11/13/2015 ieng 471 facilities planning 1 ieng 471 - lecture 03 product & process design

26
06/27/22 IENG 471 Facilities Planning 1 IENG 471 - Lecture 03 Product & Process Design

Upload: juniper-jennings

Post on 04-Jan-2016

220 views

Category:

Documents


5 download

TRANSCRIPT

Page 1: 11/13/2015 IENG 471 Facilities Planning 1 IENG 471 - Lecture 03 Product & Process Design

04/20/23 IENG 471 Facilities Planning 1

IENG 471 - Lecture 03

Product & Process Design

Page 2: 11/13/2015 IENG 471 Facilities Planning 1 IENG 471 - Lecture 03 Product & Process Design

04/20/23 IENG 471 Facilities Planning 3

Product Design

Must meet the needs of the customerQFD

Must be communicated (internally)Product Drawings (Assembly, Detail)Parts ListPart Structure

Indented BOM covers both the parts list and part structure

Page 3: 11/13/2015 IENG 471 Facilities Planning 1 IENG 471 - Lecture 03 Product & Process Design

04/20/23 IENG 471 Facilities Planning 4

Indented Bill of Materials

A “BOM” is a document that:Lists all parts in an assemblyShows the quantity of all componentsAllows for the roll-up of costsShows the sequence of assembly

Each indentation shows the components of the sub-assembly

Page 4: 11/13/2015 IENG 471 Facilities Planning 1 IENG 471 - Lecture 03 Product & Process Design

04/20/23 IENG 471 Facilities Planning 5

Example: Manual Juicer

Page 5: 11/13/2015 IENG 471 Facilities Planning 1 IENG 471 - Lecture 03 Product & Process Design

04/20/23 IENG 471 Facilities Planning 6

Example: Manual Juicer

Page 6: 11/13/2015 IENG 471 Facilities Planning 1 IENG 471 - Lecture 03 Product & Process Design

04/20/23 IENG 471 Facilities Planning 7

Example: Manual Juicer

Function of the product:Obtain seed-free juice from produce

Principle(s) of operation:Lever (Class 2) to provide pressureGrating to stop seeds Gravity to drain the juice

Page 7: 11/13/2015 IENG 471 Facilities Planning 1 IENG 471 - Lecture 03 Product & Process Design

04/20/23 IENG 471 Facilities Planning 8

Example: Manual Juicer

Materials of construction:Aluminum (sandcast) bodyRubber feet

Cost of the artifact:$ 0.32 in aluminum$ 0.04 in rubber $ ??? in labor, shipping, packaging, etc.

Page 8: 11/13/2015 IENG 471 Facilities Planning 1 IENG 471 - Lecture 03 Product & Process Design

04/20/23 IENG 471 Facilities Planning 9

Indented BOM & Cost Roll-up:

(1) Juicer Assembly $ 0.36

(1) Body Sub Assembly $ 0.18

(1) Body Casting $ 0.14

(4) Rubber Feet $ 0.01

(1) Strainer Casting $ 0.05

(1) Lever Casting $ 0.10

(1) Hinge Pin $ 0.03

Example: Manual Juicer

Page 9: 11/13/2015 IENG 471 Facilities Planning 1 IENG 471 - Lecture 03 Product & Process Design

04/20/23 IENG 471 Facilities Planning 10

BOM Example in Excel

Quantity Description Cost

1 Juicer Assembly $0.36 . .

. 1 Body Sub-Assembly . $0.18 .

. . 1 Body Casting . . $0.14

. . 4 Rubber Feet . . $0.01

. 1 Strainer Casting . $0.05 .

. 1 Lever Casting . $0.10 .

 . 1   Hinge Pin . $0.03 .

Page 10: 11/13/2015 IENG 471 Facilities Planning 1 IENG 471 - Lecture 03 Product & Process Design

04/20/23 IENG 471 Facilities Planning 11

Process Design

Steps in Process Identification1. Define elemental operations

2. Identify alternative process(es) for each operation

3. Analyze alternative processes for each operation

4. Standardize processes for each operation

5. Evaluate alternative processes for overall production

6. Select processes for overall production

Page 11: 11/13/2015 IENG 471 Facilities Planning 1 IENG 471 - Lecture 03 Product & Process Design

04/20/23 IENG 471 Facilities Planning 12

Routing ExampleROUTING

PART NAME: Shaft, Vise PREPARED BY:   DATE:  

PART NUMBER:     DRAWING NUMBER:   GT CODE:  

MATERIAL: Brass   LABOR RATE:   TOTAL COST:  

