tokyo electric power micro hydro
TRANSCRIPT
1
Workshop on Renewable EnergiesMarch 17, 2005
Majuro, Republic of the Marshall Islands
Module 4.3 Module 4.3 –– MicroMicro--HydroHydro
4.3.1 Designing 4.3.1 Designing Tokyo Electric Power Co. (TEPCO)
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
2
ContentsContents
• Design for Civil Work
• Calculation of Head Loss
• Design of Electrical and Mechanical Equipment
2
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
3
1. Selecting a Type of Intake Weir or Dam
(a) Concrete gravity dam(b) Floating concrete dam(c) Earth dam(d) Rockfill dam(e) Wet masonry dam(f) Gabion dam(g) Concrete reinforced gabion dam(h) Brushwood dam(i) Wooden dam(j) Wooden-frame dam with gravel
Design for Civil WorkDesign for Civil Worke7
/ PPA
Wor
ksho
p on
Ren
ewab
le En
ergi
es
4
1-1.Concrete gravity dam
Concrete is used for the construction of the entire body.
• Foundation : Bedrock• River conditions : Not governed by gradient, discharge or level of
sediment load• Intake conditions: Good interception performance and intake
efficiency
Design for Civil WorkDesign for Civil Work
3
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
5
1-2. Floating concrete dam
Lengthened infiltration path of the foundations by means of cut-off, etc. to improve the interception performance
•Foundations : In principle, gravel•River conditions : Not affected by the gradient, discharge or level of
sediment load•Intake conditions: Good interception performance and intake efficiency
Design for Civil WorkDesign for Civil Work
Longer
Cut-off
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
6
1-3. Earth dam
Earth is used as the main material for the body. The introduction of a riprap and core wall may be necessary depending on the situation.
•Foundations : Variable from earth to bedrock•River conditions : Gentle flow and easy to deal with flooding•Intake conditions: High interception performance and good intake
efficiency
Design for Civil WorkDesign for Civil Work
4
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
7
1-4. Rockfill dam
Gravel is used as the main material for the body. The introduction of a core wall may be necessary depending on the situation.
•Foundations : Various, from earth to bedrock•River Conditions : River where an earth dam could be washed away
by normal discharge•Intake conditions: Limited to the partial use of river water due to the
low intake efficiency
Design for Civil WorkDesign for Civil Worke7
/ PPA
Wor
ksho
p on
Ren
ewab
le En
ergi
es
8
1-5. Wet Masonry Dam
Filling of the spaces between gravel with mortar, etc.
•Foundations : Various, from earth to bedrock•River conditions : Not affected by the gradient, discharge or level of
sediment load•Intake conditions: Good interception performance and intake efficiency
Design for Civil WorkDesign for Civil Work
5
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
9
1-6. Gabion Dam
Gravel is wrapped in metal net to improve integrity.
•Foundations : Various, from earth to bedrock•River conditions : River where a rock-fill dam could be washed away
by normal discharge•Intake conditions: Limited to partial use of river water due to the low
intake efficiency
Design for Civil WorkDesign for Civil Worke7
/ PPA
Wor
ksho
p on
Ren
ewab
le En
ergi
es
10
1-7. Concrete Reinforced Gabion Dam
Reinforcement of the gabion surface with concrete
•Foundations : Various, from earth to bedrock •River conditions : River where the metal net could be damaged due to
strong flow•Intake conditions: Applicable when high intake efficiency is required
Design for Civil WorkDesign for Civil Work
6
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
11
1-8. Brushwood Dam
Simple weir using locally produced tree branches, etc.
•Foundations : Various, from earth to gravel layer•River conditions : Loss due to flooding is assumed•Intake conditions: At a site with a low intake volume or intake from a
stream to supplement the droughty water
Design for Civil WorkDesign for Civil Worke7
/ PPA
Wor
ksho
p on
Ren
ewab
le En
ergi
es
12
1-9. Wooden Dam
Weir using locally produced wood
•Foundations : Various, from earth to bedrock•River conditions : Relatively gentle flow with a low level of sediment
transport•Intake conditions: A certain level of intake efficiency is ensured with a
surface coating, etc.
