benchmarks as a tool for free allocation through comparison with similar project.pdf
TRANSCRIPT
-
8/10/2019 Benchmarks as a tool for free allocation through comparison with similar Project.pdf
1/13
Benchmarks as a tool for free allocation through comparison with similar
projects: Focused on multi-family housing complex
Taehoon Hong, Choongwan Koo, Sungug Lee
Department of Architectural Engineering, Yonsei University, Seoul 120-749, Republic of Korea
h i g h l i g h t s
We propose the model for establishing benchmarks for free allowance allocation. The model can preliminarily estimate the amount of allowances in construction site.
The prediction performance of the proposed model is superior in all classification.
For the concrete, prediction accuracy and standard deviation are 93.45% and 6.01.
For the steel bar (94.20%; 4.34) and for the formwork (94.28%; 4.67), respectively.
a r t i c l e i n f o
Article history:
Received 14 May 2012
Received in revised form 12 September 2012
Accepted 13 October 2013
Keywords:
Emission trading schemeProcess-based LCA
Product-level LCA
Multi-family housings
Reinforced concrete frame
Case based reasoning
a b s t r a c t
A multilateral effort to reduce greenhouse gas (GHG) emissions has been implemented around the world.
In particular, the Emissions Trading Scheme (ETS) emerged as a market-based approach used to control
GHG emissions by providing carbon credits (or allowances). One of the most controversial issues in the
ETS is the question of how the allowances will be distributed. Therefore, this research aimed to develop a
decision support model for establishing benchmarks as a tool for free allocation in the construction
industry. It can be used in the pre-design phase to estimate the amount of allowances in a given construc-
tion site. In this study, a total of 147 types of data on the reinforced concrete frame in multi-family hous-
ing projects in South Korea were collected and used to develop the advanced Case-Based Reasoning
(CBR), which can be used to establish benchmarks as a tool for free allocation.
Results showed that the prediction performance of the advanced CBR model was superior (prediction
accuracy; standard deviation) in all classifications: concrete (93.45%; 6.01), steel bar (94.20%; 4.34), and
formwork (94.28%; 4.67). In the case study, a total of 60 possible combinations were evaluated in terms of
the economic and environmental impact simultaneously with the retrieved cases. The results of this
study could be expanded into other areas including new renewable energy, rehabilitation projects, and
demolition projects.
2013 Elsevier Ltd. All rights reserved.
1. Introduction
The rapid growth of cities and subsequent industrialization has
led to the rise of various environmental issues, such as globalwarming and depletion of resources. With the Kyoto Protocol in
1997, however, a multilateral effort to reduce greenhouse gas
(GHG) emissions has been implemented around the world [1,2].
Under the treaty, Annex I Parties (which consist of 37 industrial-
ized countries and the European Community) commit themselves
to binding targets for GHG emissions. Toward this end, the protocol
defines three flexibility mechanisms that can be used by Annex I
Parties[3]. The three flexibility mechanisms are Emissions Trading
Scheme (ETS), Clean Development Mechanism (CDM), and Joint
Implementation (JI). Among these, the ETS (or cap-and-trade) is a
market-based approach used to control GHG emissions by provid-
ing carbon credits (or allowances) as economic incentives for
achieving the emissions reduction target. That is to say, nationsthat emit less than their quota will be able to sell the emission
credits to nations whose emissions exceed their quota [4,5].
One of the most controversial issues in the ETS is the question of
how the allowances will be distributed. Since the ETS creates a sig-
nificant value, decisions about the allocation of allowances in es-
sence result in arguable issues. It involves whether or not to
freely allocate the allowances, whether or not to auction the allow-
ances, or whether or not to use a combination of free allocation and
auctioning[6]. Emerging programs have changed in the transition
from free allocation to auction over time. A combination of both
free allocation and partial auction offers flexibility in order to
achieve environmental and economic objectives[7,8]. For example,
0306-2619/$ - see front matter 2013 Elsevier Ltd. All rights reserved.http://dx.doi.org/10.1016/j.apenergy.2013.10.035
Corresponding author. Tel.: +82 2 2123 5788; fax: +82 2 2248 0382.
E-mail address:[email protected](T. Hong).
Applied Energy 114 (2014) 663675
Contents lists available at ScienceDirect
Applied Energy
j o u r n a l h o m e p a g e : w w w . e l s e v i e r . c o m / l o c a t e / a p e n e r g y
http://dx.doi.org/10.1016/j.apenergy.2013.10.035mailto:[email protected]://dx.doi.org/10.1016/j.apenergy.2013.10.035http://www.sciencedirect.com/science/journal/03062619http://www.elsevier.com/locate/apenergyhttp://www.elsevier.com/locate/apenergyhttp://www.sciencedirect.com/science/journal/03062619http://dx.doi.org/10.1016/j.apenergy.2013.10.035mailto:[email protected]://dx.doi.org/10.1016/j.apenergy.2013.10.035http://-/?-http://-/?-http://-/?-http://-/?-http://crossmark.crossref.org/dialog/?doi=10.1016/j.apenergy.2013.10.035&domain=pdfhttp://-/?- -
8/10/2019 Benchmarks as a tool for free allocation through comparison with similar Project.pdf
2/13
in the first and second trading periods of the European Union Emis-
sions Trading Scheme (EU-ETS), the majority of emission allow-
ances have been freely given to entities covered under the
program, according to historical emissions. In the third trading per-
iod of the EU-ETS, free allocation of emission allowances will be
progressively replaced by auctioning of the allowances by 2020.
Yet, free allocation will surely continue to play a significant
role up to 2020. The proposal is being negotiated in the EuropeanParliament[9].
Within a free allocation, there may be a variety of acceptable
ways to distribute allowances: (i) grandfathering, allowances
based on historical emissions; and (ii) benchmarking, allowances
based on energy input or product output [9]. When allowances are
freely given to entities, the following requirements should be met.
They should be allocated in a manner that is fair, transparent, and
ambitious. In other words, the allocation approach needs to allow
entities getting a strong incentive for the achieving GHG emissions
reduction target. In this regard, free allocation based on historical
emissions called grandfathering is potentially problematic. Un-
der the free allocation method of grandfathering, most allowances
are assigned to the entities that have emitted most. To make the
ETS more efficient and effective, however, free allocation should
levy penalty on those who have emitted most. This can be achieved
through free allocation based on energy input or product output
called benchmarking. Theoretically, this can find the optimal
solution for allowance allocation that is fair, transparent, and
ambitious. Yet there remain considerable challenges in designing
an allocation scheme and in determining concrete values as the ac-
tual benchmarks [9,10].
South Koreas National Assembly passed legislation, The Act on
Allocation and Trading of Greenhouse Gas Emissions Allowances,
which would set the GHG emissions reduction target starting in
2015. It applies both to entities that emit more than 125,000 tCO2-eq./yr and to factories or buildings that produce more than 25,000
tCO2eq./yr. About 95% of allowances will be allocated for free to
companies, factories, or buildings for the first period (2015
2017) and the second period (20182020)[11]. To keep pace withthe current trend, the construction industry has taken various ac-
tions to reduce GHG emissions in buildings. The South Korean gov-
ernment has conducted a variety of research to establish the
allocation methods that are appropriate for the characteristics of
the construction industry. In particular, due to the uniqueness of
the construction site, which is substantially different from the
characteristics of the manufacturing industry, both policymakers
and construction entities are becoming more interested in the
benchmarking approach for allowance allocation.
Therefore, this research aimed to develop a decision support
model for establishing benchmarks as a tool for free allocation in
the construction industry. It can be used in the pre-design phase
to estimate the amount of allowances for each product (e.g., con-
crete, steel bar, or formwork) that is produced, transported, andconstructed in a given construction site. Along with this, it can pre-
liminarily estimate the construction cost that is required to achieve
the level of benchmark for allowance allocated to a given
construction site. Using the model developed in this study, both
policymakers and construction entities can establish in advance
the level of benchmark for allowance allocation specified to a given
construction site and negotiate it with each other. Also, construc-
tion entities can assess eco-friendly technologies under budget
constraints.
The scope of this study is limited to conduct the economic and
environmental impact assessment at the sites of construction pro-
jects, especially the collection of materials, which are assembled
into a reinforced concrete frame in multi-family housing complex
projects. Toward this end, the product-level LCA method wasadopted to conduct environmental impact assessment. The
product-level LCA method is one of the four-level methods (i.e.,
material-level, product-level, building-level, and industry-level)
to conduct an LCA, and is calculated as a collection of materials,
which are assembled into a final product. After a quantity takeoff
of the product is completed, the amount of the emissions from
each component of the product is determined. The detailed infor-
mation on the product-level LCA method can be founded in [12].
It has a limitation in analyzing all materials, and, thus, the mainmaterials that occupy a considerable amount of the total environ-
mental load should be determined. As proposed by [13], the
environmental load evaluation of a standard apartment unit in
Korea shows that the total ratio of CO2emissions by concrete, steel
bar, and formwork accounts for 70.12% of total CO2 emissions
generated during the construction phase of a reinforced concrete
frame in a multi-family housing complex. As provided by [12],
the ATHENA
Impact Estimator covers around 1200 assemblies,
consisting mainly of concrete, steel, and wood products used in
foundations and structural assemblies. Accordingly, this study se-
lected concrete, steel bar, and formwork as the main materials
for the reinforced concrete frame of a multi-family housing project.
