description of project requirements

    It identifies all the requirements, restrictions and products ofthe project

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    18/90

    Tasks breakdown It is the most important tool for the project manager

    It consists on dividing the project into different products andeach product into different tasks

    When you are breaking down the tasks you should only dividethem to the level you need to exert control over.

    The breakdown should be done at the control level of theproject manager

    Once it is done, the dependency determination could be done

    and also the time and cost stimation

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    19/90

    Exercise 6.1 Define the preliminary Tasks Breakdown (discussion) for the

    following project:

    Wind farm of 40 MW (2 MW x 20 turbines) in Len Mountains at 1.500masl.

    Start from the DIA application

    The closest concrete plant to the location is 45 km ahead.

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    20/90

    Time & Cost Management Project Definition

    Resources estimation and asignation

    Time planning Base line

    Management of changes

    Evaluation

    Termination strategy

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    21/90

    Resources estimation and assignation (I) What should be done?

    The products.

    Who and what is needed? Once the productos are known, it is possible to know who and what

    personnel (attitudes, experience, etc.), equipment and materials will berequired.

    Who can do the work? After answering the previous question, the following step is to find

    people in the organization that complies with the requirements.

    Which resources do we need?

    Human resources, specialized machines, materials, etc.

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    22/90

    Resources estimation and assignation (II) Who and what is available?

    Availability of resources in and out of the organization

    What level of experience and attitude is required? According to the quality standards of the project and the required time

    by the customer

    How can the resources affect time and cost? It is important to take into account the level and experience of the

    resources (human and machinery) to estimate time and cost

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    23/90

    Resources and responsibilities matrixResource 1 Resource 2 Resource 3 Resource 4

    Task 1

    Task 2

    Task 3

    Task 4

    R- Responsible. Department / person that performs the task or assists

    in its execution.

    A- Accountable. Department / person owner of the task. The

    responsible of its approval.

    C- Consulted. Departmente / person that is consulted before making a

    decision or action.

    I- Informed. Department / person to be informed of the decisions or

    taken actions.

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    24/90

    Estimation tools (I) Analogous Estimating.

    Uses the values of parameters sucha as scope, cost, budget and durationor measures of scale such as size, weight and complexity. From a

    previous, similar project as the basis for estimating the same parametersor measures for a current project.

    It is a gross value estimating approach, sometimes adjusted for knowndifferences in project complexity.

    It is frequently used when there is a limited amount of detailedinformation about the project.

    It is generally less costly and time consuming than other techniques, butit is also generally less accurate.

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    25/90

    Estimation tools (II) Cost Estimating Relationship (CER).

    Uses a statistical relationship between historical data and othervariables (square footage in construction, lineal meters in power lines

    construction, etc.) to calculate an estimate for activity parameters, suchas cost, budget and duration.

    This technique can produce higher levels of accuracy depending on thesophistication and underlying data built into the model.

    It can be applyed to a total project or segments of a project, inconjunction with other estimating methods.

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    26/90

    Estimation tools (III) Quotation of the bidders

    They are an excellent source of information.

    It is very important for the requirements to be very clear in order for thequotation to be homogeneous.

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    27/90

    Estimation tools (IV) Bottom-Up Estimating

    It is a method of estimating a component of work. The cost of individualwork packages or activities is estimated with the greatest level of

    specified detail. The detailed cost is summarized or rolled up to higher levels for

    subsequent reporting and tracking purposes.

    The cost and accuracy of bottom-up cost estimating is typically

    influenced by the size and complexity of individual activity or workpackage.

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    28/90

    Estimation tools (V-a) Three Points Estimating

    The accuracy of the previous Bottom-Up Estimating can be improved byconsidering uncertainty and risk.

    This concept originated with the program evaluation and reviewtechnique (PERT).

    Standard deviation

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    29/90

    Estimation tools (V-b) Standard deviation of a path using PERT method

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    30/90

    Cost types and categories Categories

    Direct. Clearly associated with the project or product.

