ceesp project management. units six and seven
TRANSCRIPT
-
7/29/2019 CEESP Project Management. Units Six and Seven
1/90
Project Management
Time and Cost Management
Lecturer: Javier Daz lvarez
Electrical EnergyConversion andPower Systems
Universidadde Oviedo
-
7/29/2019 CEESP Project Management. Units Six and Seven
2/90
Time & Cost Management Project Definition
Resources estimation and asignation
Time planning
Base line
Management of changes
Evaluation
Termination strategy
-
7/29/2019 CEESP Project Management. Units Six and Seven
3/90
What is time and cost control? Direct the progress
Cost-Time-Progress are terms which are closely related
Plannification process is not only finishing on time, it is also veryimportant when and how you finish.
Decide about actions
To reduce differences between the initial plan and reality Budget deviations management (more efficiency, productivity, external
and internal colaboration)
-
7/29/2019 CEESP Project Management. Units Six and Seven
4/90
What is time and cost control? (II) Control results
Through a tactical and strategical planning.
Project is also conditioned by the organization strategy
Resources management
Always taking into account that resources are allways limited and it is
not easy to change them
-
7/29/2019 CEESP Project Management. Units Six and Seven
5/90
Triple Restriction
Time
Scope
Cost
-
7/29/2019 CEESP Project Management. Units Six and Seven
6/90
Triple Restriction- It contains the more clearly measurable indexes in project
management
- It allows us controlling the result of the project
- Nevertheless, at times it is very difficult to define good indexes
that measure the success or failure of the project. Sometimes,success or failure depends on the Public Relationships abilityof the project manager to interact with the stakeholders
-
7/29/2019 CEESP Project Management. Units Six and Seven
7/90
Project Lifecycle
Concept
Planning
Execution
Monitoring and Controlling
Closing
-
7/29/2019 CEESP Project Management. Units Six and Seven
8/90
Concept (I) Gather data
Identify needs
Stablish Targets
Finantial availability (basic)
Stakeholders
Risk level
Strategy
Possible team
Estimate resources
-
7/29/2019 CEESP Project Management. Units Six and Seven
9/90
Concept (II) Identify alternatives
Present a proposal
Obtain approval for the next phase
-
7/29/2019 CEESP Project Management. Units Six and Seven
10/90
Planning (I) Assign core team members
Conduct studies
Develope scope baseline Final items
Quality standards
Resources Activities
Stablish Master plan
Budget
Tasks definition
Policies and procedures
-
7/29/2019 CEESP Project Management. Units Six and Seven
11/90
Planning (II) Risks evaluation
Present a summary Obtain approval for the next phase
-
7/29/2019 CEESP Project Management. Units Six and Seven
12/90
Execution, monitoring and controlling (I) Create
Organization
Communications
Motivate team
Detail technical requirements
Stablish: Information control systems
Work items
Obtain goods and services Execute work items
-
7/29/2019 CEESP Project Management. Units Six and Seven
13/90
Execution, monitoring and controlling (II) Direct / Follow / Anticipate / Control
Scope
Quality
Time
Cost
Risks Solve problems
-
7/29/2019 CEESP Project Management. Units Six and Seven
14/90
Closing Finish work items
Review and accept Close accountability
Transfer product responsibility
Evaluate project Document results
Liberate and reallocate resources
Reallocate project team
-
7/29/2019 CEESP Project Management. Units Six and Seven
15/90
Time and cost control documentation Project constitution document
Scope and requirements statement
Tasks breakdown
-
7/29/2019 CEESP Project Management. Units Six and Seven
16/90
Project Constitution Document Document signed by a high level manager/director who has
functional authority over all resources and organizations that
works in the project. Its approval formally initiates the project.
A project manager is identified and assigned as early in the
project as it is feasible, preferably while the projectconstitution document is being developed and always prior tothe start of the planning.
It is reccommended fot the project manager to participate inthe development of the Project Constitution Document, as itprovides to the project manager with the authority to makeuse of resources to project activities.
-
7/29/2019 CEESP Project Management. Units Six and Seven
17/90
Scope & requirements statement Document that describes the project
It can be from a high level document that describes the workto be done to a complete description of project requirements
It identifies all the requirements, restrictions and products ofthe project
-
7/29/2019 CEESP Project Management. Units Six and Seven
18/90
Tasks breakdown It is the most important tool for the project manager
It consists on dividing the project into different products andeach product into different tasks
When you are breaking down the tasks you should only dividethem to the level you need to exert control over.