Design for Civil WorkDesign for Civil Work
7
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
13
1-10. Wooden-Frame Dam with Gravel
The inside of the wooden frame is filled with gravel to increase stability.
•Foundations : Various, from earth to bedrock•River conditions : River at which a rock-fill dam could be washed away
by normal discharge•Intake conditions: Limited to the partial use of river water due to the
low intake efficiency
Design for Civil WorkDesign for Civil Worke7
/ PPA
Wor
ksho
p on
Ren
ewab
le En
ergi
es
14
Decision of weir height(1). Elevation of waterway considering:
- Geology, topography, existing structures, etc.
(2). Riverbed rise downstream
- Possibility of change of riverbed elevation
(3). Easy flushing sedimentation materials in front of intake
(4). Head acquisition and construction cost
(5). Backwater effect
Design for Civil WorkDesign for Civil Work
8
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
15
Design for Civil WorkDesign for Civil Work
2. IntakeSide intake- Typical intake
- At right angles to the river
Tyrolean intake- Along the weir
- Simple structure
- Affected by sedimentation
during flooding
- More maintenance required
Side Intake
Tyrolean Intake
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
16
3. Settling Basin
Function:•Settles and removes suspended materials of all sizes that could adversely affect the turbine.•Spills out excess water from spillway
Conduit sectionWidening section
Settling section
Bb
1.02.0
Dam
SpillwayStoplog Flushing gate
Intake
Headrace
Bsp
hs
hsp+
15cm
h0
10~
15c
m
hi
ic=1/20~1/30
IntakeStoplog
biLc Lw Ls
L
Sediment Pit Flushing gate
Design for Civil WorkDesign for Civil Work
9
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
17
4. Headrace
Function:• Conveys water from the intake to the forebay• Spillways provided along the headrace for excess water
•Flow Capacity Qd = [ A ×R 2/3×SL
1/2 ] n
where,A: Cross-sectional areaR: R = A/PP: Length of wet sidesSL: Longitudinal slope of
headracen: Coefficient of roughness
Design for Civil WorkDesign for Civil Worke7
/ PPA
Wor
ksho
p on
Ren
ewab
le En
ergi
es
18
Design for Civil WorkDesign for Civil Work
Simple earth channel Lined channel
(Rock and stone)
Wet masonry channel Concrete channel
n = 0.030n = 0.025
n = 0.020 n = 0.015
10
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
19
Design for Civil WorkDesign for Civil Work
n = 0.015
Wooded-fenced channel
Closed pipe (Hume pipe, steel pipe)
Box culvert channel
n = 0.015
n = 0.015, 0.012
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
20
5. Forebay
Function:• Regulates fluctuating
discharge in the penstock and the headrace caused by load fluctuation.
• Has final function to remove materials (silt, sand), debris (leaves, trash, driftwood, etc.) in the water
Attached Structure:• Spillway• Screen• (Regulating gate)
Design for Civil WorkDesign for Civil Work
11
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
21
6. Penstock
• Conveys water under pressure from the forebay to the turbine• Materials: Steel, resin (Hard vinyl chloride, Howell, Fibre
Reinforced Plastics)• Diameter of pipe
d = C × (Qd/Vopt)0.5
where,
Design for Civil WorkDesign for Civil Work
- ft- mDiameterd
3.38 to 9.2 ft3/s
1.0 to 2.8 m/s
Optimum velocity
Vopt
ft3/sm3/sDesigned discharge
Qd
2.3061.273CoefficientC
Imperial unitSI unit
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
22
Design for Civil WorkDesign for Civil Work
• Diameter of penstock affects output of a power plant.Increase of Diameter- Increase of Output
- Increase of CostOptimum Diameter to be determined
Output Limitation by Diameter of Penstock
0.010.020.030.040.050.060.070.080.090.0
100.0
0.10
0.15
0.20
0.25
0.30
0.35
0.40
0.45
0.50
0.55
0.60
0.65
0.70
0.75
0.80
Discharge (ft3/ s)
Out
put (
kW) D=10in
D=12inD=14inD=16inD=18in
Length of Penstock = 300ft, Coefficiency of Roughness = 0.013
12
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
23
7. Powerhouse
Function:Provides shelter for the electro-mechanical equipment (turbine, generator, control panels, etc.)