    Indirect. It is not identificable or it is more likely that they will beconsidered as structure cost.

    Types Fixed. Associated to the project and not to the production volume.

    Variable. They depend on the consumption or production.

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    31/90

    Exercise 6.2 Calculate Estimated Cost and Standard Deviation of each task

    and the whole path

    Task OptimisticMostLikely Pesimistic

    EstimatedCost

    StandardDeviation

    1 4 5 6

    2 2 5 9

    3 4 6 10

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    32/90

    Exercise 6.2. Solution Calculate Estimated Cost and Standard Deviation of each task

    and the whole path

    Task OptimisticMostLikely Pesimistic

    EstimatedCost

    StandardDeviation

    1 4 5 6 5,00 0,33

    2 2 5 9 5,17 1,17

    3 4 6 10 6,33 1,00

    1,57

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    33/90

    How to review an Estimation

    Review system definition: know what we are estimating

    Study basic rules, restrictions and asumptions: know the

    environment Focus on data sources: Where do they come from?

    Compare the estimation with established standards (if they

    exists) Determine if the methodology is acceptable: are estimations

    reasonable? Are we evaluating all the costs?

    Identify cost drivers Consider triple restriction

    Consider customer expectatives

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    34/90

    Important message

    Estimations are only

    predictions and budgets areonly estimations

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    35/90

    Time & Cost Management

    Project Definition

    Resources estimation and asignation

    Time planning Base line

    Management of changes

    Evaluation Termination strategy

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    36/90

    Sequence Activities The input for this work is the tasks breakdown

    A decomposition of the tasks in work packages is required.These could be tasks from the task breakdown or smallerpackages

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    37/90

    Tasks breakdown and Network Diagram

    Tasksbreakdonw

    1.1

    1.1.1 1.1.2

    1.2

    1.2.1 1.2.2

    1.3

    1.3.1 1.3.2

    To build the Network Diagram, work packages (1.1.1,

    1.1.2, , 1.3.2) should only be used

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    38/90

    Tasks breakdown and Network Diagram

    Start 1.1.1 1.1.2 1.2.2 Fin

    1.2.1 1.3.1 1.3.2

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    39/90

    Project time validation The customer, the organization and the team need to know:

    When can we start?

    When should we finish?

    Which is the business neccesity that defines the delivery date?

    Which are the restrictions that could affect the time?

    Which are the main risks?

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    40/90

    Consider risks in Time Estimations Identify information related to known risks

    Recognize schedule risks

    Incorporate time reserve or contingency Reduce or eliminate time reserves

    Documentate risks

    Remember Murphy law

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    41/90

    Network diagram It is a graphic representation of the logic relationships

    between the activities of the project.

    They are usually drawn from left to right to reflect thecronology of the project

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    42/90

    Basic rules of the network diagram There is only a starting point

    There is only a finishing point

    All activities have at least a predecessor one (except thestarting activity)

    All activities hava al least a successor one (except the finishingactivity)

    There must not be any loops or disconnected paths

    The logic of the diagram must be reviewed and continuouslyupdated

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    43/90

    How to draw a Network Diagram Make a list with the activities and their relationships

    Create a starting node

    Draw an arrow from the starting node to the first activity node Arrange all the activities sequencially

    Repeat the process for all the activities starting from thesuccessor

    Create a final node

    Check that all the nodes and relationships are considered

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    44/90

    How to draw a Network DiagramActivity Predeccessor Estimated time

    (a) Digging - 5

    (b) Foundations a 2

    (c) External plumbing a 6

    (d) Divisions b 12

    (e) Internal plumbing d 10

    (f) Electrical installation d 9

    (g) Roof d 5

    (h) Bricks b 9

    (i) Plumbing inspection c, e 1

    (j) Collocate tiles g 2(k) Cover walls f, i, j 3

    (l) Internal finishing k 9

    (m) External finishing h, g 7

    (n) Gardening M 8

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    45/90

    How to draw a Network Diagram

    Start (a) Digging

    (c) External

    plumbing

    (i) Plumbing

    inspection

    (k) Cover

    walls

    (l) Internal

    finishing

    (b)