    Process Parameters   Estimated  

Op. Speed Feed Depth Labor Setup    

No. Operation Description ft/min rpm ipr ipm in. Machine hrs. hrs Cost Remarks

1 Cut material from bar 150         band saw 0.10 0.10   Leave extra for machining

2 Face 1st end of shaft 150 900 0.005     lathe 0.20 0.05   take minimal needed for cleanup

3 Face 2nd end of shaft 150 900 0.005     lathe 0.20 0.05   cut to length per print

4 Turn diameter to length, rough 150 900 0.015     lathe 0.20 0.05   leave .03 for finish cut

5 Turn diameter to length, finish 150 900 0.005     lathe 0.10      

6 Cut groove 150 900 0.005     lathe 0.20 0.05    

7 Chamfer end of shaft 150 900 0.005     lathe 0.10 0.05    

8 Turn diameter to length, rough 150 900 0.015     lathe 0.20 0.05   leave .03 for finish cut

9 Turn diameter to length, finish 150 900 0.005     lathe 0.10      

10 Chamfer end of shaft 150 900 0.005     lathe 0.10 0.05    

11 Center drill end of shaft 150 900 0.010     lathe 0.10 0.10    

12 Drill hole in end 150 900 0.010     lathe 0.10 0.05   drill extra deep

13 Tap hole           lathe 0.10 0.10   hand tap, lots of oil

14 Center drill for cross hole 200 1200 0.006     mill 0.10 0.10    

15 Drill cross hole 200 1200 0.006     mill 0.10 0.05    

16 Chamfer cross hole 100 600 0.005     mill 0.05 0.05   both sides

Page 12: 11/13/2015 IENG 471 Facilities Planning 1 IENG 471 - Lecture 03 Product & Process Design

04/20/23 IENG 471 Facilities Planning 13

Operation Process Chart

Circles represent operations Number in circle represents standard operation Prefix in circle identifies:

Subassemblies (SA) – child levelsAssemblies (A) – parent level in this view

Circles are annotated with operation description

Boxes represent inspections Number in box represents standard operation Boxes are annotated with inspection description

Arcs (lines) represent component(s) Arcs are annotated with part number & description for

introduced components (See Figure 2.12 in text, p. 44)

Page 13: 11/13/2015 IENG 471 Facilities Planning 1 IENG 471 - Lecture 03 Product & Process Design

04/20/23 IENG 471 Facilities Planning 14

Example: Manual Juicer Operations-Process Chart

Body Casting

4001

Rubber Feet

4021

Strainer Casting

4002

Lever Casting

4003

Hinge Pin

4004

0101Trim, sand, inspect

0102Trim, inspect 0101

Trim, sand, inspect

0101Trim, sand, inspect

0101Trim, sand, inspect

A1

A2

Plastic Bag

4031

SA1

I1

Page 14: 11/13/2015 IENG 471 Facilities Planning 1 IENG 471 - Lecture 03 Product & Process Design

04/20/23 IENG 471 Facilities Planning 15

Standard OPC Symbols

Page 15: 11/13/2015 IENG 471 Facilities Planning 1 IENG 471 - Lecture 03 Product & Process Design

04/20/23 IENG 471 Facilities Planning 16

Process Design Result

The result of the process design can be a precedence diagram:Take the OPC and turn it on its’ side.

Connect the component arcs with a single operation (START), and you have a Precedence Diagram

The precedence diagram can be converted to a PERT chart for SCHEDULE DESIGN

Page 16: 11/13/2015 IENG 471 Facilities Planning 1 IENG 471 - Lecture 03 Product & Process Design

04/20/23 IENG 471 Facilities Planning 17

Example: Manual Juicer Precedence Diagram

4001

4021

4002

4003

4004

0101

0102

0101

0101

0101

A1 A2

4031

SA1

I10100

Page 17: 11/13/2015 IENG 471 Facilities Planning 1 IENG 471 - Lecture 03 Product & Process Design

18

PERT: Scheduling Terminology

Activity - A specific task or set of tasks that are required by the project, use up resources, and take time to complete

Event - The result of completing one or more activities. An identifiable end state occurring at a particular time. Events use no resources.