The breakdown should be done at the control level of theproject manager
Once it is done, the dependency determination could be done
and also the time and cost stimation
-
7/29/2019 CEESP Project Management. Units Six and Seven
19/90
Exercise 6.1 Define the preliminary Tasks Breakdown (discussion) for the
following project:
Wind farm of 40 MW (2 MW x 20 turbines) in Len Mountains at 1.500masl.
Start from the DIA application
The closest concrete plant to the location is 45 km ahead.
-
7/29/2019 CEESP Project Management. Units Six and Seven
20/90
Time & Cost Management Project Definition
Resources estimation and asignation
Time planning Base line
Management of changes
Evaluation
Termination strategy
-
7/29/2019 CEESP Project Management. Units Six and Seven
21/90
Resources estimation and assignation (I) What should be done?
The products.
Who and what is needed? Once the productos are known, it is possible to know who and what
personnel (attitudes, experience, etc.), equipment and materials will berequired.
Who can do the work? After answering the previous question, the following step is to find
people in the organization that complies with the requirements.
Which resources do we need?
Human resources, specialized machines, materials, etc.
-
7/29/2019 CEESP Project Management. Units Six and Seven
22/90
Resources estimation and assignation (II) Who and what is available?
Availability of resources in and out of the organization
What level of experience and attitude is required? According to the quality standards of the project and the required time
by the customer
How can the resources affect time and cost? It is important to take into account the level and experience of the
resources (human and machinery) to estimate time and cost
-
7/29/2019 CEESP Project Management. Units Six and Seven
23/90
Resources and responsibilities matrixResource 1 Resource 2 Resource 3 Resource 4
Task 1
Task 2
Task 3
Task 4
R- Responsible. Department / person that performs the task or assists
in its execution.
A- Accountable. Department / person owner of the task. The
responsible of its approval.
C- Consulted. Departmente / person that is consulted before making a
decision or action.
I- Informed. Department / person to be informed of the decisions or
taken actions.
-
7/29/2019 CEESP Project Management. Units Six and Seven
24/90
Estimation tools (I) Analogous Estimating.
Uses the values of parameters sucha as scope, cost, budget and durationor measures of scale such as size, weight and complexity. From a
previous, similar project as the basis for estimating the same parametersor measures for a current project.
It is a gross value estimating approach, sometimes adjusted for knowndifferences in project complexity.
It is frequently used when there is a limited amount of detailedinformation about the project.
It is generally less costly and time consuming than other techniques, butit is also generally less accurate.
-
7/29/2019 CEESP Project Management. Units Six and Seven
25/90
Estimation tools (II) Cost Estimating Relationship (CER).
Uses a statistical relationship between historical data and othervariables (square footage in construction, lineal meters in power lines
construction, etc.) to calculate an estimate for activity parameters, suchas cost, budget and duration.
This technique can produce higher levels of accuracy depending on thesophistication and underlying data built into the model.
It can be applyed to a total project or segments of a project, inconjunction with other estimating methods.
-
7/29/2019 CEESP Project Management. Units Six and Seven
26/90
Estimation tools (III) Quotation of the bidders
They are an excellent source of information.
It is very important for the requirements to be very clear in order for thequotation to be homogeneous.
-
7/29/2019 CEESP Project Management. Units Six and Seven
27/90
Estimation tools (IV) Bottom-Up Estimating
It is a method of estimating a component of work. The cost of individualwork packages or activities is estimated with the greatest level of
specified detail. The detailed cost is summarized or rolled up to higher levels for
subsequent reporting and tracking purposes.
The cost and accuracy of bottom-up cost estimating is typically
influenced by the size and complexity of individual activity or workpackage.
-
7/29/2019 CEESP Project Management. Units Six and Seven
28/90
Estimation tools (V-a) Three Points Estimating
The accuracy of the previous Bottom-Up Estimating can be improved byconsidering uncertainty and risk.
This concept originated with the program evaluation and reviewtechnique (PERT).
Standard deviation
-
7/29/2019 CEESP Project Management. Units Six and Seven
29/90
Estimation tools (V-b) Standard deviation of a path using PERT method
-
7/29/2019 CEESP Project Management. Units Six and Seven
30/90
Cost types and categories Categories
Direct. Clearly associated with the project or product.
