week_05 geoff outhred
DESCRIPTION
PPP Case studiesTRANSCRIPT
BUIL1154 WEEK_05 Geoff Outhred on two Case Studies
BUIL1154 WEEK_05 Geoff Outhred on two Case Studies
BUIL1154 WEEK_05 Geoff Outhred on two Case Studies
BUIL1154 Lecture 31/3/11
Two Case Studies – PPPs
Geoff Outhred
BUIL1154 WEEK_05 Geoff Outhred on two Case Studies
RMIT University Slide 2
BOOT PROJECT – CITYLINK STRUCTURE
Victorian State Government
EPA DOI VICROADS
TRANSURBAN BANKS
SERVICE AGREEMENTCONCESSIONAGREEMENT
EIA
OTHER INVESTORS
LOANAGREEMENT - 70%
SHAREHOLDERSAGREEMENT – 30%
TRANSFIELDOBAYASHID & C PMS
Joint venture CITYLINKOperator
CONSTRUCTIONAGREEMENT
OPERATINGAGREEMENT
TotalSpend $1.5b
BUIL1154 WEEK_05 Geoff Outhred on two Case Studies
RMIT University Slide 3
CITYLINK tollway Melbourne• BOOT (Build, Own,Operate,Transfer) project – a
special application of PPP• Between the Jeff Kennett State Govt. and a
private Joint Venture Concession company,Transfield Obayushi - Project Managers
• Govt. make land available to JV at no cost• 35 year operating period, after which tollway is
handed back to State Govt. in fully operationalcondition – no money changes hands
• Two short-listed JV companies submitteddetailed proposals. One accepted. Other paid forsubmission
BUIL1154 WEEK_05 Geoff Outhred on two Case Studies
RMIT University Slide 4
CITYLINK stakeholder responsibilities• Govt. sets the regulations for the project (tolls etc.)• Govt. sets key performance criteria for infrastructure• Private operators are fully accountable for service provision• Transurban set up by Trans. Obay. as the CITILINK overall
project management authority• CITILINK set up as the operating authority for tolls• Transurban manage the project, reducing Trans. Obay. to
D. & C. contractors• Transurban enter into financing contracts with banks and
investors• Transurban pay back banks and issue dividends to
investors• Trans. Obay. are responsible for providing and maintaining
infrastructure – can be sued for non-performance
BUIL1154 WEEK_05 Geoff Outhred on two Case Studies
RMIT University Slide 5
SINGAPORE NATIONAL LIBRARY
NLBClient
CONSULTANTPM
MALAYARCHITECTS
D & C PMJOINT VENTURE
NICHIMATSU- LUM CHEONG
DPARCHITECTS
OTHER DESIGNCONSULTANTS
OTHER DESIGNCONSULTANTS URA
BCA
WATCHDOG
NOVATED DESIGNAGREEMENT
DESIGNCOORDINATIONAGREEMENT
LIAISE
BUIL1154 WEEK_05 Geoff Outhred on two Case Studies
RMIT University Slide 6
National Library Singapore• NLB (National Library Board) an authority or
department of the Singapore Govt.
• Malaysian architects won design competition forlibrary – then novated to JV consortium withtheir design and other Malaysian specialistconsultants
• JV made up of Nichimatsu (Japanese PM) andLum Choeng (Singapore PM)
• DP Architects (Singapore) appointed to liaisewith Malaysian architects and their consultants
BUIL1154 WEEK_05 Geoff Outhred on two Case Studies
RMIT University Slide 7
NLB Stakeholder responsibilities
• Novated architects to deliver NLBapproved design, and work for JV
• DP help develop design and documents,and deal with authorities
• JV is a D. & C. contractor – not involved inoperation of library. Lum Choeng providelocal knowledge
• NLB appoints local “watchdog” PM toreport to them directly – oversees project
BUIL1154 WEEK_05 Geoff Outhred on two Case Studies
RMIT University Slide 8
NLB Some data• Building cost $700 Million – built under budget
• Contract time 2 years – finished early
• Won Gold Medal for EnvironmentalSustainability – beat the Biopolis building, apurpose designed environmental building
• Typical consultants – both Malaysian andSingaporean working in parallel:
Architectural, Planning, Structural and Civil, M & E,Acoustics, Library, Security, Audio Visual, “TotalBuilding Performance” from NUS
BUIL1154 WEEK_05 Geoff Outhred on two Case Studies