    Foundations

    (d)

    Divisions

    (e) Internal

    plumbing

    (f) Electrical

    installation End

    (j) Tiles

    (g) Roof(m) Externalfinishing

    (n)Gardening

    (h) Bricks

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    46/90

    Time planning

    Network calculation from the begining to the end

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    47/90

    Stablish starting date for the first activity

    Start to work on the left. Continue always from left toright and from top to bottom

    Early Start (ES) +Duration = Early Finish (EF)

    When a successor activity has multiple predecessors,use the later early finish (EF) of the predecessor as itsearly start (ES)

    Continue to the end of the network

    47

    Network calculation from the begining to the end(End-Start relationships)

    Network calculation from the begining to the end

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    48/90

    48

    Network calculation from the begining to the end(End-Start relationships)

    0 5 5 11 29 30 30 33 33 42

    Start (a) Digging

    (c) External

    plumbing

    (i) Plumbing

    inspection

    (k) Cover

    walls

    (l) Internal

    finishing

    5 7 7 19 19 29

    (b)

    Foundations

    (d)

    Divisions

    (e) Internal

    plumbing

    19 28 42

    (f) Electrical

    installation End

    24 26

    (j) Tiles

    19 24 24 31 31 39

    (g) Roof

    (m) External

    finishing

    (n)

    Gardening

    7 16

    (h) Bricks

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    49/90

    Stablish as the Late Finish (LF) the Early Finish (EF) ofthe last activity (or the date stablished by the customer)

    Start to work on the right. Continue always from rightto left and from top to bottom

    Late Finish (LF) - Duration = Late Start (LS).

    LS advancement or LS + Delay = LF of thepredecessors

    When a predeccessor activity has multiple successors,use the earlier Late Start (LS) of the successor as itsLast Finish (LF)

    Continue to the beggining of the network

    49

    Network calculation from the end to the begining

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    50/90

    50

    Network calculation from the end to the begining

    0 5 5 11 29 30 30 33 33 42

    Start (a) Digging

    (c) External

    plumbing

    (i) Plumbing

    inspection

    (k) Cover

    walls

    (l) Internal

    finishing

    0 5 23 29 29 30 30 33 33 42

    5 7 7 19 19 29

    (b)

    Foundations

    (d)

    Divisions

    (e) Internal

    plumbing

    5 7 7 19 19 29

    19 28 42

    (f) Electrical

    installation End

    21 30 42

    24 26

    (j) Tiles

    28 30

    19 24 24 31 31 39

    (g) Roof

    (m) External

    finishing

    (n)

    Gardening

    22 27 27 34 34 42

    7 16(h) Bricks

    18 27

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    51/90

    Time that an activity could be delayed from its Early Start(ES) without delaying the end of the project

    Slack = LF (Late Finish) EF (Early Finish) Slack = LS (Late Start) ES (Early Start)

    The activities, not the projects, can have slack

    51

    Slack, Float or Path Float

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    52/90

    The path which, any delay in its activities, will impact onthe project duration

    The largest path of the project The path which has the activities with slack = 0

    The shortest time to complete a project

    52

    Critical Path

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    53/90

    53

    Critical Path

    0 5 5 11 29 30 30 33 33 42

    Start (a) Digging

    (c) External

    plumbing

    (i) Plumbing

    inspection

    (k) Cover

    walls

    (l) Internal

    finishing

    0 5 23 29 29 30 30 33 33 42

    5 7 7 19 19 29

    (b)

    Foundations

    (d)

    Divisions

    (e) Internal

    plumbing

    5 7 7 19 19 29

    19 28 42

    (f) Electrical

    installation End

    21 30 42

    24 26

    (j) Tiles

    28 30

    19 24 24 31 31 39

    (g) Roof

    (m) External

    finishing

    (n)