Also, the process-based LCA method was implemented as a cra-
dle-to-gate approach for assessing the environmental load from
the material manufacturing through the on-site construction of
the building project. The process-based LCA method is one of the
two methods to conduct an LCA, and focuses on a specific product
rather than a sector. Accordingly, the major advantage of this
method is the ability to compare two products that have the same
function. The detailed information on the process-based LCA meth-
od can be founded in[12]. Since collection of the detailed design
information for performing energy simulation is limited in the
pre-design phase, an analysis of the operational environmental
load during the operation and maintenance phases was excluded
from this study.
Meanwhile, Case-Based Reasoning (CBR), one of the data-min-
ing methods, was adopted to establish the level of benchmark for
allowance allocation specified to a given construction site. CBR
has a powerful advantage because it cannot only present the pre-dicted value, but also historical data as references. Based on this
feature, policymakers or construction entities can estimate the le-
vel of benchmark for a given project by comparison with similar
projects that are retrieved through the CBR algorithm. In other
words, the CBR is characterized by suggesting the prediction re-
sults with a high explanatory power based on historical data. De-
spite such advantages of CBR, its prediction accuracy is inferior
to that of the other methodologies, such as Multiple Regression
Analysis (MRA) and Artificial Neural Network (ANN). To improve
prediction accuracy, MRA and ANN were integrated to filtering
the prediction results generated by CBR. Also, Genetic Algorithm
(GA) was used to apply the concept of optimization. The research
team names a series of processes in the advanced CBR model.
Additional information on the advanced CBR model can be foundin previous studies conducted by the research team [14,15].
In this study, a total of 147 project characteristics and quantity
data were collected on the reinforced concrete frame in multi-fam-
ily housing projects in South Korea. This study was carried out in
three steps: (i) the collected data were analyzed at the level of
the main materials (i.e., concrete, steel bar, and formwork) to
establish the case base; then, by using the advanced CBR model,
the quantity of the main materials is estimated; (ii) using the esti-
mated quantity, the construction costs and CO2 emissions in the
material manufacturing through on-site construction were esti-
mated; and (iii) based on the estimated construction costs and
CO2 emissions, the study proposed possible combinations on
which the economic and environmental impact assessment was
performed. The detailed input data can be found in Table S1 ofthe supplementary data.
664 T. Hong et al. / Applied Energy 114 (2014) 663675
http://-/?-http://-/?-http://-/?-http://-/?- -
8/10/2019 Benchmarks as a tool for free allocation through comparison with similar Project.pdf
3/13
The advanced CBR model for economic and environmental
impact assessment in the pre-design phase, which this study pro-
poses, can be characterized as follows:
Using this model, both policymakers and construction enti-
ties can establish in advance the level of benchmark for
allowance allocation specified to a given construction site
and negotiate it with each other. This model estimates the construction costs and CO2emis-
sions based on the available information at the pre-design
phase, so it can save time and effort in terms of efficiency. This model improves prediction accuracy on material quan-
tity by using the advanced CBR model with a combination
of various methodologies, including MRA, ANN, and GA,
as well as CBR in terms of effectiveness.
The proposed model suggests not only the quantity as the
result of a simple prediction, but also shows the character-
istics of the projects performed in the past, because users
can compare several design options by changing the project
characteristics or selecting more optimal options among
the retrieved cases. For example, if high-strength concrete
is used, its CO2 emissions per unit quantity can be applied
to analyze the change in the final result. By using a Microsoft Excel-based VBA, the proposed model
systemizes the complicated process and equation to calcu-
late CO2emissions; and finally. It is expected that more products or assemblies can be eval-
uated using the proposed model.
2. Literature review
2.1. Life cycle assessment for buildings
Many studies have assessed the environmental load to whole
buildings and assemblies by using the internationally recognized
Life Cycle Assessment (LCA) methodology. First, various studies
have been conducted to assess CO2 emissions from buildings.These assessments evaluated greenhouse gas emissions based on
classification standards, such as structural type, plan type, activity,
construction method, or structural strength. A detailed examina-
tion of the energy and greenhouse emissions associated with the
construction of alternative structural systems, such as wood, steel,
and concrete structural assemblies, was analyzed [16]. The com-
parison of the environmental effects of steel- and concrete-framed
buildings has been analyzed according to all life-cycle phases [17].
The environmental performance of high-strength concrete used in
super tall buildings was evaluated using the suitable LCA method
by life-cycle phases[18]. The economic and environmental assess-
ment of green roof systems or energy-saving techniques for build-
ings was conducted by using life cycle cost (LCC) and life cycle CO2
(LCCO2) analysis [1922]. Several studies on the effect of energy-saving and CO2 emissions reduction in the operation and mainte-
nance phase were carried out by using LCC, LCCO 2, or LCA[2328].
Second, there have been several studies that were focused on
developing the model for conducting LCA. A simple life cycle CO2assessment system was proposed to assess GHG emissions in the
life cycle phases of a standard Korean apartment[13,29]. A hybrid
approach, combining both process-based LCA (P-LCA) and eco-
nomic inputoutput LCA (EIO-LCA), has also been proposed
[30,31]. A new LCA approach for buildings, called region-based life
cycle impact assessment (R-LCIA), has likewise been proposed,
which consists of the local environmental burden (EB) and at-
tached EB[32]. The relevance of simplified LCA of building compo-
nents, which aims at providing results of similar quality as
comprehensive assessments with less effort, has been analyzed[33]. The LCI model was formed as a global methodology that
combined advanced optimization techniques, LCI, and cost-benefit
assessment, including boundary conditions for thermal comfort,
indoor air quality, and legal requirements for energy performance
[34].The integrated model for assessing the cost and CO2emission
(IMACC) was developed for sustainable structural design in ready-
mix concrete[35].
Third, the environmental assessment tools were examined and
analyzed in terms of their characteristics and limitations in con-ducting building environmental assessment. The role and limita-
tions of current environmental building assessment methods in
identifying building sustainability were analyzed from the per-
spective of different countries[36]. The foundations for the devel-
opment of an LCA program for buildings were established with a
comparison of domestically and foreign designed programs [37].
A review of recent developments of LCA methods was carried
out, focusing on areas where there has been significant methodo-
logical development in recent years[38]. The field of building envi-
ronmental assessment tools was clarified and discussed in terms of
the differences of the tools as a group rather than as individual fac-
tors. For example, a classification system, Assessment Tool Typol-
ogy, was introduced by the ATHENA Institute, which has three
levels: (i) Level 1 was defined as product comparison tools and
information sources (e.g.,BEES); (ii) Level 2, whole building design
or decision support tools (e.g.,ATHENA); and (iii) Level 3, whole
building assessment frameworks or systems (e.g., LEED
)[39]. The
detailed analysis on the tools can be found in Table S2 of the
supplementary data.
As mentioned above, most of the previous studies have focused
on assessing the environmental load of entire buildings or assem-
blies, but not on estimating it in the early stage of a project. In
other words, the current environmental assessment tools for build-
ings could be used after completing the detailed design, based on
the bill of quantity. Accordingly, it is determined that they have
shortcomings that could demand a considerable amount of time
and effort in assessing the environmental load, and could not be
also used in the early phase of a project. Additionally, they could
not be used to establish benchmarks as a tool for free allocationsof GHG emissions permits in the construction industry.
2.2. Preliminary estimation in the early stages of the construction
project
There are many studies on preliminary estimation in the early
stages of the construction project. Most of the previous studies
have focused on cost estimation or energy consumption prediction.
Detailed literature reviews on cost estimation can be found in the
previous studies conducted by the research team[15,40]and those
on energy consumption prediction have been also conducted
[14,25,26]. The estimation of the material quantities in the early
stages was often carried out by using data-mining methodologies,
such as MRA, ANN, and CBR in previous studies. First, the MRAmethod was used to estimate material quantities by parametric
statistical equations. Then[41]developed the early cost estimating
models for road construction projects and[42]proposed a concep-
tual cost-estimate model for bridge foundations based on the esti-
mation of materials quantities.
Second, the ANN method was used to estimate the material
quantities by repetitively performing machine learning.[43]devel-
oped a system to assist in the early cost estimation of road tunnels;
[44] established the relationship between the quantities of con-
crete and form-work required for the structural elements of
high-rise commercial buildings;[45]proposed the logarithm-neu-
ron network to improve its efficiency and accuracy in quantity esti-
mation of steel and RC buildings; and[46]developed the model for
identifying and controlling the variances in the quantity of anywork package of building construction projects.
T. Hong et al./ Applied Energy 114 (2014) 663675 665
http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?- -
8/10/2019 Benchmarks as a tool for free allocation through comparison with similar Project.pdf
4/13
-
8/10/2019 Benchmarks as a tool for free allocation through comparison with similar Project.pdf
5/13
ton/m2 under the ratio scale. Then, the study collected related data
on the project characteristics and the quantity of the reinforced
concrete frame of 147 multi-family housing projects. Based on
the collected data, a database was established.
4.2. Retrieval of similar cases
There were various methodologiesCBR, MRA, ANN, or decision
treethat could be applied to the quantity estimation of the rein-
forced concrete frame of a multi-family housing project during the
pre-design phase. However, the construction materials and meth-
ods can be changed, depending on the characteristics of a project.