Indirect. It is not identificable or it is more likely that they will beconsidered as structure cost.
Types Fixed. Associated to the project and not to the production volume.
Variable. They depend on the consumption or production.
-
7/29/2019 CEESP Project Management. Units Six and Seven
31/90
Exercise 6.2 Calculate Estimated Cost and Standard Deviation of each task
and the whole path
Task OptimisticMostLikely Pesimistic
EstimatedCost
StandardDeviation
1 4 5 6
2 2 5 9
3 4 6 10
-
7/29/2019 CEESP Project Management. Units Six and Seven
32/90
Exercise 6.2. Solution Calculate Estimated Cost and Standard Deviation of each task
and the whole path
Task OptimisticMostLikely Pesimistic
EstimatedCost
StandardDeviation
1 4 5 6 5,00 0,33
2 2 5 9 5,17 1,17
3 4 6 10 6,33 1,00
1,57
-
7/29/2019 CEESP Project Management. Units Six and Seven
33/90
How to review an Estimation
Review system definition: know what we are estimating
Study basic rules, restrictions and asumptions: know the
environment Focus on data sources: Where do they come from?
Compare the estimation with established standards (if they
exists) Determine if the methodology is acceptable: are estimations
reasonable? Are we evaluating all the costs?
Identify cost drivers Consider triple restriction
Consider customer expectatives
-
7/29/2019 CEESP Project Management. Units Six and Seven
34/90
Important message
Estimations are only
predictions and budgets areonly estimations
-
7/29/2019 CEESP Project Management. Units Six and Seven
35/90
Time & Cost Management
Project Definition
Resources estimation and asignation
Time planning Base line
Management of changes
Evaluation Termination strategy
-
7/29/2019 CEESP Project Management. Units Six and Seven
36/90
Sequence Activities The input for this work is the tasks breakdown
A decomposition of the tasks in work packages is required.These could be tasks from the task breakdown or smallerpackages
-
7/29/2019 CEESP Project Management. Units Six and Seven
37/90
Tasks breakdown and Network Diagram
Tasksbreakdonw
1.1
1.1.1 1.1.2
1.2
1.2.1 1.2.2
1.3
1.3.1 1.3.2
To build the Network Diagram, work packages (1.1.1,
1.1.2, , 1.3.2) should only be used
-
7/29/2019 CEESP Project Management. Units Six and Seven
38/90
Tasks breakdown and Network Diagram
Start 1.1.1 1.1.2 1.2.2 Fin
1.2.1 1.3.1 1.3.2
-
7/29/2019 CEESP Project Management. Units Six and Seven
39/90
Project time validation The customer, the organization and the team need to know:
When can we start?
When should we finish?
Which is the business neccesity that defines the delivery date?
Which are the restrictions that could affect the time?
Which are the main risks?
-
7/29/2019 CEESP Project Management. Units Six and Seven
40/90
Consider risks in Time Estimations Identify information related to known risks
Recognize schedule risks
Incorporate time reserve or contingency Reduce or eliminate time reserves
Documentate risks
Remember Murphy law
-
7/29/2019 CEESP Project Management. Units Six and Seven
41/90
Network diagram It is a graphic representation of the logic relationships
between the activities of the project.