    Gardening

    22 27 27 34 34 42

    7 16

    (h) Bricks

    18 27

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    54/90

    Lag (delay): A modification of a logic relationship thatimposes a delay in the begining of the following task (FS + 2)

    Example: When a foundation is finished, you have to wait 4weeks (FS + 20) to begin the erection of the wind turbine

    Lead: A modification of a logic relationship tha allows theacceleration of the succesor task (FS 1)

    Example. When the laying of the wires is almost finished(the covering works are not finished yet), you can start theterminals of the wires which are inside of the wind turbinesone week before (FS 5)

    54

    Lag and Lead

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    55/90

    FS: Finish Start. The following activity starts when theprevious is finished

    Finish the electro-mechanical erection start tests of the

    subestation Finish the road start wind turbines transportation

    55

    Types of relationships

    Activy A Activity B

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    56/90

    SS: Start Start. The following activity stars at the sametime (or with the stablished delay) of the previous one.For example SS +2.

    Start electrical installation; Start plumbing installation

    56

    Types of relationships

    Activy A

    Activity B

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    57/90

    FF: Finish Finish. Both activities have to be finished atthe same time.

    Cook turkey; boil rice Select project ; asign funding

    57

    Types of relationships

    Activy A

    Activity B

    f l h

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    58/90

    SF: Start Finish (with the stablished delay). Thefollowing activity finishes the stablished delay from thestart of the previous one

    Maintenance team start to work (A) and two days after,erection teams finish their works SF + 2

    58

    Types of relationships

    Activy A

    Activity B

    M h d f d i j d i

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    59/90

    Crashing. Reduce the duration of the tasks of the criticalpath (anyway possible).

    Network crashing. Study alternatives of cost and durationin order to obtain the maximun of compression atminimun cost

    Fast tracking. Carry out at the same time activities thatshould be done in a sequential way.

    59

    Methods of reducing project duration

    B l i

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    60/90

    The process of replanning tasks with slack in order tosolve resources problems

    Determine ES, EF, LS and LF

    Evaluate available resources for each cronogram

    Identify slack

    Adjust tasks analizing their slack to balance the resources

    Determine new cronogram

    60

    Balancing

    E i 6 3 D th t k di

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    61/90

    61

    Exercise 6.3. Draw the network diagramID Nombre de tarea Duration Predecessors Successors

