wecc regional planning project report - 11-1-07 wecc regional planning project report for the...

19
1 WECC Regional Planning Project Report For the Proposed Canada / Pacific Northwest to Northern California Transmission Project Project Steering Team: Avista Corporation British Columbia Transmission Corporation Pacific Gas and Electric Company PacifiCorp Sierra Pacific Power Company Transmission Agency of Northern California November 1, 2007

Upload: lyhuong

Post on 27-May-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: WECC Regional Planning Project Report - 11-1-07 WECC Regional Planning Project Report For the Proposed Canada / Pacific Northwest to Northern California Transmission Project Project

1

WECC Regional Planning Project Report

For the Proposed

Canada / Pacific Northwest to Northern California Transmission Project

Project Steering Team: Avista Corporation

British Columbia Transmission Corporation Pacific Gas and Electric Company

PacifiCorp Sierra Pacific Power Company

Transmission Agency of Northern California

November 1, 2007

Page 2: WECC Regional Planning Project Report - 11-1-07 WECC Regional Planning Project Report For the Proposed Canada / Pacific Northwest to Northern California Transmission Project Project

Canada / Pacific Northwest to Northern California Transmission Project WECC Regional Planning Report, November 1, 2007

2

I. Introduction

The Canada / Pacific Northwest to Northern California Transmission Project (“Project”) is envisioned to be an Extra High Voltage (EHV) transmission project between British Columbia and Northern California. The US Project Sponsors: Avista, PacifiCorp, and Pacific Gas and Electric Company (“PG&E”), along with British Columbia Transmission Corporation, Sierra Pacific Power (“SPP”), and Transmission Agency of Northern California (“TANC”), are the six transmission-owning utilities whose service footprints could be traversed by the Project. Together they form the Steering Team for the Project. The members of the Steering Team are each members of Western Electricity Coordinating Council (“WECC”) and have developed other projects within the WECC transmission system. The purpose of the report is to satisfy one of the necessary components of the WECC Regional Planning requirements for new transmission projects. In accordance with the WECC Procedures for Region Planning Project Review and Rating Transmission Facilities, a letter (Attachment A) was sent to the WECC Planning Coordination Committee (“PCC”) and the Technical Studies Subcommittee (“TSS”) on August 16, 2006 requesting the formation of a Regional Planning Review Group (“RPRG”) for the Project. The list of the RPRG participants and correspondents is attached as Attachment B. The Project was presented to stakeholders on December 12, 2006 at a “kickoff” meeting in San Francisco. A description of the project and an announcement of the first project meeting were sent to WECC members as well as public officials and other interested parties, and posted on the Project website (http://www.pge.com/biz/transmission_services/canada/). At the kickoff meeting three subcommittees were formed, a Loads and Resources (“L&R”)Working Group, Technical Analysis Committee (“TAC”), and an Economic Analysis Committee (“EAC”), inviting all interested parties to participate in any or all of the committees. The list of subcommittee membership is listed in Attachment C. These subcommittees would focus on identification of loads and resources, technical feasibility and economic feasibility. Membership on the committees was diverse, including participation from renewable developers, energy marketers, investor-owned and municipal utilities, energy industry consultants, regional planning entities, and independent transmission companies. The subcommittees met regularly and were instrumental in developing subcommittee reports, which are posted on the Project website. In addition to the regular subcommittee meetings and the December 12, 2006 kickoff meeting, two other stakeholder meetings were held on August 2, 2007 and October 22, 2007. Copies of the presentations from each of the stakeholder meetings are also available on the project website.

Page 3: WECC Regional Planning Project Report - 11-1-07 WECC Regional Planning Project Report For the Proposed Canada / Pacific Northwest to Northern California Transmission Project Project

Canada / Pacific Northwest to Northern California Transmission Project WECC Regional Planning Report, November 1, 2007

3

II. Project Description The detailed plan of service for the proposed Project will be finalized by the US Project Sponsors through the WECC Rating Process. The Project was evaluated as a regional project intended to meet three primary objectives:

1. Enhance access to significant incremental renewable resources in Canada and the Pacific Northwest.

2. Improve regional transmission reliability. 3. Provide market participants with beneficial opportunities to use the facilities.

