WEEKLY CONSTRUCTION PROGRESS REPORT Project: Mary Lin Elementary School This Week’s Activities March 17 – March 21 I. Phase 1 - Site Work
• Site utilities demolition ongoing. • Site work/grading ongoing. • Existing Detention Pond expansion completed. • New Storm System installation off Candler Park ongoing.
II. Phase 2B – Interior
• Kitchen/Cafeteria demolition ongoing. • Interior demolition at lower level Stucco building ongoing.
Figure 2- New Storm System – Candler Park Dr. Figure 1- New Storm System – Candler Park Dr.
![Page 2: WEEKLY CONSTRUCTION PROGRESS REPORT Project: Mary Lin … · 2014. 3. 24. · WEEKLY CONSTRUCTION PROGRESS REPORT . Project: Mary Lin Elementary School This Week’s Activities](https://reader036.vdocuments.us/reader036/viewer/2022062509/610b3a0ea207172bac75c6f7/html5/thumbnails/2.jpg)
WEEKLY CONSTRUCTION PROGRESS REPORT
Figure 3- Interior Demolition Figure 4- Interior Demolition
Figure 3 – Interior Demolition Figure 4 – Cooler/Freezer Demoed.
Next Week’s Activities – Site Work March 24 – March 28
• Parking lot- dirt excavation to continue. • Interior demolition to continue. • Installation of new storm system off Candler Park Dr. to continue.