    1 Parque en Len 806 days

    2 Inicio proyecto 0 days 4,6,7,8,9,10

    3 Estudios previos 265 days

    4 Estudio de viento 265 days 2 12

    5 Estudios restricciones 265 days

    6 Medio Ambiente 265 days 2 12

    7 Evacuacin 45 days 2 12

    8 Ingeniera 90 days 2 12

    9 Propiedad 30 days 2 12

    10 Administrativo 30 days 2 1211 Estudio econmico 40 days

    12 Elaborar estudio 15 days 4,6,7,8,9,10 13

    13 Aprobacin direccin 25 days 12 15

    14 Tramitacin inicial 275 days

    15 Elaborar anteproyecto 15 days 13 16

    16 Declaracin de Impacto Ambiental 130 days 15 17

    17 Elaborar proyecto ejecucin 30 days 16 18,19

    18 Autorizacin Administrativa 90 days 17 6,31,35,22FF

    19 Calificacin Urbanstica 60 days 17 20

    20 Licencia de Obras 40 days 19 6,31,35,22FF

    21 Compras 75 days

    22 Elaborar pliego licitacin 40 days 18FF,20FF 23

    23 Ofertas 25 days 22 24

    24 Adjudicacin 10 days 23 26,31,35

    25 Construccin 163 days

    26 Obra civil parque 100 days 18,20,24 7SS+30 days

    27 Obra electromecnica parque 80 days 26SS+30 days 8SS+50 days

    28 Izado aerogeneradores 50 days 27SS+50 days 9SS+40 days

    29 Pruebas aerogeneradores en vaco 20 days 28SS+40 days 0SS+10 days

    30 Pruebas aerogeneradores con tensi 20 days 29SS+10 days,3 40

    31 Obra civil lnea area 90 days 18,20,24 2SS+30 days

    32 Izado apoyos lnea area 80 days 31SS+30 days 3SS+40 days

    33 Tendido lnea area 70 days 32SS+40 days 3434 Pruebas lnea area 1 day 33,37 38

    35 Obra civil subestacin 90 days 18,20,24 6SS+60 days

    36 Equipos electromecnicos subestaci 45 days 35SS+60 days 37

    37 Pruebas en vaco subestacin 10 days 36 34,38

    38 Energizacin subestacin 2 days 34,37 30

    39 Tramitacin final 28 days

    40 Tramitacin con REE 15 days 30 41

    41 Pruebas con REE 3 days 40 42

    42 Inscripcin en el RIPRE 10 days 41 43

    43 Fin proyecto 0 days 42

    1/1

    2/3

    Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2

    1st Half 2nd Half 1st Half 2nd Half 1st Half 2nd Half 1st Half 2 l

    Ti & C t M t

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    62/90

    Time & Cost Management

    Project Definition

    Resources estimation and asignation

    Time planning Base line

    Management of changes

    Evaluation Termination strategy

    Base Line Foundations

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    63/90

    A base line is the original plan which is approved and/orscope changes approved.

    The base line stablishes a reference which is used byproject directors to check the real advance of the project

    63

    Base Line Foundations

    Cost Base Line

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    64/90

    It is obtained using estimates of work that will benecessary. Money time.

    Back Up: it is money or time that is provided in the planto attend risks of cost, time or performance

    64

    Cost Base Line

    CTC: Cost to complete

    BAC: Budget at Completion

    Base Line Review

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    65/90

    Ensure that all stakeholders agree with the Base Line.

    Work to stablish strategies of risks before stablishing theBase Line.

    Clarify when and how the project director could haveaccess to the back up.

    Know objective measures to identify when the Base Lineis out of control.

    Know when and how you must change the Base Line.

    Remake the Base Line only as last resource. The Base Line can only be changed when the change is

    approved and authorized

    65

    Base Line Review

    Time & Cost Management

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    66/90

    Time & Cost Management

    Project Definition

    Resources estimation and asignation

    Time planning Base line

    Management of changes

    Evaluation Termination strategy

    Origin of changes

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    67/90

    Customer

    Members of team project

    Government Environment

    Products obsolescence

    Management alterations Technological advances

    Financing changes

    67

    Origin of changes

    Real Vs Planning

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    68/90

    68

    Real Vs Planning

    Two months of delay 50 k of overrun

    Process of Changes Management

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    69/90

    Identify andpresente

    change requestRequest review

    Impactvaluation

    Obtaincustomerapproval

    Inform

    stakeholders

    Implement and

    document

    Distribute

    69

    Process of Changes Management

    Document change Requests

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    70/90

    Who?

    What?

    When? Impact.

    Authorization.

    70

    Document change Requests

    Make the change

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    71/90

    Evaluate incidence in:

    Triple restriction

    Functional areas

    Team

    Project

    Policies

    Organization

    71

    Make the change

    Facing the changes

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    72/90

    Project plan update:

    Cost

    Time

    Resources

    Milestones

    Documentation

    Communicate changes. It should be done in a systematicand organized way (use a document for each change anda register for the documents of change).

