brown middle school weekly construction report · weekly construction report may 6 , 2016 page 2...
TRANSCRIPT
Brown Middle School
Weekly Construction Report May 6, 2016
Page 1
Brown Middle School Weekly Progress Report 5/6/2016
Picture 1: Paving at track
Picture 2: Backstop fence at softball field
Picture 3: Finish grading at North elevation
Picture 4: Sidewalk at lower level classroom building
Brown Middle School
Weekly Construction Report May 6, 2016
Page 2
Brown Middle School Weekly Progress Report 5/6/2016
Picture 5: Sheathing at the mechanical yard screen wall Picture 6: Installing interior overhead coiling doors in kitchen
Picture 7: Installing ceiling tile in new addition
Picture 8: Installing light fixtures in corridor of new
addition
Brown Middle School
Weekly Construction Report May 6, 2016
Page 3
Brown Middle School Weekly Progress Report 5/6/2016
Picture 9: Hanging light fixtures in media center
Picture 10: Installing the kiln in the art room
Picture 11: Toilets and fixtures in new addition gang restrooms
Picture 12: Epoxy flooring in the kitchen
Brown Middle School
Weekly Construction Report May 6, 2016
Page 4
Brown Middle School Weekly Progress Report 5/6/2016
Upcoming: Site:
Gym entrance stairs
Paving at north parking lot
Sod at fields Addition:
Toilet partitions and accessories
VCT & carpet
Device trim out
Schedule Status: Base contract – June 29, 2016
On schedule *Basement Scope Schedule - TBD
Courtyard Exterior Lighting
Ongoing: Site:
Sidewalks
Trees
Addition:
Brick and cast stone
Storefront
Light fixtures
Painting
Budget Status: Project Budget - $19,500,000
Spent to Date - $16,074,145
On budget *Basement Scope Budget – TBD