Moreover, if new techniques or methods are applied to a project, it
will be difficult to produce an accurate result with a simple estima-
tion. In other words, even with an identical material quantity, the
construction costs and CO2 emissions may differ. To reflect such
changes in the characteristics of a project, it is necessary to propose
a model that can present not only the prediction result, but also the
characteristics of previous projects. This study selected CBR as a
methodology to satisfy such requirements. To improve prediction
accuracy, the study also used the advanced CBR model that com-
bined various methodologies including MRA, ANN, and GA.
The CBR methodology consists of three phases: the attribute
similarity, the case similarity, and the prediction performance.The attribute similarity can be calculated by the differences in
the independent variables between the test and the retrieved
cases, which can be shown in Eq.(1). The case similarity can be cal-
culated by using the attribute similarity and attribute weight of all
attributes, which can also be shown in Eq.(2). Finally, the predic-
tion performance can be calculated by the differences in the
dependent variables between the test and retrieved cases, as
shown in Eqs.(3) and (4).
fASx 100 jAVTest CaseAVRetrieved Case j
AVTest Case 100
if fASxPMCAS
0 if fASx
-
8/10/2019 Benchmarks as a tool for free allocation through comparison with similar Project.pdf
6/13
PVANNis the predicted value of the ANN model, and SERANN is the
standard error rate of the ANN model.
MaxMinPRMRA; MinPRANN 6 CRMA6 MinMaxPRMRA; MaxPRANN
7
MinCRMA 1 TRCRMA100
6 CRMA
6 MaxCRMA 1 TRCRMA100
8
whereCRMA is the cross-range between the predicted value of the
MRA and ANN models, TRCRMAis the tolerance range of CRMA, and
CRMA is the filtering range in which TRCRMA was applied to CRMA.
5. Calculation of construction costs and CO2 emissions
5.1. Calculation of construction costs
Construction cost can be calculated by multiplying the esti-
mated quantity by unit cost of each main material. This study se-lected concrete, steel bar, and formwork as the main materials
[13,29]. With the process in Section 4, the study estimated the
quantity of the main materials as well as the construction cost
by using the unit cost of each main material, as shown in following
equation:
Construction Cost Xni1
EMQi UCi 9
whereEMQ is the estimated material quantity, UCis the unit cost,
and n is the number of main materials including concrete, steel
bar, and formwork in this research.
5.2. Calculation of CO2 emissions
CO2 emissions can be calculated as material manufacturing,
material transportation, and on-site construction according to the
material life cycle [12]. (i) In the material manufacturing phase,
CO2 emissions are calculated by using the estimated quantity and
Life Cycle Inventory (LCI), as shown in Eq. (10). In the material
transportation phase, CO2 emissions are calculated by using the
estimated quantity, the load capacity and the fuel efficiency of
the transportation vehicle, transportation distance, and the CO2conversion factor, as shown in Eq.(11). In the on-site construction
phase, CO2emissions are calculated by the estimated quantity, the
energy consumption per unit quantity of the construction equip-
ment, and the CO2conversion factor, as shown in Eq.(12). A Micro-
soft Excel-based VBA was used in this series of processes toproduce the final result in a systematic, accurate, easy and quick
manner.
CMXni1
EMQi CCFi 10
where CM is the carbon dioxide emission in material manufactur-
ing, EMQ is the estimated material quantity, CCF is the carbon
dioxide conversion factor, and n is the number of materials.
CTXni1
EMQiELCi
TDi 2EFEi
CCFi 11
whereCTis the carbon dioxide emission in material transportation,
EMQis the estimated material quantity, ELC is the equipment loadcapacity, TD is the one-way transportation distance, EFE is the
equipment fuel efficiency,CCFis the carbon dioxide conversion fac-
tor, and n is the number of materials.
CCXni1
EMQi ECUQi CCFi 12
where CCis the carbon dioxide emission in on-site construction,
EMQis the estimated material quantity, ECUQ is the energy con-sumption per unit quantity, CCF is the carbon dioxide conversion
factor, and n is the number of materials.
6. Prediction performance
Table 2shows that the prediction performance of the advanced
CBR model is superior (prediction accuracy; standard deviation) in
all classifications: concrete (93.45%; 6.01); steel bar (94.20%; 4.34);
and formwork (94.28%; 4.67). In the case of the steel bar, the pre-
diction accuracy of the advanced CBR was somewhat smaller
(94.20%) than that of the ANN model (94.60%). However, this re-
mains an excellent result, an improvement over the prediction
accuracy of the CBR model. This result is identical to the resultsverified in previous studies that used the advanced CBR model
[14,15,25,26]. The advanced CBR model is a sophisticated model
that offers both higher explanatory power, which is an advantage
of the CBR methodology, and higher prediction accuracy, which
is an advantage of MRA, ANN, and other methodologies.
The proposed advanced CBR model is based on the CBR model,
and since more cases are accumulated in the case base, prediction
performance will be more accurate.
7. Case study
A case study was conducted to verify the reliability and applica-
bility of the proposed advanced CBR model for the economic and
environmental impact assessment in the pre-design phase.
To acquire the representability of the case study, the study se-
lected a case that is close to the average quantity per unit area of
each main materialconcrete, steel bar, and formworkas its
test case. The test case has the following characteristics: rein-
forced concrete as the type of structure; 0.6407 m3/m2 as the
quantity of concrete per unit area (14.25% less than 0.7472 on
average); 0.0795 ton/m2 as the quantity of steel bar per unit area
(1.23% more than 0.0785 on average); 5.3885 m2/m2 as the quan-
tity of formwork per unit area (8.85% less than 5.9116 on aver-
age); 4251 m2 of the total floor area (17.21% less than 5135 m 2
on average); and 56 households (4.66% less than 58.74 on
average).
Table 2
Prediction performance by model.
Classification Methodology Prediction accuracy Standard deviation
Concrete MRA 89.40 6.27
ANN 91.75 5.95
CBR 91.97 9.57
Advanced CBR 93.45 6.01
Steel bar MRA 93.03 5.23
ANN 94.60 4.37
CBR 92.69 7.02
Advanced CBR 94.20 4.34
Formwork MRA 90.95 4.91
ANN 94.18 4.15
CBR 93.07 7.59
Advanced CBR 94.28 4.67
668 T. Hong et al. / Applied Energy 114 (2014) 663675
-
8/10/2019 Benchmarks as a tool for free allocation through comparison with similar Project.pdf
7/13
In this research, the streamlined LCA process was conducted by
following four steps stipulated by ISO 14040: (1) goal and scope
definition; (2) inventory analysis; (3) impact assessment; and (4)
results and interpretations[12].
Step 1. Goal and scope definition: based on the information
available in the pre-design phase, the CO2emissions gener-
ated from the material manufacturing phase to the on-siteconstruction phase are calculated and analyzed along with
the estimated construction costs. An economic and envi-
ronmental impact assessment is subsequently performed. Step 2. Inventory analysis: the CO2 emissions per unit
quantity of the main materials of the reinforced concrete
frame of a multi-family housing are calculated using an
inter-industry analysis (domestic and overseas).
Step 3. Impact assessment: to assess global warming
potential, CO2 emissions produced in step 2 are used as a
representative index. Other greenhouse gases, such as
methane (CH4), nitrous oxide (N2O), are included in this
category, thus the term CO2 equivalent is implemented
to express an impact, and not an emission.
Step 4. Results and interpretations: using the estimated
construction cost and CO2 emissions, an economic and
environmental impact assessment is performed.
Fig. 3 shows the diagram of the scenario for the use of LCA,
based on the above four-phase LCA process in this study. The dia-
gram signifies a system boundary that dictates the breadth and
depth of the LCA process. It consists of five categories, including life
cycle phase, building systems, life cycle inventory, life cycle im-
pact, and the phase during which LCA is conducted.
7.1. Estimation of material quantities using the advanced CBR model
Tables 35 show the estimations of material quantities using
the advanced CBR model: (i) in the case of concrete (refer toTable 3), two cases were retrieved. The average prediction accuracy
was 91.43%, at which the average quantity per unit area was
0.6956 m3/m2; (ii) in the case of the steel bar (refer to Table 4), five
cases were retrieved. The average prediction accuracy was 96.78%,
at which the average quantity per unit area was 0.0791 ton/m2;
and (iii) in the case of the formwork (refer to Table 5), six cases
were retrieved. The average prediction accuracy was 95.43%, at
which the average quantity per unit area was 5.6314 m2/m2.Tables
35show the detailed description of each retrieved case.
7.2. Calculation of construction costs
Construction costs can be calculated by multiplying the
estimated quantity by the unit cost (refer to Eq.(9)).Table 6shows
the detailed explanation of the description, unit, and unit cost
of each main material[50]. For example, the quantity of concrete
is 2724.06 m3. Considering that the unit cost of concrete is
US$52.49/m3, and then the construction cost of concrete is
US$142997.85. The same process can be applied to the steel bar
and the formwork, so the construction cost for each of the two
materials is US$227308.86 and US$590983.74, respectively.
7.3. Calculation of CO2emissions
7.3.1. Material manufacturing phase
In the material manufacturing phase, the CO2emissions for the
estimated quantity based on the advanced CBR model can be calcu-
lated using the LCI (refer to Eq. (10)). Table 7 shows the carbon
dioxide conversion factor of the main materialsconcrete, steel
bar, and formwork. This study established the CO2 emissions per
unit quantity by main material through an inter-industry analysis
(domestic and overseas) [18] and a detailed description by main
material based on the data applied to the test case.
