design of micro hydro power

Upload: sufi-shah-hamid-jalali

Post on 04-Jun-2018

238 views

Category:

Documents


7 download

TRANSCRIPT

  • 8/14/2019 Design of micro hydro power

    1/119

    ID-number 28-2802-0014 -2 A

    Province: Bamyan

    District: Shebar

    Village: Gonbad

    Project type M,H,P

    No F 256

    Data from site for river foram50m(U/S) to Intak

    h1= U / S Normal elevation of ware in the river 2805.08 m

    h2= D / S Normal elevation of water in the river 2804.80 mh3= U / S flood elevation of water in the river 2805.18 m

    h4= D / S flood elevation of water in the river 2804.90 mh5= 2804.13 m

    h6 2804.95 m

    h7 2804.670 mn fom tabale 0.025

    S= length sarvay Slop 50.00 m

    B= 7.00 m

    h= h1-h2 for Normal time 0.28 m

    h= h3-h4 for Flood time 0.28 m

    h= h6-h7 for minmam water 0.28 m

    L= Horizontal Length= S^2- h^2 50.00

    Slop = V / H 0.0056

    H2= minma water depth in the river (h7 - h5 ) 0.54 m

    P= B + 2* H1 wetted perimeter for minm water depth 8.0880 m

    A= B*H3 3.8080 m2

    R= A / P the hydraulic radic for minm water depth 0.4708 m

    V= 1 /n *R^0.6667* S for Normal water 1.8116 m/secQ= minm. Water in the river 6.90 m3/sec

    H1= 0.674 mP= B + 2* H1 wetted perimeter for Normal water depth 8.3480 m

    A= B*H1 4.7180 m2

    R= A/ P the hydraulic radic for Normal water depth 0.5652 m

    V= 1 /n *R^0.6667* S for Normal water 2.046 m/secQ= Normal water in the river for normal time 9.65 m3/sec

    H3= 0.77 mP= B + 2* H2 wetted perimeter for flood water depth 8.5480 m

    A= B*H2 5.4180 m2

    R= A / P the hydraulic radic for floodl water depth 0.6338 m

    V= 1 /n *R^0.6667* S for flod water 2.2087 m/sec

    Q= Maxm water in the river for flood time 11.97 m3

    elevation for apron of river

    U/S minmam elevation of water in the river

    D/S minmam elevation of water in the river

    width of river

    Normal water depth for Norma time in the river(h2-h5)

    maxm water depth for flood time in the river(h4-h5)

  • 8/14/2019 Design of micro hydro power

    2/119

    ID-number 28-2802-0014 -2 A

    Province: Bamyan

    District: Shebar

    Village: Gonbad

    Project type M,H,P

    No F 256

    H= freeboard 0.2 m

    h1= U / S minm elevation of water in the canal 2804.7 m

    h2= D / S minm elevation of water in the canal 2803.77 m

    h3= U / S elevation for flood water in the canal 2804.90 m

    h4= D / S elevation for flood water in the canal 2804 m

    h5= 2803.27

    n fom tabale for canal 0.017

    S= length sarvay Slop 400 m

    B= 1 m

    h= h1-h2 for Normal time 0.90 m

    h= h3-h4 for Flood time 0.90 m

    L= Horizontal Length= S^2- h^2 400.00

    Slop = V / H 0.0022

    H1= 0.50 m

    P= B + 2* H1 wetted perimeter for Normal water depth 2.0000 m

    A= B*H1 0.5 m2

    R= A / P the hydraulic radic for Normal water depth 0.250 m

    V= 1 /n *R^0.6667* S for Normal water(1-1.5) 1.107 m.sec

    Q= minmam water in the canal for normal time A*V 0.554 m3/sec

    S= (n*V/ R^0.667*S*R 0.0022

    H2= 0.730 m

    P= B + 2* H2 wetted perimeter for flood water depth 2.46 m

    A= B*H2 0.73 m

    R= A / P the hydraulic radic for floodl water depth 0.297 m

    V= 1 /n *R^0.6667* S for flod water 1.24 m

    Q= 0.906 m3/secS= (n*V / R^0.667)^2 0.0023

    Q= A * 1/ n *R0.6667* R*S 0.906

    Maxm water in the canal for floodl time=A *V

    Deta from site for canal

    elevation for apron of canal

    width of canal

    minmam water depth in the canal(h2-h5)

    flood water depth in the canal(h4-h5)

  • 8/14/2019 Design of micro hydro power

    3/119

    ID-number 28-2802-0014 -2 A

    Province: Bamyan

    District: Shebar

    Village: Gunbad

    Project type : M,H,P

    No F 256

    canal type stone masonry with cement mortor

    Q flood flow m 0.906

    n coefficent 0.017

    Q desing flow m 0.554

    N for gravelly earth side slope m 0

    V choos Velocity m/s 1.107A=Q/ V Crosection area m 0.50

    X=2(1+N^2) - 2N best factor for canal 0

    m 0.500

    B=H*X m 1.000

    T=B+(2H*N) m 1.000

    Vc m/s V< 0.8 Vc ok

    Vc critical velocity A*g /T m/s 2.2

    0.8 Vc m/s 1.8 > v ok

    the wetted perimeter

    P=B + 2* H (1+N^2) m 2.000

    R= A / P m 0.250

    the reqired canal slope

    0.0023

    Cheke Q=A*1/n *R^0.1667*R*S 0.554 0k

    check the flow depth for maximum flood flow in the canal

    Q=[(B*H+N*(H)^2)^5/3*S] / n*[B+2*H(1+N^2)] 2/3

    Triaf value of H(m)

    ok

    d=11RS 6

    Canal desing

    Correspandding Q =1.11m/s

    largest particle that will be transported in the canal(mm)