Initially, the project did not provide specific terminations for such a project, but offered three distinct alternatives for satisfying the above objectives. The three alternatives included:

1. An overland alternative from Southeast British Columbia to Northern California 2. An overland alternative from Idaho to Northern California. 3. An undersea alternative from Western British Columbia to Northern California.

III. Compliance with Regional Planning Guidelines This section provides information in response to each of the Regional Planning Guidelines with respect to the Project. The Regional Planning Guidelines are presented in bold, italic text and how the Project’s Regional Planning addressed each guideline is presented in normal text. 1. Take multiple project needs and plans into account, including identified utilities’

and non-utilities’ future needs, environmental and other stakeholder interests. The first stated benefit of the Project is to enhance access to significant incremental renewable resources in Canada and the Pacific Northwest. This benefit will aid in satisfying the needs of utilities in California, which as of the writing of this report are required to satisfy at least 20% of their load with energy generated from renewable resources by the year 2010. Furthermore, in California, recent legislation (AB 32) set a state goal to reduce green house gas emissions. Nevada has had a renewable standard since 2001. Both Oregon and Washington (service territories for PacifiCorp and Avista, respectively) have enacted renewable portfolio standards as well. British Columbia has announced an energy policy goal to satisfy its entire load with clean energy, as well as becoming electricity self-sufficient. Thus the immediate and future environmental and resource needs of all six members of the Steering Team as well as other utilities in the service territories that the project will traverse will be aided by this project. In addition to meeting the future needs of utilities, this Project will satisfy the future needs of generation developers, particularly renewable generation developers, in the Pacific Northwest and Canada.

Page 4: WECC Regional Planning Project Report - 11-1-07 WECC Regional Planning Project Report For the Proposed Canada / Pacific Northwest to Northern California Transmission Project Project

Canada / Pacific Northwest to Northern California Transmission Project WECC Regional Planning Report, November 1, 2007

4

The Project does not conflict with or preclude other entities from pursuing other projects or plans.

2. Cooperate with others to look beyond specific end points of the sponsors’ project to identify broader regional and subregional needs or opportunities.

The second intended benefit of the project is to provide regional transmission reliability. The Steering Team solicited open participation in each of the subcommittees. Through the L&R Working Group the project has taken into account utilities’ and non-utilities’ future loads and resource needs, and resource development opportunities. The approach of the TAC led to a range of intermediate interconnection alternatives, each of which may prove to enhance local reliability in the areas where the interconnections are likely to take place. During the WECC Rating Process, the Steering Team aims to find the most beneficial intermediate interconnection points that will produce the intended benefits. The Steering Team met in one-on-one meetings with TransCanada (sponsor for Northern Lights), Portland General Electric (sponsor for Southern Crossing Line), and BPA (sponsor for the West of McNary project) to discuss coordination of project plans. Additionally, BCTC has considered the system north of the potential British Columbia terminals for both the east side and the west side of the province, including the tie to Alberta. The third intended benefit of the project is to provide market participants with beneficial opportunities to use the facilities. The EAC used stakeholder input to develop the assumption for its analysis, allowing committee members access to a PG&E-developed economic screening tool, with each user able to input assumptions and conduct analysis to meet its individual needs. This tool was made available to all committee members, which included various market participants, including developers, load serving entities, energy marketers, and independent transmission owners. 3. Address the efficient use of transmission corridors (e.g., rights-of-ways, new

projects, optimal line voltage, upgrades, etc.). The analysis considered three completely distinct, wide, transmission corridors to find the most efficient preliminary plan of service to meet the intended objectives. PG&E and others focused on the overland alternatives between southeast British Columbia and northern California, TANC focused on the overland alternative between Idaho and northern California, and Sea Breeze focused on the undersea/overland alternative between western British Columbia and northern California. In addition, the TAC relied upon information obtained in relation to a previous study of an undersea option performed by PG&E and Sea Breeze in order to compare all three alternatives for the cost analysis. As stated above, the Project intends to access incremental renewable resources. The L&R Working Group identified multiple areas where new resources are likely to develop, feeding that information to the TAC. This information allowed the TAC to develop various alternatives to conduct preliminary technical studies with HVAC, HVDC and