Network - The combination of all activities and events define the project and the activity precedence relationships

Meredith, J. R. & Mantel, S. J. (2006)

04/20/23 IENG 471 Facilities Planning

Page 18: 11/13/2015 IENG 471 Facilities Planning 1 IENG 471 - Lecture 03 Product & Process Design

19

PERT: Scheduling Terminology

Path - The series of connected activities (or intermediate events) between any two events in a network

Critical - Activities, events, or paths which, if delayed, will delay the completion of the project. A project’s critical path is understood to mean that sequence of critical activities that connect the project’s start event to its finish event

Meredith, J. R. & Mantel, S. J. (2006)

04/20/23 IENG 471 Facilities Planning

Page 19: 11/13/2015 IENG 471 Facilities Planning 1 IENG 471 - Lecture 03 Product & Process Design

20

PERT: Activity-on-Node Network Fundamentals

Y and Z are preceded by X

Y and Z can begin at thesame time, if you wish

(2)

A is preceded by nothingB is preceded by AC is preceded by B

(1)

J

J, K, & L can all begin atthe same time, if you wish(they need not occursimultaneously)

All (J, K, L) must becompleted before M canbegin

but

AA

(3)

(4)

Z is preceded by X and Y

AA is preceded by X and Y

Meredith, J. R. & Mantel, S. J. (2006)

04/20/23 IENG 471 Facilities Planning

Page 20: 11/13/2015 IENG 471 Facilities Planning 1 IENG 471 - Lecture 03 Product & Process Design

21

PERT: Activity on Node Notation

Early Start (ES) Early Finish (EF)

Activity Duration (D)

Late Start (LS) Late Finish (LF)

04/20/23 IENG 471 Facilities Planning

Page 21: 11/13/2015 IENG 471 Facilities Planning 1 IENG 471 - Lecture 03 Product & Process Design

22

PERT: Calculating ES and EF

Forward Pass Through Network: Move left to right, covering each simultaneous

activity in order ES = maximum of EF for all immediate predecessor

activities (0 for START activity) EF = ES + Duration

Critical Time = EF of the END activity

04/20/23 IENG 471 Facilities Planning

Page 22: 11/13/2015 IENG 471 Facilities Planning 1 IENG 471 - Lecture 03 Product & Process Design

23

PERT: Calculating LS and LF

Backward Pass Through Network: Move right to left, covering each simultaneous

activity in order LF = minimum of LS for all immediate successor

activities (Critical Time for END activity) LS = LF – Duration

Slack (Float) Time: LS – ES Note: Slack = 0 for Critical Activities

04/20/23 IENG 471 Facilities Planning

Page 23: 11/13/2015 IENG 471 Facilities Planning 1 IENG 471 - Lecture 03 Product & Process Design

PERT: Critical Path Example

24

A 1

B 3

C 3

D 2

F 1

E 4

G 1

H 1 Z 2

1 4 4 5 5 6

1 4

1 3 4 8

8 9

3 6 6 7 7 8

1 4

2 4 4 8

8 9 9 11

9 11

0 1

0 1

Critical Time = 11 sec

Critical Path = A, C, E, H, ZSlack B, F, G = 2 sec

Slack D = 1 sec

04/20/23 IENG 471 Facilities Planning

Page 24: 11/13/2015 IENG 471 Facilities Planning 1 IENG 471 - Lecture 03 Product & Process Design

25

PERT: Critical Path Management

CP are those activities where ES = LS Any delay in these activities will delay production! Wrong to say that these activities are the most

important, though:Frequently, activities with slack are put off until too late if

not monitored!Other paths may be near-critical, and will also delay the

project if not monitored!

04/20/23 IENG 471 Facilities Planning

Page 25: 11/13/2015 IENG 471 Facilities Planning 1 IENG 471 - Lecture 03 Product & Process Design

04/20/23 IENG 471 Facilities Planning 26

Tying Critical Path to Facilities

Critical Path is connected to Makespan If this were a repetitive operation environment:

Makespan is the total time for a single, physical unit to go through all operations

In manufacturing, the time difference between the start and finish of a sequence of jobs or tasks

In health care, the duration of a patient’s medical experience for a treatment episode

Team exerciseSuppose that you had to schedule people to produce a

product What would you do to operations on the CP? What might you do with non-CP operations?

Skorin-Kapov, J. & A. J. Vakharia

Page 26: 11/13/2015 IENG 471 Facilities Planning 1 IENG 471 - Lecture 03 Product & Process Design

04/20/23 IENG 471 Facilities Planning 27

Questions & Issues

HW 2: Hands on assignment to develop:

BOMOperations Process ChartPrecedence Diagram

Team exerciseTeams must be different from Project Teams

Semi-randomly assigned

4 people per team (5 people, if necessary)Other tools are in MIL Lab (IER 310)

Leave the tools there, but OK to take the product parts