    0.408

    the hydraulic radic

    S=[n*V / R^0.667]^2

    H= A / (X+N) the water depth incana

    The bed width

    0.4

    0.27

    0.90

    top width

    (Rectangular canal)

    0.3

    0.73

    By trall and error method H

  • 8/14/2019 Design of micro hydro power

    4/119

    Desing of Channel for Q= 1 m3 for shadman CDCs

    No n s b,m h,m A,m2 P(m) R(m) R S (m/s Q,m33 0.017 0.0023 1.0 0.3 0.3 1.6 0.188 0.326 0.05 0.91 0.27

    4 0.017 0.0023 1.0 0.4 0.40 1.8 0.222 0.365 0.05 1.02 0.41

    5 0.017 0.0023 1.0 0.73 0.73 2.5 0.297 0.443 0.05 1.24 0.90

    Note: Mostly when we going to make Design for channel we can uese the Trille Method

    and also we can uese the mening formula for design of the channel.you can see the

    following

    Lenth of channel=245m

    Q=V*A s=slope of channel=2% R=A/P Design for Q=1m3

    V=CRS n=0.014 P=2h+b

    C=1/n*R1/6 A=b*h

    Q=V*A=CRS*A=1/n*R*A*S

    Section Free board=20cm

    Actual diminstion=(100*200)cm

    100

    0.579

    73

  • 8/14/2019 Design of micro hydro power

    5/119

    ID-number 28-2802-0014 -2 A

    Province: Bamyan

    District: Shebar

    Village: Gunbad

    Project type : M,H,P

    No F 256

    g 9.81 m/s

    C for roughlyfinshed stone masonry oriffic 0.6 m/s

    V1 velocity for M.H.P 1-1.5 1.107 m/s ok

    Q desing flow 0.554 m

    Q 0.906

    w width of canal 1.000 m

    Hh headrace canal 0.50 m

    Hfr flood water level in to river 0.77 m

    Hnr Normal water Level in the river 0.67

    Q increased Trashrack and seepeage losses 15%

    Q Q desing*1.15 15% increased to meet trashrack 0.637 m/s

    A oriffice area Q / V1 0.58 m

    H oriffice height choose 0.2 m

    W oriffice width A / H 2.88 m

    h bottom of the oriffic above the river bed level 0.2 m

    Q discharge in oriffic 0.637 m/s ok

    V acceptable rang Q / A 1.108 m/s ok

    Qflood Discharge through the oriffic during flood flow m/s

    Q= A*C 2*g *(Hf - Hh) 0.80 m/s

    H= depth of water in the canal A / width canalfor normal0.58

    m

    Spill excessflood water= Q flood -Q desing 0.246 m/sec

    Spill Normal excess water= Q discharge in oriffiic - Qdesing

    0.083 m/sec

    A*C2g*(Hr-Hh)

    desing flood

    Design sizing Oriffice

    Spill normal water=

  • 8/14/2019 Design of micro hydro power

    6/119

    ID-number 28-2802-0014 -2 A

    Province: Bamyan

    District: Shebar

    Village: Gonbad

    Project type : M,H,P

    No F 256

    Step 1.

    Q= Maximum flood discharge 11.97 m/sec

    L = 4.75 Q1/2

    = Length of water way 16.432 m

    L= Provide 7.00 m

    q= Q/L= discharge per unit length of water way 0.728 m

    Step 2.

    f= Lacey ,s silt factor 1

    R= 1.35 (q2/f)

    1/3Scour depth 0.239 m

    Regime Velocity = q / R 3.05 m/sec

    Velocity hea = V2/2g 0.475 m

    Step3

    H.F L before construction 2804.90 m

    Level of d/s T.E.L.= H.F.L before cons. + V2/2g 2805.37 m

    Afflux 1 m

    Level of u/s T.E.L.= d/s T.E.L. + Afflux 2806.37

    U/s H.F.L= Us T.E.L - V^/ 2*g 2805.90 m

    Actual d/s H.F.L. allowing 0.5 m for retrogressio H.F L before construction - 0.5 2804.4 m

    Step 4.

    Discharge Over crest of the weir is given bay

    q= 1.7 k3/2

    k = (q/1.7)2/3

    0.568 m

    Crest level= u/s T.E.L. k 2805.81 m

    Step 6.

    Level of bottom of u/s pile(d1) = u/s H.F.L. 1.5 R 2805.54 m

    Design of Vertical drop weir

  • 8/14/2019 Design of micro hydro power

    7/119

    u/s pile may take up to a level ( d1 ) 2803.8 m

    d/s bed level m 2804.126 m

    Minmam water Level -U/s Pile 0.33 m

    Level of bottom of d/s pile (d2) = d/s H.F.L. after retrogression 2R 2803.92 m

    d2= Manimam water water level -Level of bottum of d/s pile 0.48 m

    Step 7.

    Head of wate 1.68 m

    H= crest level - Bed Level 1.68 m

    (B) Design of weir wall (B1)Step 8.

