box street and newtown barge parks · 5-7: existing site photo of newton barge terminal greenpoint...

12
BOX STREET AND NEWTOWN BARGE PARKS

Upload: others

Post on 12-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: BOX STREET AND NEWTOWN BARGE PARKS · 5-7: existing site photo of newton barge terminal greenpoint playgrounds greenpoint playground newtown barge terminal playgro little league field

BOX STREET AND NEWTOWN BARGE PARKS

Page 2: BOX STREET AND NEWTOWN BARGE PARKS · 5-7: existing site photo of newton barge terminal greenpoint playgrounds greenpoint playground newtown barge terminal playgro little league field

BOX STREET AND NEWTOWN BARGE PARKS: Location

Page 3: BOX STREET AND NEWTOWN BARGE PARKS · 5-7: existing site photo of newton barge terminal greenpoint playgrounds greenpoint playground newtown barge terminal playgro little league field

BOX STREET PARK:

- 2.81 acres total

-$8mm funding

NEWTOWN BARGE PARK EXPANSION:

- 2.27 acres total

- $7mm funding

Page 4: BOX STREET AND NEWTOWN BARGE PARKS · 5-7: existing site photo of newton barge terminal greenpoint playgrounds greenpoint playground newtown barge terminal playgro little league field

NEWTOWN BARGE AND BOX STREET PARKS

PROJECT SCOPE:

- Environmental investigation- Surveys and site analysis- Design- Demolition- Remediation- Construction

Page 5: BOX STREET AND NEWTOWN BARGE PARKS · 5-7: existing site photo of newton barge terminal greenpoint playgrounds greenpoint playground newtown barge terminal playgro little league field

BOX STREET PARK:

EXISTING CONDITIONS

Page 6: BOX STREET AND NEWTOWN BARGE PARKS · 5-7: existing site photo of newton barge terminal greenpoint playgrounds greenpoint playground newtown barge terminal playgro little league field

NEWTOWNBARGE PARK:

EXISTING CONDITIONS

Page 7: BOX STREET AND NEWTOWN BARGE PARKS · 5-7: existing site photo of newton barge terminal greenpoint playgrounds greenpoint playground newtown barge terminal playgro little league field

NEWTOWN BARGE PARK:

EXISTING CONDITIONS

Page 8: BOX STREET AND NEWTOWN BARGE PARKS · 5-7: existing site photo of newton barge terminal greenpoint playgrounds greenpoint playground newtown barge terminal playgro little league field
Page 9: BOX STREET AND NEWTOWN BARGE PARKS · 5-7: existing site photo of newton barge terminal greenpoint playgrounds greenpoint playground newtown barge terminal playgro little league field
Page 10: BOX STREET AND NEWTOWN BARGE PARKS · 5-7: existing site photo of newton barge terminal greenpoint playgrounds greenpoint playground newtown barge terminal playgro little league field
Page 11: BOX STREET AND NEWTOWN BARGE PARKS · 5-7: existing site photo of newton barge terminal greenpoint playgrounds greenpoint playground newtown barge terminal playgro little league field

BOX STREET AND NEWTOWN BARGE PARKS: Timeline

Preliminary Design: Fall 2013

Final Design: Summer 2014

Construction Start: Spring 2015

Construction Complete: 2016

Page 12: BOX STREET AND NEWTOWN BARGE PARKS · 5-7: existing site photo of newton barge terminal greenpoint playgrounds greenpoint playground newtown barge terminal playgro little league field

Questions/comments:

[email protected]