They are usually drawn from left to right to reflect thecronology of the project
-
7/29/2019 CEESP Project Management. Units Six and Seven
42/90
Basic rules of the network diagram There is only a starting point
There is only a finishing point
All activities have at least a predecessor one (except thestarting activity)
All activities hava al least a successor one (except the finishingactivity)
There must not be any loops or disconnected paths
The logic of the diagram must be reviewed and continuouslyupdated
-
7/29/2019 CEESP Project Management. Units Six and Seven
43/90
How to draw a Network Diagram Make a list with the activities and their relationships
Create a starting node
Draw an arrow from the starting node to the first activity node Arrange all the activities sequencially
Repeat the process for all the activities starting from thesuccessor
Create a final node
Check that all the nodes and relationships are considered
-
7/29/2019 CEESP Project Management. Units Six and Seven
44/90
How to draw a Network DiagramActivity Predeccessor Estimated time
(a) Digging - 5
(b) Foundations a 2
(c) External plumbing a 6
(d) Divisions b 12
(e) Internal plumbing d 10
(f) Electrical installation d 9
(g) Roof d 5
(h) Bricks b 9
(i) Plumbing inspection c, e 1
(j) Collocate tiles g 2(k) Cover walls f, i, j 3
(l) Internal finishing k 9
(m) External finishing h, g 7
(n) Gardening M 8
-
7/29/2019 CEESP Project Management. Units Six and Seven
45/90
How to draw a Network Diagram
Start (a) Digging
(c) External
plumbing
(i) Plumbing
inspection
(k) Cover
walls
(l) Internal
finishing
(b)
Foundations
(d)
Divisions
(e) Internal
plumbing
(f) Electrical
installation End
(j) Tiles
(g) Roof(m) Externalfinishing
(n)Gardening
(h) Bricks
-
7/29/2019 CEESP Project Management. Units Six and Seven
46/90
Time planning
Network calculation from the begining to the end
-
7/29/2019 CEESP Project Management. Units Six and Seven
47/90
Stablish starting date for the first activity
Start to work on the left. Continue always from left toright and from top to bottom
Early Start (ES) +Duration = Early Finish (EF)
When a successor activity has multiple predecessors,use the later early finish (EF) of the predecessor as itsearly start (ES)
Continue to the end of the network
47
Network calculation from the begining to the end(End-Start relationships)
Network calculation from the begining to the end
-
7/29/2019 CEESP Project Management. Units Six and Seven
48/90
48
Network calculation from the begining to the end(End-Start relationships)
0 5 5 11 29 30 30 33 33 42
Start (a) Digging
(c) External
plumbing
(i) Plumbing
inspection
(k) Cover
walls
(l) Internal
finishing
5 7 7 19 19 29
(b)
Foundations
(d)
Divisions
(e) Internal
plumbing
19 28 42
(f) Electrical
installation End
24 26
(j) Tiles
19 24 24 31 31 39
(g) Roof
(m) External
finishing
(n)
Gardening
7 16
(h) Bricks
-
7/29/2019 CEESP Project Management. Units Six and Seven
49/90
Stablish as the Late Finish (LF) the Early Finish (EF) ofthe last activity (or the date stablished by the customer)
Start to work on the right. Continue always from rightto left and from top to bottom
Late Finish (LF) - Duration = Late Start (LS).
LS advancement or LS + Delay = LF of thepredecessors
When a predeccessor activity has multiple successors,use the earlier Late Start (LS) of the successor as itsLast Finish (LF)
Continue to the beggining of the network
49
Network calculation from the end to the begining
-
7/29/2019 CEESP Project Management. Units Six and Seven
50/90
50
Network calculation from the end to the begining
0 5 5 11 29 30 30 33 33 42
Start (a) Digging
(c) External
plumbing
(i) Plumbing
inspection
(k) Cover
walls
(l) Internal
finishing
0 5 23 29 29 30 30 33 33 42
5 7 7 19 19 29
(b)
Foundations
(d)
Divisions
(e) Internal
plumbing
5 7 7 19 19 29
19 28 42
(f) Electrical
installation End
21 30 42
24 26
(j) Tiles
28 30
19 24 24 31 31 39
(g) Roof
(m) External
finishing
(n)
Gardening
22 27 27 34 34 42
7 16(h) Bricks
18 27
-
7/29/2019 CEESP Project Management. Units Six and Seven
51/90
Time that an activity could be delayed from its Early Start(ES) without delaying the end of the project
Slack = LF (Late Finish) EF (Early Finish) Slack = LS (Late Start) ES (Early Start)
The activities, not the projects, can have slack
51
Slack, Float or Path Float
-
7/29/2019 CEESP Project Management. Units Six and Seven
52/90
The path which, any delay in its activities, will impact onthe project duration
The largest path of the project The path which has the activities with slack = 0
The shortest time to complete a project
52
Critical Path
-
7/29/2019 CEESP Project Management. Units Six and Seven
53/90
53
Critical Path
0 5 5 11 29 30 30 33 33 42
Start (a) Digging
(c) External
plumbing
(i) Plumbing
inspection
(k) Cover
walls
(l) Internal
finishing
0 5 23 29 29 30 30 33 33 42
5 7 7 19 19 29
(b)
Foundations
(d)
Divisions
(e) Internal
plumbing
5 7 7 19 19 29
19 28 42
(f) Electrical
installation End
21 30 42
24 26
(j) Tiles
28 30
19 24 24 31 31 39
(g) Roof
(m) External
finishing
(n)
Gardening
22 27 27 34 34 42
7 16
(h) Bricks
18 27
-
7/29/2019 CEESP Project Management. Units Six and Seven
54/90
Lag (delay): A modification of a logic relationship thatimposes a delay in the begining of the following task (FS + 2)
Example: When a foundation is finished, you have to wait 4weeks (FS + 20) to begin the erection of the wind turbine
Lead: A modification of a logic relationship tha allows theacceleration of the succesor task (FS 1)
Example. When the laying of the wires is almost finished(the covering works are not finished yet), you can start theterminals of the wires which are inside of the wind turbinesone week before (FS 5)
54
Lag and Lead
-
7/29/2019 CEESP Project Management. Units Six and Seven
55/90
FS: Finish Start. The following activity starts when theprevious is finished
Finish the electro-mechanical erection start tests of the
subestation Finish the road start wind turbines transportation
55
Types of relationships
Activy A Activity B
-
7/29/2019 CEESP Project Management. Units Six and Seven
56/90
SS: Start Start. The following activity stars at the sametime (or with the stablished delay) of the previous one.For example SS +2.