The size of the powerhouse and the layout:Determined taking into account convenience during installation, operation and maintenance.
Foundation:Classified into two:
•For Impulse turbine -Pelton turbine, Turgo turbine or cross-flow turbine, etc.
•For Reaction turbine -Francis turbine or propeller turbine, etc.
Design for Civil WorkDesign for Civil Worke7
/ PPA
Wor
ksho
p on
Ren
ewab
le En
ergi
es
24
a. Foundation for Impulse Turbine
The figures shows the foundation for the cross flow turbine. There is a space between the turbine and the surface of discharged water.
Flood W ater Level(M axim um )
20cm
boSection A -A
20cmb
bo: depends on Q d and H e
30~ 50cm
hc
30~ 50cm
H L3
(see Ref.5 -3)
hc={ }1/ 31 .1×Q d 2
9 .8×b2
A
A
A fterbay T ailrace cannel O utle t
Design for Civil WorkDesign for Civil Work
13
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
25
Section A-A
1.5×d3
Flood Water Level(Maximum)30~50cmhc
2× d3
d3
20cm
1.15× d3
1.5×d3
Hs
Hs:depens on characteristic of turbine
HL3
(see Ref.5-3)
hc={ }1/ 31.1×Qd2
9.8×b2
A
A
b. Foundation for Reaction Turbine
The below figures show the foundation for the Francis turbine. The outlet of the turbine is installed under the level of discharged water.
Pump
Gate
HL3
Flood Water Level (Maxmum)
Design for Civil WorkDesign for Civil Worke7
/ PPA
Wor
ksho
p on
Ren
ewab
le En
ergi
es
26
Calculation of Head LossCalculation of Head Loss
HgHHe
HL3
HL1
HL2
Intake
Settling Basin
Headrace
ForebayPenstock
Powerhouse
Tailrace
Head losses are indicated by the following figures at hydropowersystems. HL1 can be calculated easily as the differential water level between the intake to the forebay tank. Similarly HL3 can be calculated as the differential level between the center of the turbine to the tailrace.
He = Hg – (HL1 + HL2 + HL3)where, He: Effective head
Hg: Gross headHL1: Loss from intake to forebayHL2: Loss at penstockHL3: Installation head and loss at tailrace
14
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
27
Calculation of Head LossCalculation of Head LossThe head loss at the penstock (HL2) can be calculated by the following equations.
HL2 = hf + he + hv + howhere,
hf: Frictional loss at penstockhe: Inlet losshv: Valve lossho: Other losses (Bend losses, loss on changes in cross-
sectional area and others)
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
28
<Reference > Head Loss at Penstock<Reference > Head Loss at Penstock(1) Frictional Loss
hf = f × (Lp/Dp )× Vp2/2g
where, hf: Frictional loss at penstock (ft)f: Coefficient on the diameter of penstock pipe (Dp)
f = 185 × n2/Dp1/3
Lp: Length of penstock (ft)Vp: Velocity at penstock (ft/s)
Vp = Q/Apg: Acceleration due to gravitation (32.14 ft/s2)Dp: Diameter of penstock pipe (ft)n: Coefficient of roughness
(steel pipe: n = 0.012, plastic pipe: n = 0.011)Q: Design discharge (ft3/s)Ap: Cross sectional area of penstock pipe (ft2)
Ap = 3.14 × Dp2/4.0
15
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
29
<Reference > Head Loss at Penstock<Reference > Head Loss at Penstock(2) Inlet Loss
he = fe × Vp2/2g
where, he: Inlet loss (ft)fe: Coefficient on the form at inlet.