7.3.2. Material transportation phase
In the material transportation phase, the CO2 emissions for the
estimated quantity based on the advanced CBR model can becalculated using the characteristics of each transportation vehicle
(e.g., load capacity, fuel efficiency, transportation distance, and
Fig. 3. Scenario for the use of LCA.
T. Hong et al./ Applied Energy 114 (2014) 663675 669
http://-/?-http://-/?- -
8/10/2019 Benchmarks as a tool for free allocation through comparison with similar Project.pdf
8/13
CO2 conversion factor (diesel, 2.5841 kgCO2/))[17],[29]and[32]
(refer to Eq. (11)).Table 8 shows the characteristics of the trans-portation vehicle used in this study. Based on the data applied to
the test case, this study established the characteristics of the trans-
portation vehicles (such as the type of transportation vehicles ortransportation distances).
Table 3
The retrieved cases using the advanced CBR model (concrete).
Variable Case
No.
Total
floor
area
(m2)
Exclusive
use area
(m2)
Common
use area
(m2)
Building
area
(m2)
Ground
floor
area
(m2)
Standard
floor area
(m2)
No. of
stories
No. of
households
Size of
households
Case
similarity
score
Quantity
per unit
area (m3/
m2)
Prediction
accuracy
(%)
Test case 84 4251.78 3349.75 966.56 340.22 173.80 299.12 15 56 59 0.6407
Retrieved
case 1
6 4282.81 3349.64 1095.92 391.82 173.74 298.09 15 57 59 0.96 0.6916 92.05
Retrieved
case 2
37 3979.24 3110.49 897.52 340.22 37.49 299.12 15 52 59 0.96 0.6996 90.81
Average quantity per unit area 0.6956 91.43
Table 4
The retrieved cases using the advanced CBR model (steel bar).
Variable Case
No.
Total
floor
area
(m2)
Exclusive
use area
(m2)
Common
use area
(m2)
Building
area
(m2)
Ground
floor
area
(m2)
Standard
floor area
(m2)
No. of
stories
No. of
households
Size of
households
Case
similarity
score
Quantity
per unit
area
(ton/m2)
Prediction
accuracy
(%)
Test case 84 4251.78 3349.75 966.56 340.22 173.80 299.12 15 56 59 0.0795
Retrieved
case 1
85 4692.62 3351.04 964.88 380.32 210.22 329.48 15 56 59 0.92 0.0773 97.23
Retrieved
case 2
103 4823.90 3470.72 1133.32 376.20 211.18 329.48 15 58 59 0.90 0.0760 95.56
Retrieved
case 3
102 4823.90 3470.72 1133.32 376.20 211.18 329.48 15 58 59 0.90 0.0779 97.98
Retrieved
case 4
108 3807.54 2692.80 879.30 376.20 211.18 265.27 15 45 59 0.87 0.0828 95.81
Retrieved
case 5
82 4005.64 3110.82 897.52 466.28 248.69 299.12 15 52 59 0.83 0.0816 97.31
Average quantity per unit area 0.0791 96.78
Table 5
The retrieved cases using the advanced CBR model (formwork).
Variable Case
No.
Total
floorarea
(m2)
Exclusive
use area(m2)
Common
use area(m2)
Building
area(m2)
Ground
floorarea
(m2)
Standard
floor area(m2)
No. of
stories
No. of
households
Size of
households
Case
similarityscore
Quantity
per unitarea (m2/
m2)
Prediction
accuracy(%)
Test case 84 4.251.78 3.349.75 966.56 340.22 173.80 299.12 15 56 59 5.3885
Retrieved
case 1
105 4282.81 3.349.64 1.095.92 391.82 173.74 298.09 15 57 59 0.98 5.8145 92.10
Retrieved
case 2
85 4.692.62 3.351.04 964.88 380.32 210.22 329.48 15 56 59 0.95 5.3780 99.81
Retrieved
case 3
99 4347.00 3.469.27 1.135.06 427.32 173.74 298.09 15 58 59 0.94 5.7707 92.91
Retrieved
case 4
103 4.823.90 3.470.72 1.133.32 376.20 211.18 329.48 15 58 59 0.92 5.4436 98.98
Retrieved
case 5
102 4.823.90 3.470.72 1.133.32 376.20 211.18 329.48 15 58 59 0.92 5.6421 95.29
Retrieved
case 6
108 3.807.54 2.692.80 879.30 376.20 211.18 265.27 15 45 59 0.90 5.7397 93.48
Average quantity per unit area 5.6314 95.43
Table 6
Unit cost by main material.
Main materials Description Unit Quantity Unit cost (US$) Construction cost (US$)
Concrete Ready mixed concrete m3 2724.06 52.49 142997.85
Steel bar Deformed steel bar ton 337.94 672.64 227308.86
Formwork Plywood m2 22910.88 25.79 590983.74
Note: The exchange rate (KRW/USD) is 1116.5 won to a US dollar (as of 5 March 2012). The quantity is based on the actual value of the main materials of Case No. 84, which is
the test case of the case study.
670 T. Hong et al. / Applied Energy 114 (2014) 663675
-
8/10/2019 Benchmarks as a tool for free allocation through comparison with similar Project.pdf
9/13
7.3.3. On-site construction phase
In the on-site construction phase, the CO2emissions for the esti-
mated quantity based on the advanced CBR model can be calcu-
lated using the characteristics of each construction equipment
(e.g., energy consumption per unit quantity, CO2conversion factor
(electricity, 0.4705 kgCO2/kW h; diesel, 2.5841 kgCO2/)) [29]
(refer to Eq. (12)). Table 9 shows the characteristics of the
construction equipment used in this study, which was limited to
the equipment commonly used in the reinforced concrete frame,
the tower crane for lifting materials, the hoist for lifting workers,
the pump car for pouring concrete, and the vibrator for consolidat-
ing concrete.
7.3.4. Total amount of CO2emissionsTables 1012show the total amount of CO2emissions from the
material manufacturing phase to the on-site construction phase by
using the estimated quantity based on the advanced CBR model.
The results of the analysis on the main materials (concrete, steel
bar, and formwork) are shown inTables 10, 11 or 12, respectively.
7.4. Economic and environmental impact assessment
As illustrated in Section7.1, the quantity per unit area for the
main materials (i.e., concrete, steel bar, and formwork) in the rein-
forced concrete frame of a multi-family housing project was esti-
mated. Based on these results, the construction costs and CO2emissions by main material were calculated in Sections 7.2 and
7.3. However, when more than one retrieved case is presenteddue to the characteristics of the CBR methodology, the final result
can be presented as a range instead. Table 13shows the range of
the estimates of the construction cost and CO2 emissions by main
material. Here, the unit of the construction cost is $1K, and that of
the CO2emissions is tCO2.
As shown inTable 13, the best estimate of the construction cost
for the concrete was 155.26 with a range of 154.37156.14. The
best estimate of the CO2 emissions for the concrete was 567.65
with a range of 564.40570.92. The same type of result was pre-
sented for the steel bar and the formwork. Finally, the estimated
results of each main material were summed together to calculate
the total construction cost and CO2 emissions. As mentioned in
Section 1, however, this study analyzed the main materials (i.e.,
concrete, steel bar, and framework) that occupy a considerable
amount of the total environmental load of a standard apartment
unit in Korea, which accounts for 70.12% of total CO2 emissions
generated from a reinforced concrete frame in a multi-family hous-
ing complex. Therefore, the results mentioned above have been
converted into a percentage. The best estimate of the totalconstruction cost resulted in 1424.87 with a range of 1371.11
1469.87. The best estimate of the total CO2 emissions resulted in
3314.97 with a range of 3195.543428.95.
The final decision-maker (i.e., policymakers or construction
entities) can establish the target construction costs and CO2emis-
sions of a given project in the pre-design phase by using the result
presented. However, the result may be different depending on the
decision made by the final decision-maker (refer to Fig. 4).Fig. 4
shows 60 possible combinations of the estimated construction
costs and CO2 emissions in the scatter diagram. In the case study
of this research, two similar cases were retrieved for the concrete,
five cases for steel bar, and six cases for formwork. Thus, the case
study had 60 possible combinations (2 5 6; refer toTables 35).
As shown inFig. 4, the low and high estimates are located in the
bottom left-hand corner and the upper right-hand corner of the
scatter diagram, respectively, while the best estimate is in the cen-
ter of the scatter diagram because it is the average value. However,
Fig. 4shows that the actual value of the test case (Case No. 84) is
located very closely to the low estimate. This result may differ on
a case-to-case basis. Thus, depending on the criteria of the final
decision-maker, the difference between the target value and the
actual value of the construction costs and CO2 emissions may be
changed.
Figs. 5 and 6show the difference between the target and actual
values (test case) of the construction costs and CO2 emissions,
depending on the final decision-maker. Figs. 5 and 6 also show
the most similar case proposed by the advanced CBR model: the
case with the highest case similarity score (Scenario 1). In terms
of the economic impact, the construction cost showed an error of+3.94%, +0.01%, +7.22% and +5.39% for the best estimate, the low
estimate (Scenario 8; here, Scenario 8 means a combination of the
1st ranked retrieved cases for the concrete, the 2nd ranked for the
steel bar, and the 2nd ranked for the formwork, which is abbrevi-
ated as C1 + S2 + F2), high estimate (scenarios 49; C2 + S4 + F1),
and the 1st case similarity (scenario 1; C1 + S1 + F1), respectively.