Page 5: WECC Regional Planning Project Report - 11-1-07 WECC Regional Planning Project Report For the Proposed Canada / Pacific Northwest to Northern California Transmission Project Project

Canada / Pacific Northwest to Northern California Transmission Project WECC Regional Planning Report, November 1, 2007

5

Hybrid (combination of the HVAC and HVDC) interconnections. The alternatives considered ranged from 1,500MW to 4,500MW capacity. Additionally, the TAC estimated project costs as well as local area upgrades in areas where the Project might interconnect to the existing transmission network in British Columbia, the Pacific Northwest and Nevada. 4. Identify and show how the project improves efficient use of, or impacts existing and

planned resources of the region (e.g., benefits and impacts, transmission constraint mitigation).

Through the work of the L&R Working Group, areas of incremental resource development were identified, as well as the need for new transmission facilities in order to allow for efficient connection of multiple markets to accommodate trade of those resources. In developing a conceptual plan of service, the TAC considered multiple alternatives that provided positive impacts in the region. These alternatives are expected to reduce congestion and encourage international and interstate trade between local energy markets. 5. Cooperate with Regional Planning Review Group members in determining the

benefits and impacts due to the project. The Steering Team provided multiple avenues for RPRG members and other interested parties to participate, provide input and identify benefits and impacts due to the project. The three subcommittees were open-invitation participation. Each of the subcommittees solicited stakeholder input to form assumptions, conduct analysis, and provide comments and feedback. Three stakeholder meetings were held. At both the December 12, 2006 and August 2, 2007 stakeholder meetings, committee participation was encouraged. Additionally, committee chairs gave presentations and solicited comments from all stakeholders. Additionally, a Project website was set up prior to the December 12, 2006 kickoff meeting. The Project website has been updated regularly, announcing upcoming meetings and posting presentation materials. In addition a Project email box was established to address member comments and questions. In addition to the broad public general stakeholder outreach, the Steering Team members have been meeting frequently with individual stakeholders at their request to allow for more in-depth collaborative planning and communication. 6. Identify transmission physical and operational constraints resulting from the

project or that are removed by the project. The TAC analysis did not identify any new physical or operational constraints on existing transmission paths resulting from the Project. Most of the major transmission paths between Canada, the Pacific Northwest and California were loaded at or close to their Operational Transfer Capability (OTC) ratings in the studies, and there were no new overloads or voltage criteria violations resulting from any of the contingencies studied by the TAC with the Project in service. The tripping of some of the incremental generation resources was required for single and double line outages of the Project line. The

Page 6: WECC Regional Planning Project Report - 11-1-07 WECC Regional Planning Project Report For the Proposed Canada / Pacific Northwest to Northern California Transmission Project Project

Canada / Pacific Northwest to Northern California Transmission Project WECC Regional Planning Report, November 1, 2007

6

preliminary power flow studies did not show any adverse impacts in other regions of the WECC interconnection. There were some potential reliability benefits identified by the TAC analysis as indicated by the increase in system reactive margin following the double-Palo Verde generator outage for the Project case compared to the pre-Project benchmark case. This result indicates that the North of John Day nomogram could be less restrictive if the Project is built, even if the North of John Day path rating increases. The WECC Phase 2 Rating Process will ultimately determine the physical and operational constraints that will result from or be removed by the Project. 7. Coordinate project plans with and seek input from all interested members,

subregional planning group, power pools, and region-wide planning group(s). Each of the entities that make up the Steering Team participates in one of the sub-regional planning groups which the Project will likely traverse. The Project has not only been providing outreach through the stakeholder process and subcommittee participation, but through regional planning forums including Columbia Grid, Northern Tier Transmission Group, West Connect, Northwest Transmission Assessment Committee (NTAC) of the Northwest Power Pool, the California Independent System Operator (CAISO), WECC Transmission Expansion Planning Policy Committee (TEPPC), and industry conferences sponsored by the Edison Electric Institute (EEI) and the Electric Utility Consultants, Incorporated (EUCI). 8. Coordinate project plans with and seek input from other stakeholders including

utilities, independent power producers, environmental and land use groups, regulators, and other stakeholders that may have an interest.