    Calculation of top width

    d = u/s T,E.L. Crest level = 0.568 m

    Top width B1 = d/G 0.85 m

    B1provide 1.00 m

    From sliding consideration,

    a = 3d/2G = 0.57 m

    From practical considerations, B1= s + 1 = 1.00 m

    Step 9.

    Calculation of bottom width (B)

    Consideration II.

    Mo = wh H2/2

    When the water is at the crest, dandhwill be equal. For this case, the value of d is given by

    h= d = [q2/ (2/3C)

    2x 2g]

    1/3

    (Neglecting the velocity of approach) where C = 0.58 is the coefficient of discharge. 0.58

    Substituting q= 0.673 M3/sec/m, we get 0.728 m/sec

    q= 0.53 m/sec

    (2/3C)^2= 0.15

    Height of crest

    Hence provide concrete cutoff of 0.5 m depth below the bed of river at the u/s end of

    Dept of u/s cut off = d1

    Hs =crest Level - Bed level

    the weir overturning moment given by

    When the water is flowing over the weir and the weir is submerged. Considering the tail water

  • 8/14/2019 Design of micro hydro power

    8/119

    2g= 19.62 m/sec

    d= water depth over the weir 0.565 m

    h=d= [q2/ (2/3C)

    2x 2g]

    1/30.566 m

    Mo= W h H2/2 0.80 tm

    if u/s is level The moment of resistance is given by:

    Mr = {WH(G-1)/6} (B2+ B1B - B1)

    Mr= 2.24*1.5(2.24-1)/6(B+0.85*B-0.85^)= 0.43B +0.43B -0.43*(0.85)=Mo

    0.31 +0.26B -1.18 =0

    0.31 B + 0.31 B -1.11 = 0

    B=- b+(b^2-4ac)^0.5 /2*a 1.1087 0 1.46 m

    B provide 2.2 m

    (C) Design of impervious and pervious aprons:Step 10.

    Assuming C = 12, total creep length is L = CHs

    C= 12

    L= C*Hs 20.2 m

    Step 11.

    d/s impervious apron (L1): without crest shutter L1 = 2.21*C Hs / 10 10.9 m

    Step 12.

    u/s impervious apron (L2): L2= L L1 (B + 2d1+ 2d2) 5.5 m

    Step 13.

    Total length of d/s apron L3= 18*C (Hs / 10 ) ( q / 75 ) 8.72 m

    Step 14.

    Length of filter + launching apron = L3 - L1 -2.15 m

    OR L3= Min,inve+Min,hor,Lan+L1 12.78 m

    Minimum length of inverted filter

    1.5 d2 0.72 m

    Minimum horizontal length of launching apron

    2.5 d2 1.19 m

    Total minimum length of both inverted filter+launching apron 1.91 m

  • 8/14/2019 Design of micro hydro power

    9/119

    Step 15.

    u/s block protection and launching apron:

    d1= 0.33 m

    Length of u/s block protection = d1= m. 0.33 m

    Length of u/s Talus = 2d1=. 0.652 mStep 16.

    Thickness of impervious floor

    Provide a nominal thickness of 0.2 m to the u/s of the weir wall and 0.5 m below the weir wall

    Residual pressure at point A of figure just at the d/s of weir wall

    Hr= Hs (Hs/L) x(2*d2+L-L1+B) 0.64 m

    Thickness (t) = 4/3* (Hr/G 1) 0.69 m

    Hence provide a thickness of0.59 m from the d/s of weir wall to a point 5m from

    Breing capocity of soil Sand and garval 20 T / m

    Cf Coefficient of friction 0.6

    rwater = Density of water 1 t/m

    rstone = Density of stone 2.24 t/m

    P= H/2*(2*h+H) *D,water 2.36 t/m

    Ww=Ww*(a+b)/2*H 6.02 tm

    Mo= P*H/3 (3*h+H)/(2*h+H) 1.59 tm

    X=W1*(B-B1/2)+W2*2/3*(B-B1)-Mo / Ww 1.099 m

    Mr=Ww*X 6.62 tm

    e=B/2-X 0.001 m

    ChekPmax= Ww/B *(1+6*e/B) 20 < 2.75 tm

    SFs=* Ww / P> 1.5 1.53 ok

    SFO=MR / MO> 1.5 4.16 ok

  • 8/14/2019 Design of micro hydro power

    10/119

    ID-number 28-2802-0014 -2 A

    Province: Bamyan

    District: Shebar

    Village: Gonbad

    Project type : M,H,P

    256

    pagr 5

    Breing capocity of soil Sand and garval 20 T / m h freeboard 0.2 m

    H the wire height 1.68 mL length or weir 16.432 m

    Cw were coefficint 1.5b Top width of weir 1.00 mB Bottom width of weir 2.20 mh Height of water form Top of weir 0.565 mm Coefficient of friction 0.6

    rwater = Density of water 1 t/mrstone = Density of stone 2.24 t/mQ= Maxm water in the river for flood time 11.97 md H/3 { (3h+H) / (2h + H ) } 0.673 mW1 = b*H *rstone 3.76 t/mW2 = 0.5 ( B - b)* H*Drstone 2.3 t/mW = W1 + W2 6.02 t/mP = 2.36 t/m

    Let x be the distance from toe where resultant of forces strike the base.Taking moment about toe,X=W1*(B-b/2)+W2*2/3(B-b)-P*d/w 1.0984

