Period: 3/19/20 - 3/25/20
Community High School District 99
Master Facility Plan Implementation
Wight Construction Services2500 North Frontage RoadDarien, IL 60561
Weekly Construction Progress Report
![Page 2: Weekly Construction Progress Report - Amazon Web Services · Weekly Construction Progress Report. Author: ielizondo Created Date: 3/26/2020 8:22:34 AM](https://reader030.vdocuments.us/reader030/viewer/2022040614/5f0a7e787e708231d42be8f1/html5/thumbnails/2.jpg)
Community High School District 99
Master Facility Plan Implementation
Downers Grove South High School
Phase B - Fine Arts Addition
360° Pictures: 1st Floor Alley 2nd Floor Bridge 2nd Floor Corridor 2nd Floor Classroom
• MEP/Fire Alarm/Fire Sprinkler Trades continue to work on rough-in.
• Piping insulation completed on the first floor.
• Controls for HVAC equipment in progress.
• DBM continues wall framing and Hargrave installs in-wall wood blocking.
• Lake Shore Glass is installing the glass at curtainwall locations.
• Waukegan Steel delivered the metal stair and started installation.
• Green Demolition is working on openings from school to new Arts Addition.
![Page 3: Weekly Construction Progress Report - Amazon Web Services · Weekly Construction Progress Report. Author: ielizondo Created Date: 3/26/2020 8:22:34 AM](https://reader030.vdocuments.us/reader030/viewer/2022040614/5f0a7e787e708231d42be8f1/html5/thumbnails/3.jpg)
Community High School District 99
Master Facility Plan Implementation
Downers Grove South High School
Phase B - Bleachers & Squad Rooms
• Dant Clayton working on visitor bleachers ramps and stairs.
• JWI completed the structure for the bleachers prior to start decking. Their crew returned homefor the week of 3/23/20 due to COVID-19 challenged for lodging and will be back week of3/30/20.
![Page 4: Weekly Construction Progress Report - Amazon Web Services · Weekly Construction Progress Report. Author: ielizondo Created Date: 3/26/2020 8:22:34 AM](https://reader030.vdocuments.us/reader030/viewer/2022040614/5f0a7e787e708231d42be8f1/html5/thumbnails/4.jpg)
Community High School District 99
Master Facility Plan Implementation
Downers Grove South High School
Phase C - Auditorium
• Arc 1 mobilized to the site to start removal/salvage of existing can light & controls to bedelivered to Downers Grove North.
• MG Mechanical started the gas piping relocation in the band hallway.
• Colfax started abatement of existing areas in preparation for new Phase C work. GBTA has beensupervising and monitoring work onsite.
• Weekly BIM coordination meetings are schedule with trade partners to resolve any futurepotential conflicts with MEP rough-in and equipment.
![Page 5: Weekly Construction Progress Report - Amazon Web Services · Weekly Construction Progress Report. Author: ielizondo Created Date: 3/26/2020 8:22:34 AM](https://reader030.vdocuments.us/reader030/viewer/2022040614/5f0a7e787e708231d42be8f1/html5/thumbnails/5.jpg)
Community High School District 99
Master Facility Plan Implementation
Downers Grove South High School
Phase C - Learning Commons
• Compass set control points and grid lines for layout in existing courtyard.
• Green Demolition completed demolition necessary for access to the courtyard.
• Kane County Excavating & Werner Nugent preparing to mobilize equipment to start demolition,excavation & underground utilities in the courtyard.
• Colfax removed existing window for access to courtyard from band hallway.
![Page 6: Weekly Construction Progress Report - Amazon Web Services · Weekly Construction Progress Report. Author: ielizondo Created Date: 3/26/2020 8:22:34 AM](https://reader030.vdocuments.us/reader030/viewer/2022040614/5f0a7e787e708231d42be8f1/html5/thumbnails/6.jpg)
Community High School District 99
Master Facility Plan Implementation
Downers Grove North High School
Phase B - Gym, Kitchen, Alley, Multipurpose,and Gymnastics Loft Addition
360° Pictures: Main Gym Kitchen Multi-Purpose Room Gymnastics Room
• Completed exterior brick work with the exception of where construction access ramp is. Masonshave moved into the building for interior CMU walls.
• Poured gym slab on grade. All interior concrete work has been completed.
• Overhead MEP rough in continues to progress on both floors.
• Roofers have completed the high roof and are working on the lower roof currently. Currentlyscheduled to have the roof complete next week.
• Metal framing throughout 2nd floor continues to progress along with in wall rough in.
![Page 7: Weekly Construction Progress Report - Amazon Web Services · Weekly Construction Progress Report. Author: ielizondo Created Date: 3/26/2020 8:22:34 AM](https://reader030.vdocuments.us/reader030/viewer/2022040614/5f0a7e787e708231d42be8f1/html5/thumbnails/7.jpg)
Community High School District 99
Master Facility Plan Implementation
Downers Grove North High School
Phase B - Bleachers & Squad Rooms
• Home bleachers will be complete with all 180 ea rammed aggregate piers this week. Will beginbleacher foundations next week.
• Visitor Bleacher will complete concrete foundations next week, followed by the remainingbleacher assembly.
![Page 8: Weekly Construction Progress Report - Amazon Web Services · Weekly Construction Progress Report. Author: ielizondo Created Date: 3/26/2020 8:22:34 AM](https://reader030.vdocuments.us/reader030/viewer/2022040614/5f0a7e787e708231d42be8f1/html5/thumbnails/8.jpg)
Community High School District 99
Master Facility Plan Implementation
Downers Grove North High School
Phase C - Cafeteria, Culinary Arts, Commons,and Southeast Addition
• Installed temp fence, removed trees & shrubs, and removed 1 story building.
• Performing environmental abatement ahead of schedule with school being closed. Currentlyscheduled to jump ahead with abatement scheduled for beginning of summer.
• Weekly BIM coordination meetings are schedules with Trade Partners to identify and resolve anypotential conflicts with rough-in and equipment location in the field.
360° Pictures: Servery Commons