The August 16, 2006 letter soliciting interest in participation in the Project’s RPRG went to all members of PCC, the TSS and a list of likely interested stakeholders. The list of RPRG participants is included in Attachment B. The RPRG includes representation of utilities, transmission owning utilities, independent transmission companies, independent power producers, marketers, regulators, industry consultants and other interested parties. As stated above, subcommittee participation was open to any and all stakeholders. The committee work relied heavily on information gathered from these various stakeholders, particularly in setting assumptions for incremental generation development in the L&R Working Group that were the basis of subsequent committee work. This stakeholder group was able to provide valuable input to the TAC, which in turn developed the transmission alternatives to be studied. Furthermore, input from stakeholders drove the economic analysis, providing recommendations on ranges of data that was used to frame the analysis. Invitations to the public stakeholder meetings were posted on the Project website and open to any party to participate whether or not they showed interest in joining the RPRG.

Page 7: WECC Regional Planning Project Report - 11-1-07 WECC Regional Planning Project Report For the Proposed Canada / Pacific Northwest to Northern California Transmission Project Project

Canada / Pacific Northwest to Northern California Transmission Project WECC Regional Planning Report, November 1, 2007

7

9. Review the possibility of using the existing system, upgrades or reasonable alternatives to the project to meet the need (including non-transmission alternatives where appropriate).

One of the tasks of the L&R Working Group was to identify loads, resources and scenarios of resource development and to determine if the current transmission system could support those needs. It concluded that the existing system is not adequate to accommodate the delivery of production from incremental renewable and conventional resources to the loads looking to be served by those resources. Additionally, the EAC took into account the non-transmission alternative (i.e. accessing local resources, demand-side management, and/or using the existing transmission system) and has shown that under a variety of conditions, a transmission alternative would be justified. 10. Indicate that the sponsor’s evaluation of the project has taken into account costs

and benefits of the project compared with reasonable alternatives. One of the main tasks of the TAC was to estimate the costs of various alternatives. The TAC compared thirteen alternatives that had potential to provide the intended benefits outlined in the regional planning initiation letter. Additionally, in screening the alternatives, the TAC took into account the possibility of interconnections in the Pacific Northwest and Nevada that could provide reliability or other benefits to the existing system. 11. Coordinate with potentially parallel or competing projects and consolidate projects

where practicable. Other project developers in the region, including Sea Breeze, TransCanada, BPA, PacifiCorp and Portland General Electric were all participants on the RPRG, and in the subcommittees. Members of the Steering Team have been meeting and coordinating with TransCanada, BPA and Portland General Electric. As stated previously, PG&E and Sea Breeze participated in joint studies prior to initiation of the Regional Planning Review and the TAC utilized that information as inputs for its study results. .

Page 8: WECC Regional Planning Project Report - 11-1-07 WECC Regional Planning Project Report For the Proposed Canada / Pacific Northwest to Northern California Transmission Project Project

ATTACHMENT A: Regional Planning letter

Page 9: WECC Regional Planning Project Report - 11-1-07 WECC Regional Planning Project Report For the Proposed Canada / Pacific Northwest to Northern California Transmission Project Project
Page 10: WECC Regional Planning Project Report - 11-1-07 WECC Regional Planning Project Report For the Proposed Canada / Pacific Northwest to Northern California Transmission Project Project
Page 11: WECC Regional Planning Project Report - 11-1-07 WECC Regional Planning Project Report For the Proposed Canada / Pacific Northwest to Northern California Transmission Project Project
Page 12: WECC Regional Planning Project Report - 11-1-07 WECC Regional Planning Project Report For the Proposed Canada / Pacific Northwest to Northern California Transmission Project Project

ATTACHMENT B: Regional Planning Group Participants

Page 13: WECC Regional Planning Project Report - 11-1-07 WECC Regional Planning Project Report For the Proposed Canada / Pacific Northwest to Northern California Transmission Project Project

Canada / Pacific Northwest to Northern California Transmission Project Regional Planning Group Participants