Start electrical installation; Start plumbing installation
56
Types of relationships
Activy A
Activity B
-
7/29/2019 CEESP Project Management. Units Six and Seven
57/90
FF: Finish Finish. Both activities have to be finished atthe same time.
Cook turkey; boil rice Select project ; asign funding
57
Types of relationships
Activy A
Activity B
f l h
-
7/29/2019 CEESP Project Management. Units Six and Seven
58/90
SF: Start Finish (with the stablished delay). Thefollowing activity finishes the stablished delay from thestart of the previous one
Maintenance team start to work (A) and two days after,erection teams finish their works SF + 2
58
Types of relationships
Activy A
Activity B
M h d f d i j d i
-
7/29/2019 CEESP Project Management. Units Six and Seven
59/90
Crashing. Reduce the duration of the tasks of the criticalpath (anyway possible).
Network crashing. Study alternatives of cost and durationin order to obtain the maximun of compression atminimun cost
Fast tracking. Carry out at the same time activities thatshould be done in a sequential way.
59
Methods of reducing project duration
B l i
-
7/29/2019 CEESP Project Management. Units Six and Seven
60/90
The process of replanning tasks with slack in order tosolve resources problems
Determine ES, EF, LS and LF
Evaluate available resources for each cronogram
Identify slack
Adjust tasks analizing their slack to balance the resources
Determine new cronogram
60
Balancing
E i 6 3 D th t k di
-
7/29/2019 CEESP Project Management. Units Six and Seven
61/90
61
Exercise 6.3. Draw the network diagramID Nombre de tarea Duration Predecessors Successors
1 Parque en Len 806 days
2 Inicio proyecto 0 days 4,6,7,8,9,10
3 Estudios previos 265 days
4 Estudio de viento 265 days 2 12
5 Estudios restricciones 265 days
6 Medio Ambiente 265 days 2 12
7 Evacuacin 45 days 2 12
8 Ingeniera 90 days 2 12
9 Propiedad 30 days 2 12
10 Administrativo 30 days 2 1211 Estudio econmico 40 days
12 Elaborar estudio 15 days 4,6,7,8,9,10 13
13 Aprobacin direccin 25 days 12 15
14 Tramitacin inicial 275 days
15 Elaborar anteproyecto 15 days 13 16
16 Declaracin de Impacto Ambiental 130 days 15 17
17 Elaborar proyecto ejecucin 30 days 16 18,19
18 Autorizacin Administrativa 90 days 17 6,31,35,22FF
19 Calificacin Urbanstica 60 days 17 20
20 Licencia de Obras 40 days 19 6,31,35,22FF
21 Compras 75 days
22 Elaborar pliego licitacin 40 days 18FF,20FF 23
23 Ofertas 25 days 22 24
24 Adjudicacin 10 days 23 26,31,35
25 Construccin 163 days
26 Obra civil parque 100 days 18,20,24 7SS+30 days
27 Obra electromecnica parque 80 days 26SS+30 days 8SS+50 days
28 Izado aerogeneradores 50 days 27SS+50 days 9SS+40 days
29 Pruebas aerogeneradores en vaco 20 days 28SS+40 days 0SS+10 days
30 Pruebas aerogeneradores con tensi 20 days 29SS+10 days,3 40
31 Obra civil lnea area 90 days 18,20,24 2SS+30 days
32 Izado apoyos lnea area 80 days 31SS+30 days 3SS+40 days
33 Tendido lnea area 70 days 32SS+40 days 3434 Pruebas lnea area 1 day 33,37 38
35 Obra civil subestacin 90 days 18,20,24 6SS+60 days
36 Equipos electromecnicos subestaci 45 days 35SS+60 days 37
37 Pruebas en vaco subestacin 10 days 36 34,38
38 Energizacin subestacin 2 days 34,37 30
39 Tramitacin final 28 days
40 Tramitacin con REE 15 days 30 41
41 Pruebas con REE 3 days 40 42
42 Inscripcin en el RIPRE 10 days 41 43
43 Fin proyecto 0 days 42
1/1
2/3
Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2 Qtr 3 Qtr 4 Qtr 1 Qtr 2
1st Half 2nd Half 1st Half 2nd Half 1st Half 2nd Half 1st Half 2 l
Ti & C t M t
-
7/29/2019 CEESP Project Management. Units Six and Seven
62/90
Time & Cost Management
Project Definition
Resources estimation and asignation
Time planning Base line
Management of changes
Evaluation Termination strategy
Base Line Foundations
-
7/29/2019 CEESP Project Management. Units Six and Seven
63/90
A base line is the original plan which is approved and/orscope changes approved.