    Protect team members Close project

    72

    Facing the changes

    Time & Cost Management

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    73/90

    g

    Project Definition

    Resources estimation and asignation

    Time planning Base line

    Management of changes

    Evaluation Termination strategy

    Evaluation

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    74/90

    Evaluation consists on an exam and oficial verification of:

    Advancement

    Status

    Finantial health (of the project)

    74

    Control

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    75/90

    The process of:

    Comparing actual with planned performance

    Analyzing variations

    Evaluating trends to

    To make process improvements and alternatives

    To recommed appropriate corrective actions

    Control

    Should be done regularly

    It should be concentrated in specific tasks and performanceanalysis

    Its relative cost is low

    75

    Time and Cost Control

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    76/90

    Time control

    It compares planned project advance Vs real project advance

    It defines a strategy to limit the variation in time

    It manages activities to mantain an acceptable variation of thetime base line

    Cost control It compares planned project costs Vs real project costs

    It defines a strategy to limit the variation in the costs base line

    of the project It manages activities to mantain budget

    76

    Earned Value Technique (EVT)

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    77/90

    What is it?

    An objective assessment of variations

    A standard calculation

    A consistent measure among all project manage

    Compare the planned costs to the actual costs of theperformed work.

    77

    Earned Value Technique (EVT). Definitions

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    78/90

    Planned Value (PV): The sum of the approved costestimates for activities scheduled to run within aspecified period.

    Actual Cost (AC): The total cost incurred in theperformance of work for a specified period.

    Earned Value (EV): The sum of the approved cost

    estimates for completed activities in a specified period oftime.

    Budget at Completion (BAC): The sum of the approved

    cost estimates for all project activities

    78

    Earned Value Technique (EVT). Definitions

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    79/90

    Cost Variance (CV): The difference between the plannedcost of work completed and the actual cost of that work.

    Schedule Variance (SV): The difference between thescheduled end of one activity and the really amount ofwork performed expressed in money.

    Cost Performance Index (CPI): The return of spent money.

    The value of work completed by each spent euro.

    Schedule Performance Index (SPI): The performance ofthe invested money. The value of completed work by

    each euro planned to be completed

    79

    Earned Value Technique (EVT). Formulas

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    80/90

    SV = EV PV

    CV = EV AC

    SPI = EV / PV

    CPI = EV / AC

    Completed percentage. PC = EV / BAC

    Wasted percentage. PS = AC / BAC

    Estimate to completion (the expected additional cost tocomplete the project or some specific activities). ETC =AC + ETC

    Estimate at completion (the expected total cost of theentire project or specific activities). EAC = AC + (BAC EV) = AC + ((BAC-EV)/CPI)

    80

    Earned Value Technique (EVT)

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    81/90

    81

    Time & Cost Management

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    82/90

    Project Definition

    Resources estimation and asignation

    Time planning Base line

    Management of changes

    Evaluation Termination strategy

    Project closure

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    83/90

    Three points to take into account:

    Scope verification

    Agreements closing

    Administrative closing

    83

    The process of closing strategy

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    84/90

    Fulfill contractualobligations

    Conduct final

    review of theWBS

    Organize files

    Finish therelationship with

    the customer

    Celebratingsuccess

    Manage closure

    84

    Fulfill contractual obligations

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    85/90

    Identify pending deliverables

    Client analysis

    Internal analysis

    Identify broke promises

    Written

    Oral

    Review budget

    Deliver products

    Ensure client acceptance

    85

    Conduct final review of the WBS

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    86/90

    Has each work package been completed?

    Yes. Document the closing date, who decided to close it, etc.

    No. Document why not, who decided not to complete it, etc.

    86

    Organize files

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    87/90

    Make a complete dossier of the project documentation.

    Make the final revision of learnt lessons

    Circulate a preliminary list of learnt lessons

    Make a workshop with the team members to documentnew best practices and learnt lessons.

    87

    Finish the relationship with the customer

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    88/90

    Sign of TOC and all the certificates.

    Start next responsibilities:

    Maintenance

    Audit

    88

    Celebrating Success

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    89/90

    Celebration

    Awards

    Remember memorable moments

    89

    Manage closure

  • 7/29/2019 CEESP Project Management. Units Six and Seven

    90/90

    Reassign team members to other projects

    Reassign materials

    File documentation for historical reference

    90