In terms of the environmental impact, CO2 emissions showed an
error of +3.21%, 0.51%, +6.75%, and +3.29%, respectively (refer to
Fig. 6).
Such results can be changed depending on the attributes of var-
ious factors, such as estimated quantity, the type of material and
Table 7
CO2emission per unit quantity by main material in the material manufacturing stage.
Main materials Detailed description CO2 emission per unit quantity
Co ncre te Ready mi xed con cre te 18 6. 493 kg CO2/m3
Steel bar Deformed s teel bar 3.052 kgCO2/kg
Formw ork W at erproof plywood 1.516 kg CO2/kg
Table 8
The characteristics of transportation vehicle by main material in material transportation stage.
Main materials Transport vehicle Load capacity Fuel efficiency (km/) Tra nsport ation d istance s ( km) Powe r sourc e
Concrete Ready mixed concrete truck 6 m3 (13.11 ton) 2.44 8.66 Diesel
Steel bar 20 ton trailer 20 ton 3.1 82.85 Diesel
Formwork 8 ton truck 8 ton 4.5 43.92 Diesel
Table 9
The characteristics of the construction equipment by main material in the on-site construction stage.
Main materials Construction equipment
Tower crane (kW h/ton, electricity) Hoist (kW h/ton, electricity) Pump car (/ton, diesel) Vibrator (/ton, diesel)
Concrete 0.553 0.238 0.183
Steel bar 1.354 0.553
Formwork 1.354 0.553
T. Hong et al./ Applied Energy 114 (2014) 663675 671
http://-/?-http://-/?-http://-/?-http://-/?-http://-/?-http://-/?- -
8/10/2019 Benchmarks as a tool for free allocation through comparison with similar Project.pdf
10/13
equipment, unit cost, or carbon dioxide conversion factor. There-
fore, the economic and environmental assessment should consider
the characteristics of a given project. The result should be used to
establish the target criteria for the construction costs and CO2
emissions of the given project.
8. Conclusions and discussion
The objective of this study is to develop a decision support
model for establishing benchmarks as a tool for free allocation in
the construction industry, which can be used in the pre-design
phase. The scope of this study is limited to conduct the economic
and environmental impact assessment at the sites of construction
projects, especially the collection of materials that are assembled
into a reinforced concrete frame in multi-family housing complex
projects.
The process-based LCA method was implemented as a cradle-
to-gate approach to assess the environmental load from the mate-
rial manufacturing phase to the on-site construction phase of abuilding project. The product-level LCA method was also adopted
to calculate the collection of materials, which are assembled into
the reinforced concrete frame in a multi-family housing project.
Material quantity was estimated using the advanced CBR model
that was proposed in this study. A total of 147 project characteris-
tics and quantity data were collected on the reinforced concreteframe in multi-family housing projects in South Korea. This study
was carried out in three steps: (i) the collected data were analyzed
at the level of the main materials (i.e., concrete, steel bar, and form-
work) to establish the case base and the quantity of the main mate-
rials is estimated using the advanced CBR model; (ii) using the
estimated quantity, the construction costs and CO2 emissions in
the material manufacturing phase to the on-site construction
phase were estimated; and (iii) based on the estimated construc-
tion costs and CO2 emissions, the study proposed possible
combinations on which the economic and environmental impact
assessment was performed.
A case study was conducted to verify the reliability and applica-
bility of the advanced CBR model, which was proposed for the eco-
nomic and environmental impact assessment in the pre-design
phase of the construction project. The results are discussed below.
Table 10
Total amount of CO2 emission (concrete).
Variable Case
No.
Quantity per unit area (m3/
m2)
Amount of CO2 emission (kgCO2)
Material
manufacturing
Material
transportation
On-site
construction
Total amount of CO2emission
Test case 84 0.6407 508028.46 8346.0076 6489.31 522863.78
Retrieved case 1 6 0.6916 548388.46 9006.3510 7004.84 564399.65
Retrieved case 2 37 0.6996 554731.87 9098.0654 7085.87 570915.81
Average 0.6956 551560.17 9043.0368 7045.36 567648.56
Note: If the quantity per unit area (0.6916 m3/m2) of the concrete in Retrieved Case 1 (Case No. 6) is applied to the total floor area of the test case (Case No. 84) (4251.78 m 2)
(refer toTable 3), the total quantity of the concrete will be 2940.53 m3. Applying this result to the CO2emission per unit quantity (186,493 kg of CO2/m3) in the manufacturing
stage of concrete, which is shown inTable 7, produces 548388.49 kg of CO2.Tables 8 and 9can be used to calculate the total amount of CO2emissions in the stages of material
transportation and on-site construction. As a result, the total amount of CO2emission of Retrieved Case 1 (Case No. 6) is 564399.65 kg of CO2. Such a process can be equally
applied to the steel bar (refer to Table 11) and formwork (refer toTable 12).
Table 11
Total amount of CO2 emission (steel bar).
Variable Case
No.
Quantity per unit area
(ton/m2)
Amount of CO2 emission (kgCO2)
Material
manufacturing
Material
transportation
On-site
construction
Total amount of CO2emission
Test case 84 0.0795 1031626.39 2348.1133 239.81 1034214.31Retrieved case 1 85 0.0773 1003078.24 2348.1133 233.18 1005659.53
Retrieved case 2 103 0.0760 986208.87 2348.1133 229.25 988786.24
Retrieved case 3 102 0.0779 1010864.10 2348.1133 234.99 1013447.20
Retrieved case 4 108 0.0828 1074448.62 2486.2376 249.77 1077184.62
Retrieved case 5 82 0.0816 1058876.90 2486.2376 246.15 1061609.28
Average 0.0791 1026435.82 2348.1133 238.61 1029022.53
Table 12
Total amount of CO2 emission (formwork).
Variable Case
No.
Quantity per unit area
(m2/m2)
Amount of CO2 emission (kgCO2)
Material
manufacturing
Material
transportation
On-site
construction
Total amount of CO2emission
Test case 84 5.3885 691965.38 2925.6147 345.41 695236.41Retrieved case 1 105 5.8145 752680.99 3228.2644 375.24 756284.50
Retrieved case 2 85 5.3780 684307.93 2875.1730 342.08 687525.19
Retrieved case 3 99 5.7707 748351.68 3127.3812 372.98 751852.04
Retrieved case 4 103 5.4436 697713.27 2925.6147 348.38 700987.27
Retrieved case 5 102 5.6421 729053.32 3076.9396 363.57 732493.82
Retrieved case 6 108 5.7397 734998.11 3127.3812 367.05 738492.55
Average 5.6314 738331.49 3127.3812 368.45 741827.32
672 T. Hong et al. / Applied Energy 114 (2014) 663675
-
8/10/2019 Benchmarks as a tool for free allocation through comparison with similar Project.pdf
11/13
First, the study applied the advanced CBR model to each of the
main materials of the reinforced concrete frame of a multi-family
housing project. The result showed that the prediction perfor-
mance of the advanced CBR model was superior to that of the other
models (i.e., MRA, ANN, or CBR) (refer toTable 2). The result proved
that the advanced CBR model is a sophisticated model that offers
both higher explanatory power, which is the advantage of the
CBR methodology, and higher prediction accuracy, which is the
advantage of MRA, ANN, and other methodologies.
Second,using theestimatedquantity bythe advancedCBR model,
thestudy could estimatethe constructioncosts andCO2 emissionsof
each main material. Particularly, CO2 emissions were subdivided
into the material manufacturing phase, the material transportation
phase, and the on-site construction phase so as to systematically
and accurately calculate the result. Toward this end, the Microsoft
Excel-based VBA was used in this series of processes.
Third, possible combinations were constructed based on the
estimated construction costs and CO2 emissions, which were the
object of the economic and environmental impact assessment.
The result was presented both in a scatter diagram and in a bar
chart. In this way, the study offered visible and concrete references
to support final decisions. In other words, policymakers and
Table 13
Range of estimates of the construction cost and CO 2 emission by main material.
Main materials Evaluation index Estimates range (70.12%) Estimates range (100%)
Best Low High Best Low High
Concrete Construction cost 155.26 154.37 156.14 221.42 220.15 222.68
CO2 emission 567.65 564.4 570.92 809.54 804.91 814.20
Steel bar Construction cost 226.24 217.22 236.83 322.65 309.78 337.75
CO2 emission 1029.02 988.79 1077.18 1467.51 1410.14 1536.20
Formwork Construction cost 617.62 589.83 637.7 880.80 841.17 909.44
CO2 emission 727.79 687.53 756.28 1037.92 980.50 1078.55
Total Construction cost 999.12 961.42 1030.67 1424.87 1371.11 1469.87
CO2 emission 2324.46 2240.71 2404.38 3314.97 3195.54 3428.95
Note: The unit of the construction cost is US$1K and the unit of the CO 2 emissions is tCO2.
Fig. 4. Scatter diagram of estimated construction costs and CO2emissions.
Fig. 5. Comparison of estimated construction costs in terms of economic impact.