The base line stablishes a reference which is used byproject directors to check the real advance of the project
63
Base Line Foundations
Cost Base Line
-
7/29/2019 CEESP Project Management. Units Six and Seven
64/90
It is obtained using estimates of work that will benecessary. Money time.
Back Up: it is money or time that is provided in the planto attend risks of cost, time or performance
64
Cost Base Line
CTC: Cost to complete
BAC: Budget at Completion
Base Line Review
-
7/29/2019 CEESP Project Management. Units Six and Seven
65/90
Ensure that all stakeholders agree with the Base Line.
Work to stablish strategies of risks before stablishing theBase Line.
Clarify when and how the project director could haveaccess to the back up.
Know objective measures to identify when the Base Lineis out of control.
Know when and how you must change the Base Line.
Remake the Base Line only as last resource. The Base Line can only be changed when the change is
approved and authorized
65
Base Line Review
Time & Cost Management
-
7/29/2019 CEESP Project Management. Units Six and Seven
66/90
Time & Cost Management
Project Definition
Resources estimation and asignation
Time planning Base line
Management of changes
Evaluation Termination strategy
Origin of changes
-
7/29/2019 CEESP Project Management. Units Six and Seven
67/90
Customer
Members of team project
Government Environment
Products obsolescence
Management alterations Technological advances
Financing changes
67
Origin of changes
Real Vs Planning
-
7/29/2019 CEESP Project Management. Units Six and Seven
68/90
68
Real Vs Planning
Two months of delay 50 k of overrun
Process of Changes Management
-
7/29/2019 CEESP Project Management. Units Six and Seven
69/90
Identify andpresente
change requestRequest review
Impactvaluation
Obtaincustomerapproval
Inform
stakeholders
Implement and
document
Distribute
69
Process of Changes Management
Document change Requests
-
7/29/2019 CEESP Project Management. Units Six and Seven
70/90
Who?
What?
When? Impact.
Authorization.
70
Document change Requests
Make the change
-
7/29/2019 CEESP Project Management. Units Six and Seven
71/90
Evaluate incidence in:
Triple restriction
Functional areas
Team
Project
Policies
Organization
71
Make the change
Facing the changes
-
7/29/2019 CEESP Project Management. Units Six and Seven
72/90
Project plan update:
Cost
Time
Resources
Milestones
Documentation
Communicate changes. It should be done in a systematicand organized way (use a document for each change anda register for the documents of change).
Protect team members Close project
72
Facing the changes
Time & Cost Management
-
7/29/2019 CEESP Project Management. Units Six and Seven
73/90
g
Project Definition
Resources estimation and asignation
Time planning Base line
Management of changes
Evaluation Termination strategy
Evaluation
-
7/29/2019 CEESP Project Management. Units Six and Seven
74/90
Evaluation consists on an exam and oficial verification of:
Advancement
Status
Finantial health (of the project)
74
Control
-
7/29/2019 CEESP Project Management. Units Six and Seven
75/90
The process of:
Comparing actual with planned performance
Analyzing variations
Evaluating trends to
To make process improvements and alternatives
To recommed appropriate corrective actions
Control
Should be done regularly
It should be concentrated in specific tasks and performanceanalysis
Its relative cost is low
75
Time and Cost Control
-
7/29/2019 CEESP Project Management. Units Six and Seven
76/90
Time control
It compares planned project advance Vs real project advance
It defines a strategy to limit the variation in time
It manages activities to mantain an acceptable variation of thetime base line
Cost control It compares planned project costs Vs real project costs
It defines a strategy to limit the variation in the costs base line
of the project It manages activities to mantain budget
76
Earned Value Technique (EVT)
-
7/29/2019 CEESP Project Management. Units Six and Seven
77/90
What is it?