FIRST NAME LAST NAME COMPANY Juergen Puetter Aeolis Wind Don Bain AeroPower Services, Inc. Neil, J. Brausen Alberta Electric System Operator Dave Johnson ATCO Power Marketing Dave Defelice AVISTA Corp Don Kopczynski AVISTA Corp Scott Waples AVISTA Corp Ed Groce AVISTA Corp Guy Dauncey BC Sustainable Energy Ass'n Cam Matheson BC Hydro John Rich BC Hydro Lindsay Fane BC Hydro Doug Little BCTC Amir Amjadi BCTC Rohan Soulsby BCTC Mike Kreipe BPA Transmission Chuck Matthews BPA Transmission Elliot Mainzer BPA Transmission Rebecca Berdahl BPA Power Kevin Wedman Bureau Veritas North America, Inc. Robert DeKruse Bureau Veritas North America, Inc. Chris Sibley CAISO Gary DeShazo CAISO Paul Didsayabutra CAISO Christine Cordner California Energy Markets Jim McKluskey CEC Anne Gillette CPUC Paul Douglas CPUC Regina DeAngelis CPUC John Montgomery Ecology & Environment, Inc. Steve, F. Ghadiri Electricity Oversight Board Kelly Francone Energy Strategies Shamir Ladhani Enmax Power Corporation Darrel, G. VanCoevering Entrantek LLC Lorne Whittles EPCOR Energy Marketing (US) Inc. Barry, R. Flynn Flynn Resource Consultants, Inc. Ed Chang Flynn Resource Consultants, Inc. Jeremiah, F. Hallisey Hallisey and Johnson Nan Nalder Hatch Acres Elroy Switlishoff Jetson Consulting Engrs. Ltd

Page 14: WECC Regional Planning Project Report - 11-1-07 WECC Regional Planning Project Report For the Proposed Canada / Pacific Northwest to Northern California Transmission Project Project

Canada / Pacific Northwest to Northern California Transmission Project Regional Planning Group Participants

FIRST NAME LAST NAME COMPANY Gavin Berg Katabatic Power Jonathan Raymond Katabatic Power Tony Duggleby Katabatic Power Frank Cady Lassen Municipal Utility District Reynold Roeder LECTRIX LLC George, F. Morrow Lodi Electric Utility Michael Edds Mitsubishi Power Michael Margolick Naikun Wind Development, Inc. Les Pereira NCPA Tajinder Grewal NCPA Aseem Bhatia Nevada Power Rebecca Wagner Nevada Public Utilities Commission Cathy Kahn NIPCC Bill Hosie Northern Lights Trans/TransCanada Neil Parekh Pacific North West Economic Region Darrell Gerrard PacifiCorp Edison, G. Elizeh PacifiCorp Gayle MacKenzie PacifiCorp Jeff Miller PacifiCorp Michael Sidiropoulos PacifiCorp Manho Yeung PG&E Thomas E Miller PG&E Curtis A Hatton PG&E Dennis Sullivan PG&E Dede Hapner PG&E Robert Jenkins PG&E ES Marc Bommersbach PG&E ES Ben Morris PG&E ET Jason Yan PG&E ET Stephen Metague PG&E ET Vijayraghavan Bangalore PG&E ET Eric Law PG&E ET Sherman Chen PG&E ET Kenneth Dillon Portland General Electric Company Philip Augustin Portland General Electric Company Gordon Dobson-Mack PowerEx Chris Reese Puget Sound Energy Hugh Nguyen Puget Sound Energy Nancy Bougher Roseville Electric Dana Cabbell SCE E. John Thompkins Sea Breeze Pacific West Coast Cable

Page 15: WECC Regional Planning Project Report - 11-1-07 WECC Regional Planning Project Report For the Proposed Canada / Pacific Northwest to Northern California Transmission Project Project

Canada / Pacific Northwest to Northern California Transmission Project Regional Planning Group Participants