T. Hong et al./ Applied Energy 114 (2014) 663675 673
http://-/?-http://-/?-http://-/?- -
8/10/2019 Benchmarks as a tool for free allocation through comparison with similar Project.pdf
12/13
construction entities can establish in advance the level of bench-
mark for allowance allocation specified to a given construction site
and negotiate it with each other. Also, it is expected that construc-
tion entities can assess the eco-friendly technologies under budget
constraints by changing the project characteristics or selecting
more optimal choices among the retrieved cases.
With the reinforced concrete frame of a multi-family housing
project, this study limited its scope to performing the economic
and environmental impact assessment during the pre-design
phase. To complement this studys limitation, the following re-
search efforts are currently being conducted by the research
team:
Extended research on finishing and mechanical electrical
plumbing, other than the reinforced concrete frame of a
multi-family housing project.
Research on the establishment of assembly costs and CO2
emissions data at the level of building components (e.g.,wooden wall, concrete roof, etc.) to perform economic
and environmental impact assessment in the schematic
design phase. Research on performing an economic and environmental
impact assessment according to changes in the structural
type, plan type, activity, construction method, or structural
strength. Research on multilateral impact categories based on the
factors affecting life cycle impact assessment, such as glo-
bal warming potential, acidification potential, eutrophica-
tion potential, and ozone depletion potential. Research related to expansion into other areas, such as new
renewable energy sources, rehabilitation projects, and
demolition projects.
Acknowledgements
This research was supported by Basic Science Research Program
through the National Research Foundation of Korea (NRF) funded
by the Ministry of Education, Science and Technology (Nos.
2012-004376 and 2012-0001247).
Appendix A. Supplementary material
Supplementary data associated with this article can be found, in
the online version, at http://dx.doi.org/10.1016/j.apenergy.2013.10.035.
References
[1] Sayigh A. Renewable energy the way forward. Appl Energy 1999;64:1530.
[2] rge-Vorsatz D, Harvey LDD, Mirasgedis S, Levine MD. Mitigating CO2emissions from energy use in the worlds buildings. Build Res Inform2007;35(4):37998.
[3] Bashmakov I, Jepma C. Climate Change 2001 (6. Policies, Measures, andInstruments). The IPCC Third Assessment Report (TAR) Work Group III (WG3),2001.
[4] Bartels M, Msgens F. Is a cap-and-trade system always efficient? The case ofnew entrants in the emissions trading system of the EU. J Energy Eng2008;134:339.
[5] Cl S. The effectiveness of the EU emissions trading scheme. Clim Policy2009;9:22741.
[6] C2ES. Greenhouse Gas Emissions Allowance Allocations (PreliminarySeptember 2007 version). Center for Climate and Energu Solutions; 2007.
[7] Sijm JPM, Hers JS, Lise W. The implications of free allocation versus auctioningof EU ETS allowances for the power sector in the Netherlands. Energy ResearchCenter of the Netherlands (ECN); 2008.
[8] Wrke M, Myers E, Burtraw D, Mandell S, Holt C. Opportunity cost for freeallocations of emissions permits: an experimental analysis. Environ ResourceEcon 2010;46:3316.
[9] DEHSt. Benchmarks as a Tool for Allocation in the Future EU ETS. GermanEmissions Trading Authority (DEHSt) at the Federal Environment Agency,Germany; 2009.
[10] Groenenberg H, Blok K. Benchmark-based emission allocation in a cap-and-trade system. Clim Policy 2020;2(1):105109.
[11] The 18th Korean Congress. The Act on Allocation and Trading of GreenhouseGase Emission Allowances; 2012.
[12] AIA. A Guide to Life Cycle Assessment of Buildings. New York (United States):The American Institute of Architects; 2010.
[13] Shin S, Tae S, Woo J, Roh S. The development of environmental load evaluationsystem of a standard Korean apartment house. Renew Sustain Energy Rev2011;15(2):123949.
[14] Hong T, Koo C, Jeong K. A decision support model for reducing electric energyconsumption in elementary school facilities. Appl Energy 2012;95(7):25366.
[15] Koo C, Hong T, Hyun C. The development of a construction cost predictionmodel with improved prediction capacity using the advanced CBR approach.Expert Syst Appl 2011;38(7):8597606.
[16] Cole RJ. Energy and greenhouse gas emission associated with the construction
of alternative structural systems. Build Environ 1998;34(3):33548.[17] Guggemos AA, Horvath A. Comparison of environmental effects of steel- andconcrete-framed buildings. J Infrastructure Syst 2005;11(2):93101.
[18] Tae S, Baek C, Shin S. Life cycle CO2 evaluation on reinforced concretestructures with high-strength concrete. Environ Impact Assess Rev2011;31(3):25360.
[19] Hong T, Kim J, Koo C. LCC and LCCO2 analysis of green roofs in elementaryschools with energy saving measures. Energy Build 2012;45(2):22939.
[20] Kim J, Hong T, Koo C. Economic and environmental evaluation model forselecting the optimum design of green roof systems in elementary schools.Environ Sci Technol 2012;46(15):847583.
[21] Saiz S, Kennedy C, Bass B, Presssnail K. Comparative life cycle assessment ofstandard and green roofs. Environ Sci Technol 2006;40:43126 .
[22] Hong T, Kim H, Kwak T. Energy-saving techniques for reducing CO2Emission inelementary schools. J Manage Eng 2012;28(1):112.
[23] Ortiz O, Castells F, Sonnemann G. Operational energy in the life cycle ofresidential dwellings: the experience of Spain and Colombia. Appl Energy2010;87(2):67380.
[24] Chantrelle FP, Lahmidi H, Keilholz W, Mankibi ME, Michel P. Development of a
multicriteria tool for optimizing the renovation of buildings. Appl Energy2011;88(4):138694.
Fig. 6. Comparison of estimated CO2 emissions in terms of environmental impact.
674 T. Hong et al. / Applied Energy 114 (2014) 663675
http://dx.doi.org/10.1016/j.apenergy.2013.10.035http://dx.doi.org/10.1016/j.apenergy.2013.10.035http://refhub.elsevier.com/S0306-2619(13)00855-6/h0005http://refhub.elsevier.com/S0306-2619(13)00855-6/h0010http://refhub.elsevier.com/S0306-2619(13)00855-6/h0010http://refhub.elsevier.com/S0306-2619(13)00855-6/h0010http://refhub.elsevier.com/S0306-2619(13)00855-6/h0010http://refhub.elsevier.com/S0306-2619(13)00855-6/h0015http://refhub.elsevier.com/S0306-2619(13)00855-6/h0015http://refhub.elsevier.com/S0306-2619(13)00855-6/h0015http://refhub.elsevier.com/S0306-2619(13)00855-6/h0015http://refhub.elsevier.com/S0306-2619(13)00855-6/h0020http://refhub.elsevier.com/S0306-2619(13)00855-6/h0020http://refhub.elsevier.com/S0306-2619(13)00855-6/h0020http://refhub.elsevier.com/S0306-2619(13)00855-6/h0025http://refhub.elsevier.com/S0306-2619(13)00855-6/h0025http://refhub.elsevier.com/S0306-2619(13)00855-6/h0025http://refhub.elsevier.com/S0306-2619(13)00855-6/h0030http://refhub.elsevier.com/S0306-2619(13)00855-6/h0030http://refhub.elsevier.com/S0306-2619(13)00855-6/h0030http://refhub.elsevier.com/S0306-2619(13)00855-6/h0030http://refhub.elsevier.com/S0306-2619(13)00855-6/h0035http://refhub.elsevier.com/S0306-2619(13)00855-6/h0035http://refhub.elsevier.com/S0306-2619(13)00855-6/h0035http://refhub.elsevier.com/S0306-2619(13)00855-6/h0040http://refhub.elsevier.com/S0306-2619(13)00855-6/h0040http://refhub.elsevier.com/S0306-2619(13)00855-6/h0040http://refhub.elsevier.com/S0306-2619(13)00855-6/h0045http://refhub.elsevier.com/S0306-2619(13)00855-6/h0045http://refhub.elsevier.com/S0306-2619(13)00855-6/h0050http://refhub.elsevier.com/S0306-2619(13)00855-6/h0050http://refhub.elsevier.com/S0306-2619(13)00855-6/h0055http://refhub.elsevier.com/S0306-2619(13)00855-6/h0055http://refhub.elsevier.com/S0306-2619(13)00855-6/h0055http://refhub.elsevier.com/S0306-2619(13)00855-6/h0055http://refhub.elsevier.com/S0306-2619(13)00855-6/h0055http://refhub.elsevier.com/S0306-2619(13)00855-6/h0060http://refhub.elsevier.com/S0306-2619(13)00855-6/