An objective assessment of variations
A standard calculation
A consistent measure among all project manage
Compare the planned costs to the actual costs of theperformed work.
77
Earned Value Technique (EVT). Definitions
-
7/29/2019 CEESP Project Management. Units Six and Seven
78/90
Planned Value (PV): The sum of the approved costestimates for activities scheduled to run within aspecified period.
Actual Cost (AC): The total cost incurred in theperformance of work for a specified period.
Earned Value (EV): The sum of the approved cost
estimates for completed activities in a specified period oftime.
Budget at Completion (BAC): The sum of the approved
cost estimates for all project activities
78
Earned Value Technique (EVT). Definitions
-
7/29/2019 CEESP Project Management. Units Six and Seven
79/90
Cost Variance (CV): The difference between the plannedcost of work completed and the actual cost of that work.
Schedule Variance (SV): The difference between thescheduled end of one activity and the really amount ofwork performed expressed in money.
Cost Performance Index (CPI): The return of spent money.
The value of work completed by each spent euro.
Schedule Performance Index (SPI): The performance ofthe invested money. The value of completed work by
each euro planned to be completed
79
Earned Value Technique (EVT). Formulas
-
7/29/2019 CEESP Project Management. Units Six and Seven
80/90
SV = EV PV
CV = EV AC
SPI = EV / PV
CPI = EV / AC
Completed percentage. PC = EV / BAC
Wasted percentage. PS = AC / BAC
Estimate to completion (the expected additional cost tocomplete the project or some specific activities). ETC =AC + ETC
Estimate at completion (the expected total cost of theentire project or specific activities). EAC = AC + (BAC EV) = AC + ((BAC-EV)/CPI)
80
Earned Value Technique (EVT)
-
7/29/2019 CEESP Project Management. Units Six and Seven
81/90
81
Time & Cost Management
-
7/29/2019 CEESP Project Management. Units Six and Seven
82/90
Project Definition
Resources estimation and asignation
Time planning Base line
Management of changes
Evaluation Termination strategy
Project closure
-
7/29/2019 CEESP Project Management. Units Six and Seven
83/90
Three points to take into account:
Scope verification
Agreements closing
Administrative closing
83
The process of closing strategy
-
7/29/2019 CEESP Project Management. Units Six and Seven
84/90
Fulfill contractualobligations
Conduct final
review of theWBS
Organize files
Finish therelationship with
the customer
Celebratingsuccess
Manage closure
84
Fulfill contractual obligations
-
7/29/2019 CEESP Project Management. Units Six and Seven
85/90
Identify pending deliverables
Client analysis
Internal analysis
Identify broke promises
Written
Oral
Review budget
Deliver products
Ensure client acceptance
85
Conduct final review of the WBS
-
7/29/2019 CEESP Project Management. Units Six and Seven
86/90
Has each work package been completed?
Yes. Document the closing date, who decided to close it, etc.
No. Document why not, who decided not to complete it, etc.
86
Organize files
-
7/29/2019 CEESP Project Management. Units Six and Seven
87/90
Make a complete dossier of the project documentation.
Make the final revision of learnt lessons
Circulate a preliminary list of learnt lessons
Make a workshop with the team members to documentnew best practices and learnt lessons.
87
Finish the relationship with the customer
-
7/29/2019 CEESP Project Management. Units Six and Seven
88/90
Sign of TOC and all the certificates.
Start next responsibilities:
Maintenance
Audit
88
Celebrating Success
-
7/29/2019 CEESP Project Management. Units Six and Seven
89/90
Celebration
Awards
Remember memorable moments
89
Manage closure
-
7/29/2019 CEESP Project Management. Units Six and Seven
90/90
Reassign team members to other projects
Reassign materials
File documentation for historical reference
90