Usually fe = 0.5 in micro-hydro scheme
(3) Valve Losshv = fv × Vp2 /2g
where, hv: Valve loss (ft)fv: Coefficient of the type of valve
fv = 0.1 ( butterfly valve)
(4) Others“Bend loss” and “loss on changes in cross-sectional area” are considered other losses. However these losses can be neglected in micro-hydro schemes. Usually, people planning micro-hydro schemes must take account of following margin for other losses.
ho = 5 to 10% × (hf + he +hv)
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
30
<Reference > Head Loss at Penstock<Reference > Head Loss at PenstockIn SI Unit
(1) Frictional lossFrictional loss (hf) is the biggest of the losses at penstock.
hf = f ×(Lp/Dp ) ×Vp2/2g
where, hf: Frictional loss at penstock (m)f : Coefficient on the diameter of penstock pipe (Dp).
f = 124.5×n2/Dp1/3
Lp: Length of penstock (m)Vp: Velocity at penstock (m/s)
Vp = Q/Apg: Acceleration due to gravity (9.8m/sec2)Dp: Diameter of penstock pipe (m)n : Coefficient of roughness
(steel pipe: n = 0.012, plastic pipe: n = 0.011)Q: Design discharge (m3/s)Ap: Cross sectional area of penstock pipe (m2)
Ap = 3.14×Dp2/4.0
16
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
31
<Reference > Head Loss at Penstock<Reference > Head Loss at Penstock(2) Inlet Loss
he = fe × Vp2/2g
where, he: Inlet loss (m)fe: Coefficient on the form at the inlet
Usually fe = 0.5 in micro-hydro schemes.
(3) Valve Losshv = fv × Vp2 /2g
where, hv: Valve loss (m)fv: Coefficient on the type of valve,
fv = 0.1 (butterfly valve)
(4) OthersBend loss and loss due to changes in cross-sectional area are considered other losses. However, these losses can be neglected in micro-hydro schemes. Usually, the person planning the micro-hydro scheme must take account of following margins as other losses.
ho = 5 to 10%× (hf + he +hv)
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
32
Equipment and Functions
1. Inlet valve:Controls the supply of water from the penstock to the turbine.
2. Water turbine:Converts the water energy into rotating power.
3. Turbine governor:Controls the speed and output of the turbine
4. Power transmission facility:Transmits the rotation power of the turbine to the generator.
5. Generator:Generates the electricity from the turbine or its transmitter.
6. Control panels:Controls and protects the above facilities for safe operation.
7. Switchgear (with transformer):Controls the electric power and increases the voltage of transmission
lines, if required
Note: Items 3, 6 & 7 above may sometimes be combined in one panel.
Design of E/M EquipmentDesign of E/M Equipment
17
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
33
1. Inlet Valve
Design of E/M EquipmentDesign of E/M Equipmente7
/ PPA
Wor
ksho
p on
Ren
ewab
le En
ergi
es
34
2. Water Turbine Types:Impulse turbines: Rotates the runner by the impulse of water jets by converting the pressure head into the velocity head through nozzles.
Reaction turbines: Rotates the runner by the pressure head.
Design for E/M EquipmentDesign for E/M Equipment
PropellerKaplan
FransisPump-as-Turbine
Reaction
CrossflowCrossflowTurgo
PeltonTurgo
ImpulseLowMediumHigh
HeadType
18
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
35
1
10
100
1000
0.01 0.1 1 10 100Water Discharge
Effe
ctive
Hea
d
Design Design ofof E/M EquipmentE/M Equipment
Selection of turbine type i.e.:i.e.: H = 25m, Q = 0.45mH = 25m, Q = 0.45m33/s/s
→→ Cross FlowCross Flow
oror Horizontal FrancisHorizontal Francis
Horizontal FrancisHorizontal Francis
Cross FlowCross Flow
Horizontal Horizontal PeltonPelton
Horizontal PropellerHorizontal Propeller
(m3/s, ft3/s)
(m, ft)
(3,529)(352.9)(35.29)(3.529)(0.3529)
(3.28)
(3,280)
(32.8)
(328)
(82ft) (15.88ft3/s)
Vertical FrancisVertical Francis
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
36
Design of E/M EquipmentDesign of E/M Equipment
CrossCross--Flow TurbineFlow Turbine
19
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
37