FIRST NAME LAST NAME COMPANY Rod Lenfest Sea Breeze Pacific West Coast Cable Paul Manson Sea Breeze Pacific West Coast Cable Paul Schmidt Sierra Pacific Power Carolyn Barbash Sierra Pacific Power Jim McMorran Sierra Pacific Power Renee Hull Sierra Pacific Power Joe Tarantino SMUD Jim Feider TANC Jim Beck TANC Bryan Griess TANC David Larsen TANC Howard Shapiro TID Thom Fischer Tollhouse Energy Larry Gilbertson Turlock Irrigation District Jerry Pell U. S. Dept. of Energy Daniel, H. Wood Utility System Efficiencies, Inc. Mariam Mirzadeh WAPA-SNR Morteza Sabet WAPA-SNR

Page 16: WECC Regional Planning Project Report - 11-1-07 WECC Regional Planning Project Report For the Proposed Canada / Pacific Northwest to Northern California Transmission Project Project

ATTACHMENT C: Subcommittee Membership

Page 17: WECC Regional Planning Project Report - 11-1-07 WECC Regional Planning Project Report For the Proposed Canada / Pacific Northwest to Northern California Transmission Project Project

Canada / Pacific Northwest to Northern California Transmission Project Loads and Resources Working Group

First Last Company Juergen Puetter Aeolis Wind Don Bain Aero Power Service Cam Matheson BC Hydro John Rich BC Hydro Rohan Soulsby BCTC Elliot Mainzer BPA Transmission Ed Chang Flynn RCI Elroy Switlishoff Jetson Consulting Engineers Gavin Berg Katabatic Power Tony Duggleby Katabatic Power Michael Margolick Naikun Wind Development Kurt Granat PacifiCorp Curtis A Hatton PG&E Thomas E Miller PG&E Dennis Sullivan PG&E (Committee Chair) Robert Jenkins PG&E ES Eric Law PG&E ET Chris Reese Puget Sound Energy Renee Hull Sierra Pacific Power Jim McMorran Sierra Pacific Power Thom Fischer Toll House Energy Bill Hosie TransCanada

Page 18: WECC Regional Planning Project Report - 11-1-07 WECC Regional Planning Project Report For the Proposed Canada / Pacific Northwest to Northern California Transmission Project Project

Canada / Pacific Northwest to Northern California Transmission Project Technical Analysis Committee Members

First Last Company Don Bain Aeropower Services Scott Waples AVISTA Corp Allen Hiebert BCTC Amir Amjadi BCTC Rebecca Berdahl BPA Power Michael Kreipe BPA Transmission Chuck Matthews BPA Transmission Paul Didsayabutra CAISO Shamir Ladhani ENMAX Barry Flynn Flynn RCI Frank Cady LMUD Michael Sidiropoulos PacifiCorp Tom Tjoelker PacifiCorp Robert T Jenkins PG&E ES Vijayraghavan Bangalore PG&E ET Sherman Chen PG&E ET Ben Morris PG&E ET Philip Augustin Portland General Ellen Feng PowerEx Gordon Dobson-Mack PowerEx Chris Reese Puget Sound Energy Hugh Nguyen Puget Sound Energy Dana Cabbell SCE Vishal Patel SCE Rod Lenfest Sea Breeze Paul Schmidt Sierra Pacific Power Joe Tarantino SMUD Bryan Bryan Greiss TANC Dave Larsen TANC Bill Hosie TransCanada Mariam Mirzadeh WAPA Morteza Sabet WAPA Sam Kwong Williams

Page 19: WECC Regional Planning Project Report - 11-1-07 WECC Regional Planning Project Report For the Proposed Canada / Pacific Northwest to Northern California Transmission Project Project

Canada / Pacific Northwest to Northern California Transmission Project

Economic Analysis Committee Members

First Last Company Dave Defelice AVISTA Corp James Gall AVISTA Corp Rohan Soulsby BCTC Pushkar Wagle Flynn RCI Susan Williams Northern Arizona University Kurt Granat PacifiCorp Jamie Austin PacifiCorp Manho Yeung PG&E (Committee Chair) Curtis A Hatton PG&E Thomas E Miller PG&E Todd Strauss PG&E Robert T. Jenkins PG&E ES Gordon Dobson-Mack PowerEx Jim McMorran Sierra Pacific Power Patrick Mealoy TANC Thom Fischer Toll House Energy Bill Hosie TransCanada Jerry Valenti Trans-Elect