    P = P siol Pmatrail W 20 6.02 ok

    e = B/2 - x 0.002B/6 0.367

    < 0.367 okSliding check W * m > P

    W * m 3.61

    3.6 > 2.36 okChekPmax= Ww/B *(1+6*e/B) 20 > 2.75

    SFs=* Ww / P> 1.5 1.53 ok

    Mo= P*d 1.59 tm

    MR=Ww*(X) 6.61 tm

    SFO=MR / MO> 1.5 4.16 ok

    H/2 ( 2h + H )*D rwater

    Weir Design

    0.002

  • 8/14/2019 Design of micro hydro power

    11/119

    ID-number 28-2802-0014 -2A

    Province:

    District:

    Village:

    Project type : M.H.PNo F 256

    Head Loss:

    hf = 10 L nQ 20

    D5.3

    Pipe dia : 0.508

    hf = head loss due to friction (m) 0.27

    L = penstock length (m) 9.0 2n = roughness coefficient 0.012

    Q = flow for one pensto (m3/s) 0.554 1

    D = 41*Q^0.38

    D = internal pipe diameter (m) 0.452

    (SB p.126, "n" p.128)

    28

    Gross head (w/ forebay) (m) 8.5

    Turbulence head loss (m) 0.26

    Friction head loss (hf) (m) 0.3

    Total head loss (m) 0.5

    % loss < 10%hg (%) 6 o k

    Net Head (m) 7.97

    Velocity: v = 4 Q3.14 * d

    v = velocity limit 2.5 to3.5 (m / s) 2.73 ok

    Q = flow (m3/s) 0.554

    Provide d = Inside diameter (m) 0.508 provide

    Turbulence Losses: (DM. p. 127, SB p. 130)

    htl = v (K entrance + K bend + K valve + K contraction)

    2 g

    htl = total turbulence head loss (m) 0.26

    v = penstock water velocity (m/s) 2.73

    K entrance = 0.2

    K bend = 0.14

    K valve = 0.1

    K contraction = 0.25

    PENSTOCK Desing

    Bamyan

    shebar

    Gunbad

  • 8/14/2019 Design of micro hydro power

    12/119

    ID-number 28-2802-0014 -2A

    Province:

    District:

    Village:

    Project type : M.H.PNo F 256

    Surge calcultion

    E=youngs pressure wave velocity 200000 N/mm

    3 mm

    t=choos closuer time 5 s

    a=pressurewave velocity=1+(2150*d)/E*t 1423 m/sTc=2*L /a Critical timme of close 0.0127 sec < 5sec ok

    K=(L*V / g*hgross* T ) 0.00014

  • 8/14/2019 Design of micro hydro power

    13/119

    ID-number

    Province:

    District:

    Village:

    Project type : M.H.P

    No F 256

    H forbay 2.74

    F uried pip 5

    t thickness penstock3

    mm

    Q Flow for one penstack553.6

    L /s

    E ToungsMudlus200000

    N/mm

    D Di of penstock 14"508

    mm

    t=(effective thickness)=( t / 1.1*1.2 ) - 1 1.27 mm

    (D/ T effective)^363589452.43

    Q*(F/E)0.01

    (D/T)^3*Q*(F/E)880123.24

    (D/T)^3*Q*(F/E)938.15

    30.629mm

    L= Lingth= hf +20% 3.288 m

    d= {Q*((F/E)*(D/Teffective)3)1/2}1/2 1.206 in

    28-2802-0014 -2A

    Airvent pip desing

    d= {Q*((F/E)*(D/Teffective)3)1/2

    }1/2

    Bamyan

    shebar

    Gunbad

  • 8/14/2019 Design of micro hydro power

    14/119

    ID-numbe 28-2802-0014 -2 A

    Province: Bamyan

    District: Shebar

    Village: Gunbad

    Project ty M,H,P

    No F 256

    D penstok 0.508 m

    h1 free bourd 0.2 m

    Q discharge 0.554 m/s

    V 2.73 m/s

    hs= 1.5V/2g or we can 4*Di penstock 2.03 m

    Hf= Hf =hs+Di penstock+fery bourd +free bourd 2.74 m

    V1= vulem of forbay=20* Q discharge 11.1 m

    A= V1 / hs 5.4 m

    L= 2*A 3.30 m

    W= L / 2 1.65 m

    velocity in the penstock

    Desing Foreby for one turbin

    Width of foreby

    Length of foreby

  • 8/14/2019 Design of micro hydro power

    15/119

    28-2802-0014 -2 A

    Bamyan

    Shebar

    Gunbad

    Project type : M,H,P

    No F 256

    11

    26.5

    Width of canal 1.00

    TAN15 0.26

    V 1.11

    Q desing flow 0.5536

    d lomit 0.3 mm

    W from shilels graph 0.037 m/s

    A Required basin surface area 2*Q / W 30 m

    B width =Assum 3.30 m

    L A / B provide 10.0 m

    Vp 0.44d limit 0.24 m/s

    Y Q / B*Vp 0.70 m

    freeborad 0.2

    P=packingfactor 1

    S=density 2600 kg/m

    T=Flushing frequncy( 6 ) h 28800 sec

    C=Assum sediment concentration (kg) 2 kg

    Sedimen load Q*T*C 31889.00 kg

    V sediment=S lod / Sdecnity* P factor 12.26 m

    Ystorege= V sediment / Basin area 0.37 m

    Actual area L*B 33 m

    L inIet= Y storege / sin 1.94 m

    Required Basin depth= Y+Y storeg+Freebourd 1.27 m

    L outlet= Y storeg / sin 0.80 m

    Storage Desing

    District:

    Village:

    ID-number

    Province:

    Settling Desing

  • 8/14/2019 Design of micro hydro power

    16/119

    M.H.P

    256

    Penstock Internal Diameter d = 0.31 m

    Penstock thickness t = 0.003 m

    U/s penstock inclination R a= 28

    D/s penstock inclination R b= 2.7

    Dist. to upper support pier L2u= 0 m

    L1u= 0 m

    Dist. to lower support pier L2d= 4.5 m

    L1d= 3 m

    Buired depth of block at u/s face h1= 1 m

    Buired depth of block at d/s face h2= 0.6 m

    Ht. of block from GL to bottom of pipe at d/sh

    3=

    0.8 mLength of block (Base) B = 1.8 m

    Length of block (Top) B1= 0.89 m

    Width of block W = 1.3

    Uphill ground slope R i = 25o

    Angle of friction (soil) R fsoil= 25o

    Coefficient of friction (tar sheet used) f = 0.25

    Unit weight of soil gsoil= 17 KN/m .

    Allowable bearing pressure P = 100

    Coefficient of friction between soil and concrete m = 0.5

    Unit weight of masonry gconcrete= 20 KN/m .

    Unit weight of steel gsteel= 77 KN/m .

    Unit weight of water gwater= 9.8 KN/m .

    Ht. of block at u/s face H1= 2.1 m.

    Ht. of block at d/s face [ = h2+h3] H2= 1.4 m.

    Ht. of block from base to c.l. of bend [ = h2+h3+(.5B)Tanl ] H3= 8.432 m.

    b1= 0.856 m.

    b2= 0.054 m.

    Calculation of Block volume excluding volume of pipe

    Volume of pipe upper side 0.055Block areas h2*B a1 = 1.080 0.9 X1

    b1*(h1-h2) a2 = 0.342 0.43 X2

    a3 = 0.712 0.381 X3

    0.5*b2*h3 a4 = 0.022 1.764 X4

    0.5*B1*(H1-H2) a5 = 0.309 1.152 X5

    0.5* b1(H1-h1) a6 = 0.469 0.571 X6

    Total area of block 2.934 m

    Volume of block 3.814 m

    Bamyan

    shebar

    Gunbad

    No F

    ID-number

    Province:

    District:

    Village:

    [ = h2+h3+(B1*tan l) ]

    B1**d^2 /4*COS

    B1 *h3

    Total area of block*Width of blok

    28-2802-0014 -2A

    Design of Support Pier (SP1)

    0.663225116

    0.04712389

    0.436332313

    0.436332313

  • 8/14/2019 Design of micro hydro power

    17/119

  • 8/14/2019 Design of micro hydro power

    18/119

    Check against overturning

    1. Expansio n case

    M @O = 87.28

    d = 0.891 [ = M / V ]e = 0.009 [ = (B/2) -d ]

    eeffective= 0.300 >e ok [ = (B/6) ]

    2. Contractio n case

    M @O = 73.47

    d = 0.757 [ = M / V ]e = 0.143 [ = (B/2) -d ]

    eeffective= 0.300 >e ok [ = (B/6) ]

    Check against bearing capacity

    1. Expansio n case

    Pbase= 43.02 KN/m2 [ = (V/Abase) (1 + 6e/Lbase) ]

    2. Contractio n casePbase= 61.32 KN/m

    2

    Pallowable= 100 KN/m2 Pbase ok

    Check against sliding

    1. Expansio n case

    H < mV

    41.831 < 48.95 ok

    2. Contractio n case

    H < mV

    40.317 < 48.55 ok

  • 8/14/2019 Design of micro hydro power

    19/119

    B1

    B

    b2

    h2

    h2

    H1

    90

    h1

    b1

    l

    i

    H3

    H2

  • 8/14/2019 Design of micro hydro power

    20/119

  • 8/14/2019 Design of micro hydro power

    21/119

  • 8/14/2019 Design of micro hydro power

    22/119

  • 8/14/2019 Design of micro hydro power

    23/119

  • 8/14/2019 Design of micro hydro power

    24/119

    ID-number 28-2802-0014 -2A

    Province:

    District:

    Village:Project type : M.H.P

    No F 256

    gras head 8.50 m

    Flow= atention 0.25m for one Turbine Q= 0.554 CMS

    Net Head=Hg-Total head loss H = 7.97 Meters

    Turbine efficiency e,turb = 0.65

    V-belt efficiency e,belts = 0.90

    Generator efficiency e,gen = 0.85

    Overall efficiency e = 0.50

    23.1 KW

    Turbine shaft Power Output=1.1*Genretor out put / ( G , efficincy *V-belt efficincy) 33.2 KW

    p,turb = Shaft output power of turbine in KW.= 9.8XQ XHnXe turb 28.11 KWD runner for T12 D1 = 0.300 m

    ideal Turbine Rpm=(40 *Hn) / D runnr OR 133 *Hn RPm = 375 R/mTjet=0.2 Drunnr 0.060 m

    Rotor length (width)=0.23 *Q / Tj*Hn OR 3.623*Q/Hn bo= 0.71 mb0 to D1 ratio =bo / D1 Normal range=0.3 up to 4.0=ratios of (0.3:1) up to (4:1) 2.4 ok