h0060http://refhub.elsevier.com/S0306-2619(13)00855-6/h0060http://refhub.elsevier.com/S0306-2619(13)00855-6/h0060http://refhub.elsevier.com/S0306-2619(13)00855-6/h0065http://refhub.elsevier.com/S0306-2619(13)00855-6/h0065http://refhub.elsevier.com/S0306-2619(13)00855-6/h0065http://refhub.elsevier.com/S0306-2619(13)00855-6/h0065http://refhub.elsevier.com/S0306-2619(13)00855-6/h0070http://refhub.elsevier.com/S0306-2619(13)00855-6/h0070http://refhub.elsevier.com/S0306-2619(13)00855-6/h0075http://refhub.elsevier.com/S0306-2619(13)00855-6/h0075http://refhub.elsevier.com/S0306-2619(13)00855-6/h0075http://refhub.elsevier.com/S0306-2619(13)00855-6/h0075http://refhub.elsevier.com/S0306-2619(13)00855-6/h0080http://refhub.elsevier.com/S0306-2619(13)00855-6/h0080http://refhub.elsevier.com/S0306-2619(13)00855-6/h0080http://refhub.elsevier.com/S0306-2619(13)00855-6/h0080http://refhub.elsevier.com/S0306-2619(13)00855-6/h0085http://refhub.elsevier.com/S0306-2619(13)00855-6/h0085http://refhub.elsevier.com/S0306-2619(13)00855-6/h0085http://refhub.elsevier.com/S0306-2619(13)00855-6/h0085http://refhub.elsevier.com/S0306-2619(13)00855-6/h0085http://refhub.elsevier.com/S0306-2619(13)00855-6/h0085http://refhub.elsevier.com/S0306-2619(13)00855-6/h0085http://refhub.elsevier.com/S0306-2619(13)00855-6/h0080http://refhub.elsevier.com/S0306-2619(13)00855-6/h0080http://refhub.elsevier.com/S0306-2619(13)00855-6/h0080http://refhub.elsevier.com/S0306-2619(13)00855-6/h0075http://refhub.elsevier.com/S0306-2619(13)00855-6/h0075http://refhub.elsevier.com/S0306-2619(13)00855-6/h0075http://refhub.elsevier.com/S0306-2619(13)00855-6/h0070http://refhub.elsevier.com/S0306-2619(13)00855-6/h0070http://refhub.elsevier.com/S0306-2619(13)00855-6/h0065http://refhub.elsevier.com/S0306-2619(13)00855-6/h0065http://refhub.elsevier.com/S0306-2619(13)00855-6/h0065http://refhub.elsevier.com/S0306-2619(13)00855-6/h0060http://refhub.elsevier.com/S0306-2619(13)00855-6/h0060http://refhub.elsevier.com/S0306-2619(13)00855-6/h0060http://refhub.elsevier.com/S0306-2619(13)00855-6/h0055http://refhub.elsevier.com/S0306-2619(13)00855-6/h0055http://refhub.elsevier.com/S0306-2619(13)00855-6/h0055http://refhub.elsevier.com/S0306-2619(13)00855-6/h0055http://refhub.elsevier.com/S0306-2619(13)00855-6/h0050http://refhub.elsevier.com/S0306-2619(13)00855-6/h0050http://refhub.elsevier.com/S0306-2619(13)00855-6/h0045http://refhub.elsevier.com/S0306-2619(13)00855-6/h0045http://refhub.elsevier.com/S0306-2619(13)00855-6/h0040http://refhub.elsevier.com/S0306-2619(13)00855-6/h0040http://refhub.elsevier.com/S0306-2619(13)00855-6/h0040http://refhub.elsevier.com/S0306-2619(13)00855-6/h0035http://refhub.elsevier.com/S0306-2619(13)00855-6/h0035http://refhub.elsevier.com/S0306-2619(13)00855-6/h0030http://refhub.elsevier.com/S0306-2619(13)00855-6/h0030http://refhub.elsevier.com/S0306-2619(13)00855-6/h0030http://refhub.elsevier.com/S0306-2619(13)00855-6/h0025http://refhub.elsevier.com/S0306-2619(13)00855-6/h0025http://refhub.elsevier.com/S0306-2619(13)00855-6/h0025http://refhub.elsevier.com/S0306-2619(13)00855-6/h0020http://refhub.elsevier.com/S0306-2619(13)00855-6/h0020http://refhub.elsevier.com/S0306-2619(13)00855-6/h0015http://refhub.elsevier.com/S0306-2619(13)00855-6/h0015http://refhub.elsevier.com/S0306-2619(13)00855-6/h0015http://refhub.elsevier.com/S0306-2619(13)00855-6/h0010http://refhub.elsevier.com/S0306-2619(13)00855-6/h0010http://refhub.elsevier.com/S0306-2619(13)00855-6/h0010http://refhub.elsevier.com/S0306-2619(13)00855-6/h0005http://dx.doi.org/10.1016/j.apenergy.2013.10.035http://dx.doi.org/10.1016/j.apenergy.2013.10.035 -
8/10/2019 Benchmarks as a tool for free allocation through comparison with similar Project.pdf
13/13
[25] Hong T, Koo C, Park S. A decision support model for improving a multi-familyhousing complex based on CO2 emission from gas energy consumption. BuildEnviron 2012;52(6):14251.
[26] Hong T, Koo C, Kim H. A decision support model for improving a multi-familyhousing complex based on CO2 emission from electricity consumption. JEnviron Manage 2012;112(15):6778.
[27] Lee C, Hong T, Lee G, Jeong J. Life cycle cost analysis on glass type of high-risebuildings for increasing energy efficiency and reducing CO2 emissions inKorea. J Constr Eng Manage 2012. [Available, online 24 October 2011].
[28] Jing YY, Bai H, Wang JJ, Liu L. Life cycle assessment of a solar combined cooling
and heating and power system in different operation strategies. Appl Energy2012;92:84353.
[29] Tae S, Shin S, Woo J, Roh S. The development of apartment house life cycle CO 2simple assessment system using standard apartment house of South Korea.Renew Sustain Energy Rev 2011;15(3):145467.
[30] Bilec MM, Ries RJ, Matthews HS, Sharrard AL. Example of a hybrid life-cycleassessment of construction processes. J Infrastructure Syst2006;12(4):20715.
[31] Bilec MM, Ries RJ, Matthews HS. Life-cycle assessment modeling ofc onstruc tion p roce sses f or build ings. J Infrastruct ure Sy st2010;16(3):199205.
[32] Li Z. A new life cycle impact assessment approach for buildings. Build Environ2006;41(10):141422.
[33] Kellenberger D, Althaus HJ. Relevance of simplifications in LCA of buildingcomponents. Build Environ 2009;44(4):81825.
[34] Cerbeeck G, Hens H. Life cycle inventory of buildings: a calculation method.Build Environ 2010;45(4):103741.
[35] Hong T, Ji C, Park H. Integrated Model for Assessing the Cost and CO 2Emission(IMACC) for sustainable structural design in ready-mix concrete. J Environ Eng2012;103:18.
[36] Ding GKC. Sustainable constructionthe role of environmental assessmenttools. J Environ Manage 2008;86(3):45164.
[37] Lee K, Tae S, Shin S. Development of a life cycle assessment program forbuilding (SUSB-LCA) in South Korea. Renew Sustain Energy Rev2009;13(8):19942002.
[38] Finnveden G, Hauschild MZ, Ekvall T, Guinee J, Heijungs R, Ekvall T, et al.Recent developments in life cycle assessment. J Environ Manage2009;91:121.
[39] Haapio A, Viitaniemi P. A critical review of building environmental assessmenttools. Environ Impact Assess Rev 2008;28:46982.
[40] Koo C, Hong T, Hyun C, Koo K. A CBR-based hybrid model for prediction aconstruction duration and cost based on project characteristics in multi-familyhousing projects. Can J Civ Eng 2010;37(5):73952.
[41] Mahamid I. Early cost estimating for road construction projects using multipleregression techniques. Australasian J Constr Econ Build 2011;11(4):87101.
[42] Fragkakis N, Lambropoulos S, Tsiambaos G. Parametric model for conceptualcost estimation of concrete bridge foundations. J Infrastructure Syst2011;17(2):6674.
[43] Petroutsatou K, Georgopoulos E, Lambropoulos S, Pantouvakis JP. Early costestimating of road tunnel construction using neural networks. J Constr EngManage 2012;138(6):67987.
[44] Tam CM, Fang CF. Comparative cost analysis of using high-performanceconcrete in tall building construction by artificial neural networks. ACI Struct J1999;96(6):92736.
[45] Yeh IC. Quantity estimating of building with logarithm-neuron networks. JConstr Eng Manage 1998;124(5):37480.
[46] Al-Tabtabai H, Kartam N, Alex AP. Neural networks for the identification andcontrol of quantity variance in construction projects. Computing in, Civil Eng1996:22732.
[47] Hong T, Hyun C, Moon H. CBR-based cost prediction model-II of the designphase f or multi-fa mily housing proje ct s. Expe rt S yst A pp l2011;38(3):2797808.
[48] Kang T, Park W, Lee Y. Development of CBR-based road construction projectcost estimation system. In: Proceedings of the 28th international symposiumon automation and robotics in construction, ISARC 2011:13149.
[49] Kim D, Kim B, Han S. Two-staged early cost estimation for highwayconstruction projects. In: Proceedings of the 25th international symposiumon automation and robotics in construction, ISARC 2008:4905.
[50] Construction Association of Korea (CAK). Monthly Construction Market Price:477 October. Seoul, South Korea: Construction Association of Korea; 2010.