Design Design ofof E/M EquipmentE/M Equipment
WaterWater
Guide VaneGuide VaneCrossCross--Flow W/TFlow W/T
Speed GovernorSpeed Governor
CrossCross--Flow TurbineFlow Turbinee7
/ PPA
Wor
ksho
p on
Ren
ewab
le En
ergi
es
38
Design Design ofof E/M EquipmentE/M Equipment
Francis TurbineFrancis Turbine
20
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
39
Design Design of of E/M EquipmentE/M Equipment
Francis TurbineFrancis Turbinee7
/ PPA
Wor
ksho
p on
Ren
ewab
le En
ergi
es
40
Design Design ofof E/M EquipmentE/M Equipment
Tubular TurbineTubular Turbine
21
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
41
Design Design ofof E/M EquipmentE/M Equipment
GeneratorGenerator
Propeller RunnerPropeller RunnerGuide Vane Guide Vane (Wicket Gate)(Wicket Gate)
Timing BeltTiming BeltDraft Tube Draft Tube
Tubular TurbineTubular Turbinee7
/ PPA
Wor
ksho
p on
Ren
ewab
le En
ergi
es
42
Design of E/M EquipmentDesign of E/M Equipment
PeltonPelton TurbineTurbine
22
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
43
Design Design ofof E/M EquipmentE/M Equipment
PeltonPelton TurbineTurbinee7
/ PPA
Wor
ksho
p on
Ren
ewab
le En
ergi
es
44
Design Design ofof E/M EquipmentE/M Equipment
Reverse Pump Turbine (Pump as Turbine)Reverse Pump Turbine (Pump as Turbine)
23
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
45
Design Design ofof E/M EquipmentE/M Equipment
Pico HydroPico Hydro
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
46
3. GeneratorSynchronous:
Independent exciter rotor, applicable for both isolated and existing power networks
Asynchronous (induction):
No exciter rotor is usually applicable in networks with other power sources. In isolated or independent networks, it must be connected to capacitors to generate electricity.
Generator output: Pg (kVA) = (0.0847 x H x Q x η)/pfPg (kVA) = (9.8 x H x Q x η)/pf (in SI unit)
WherePg: output (kVA) H: Net head (ft, m)Q: Rated discharge (ft3/s, m3/s)η: Combined efficiency of turbine, transmitter & generator (%) pf: Power factor ( %). The value is based on the type of load in the system.
Design Design ofof E/M EquipmentE/M Equipment
24
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
47
3. Generator
• Speed and Number of Generator Poles - The rated rotational speed is specified according to the frequency
(50 or 60 Hz) of the power network and the number of poles by the following formula:
For synchronous generators:P (nos.) = 120 x f/N0 N0 (rpm) = 120 x f/P
where, P : Number of poles f : Frequency (HZ)
N0 : Rated rotation speed rpm)
For induction generators: N (rpm) = (1-S) x N0
where, N : Actual speed of induction generator (rpm) S : Slip (normally S= -0.02)N0 : Rated rotation speed rpm)
Design Design ofof E/M EquipmentE/M Equipmente7
/ PPA
Wor
ksho
p on
Ren
ewab
le En
ergi
es
48
4. Power Transmission Facility (Speed Increaser)To match the speed of the turbine and generator.
– Gearbox type:The turbine shaft and generator shaft are coupled with helical gears with parallel shafts in one box with anti-friction bearings according to the speed ratio between the turbine and generator. The life is long but the cost is relatively high. (Efficiency: 95 –97% subject to the type)
– Belt type:The turbine shaft and generator shaft are coupled with pulleys or flywheels and belts according to the speed ratio between the turbine and generator. The cost is relatively low but the life is short. (Efficiency: 95 – 98% subject to the type of belt)
In the case of a micro hydro-power plant, a V-belt or flat belt type coupling is usually adopted to save the cost because the gear-type transmitter is very expensive.
Design Design of of E/M EquipmentE/M Equipment
25
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
49
5. Control Facility of Turbine and Generator
5.1 Speed Governor:The speed governor is adopted to keep the turbine speed constantbecause the speed fluctuates if there are changes in the load, water head or flow.