    Rpm generator 1500.0 R/m

    Generator pulley OD 0.127 m

    Turbine pulley OD D>we need make Intermediate shaft 0.507 m

    after Intemediaftn shaft Turbine pulley OD (It,s raed N,S,P) 20.000 in

    NSP porogerams= Pulley ,G / Pulley ,T ( 1 / 4 ) 4.00 ok

    Ideal Specific Speed=1.2*Rp Turbine*Turbine shaft power / Hn^1.25 193.83Overspeed Specific Speed=Ideal specific speed+20% 232.59Selected Over speed Specific Speed= form geraf (Maxm) 150

    , ,

    *291

    Specific Speed=1.2*RPM TURBIN*Turbine shaft power / Hn^1.25 150% Over speed= (Overspeed R,P,M - Turbin R,P,M) / Tubin R,P,M * 100 (22.6) %

    Pulley Ratio= R,P ,M generator / Over speed R, P ,M 5.16

    Overspeed Turbine RPM for puly sizing =Ideal RPM Turbin+20% 450.59 R/m

    Turbine pulley OD = 0.423 m

    Ideal RPM ratio = 1500 / Ideal RPMTurbin 3.99 ok

    Normal range=2.0 up to 6.0=ratios of (2:1) up to (6:1)

    Overspeed RPM ratio =1500/ over speed Turbin RPM 3.33 ok

    Normal range=2.0 up to 6.0=ratios of (2:1) up to (6:1)

    Circumference of rotor Cr = 0.942

    Number of blades Nb = 28

    Distance between blades Db = 0.034

    Number of belt=Total Power to shaft / Power of one belt 4.1 Pc

    T of belt BV Power of one belt 8 kw

    Center distnce between tow puly= G Di + T Di 0.634 m

    POWER & TURBINE Desing

    Total Power=belt e*gen ,e * turbine ,e* 9.81Q*Hg ((( Not: one ,turbine ))) or P=Q*gras,H*g *0

    Bamyan

    shebar

    Gunbad

  • 8/14/2019 Design of micro hydro power

    25/119

    ID-number 28-2802-0014 -2A

    Province:

    District:

    Village:Project type : M.H.P

    No F 256

    Intermediate shaftGenerator

    (Fixed ) RPM 1500 Intermediate shaft

    inches 5 ------------- 5

    RPM 1500.0 Turbine

    5 ------------- 20 Diff

    Target RPM = 375 >>>>>>> RPM 375.00 0.5

    Target RPM Ratio = 4.00 0.13 19%

    sqrt of RPM Ratio = 2.0

    1500.0 20 1500 5 3755 375 5 1500.0

    Available Pulley Sizes

    Inches Mms Note: For T7, standard bo (mm)

    5 127 85, 100, 120, 145, 175, 210, 250, 300, 360, 430, 520,620

    6 152 For HKT, bo is upto 645mm

    7 178 Max b0 in Afg = 1.3m HKT

    8 203 For TMT, bo is generally either 165mm or 320mm

    10 254 Rote dia T12 T7 HKT A10 TMT

    12 305 D(m) 0.300 0.360 0.340 0.300 0.270

    14 356 No-blades 28 30 24 24 24

    16 406 Typ of belt A B C D

    18 457 Power(kw) 2 4 8 1120 508 RPM T12= 133*Hn bo=3.623 * Q / Hn for T12 form 100 to1120mm22 559 RPM T7= 114*Hn o= . n o

    24 610 Specific

    23 584 Speeds

    25 635.00 Pelton, single jet: 10 - 30

    26 660 Pelton, multi-jet: 18 - 70

    27 686 Turgo: 20 - 70

    28 711 Crossflow: 20 - 150

    30 762 Francis: 80 - 400

    Prop & Kaplan: 340 - 1000

    R,Pl,Md XDiPl,Md=R,Pm,G XDi,Pl G

    Di,Pl, turbin X Rp,m, turb=Rpm ,Md XD, P,Mp,turb = Shaft output power of turbine in KW.

    = 9.8 x Q x H x e,turb

    KW Q Net H e,turb= . . . .

    = 13.3 0.4 5.65 0.6

    Gunbad

    Bamyan

    shebar

  • 8/14/2019 Design of micro hydro power

    26/119

    ID-number

    Province:

    District:

    Village:

    Project type : M.H.P

    No F 256

    P power 23.082 KW

    P1 phase 3

    pf power factor 0.8

    S.F seftefactor 1.33

    V voltage 400 V

    I current Rating 95.9 A

    A area form tebal 50 and 35 mm

    arder cable form genrator to canto Cu 4X25 mm

    arder cable form cantorol panal to AL 4X50 mm

    arder cable 1.6*P for theer phase 69.2 mm

    28-2802-0014 -2A

    Bamyan

    shebar

    Gunbad

    Cable sizing

    1.33 * P / V*pf

  • 8/14/2019 Design of micro hydro power

    27/119

    Copper(C

    U)(Amps

    um nu

    m(AL)

    Amps

    Copper(C

    U)(Amps)

    um nu

    m(AL)

    (Amps)

    Copper(C

    U)(Amps)

    um nu

    m(AL)

    (Amps)