T. Hong et al./ Applied Energy 114 (2014) 663675 675
http://refhub.elsevier.com/S0306-2619(13)00855-6/h0090http://refhub.elsevier.com/S0306-2619(13)00855-6/h0090http://refhub.elsevier.com/S0306-2619(13)00855-6/h0090http://refhub.elsevier.com/S0306-2619(13)00855-6/h0090http://refhub.elsevier.com/S0306-2619(13)00855-6/h0090http://refhub.elsevier.com/S0306-2619(13)00855-6/h0095http://refhub.elsevier.com/S0306-2619(13)00855-6/h0095http://refhub.elsevier.com/S0306-2619(13)00855-6/h0095http://refhub.elsevier.com/S0306-2619(13)00855-6/h0095http://refhub.elsevier.com/S0306-2619(13)00855-6/h0095http://refhub.elsevier.com/S0306-2619(13)00855-6/h0100http://refhub.elsevier.com/S0306-2619(13)00855-6/h0100http://refhub.elsevier.com/S0306-2619(13)00855-6/h0100http://refhub.elsevier.com/S0306-2619(13)00855-6/h0105http://refhub.elsevier.com/S0306-2619(13)00855-6/h0105http://refhub.elsevier.com/S0306-2619(13)00855-6/h0105http://refhub.elsevier.com/S0306-2619(13)00855-6/h0105http://refhub.elsevier.com/S0306-2619(13)00855-6/h0110http://refhub.elsevier.com/S0306-2619(13)00855-6/h0110http://refhub.elsevier.com/S0306-2619(13)00855-6/h0110http://refhub.elsevier.com/S0306-2619(13)00855-6/h0115http://refhub.elsevier.com/S0306-2619(13)00855-6/h0115http://refhub.elsevier.com/S0306-2619(13)00855-6/h0115http://refhub.elsevier.com/S0306-2619(13)00855-6/h0120http://refhub.elsevier.com/S0306-2619(13)00855-6/h0120http://refhub.elsevier.com/S0306-2619(13)00855-6/h0125http://refhub.elsevier.com/S0306-2619(13)00855-6/h0125http://refhub.elsevier.com/S0306-2619(13)00855-6/h0130http://refhub.elsevier.com/S0306-2619(13)00855-6/h0130http://refhub.elsevier.com/S0306-2619(13)00855-6/h0135http://refhub.elsevier.com/S0306-2619(13)00855-6/h0135http://refhub.elsevier.com/S0306-2619(13)00855-6/h0135http://refhub.elsevier.com/S0306-2619(13)00855-6/h0135http://refhub.elsevier.com/S0306-2619(13)00855-6/h0135http://refhub.elsevier.com/S0306-2619(13)00855-6/h0140http://refhub.elsevier.com/S0306-2619(13)00855-6/h0140http://refhub.elsevier.com/S0306-2619(13)00855-6/h0145http://refhub.elsevier.com/S0306-2619(13)00855-6/h0145http://refhub.elsevier.com/S0306-2619(13)00855-6/h0145http://refhub.elsevier.com/S0306-2619(13)00855-6/h0150http://refhub.elsevier.com/S0306-2619(13)00855-6/h0150http://refhub.elsevier.com/S0306-2619(13)00855-6/h0150http://refhub.elsevier.com/S0306-2619(13)00855-6/h0150http://refhub.elsevier.com/S0306-2619(13)00855-6/h0150http://refhub.elsevier.com/S0306-2619(13)00855-6/h0155http://refhub.elsevier.com/S0306-2619(13)00855-6/h0155http://refhub.elsevier.com/S0306-2619(13)00855-6/h0155http://refhub.elsevier.com/S0306-2619(13)00855-6/h0160http://refhub.elsevier.com/S0306-2619(13)00855-6/h0160http://refhub.elsevier.com/S0306-2619(13)00855-6/h0160http://refhub.elsevier.com/S0306-2619(13)00855-6/h0165http://refhub.elsevier.com/S0306-2619(13)00855-6/h0165http://refhub.elsevier.com/S0306-2619(13)00855-6/h0170http://refhub.elsevier.com/S0306-2619(13)00855-6/h0170http://refhub.elsevier.com/S0306-2619(13)00855-6/h0170http://refhub.elsevier.com/S0306-2619(13)00855-6/h0175http://refhub.elsevier.com/S0306-2619(13)00855-6/h0175http://refhub.elsevier.com/S0306-2619(13)00855-6/h0175http://refhub.elsevier.com/S0306-2619(13)00855-6/h0180http://refhub.elsevier.com/S0306-2619(13)00855-6/h0180http://refhub.elsevier.com/S0306-2619(13)00855-6/h0180http://refhub.elsevier.com/S0306-2619(13)00855-6/h0180http://refhub.elsevier.com/S0306-2619(13)00855-6/h0185http://refhub.elsevier.com/S0306-2619(13)00855-6/h0185http://refhub.elsevier.com/S0306-2619(13)00855-6/h0190http://refhub.elsevier.com/S0306-2619(13)00855-6/h0190http://refhub.elsevier.com/S0306-2619(13)00855-6/h0190http://refhub.elsevier.com/S0306-2619(13)00855-6/h0190http://refhub.elsevier.com/S0306-2619(13)00855-6/h0190http://refhub.elsevier.com/S0306-2619(13)00855-6/h0190http://refhub.elsevier.com/S0306-2619(13)00855-6/h0185http://refhub.elsevier.com/S0306-2619(13)00855-6/h0185http://refhub.elsevier.com/S0306-2619(13)00855-6/h0180http://refhub.elsevier.com/S0306-2619(13)00855-6/h0180http://refhub.elsevier.com/S0306-2619(13)00855-6/h0180http://refhub.elsevier.com/S0306-2619(13)00855-6/h0175http://refhub.elsevier.com/S0306-2619(13)00855-6/h0175http://refhub.elsevier.com/S0306-2619(13)00855-6/h0175http://refhub.elsevier.com/S0306-2619(13)00855-6/h0170http://refhub.elsevier.com/S0306-2619(13)00855-6/h0170http://refhub.elsevier.com/S0306-2619(13)00855-6/h0170http://refhub.elsevier.com/S0306-2619(13)00855-6/h0165http://refhub.elsevier.com/S0306-2619(13)00855-6/h0165http://refhub.elsevier.com/S0306-2619(13)00855-6/h0160http://refhub.elsevier.com/S0306-2619(13)00855-6/h0160http://refhub.elsevier.com/S0306-2619(13)00855-6/h0160http://refhub.elsevier.com/S0306-2619(13)00855-6/h0155http://refhub.elsevier.com/S0306-2619(13)00855-6/h0155http://refhub.elsevier.com/S0306-2619(13)00855-6/h0150http://refhub.elsevier.com/S0306-2619(13)00855-6/h0150http://refhub.elsevier.com/S0306-2619(13)00855-6/h0150http://refhub.elsevier.com/S0306-2619(13)00855-6/h0145http://refhub.elsevier.com/S0306-2619(13)00855-6/h0145http://refhub.elsevier.com/S0306-2619(13)00855-6/h0145http://-/?-http://refhub.elsevier.com/S0306-2619(13)00855-6/h0140http://refhub.elsevier.com/S0306-2619(13)00855-6/h0140http://-/?-http://refhub.elsevier.com/S0306-2619(13)00855-6/h0135http://refhub.elsevier.com/S0306-2619(13)00855-6/h0135http://refhub.elsevier.com/S0306-2619(13)00855-6/h0135http://refhub.elsevier.com/S0306-2619(13)00855-6/h0135http://-/?-http://refhub.elsevier.com/S0306-2619(13)00855-6/h0130http://refhub.elsevier.com/S0306-2619(13)00855-6/h0130http://-/?-http://refhub.elsevier.com/S0306-2619(13)00855-6/h0125http://refhub.elsevier.com/S0306-2619(13)00855-6/h0125http://-/?-http://refhub.elsevier.com/S0306-2619(13)00855-6/h0120http://refhub.elsevier.com/S0306-2619(13)00855-6/h0120http://-/?-http://refhub.elsevier.com/S0306-2619(13)00855-6/h0115http://refhub.elsevier.com/S0306-2619(13)00855-6/h0115http://refhub.elsevier.com/S0306-2619(13)00855-6/h0115http://-/?-http://refhub.elsevier.com/S0306-2619(13)00855-6/h0110http://refhub.elsevier.com/S0306-2619(13)00855-6/h0110http://refhub.elsevier.com/S0306-2619(13)00855-6/h0110http://-/?-http://refhub.elsevier.com/S0306-2619(13)00855-6/h0105http://refhub.elsevier.com/S0306-2619(13)00855-6/h0105http://refhub.elsevier.com/S0306-2619(13)00855-6/h0105http://-/?-http://refhub.elsevier.com/S0306-2619(13)00855-6/h0100http://refhub.elsevier.com/S0306-2619(13)00855-6/h0100http://refhub.elsevier.com/S0306-2619(13)00855-6/h0100http://-/?-http://-/?-http://refhub.elsevier.com/S0306-2619(13)00855-6/h0095http://refhub.elsevier.com/S0306-2619(13)00855-6/h0095http://refhub.elsevier.com/S0306-2619(13)00855-6/h0095http://refhub.elsevier.com/S0306-2619(13)00855-6/h0095http://-/?-http://refhub.elsevier.com/S0306-2619(13)00855-6/h0090http://refhub.elsevier.com/S0306-2619(13)00855-6/h0090http://refhub.elsevier.com/S0306-2619(13)00855-6/h0090http://refhub.elsevier.com/S0306-2619(13)00855-6/h0090http://-/?-