(1) Mechanical type: Controls the water discharge constantly with the automatic operation of the guide vane(s) according to load. There are two types:
• Pressure-oil type• Motor type
Ancillary Equipment: Guide vane servomotor, pressure pump and tank, sump tank, piping or guide vane operated by electric motor
Design Design ofof E/M EquipmentE/M Equipmente7
/ PPA
Wor
ksho
p on
Ren
ewab
le En
ergi
es
50
(2) Dummy load type:To balance both the actual load and dummy load using a thyristor i.e. to keep the total of both the actual and dummy load constant for the same generator output and speed. The load is controlled by an electronic load controller (ELC).
The capacity of the dummy load is calculated as follows:
Pd (kW) = Pg (kVA) x pf (decimal) x SF where,
Pd: Capacity of dummy load (Unity load: kW)Pg: Rated output of generator (KVA) pf: Rated power factor of generator SF: Safety factor according to cooling method (1.2 – 1.4 times
generator output in kW) to avoid over-heating the heater
Design Design ofof E/M EquipmentE/M Equipment
26
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
51
5.2 Generator ExciterIn the case of a synchronous generator, an exciter is necessary for supplying field current to the generator and keeping the output voltage constant if the load fluctuates.
• Brush type: Direct thyristor excitation method. DC current for the field coil is supplied through a slip ring from a thyristor with an excitation transformer. (Low initial cost but high maintenance cost)
• Brushless type:The basic circuit consists of an AC exciter directly coupled to the main generator, a rotary rectifier and a separately provided automatic voltage regulator with a thyristor (AVR). (High initial cost but low maintenance cost)
Design Design ofof E/M EquipmentE/M Equipmente7
/ PPA
Wor
ksho
p on
Ren
ewab
le En
ergi
es
52
G
PT
CT
Ex. Tr
AVR PulseGenerator
Slip ring
(Speed Detector)
G
PT
CT
Ex. Tr
AVR
DC100V
PulseGenerator
Rotating section
ACEx
(Speed Detector)
5.2 Generator Exciter
Wiring diagram of exciter with brush Wiring diagram of brushless exciter
Design Design ofof E/M EquipmentE/M Equipment
27
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
53
5.3 Single Line Diagram
The typical single diagram for a 380/220V distribution line
V
Hz
H
A x3
ELC (with Hz Relay)G
Turbine
Transmitterif required
Dummy Load
MagnetContactor
x3
NFB
Generator
V x3
Fuse
To Custmer
LampIndicator
Design Design ofof E/M EquipmentE/M Equipmente7
/ PPA
Wor
ksho
p on
Ren
ewab
le En
ergi
es
54
6.Control, Instrumentation and Plant Protection
6.1 Control Methods:
• Supervisory control method is classified into continuous supervisory, remote continuous control and occasional control.
• The operational control method is classified into manual control, single-person control and fully automatic control.
• The output control method is classified into output by single governor for independent network and water level control, discharge control and program control for parallel operation with another power source.
Design Design ofof E/M EquipmentE/M Equipment
28
e7 / P
PA W
orks
hop
on R
enew
able
Ener
gies
55
6.2 Instrumentation
• Pressure gauge for penstock• Voltmeter with change-over switch for output voltage • Voltmeter with change-over switch for output of dummy load
(ballast) • Ammeter with change-over switch for ampere of generator output • Frequency meter for rotational speed of generator• Hour meter for operating time• KWH (kW hour) meter and KVH (Kvar hour) meter, which is
recommended to check and summarize total energy produced by the power plant
Design Design ofof E/M EquipmentE/M Equipmente7
/ PPA
Wor
ksho
p on
Ren
ewab
le En
ergi
es
56
6.3 Protection of Plant and 380/220V Distribution Line
Considering the same reason for cost saving in instrumentation, the following minimal protection is required for micro-hydro power plants in rural electrification.1. Over-speed of turbine and generator (detected by frequency)2. Under-voltage 3. Over-voltage4. Over-current by NFB (No Fuse Breaker) or MCCB (Molded Case Circuit
Breaker) for low-tension circuits.
When items 1, 2 and 3 are detected by an ELC (with screw adjustment), the magnet contactor (MC) is activated and trips the main circuit of the generator.
Design Design ofof E/M EquipmentE/M Equipment