    1.5 21 16 17 13 17 13

    2.5 27 21 24 19 24 19

    4 36 30 30 23 30 23

    6 45 35 38 30 39 30

    10 60 47 50 39 52 40

    16 77 60 64 50 66 51

    25 99 77 81 63 90 70

    35 120 94 99 77 110 86

    50 145 110 125 95 135 105

    70 175 135 150 115 165 130

    95 210 165 175 140 200 155

    120 240 185 195 155 230 180

    150 270 210 225 175 265 205

    185 300 235 255 200 305 240

    Current rating (AC) for three and four core 110 volts armoured or

    unarmoured cables

    cross

    section

    area

    (mm)

    Laid direct in Ground Laid Duct Laid in Air

  • 8/14/2019 Design of micro hydro power

    28/119

    temperature in C 20 25 30 35 40

    A Temperature factor 1.1 1.08 1.06 1.03 1

    Altitudes 1000 1250 1500 1750 2000

    B1 altitude factor 1.00 0.98 0.96 0.945 0.93

    Altitudes 3000 3250 3500 3750 4000

    B2 altitude factor 0.86 0.845 0.83 0.815 0.80

    C ELC corection factor

    when load is light bulbs only

    D power factor

    when load includes tube light and other imductive lodes

    max.Ambeant

    generator rating factors

  • 8/14/2019 Design of micro hydro power

    29/119

    ID-numbe

    Province

    District:

    Village:

    Project ty M.H.P

    No F 256

    A- temperature in C 1.03 c

    B- Altitudes 2250 0.915

    C- ELC corection factor 0.83D- power factor 0.8

    S- seftefactor 1.3

    P- power 23.082 kw

    G- generator *P /A*B*C*D 48.0 KVA

    G- generator 1.3* P 30 kw

    Bamyan

    shebar

    Gunbad

    Genertor Selection

    28-2802-0014 -2A

  • 8/14/2019 Design of micro hydro power

    30/119

    ID-number

    Province: Bamyan

    District: shebar

    Village:

    Project type : M,H,P

    No F 256

    P= 23.0822 kwat90.16 wat

    o age rop a cu a on or ransm ss on an s r u on ys em:

    3

    Conde

    ctivity

    0f AL

    Power

    factor

    Sectio

    n

    No-F

    in

    section

    To-No-

    F in

    section

    Length

    between

    nodes (m)

    ACSR

    area(

    mm)

    Phase

    1,3

    Power at

    node (W)

    Rated

    Voltage

    (V)

    Current

    (A)

    Voltage

    drop

    (V)

    Volt

    nod

    branc

    (V)

    S 256 1624 K 3 400 400

    1.73 35 0.8 PH-A 103 256 694 50 3 23082.2 400 41.65 28.6 371

    1.73 35 0.8 A-B 55 153 533 50 3 13795.19 400 26.81 14.1 357

    1.73 35 0.8 B-C 68 98 255 50 3 8836.14 400 17.85 4.5 3521.73 35 0.8 C-D 30 30 142 50 3 2704.94 400 . .

    3 400 371

    1.73 35 0.8 A-K 70 70 300 16 1 6311.53 230 12.26 13.1 201

    3 400 357

    1.73 35 0.8 B-J 49 49 200 50 1 4418.07 230 15.84 3.6 202

    3 400 352

    1.73 35 0.8 C--H 51 51 50 16 1 4598.40 230 9.41 1.68 202

    3 400 352

    1.73 35 0.8 D-E 23 23 300 16 1 2073.79 230 4.25 4.6 198

    3 400 352

    1.73 35 0.8 D-F 39 39 281 16 1 3516.42 230 7.21 7.2 196

    3 400 352

    1.73 35 0.8 D-G 24 24 500 16 1 2163.95 230 4.44 7.9 195

    for 3 phase for 1 phase

    I= P / 1.732 x 0.8 x V I= P/V*pf

    V= I x 1.732 x L / K* A V= (2X L X I ) / K x A

    Wat /Family

    28-2802-0014-2A

    Gunbad

  • 8/14/2019 Design of micro hydro power

    31/119

    ID-number

    Province: Bamyan

    District: shebar

    Village:

    Project type M,H,P

    No F 256

    P= 23.0822 kwat

    90.164664 wat

    Voltage Drop Calculation for Transmission and Distribution System:

    3

    Conde

    ctivity

    0f AL

    Power

    factor

    Sectio

    n

    No-F

    in

    section

    To-No-

    F in

    section

    Length

    between

    nodes (m)

    ACSR

    area(

    mm)

    Phase

    1,3

    Power at

    node (W)

    Rated

    Voltage

    (V)

    Current

    (A)

    Voltage

    drop

    (V)

    b

    S 256 3070 3 400

    1.732 35 0.8 PH-A 256 256 694 50 3 23082.2 400 41.65 28.61

    85 850 3 400

    1.732 35 0.8 A-K 36 85 300 50 1 7664.0 230 14.89 5.111.732 35 0.8 K-L 24 49 200 35 1 4418.1 230 26.39 8.62

    1.732 35 0.8 L-M 18 25 170 35 1 2254.1 230 14.04 3.90

    1.732 35 0.8 M-N 7 7 180 16 1 631.2 230 4.01 2.58

    85 653 3 400

    1.732 35 0.8 A-D 47 85 300 35 1 7664.0 230 14.89 7.29

    1.732 35 0.8 D-E 25 38 200 25 1 3426.3 230 20.68 9.45

    1.732 35 0.8 E-F 13 13 153 16 1 1172.1 230 7.41 4.05

    86 873 3 400

    1.732 35 0.8 A-G 42 86 500 50 1 7754.2 230 15.07 8.61

    1.732 35 0.8 G-H 25 44 198 35 1 3967.2 230 24.10 7.79

    1.732 35 0.8 H-I 19 19 175 25 1 1713.1 230 10.82 4.33

    for 3 phase for 1 phase

    I= P / 1.732 x 0.8 x V I= P/V*pf V= I x 1.732 x L / K* A V= (2X L X I ) / K x A

    Wat /Family

    28-2802-0014-2A

    Gunbad

  • 8/14/2019 Design of micro hydro power

    32/119

    ID-number

    Province:

    District:

    Village:

    Project type : M.H.P

    No F 256

    P power 33.19 KW

    P1 phase 3

    pf power factor 0.8

    S.F seftefactor 1.25

    V voltage 400 V

    I current Rating 43.2 A

    Fuse sizing

    28-2802-0014 -2A

    SF * P / 3* V*pf

    Bamyan

    shebar

    Gunbad

  • 8/14/2019 Design of micro hydro power

    33/119

    ID-number 28-2802-0014 -2 A

    Province: Bamyan

    District: Shebar

    Village: GunbadProject type : M,H,P

    No F 256

    11

    26.5

    d limet 2 mm

    Q Full canal flow, 0.903 m3/sec.

    H flow depth 0.7300 m

    B width of headrace 1.00 mV Velocity 1.11 m/s

    A area Q / V 0.815 m

    dimension such 4 L / b 10

    B Width 6.00 m

    L Length of the gravel trap 6*B 10.00 m

    L/ B= 1.67 ok

    Vp Maximum Horizontal vlocity 0.44 dlim 0.62 m/s

    Y depth of basin Q / B* Vp 0.2 m

    0.73 okL inIet= Y storege / sin 1.3 m

    Sediment storage requirement Assume sediment concetration

    h freeborad 0.2

    C 2 kg/m

    S density 2600 kg/m

    P Pfactor 1

    T 21600 ses

    S Sedimen load Q*T*C 39005.77 kg

    V V sediment=S lod / Sdecnity* P factor 15.0 m

    Y depth of storege= V sediment / Basin area 0.25 m

    A Actual area L*B 60 m

    L outlet= Y storeg / sin 0.54 m

    Required Basin depth= Y+Y storeg + Freebourd 1.18 m

    Flushing frequency( 6 ,h )

    DesingGravel trap

    Y =flood hight

  • 8/14/2019 Design of micro hydro power

    34/119

    ID-number

    Province:

    District:

    Village:M.H.P

    No F 256

    h= freebourd 0.2 M

    Q= desing flow 0.554 M / S

    Cw= 2.76

    H= 2.74 m

    H= 2.54 m

    d= {(4*Qdesing / *C * (h flush)}^1.2

    d= 0.40 m

    d= 16 in

    A= is the area of pipe= *d^ / 4 0.126 m

    Q desing C*A * h flush 0.554 m /sec ok

    d= {(6*Qdesing / *C * (h flush+h basin)}^1.2 0.408 m

    A= is the area of pipe= *d^ / 4 0.131 m

    1.5 *Q desing = C*A * hflush+h basin 0.830 m /sec

    1.5*Q desing= 0.830 m /sec ok

    28-2802-0014 -2A

    is the flushing head when basin is empty

    the pipe dimeter can be determined by rewriting the above equation as

    water depth in the basin during the desing

    flow prior to flushing

    orifice coefficient

    Vertical flush pipe

    Bamyan

    shebar

    Gunbad

  • 8/14/2019 Design of micro hydro power

    35/119

    ID-number28-2802-0014 -2 A

    Province: Bamyan

    District: Shebar

    Village: GunbadProject type : M,H,P

    No F 256

    h= freebourdM

    Q= Q desingM / S

    Q=M / S

    Cw=

    hm

    1

    2

    Cas-2 during flood Q flood - Q desingM / S

    L= length of spillway L = 2* Q / Cw X h ^1.5M

    h= freebourdM

    Q= Q designM / S

    Q= discharge in oriffic

    Q= Excess water

    Cw=

    hm

    L= length of spillwayM

    weir coefficient

    spillway crest should be 0.05m above normal canal water level no morden 50%of the freebourd

    Spillway (Weir ) Calculations for geraval terips

    0.2

    0.05overtop= (0.5*freeborard-0.05)

    0.554

    1.6

    9.33

    0.554

    overtop= (0.5*freeborard-0.05)

    L = 2* Q excess / Cw X h 1.5

    Spillway (Weir ) Calculations for spill deschage

    0.083

    0.637

    0.05

    1.6

    0.353

    Maxm water in the canal for floodl time=A *V 0.906

    0.5

    weir coefficient

    Qdesign - Qdischarch in oriffice

    the spillway shuld be able to spil the excess flow when there is no obstruction

    39

    0.2

    the spillway must be abie to conveey the entire flood floe of in case the headrace canal

    downstream gets obstructed

  • 8/14/2019 Design of micro hydro power

    36/119

  • 8/14/2019 Design of micro hydro power

    37/119

    ID-number

    Province:

    District:

    Village:

    Project type : M.H.P

    No F 256

    h1= highte,c 3 m

    h= hight e,c materials 10 m

    ha= h-h1 7 m

    rx= 1.6 *ha / ( 1+h1 / h) 8.62 m

    Thunderbolt cacolation

    28-2802-0014 -2A

    Bamyan

    shebar

    Gunbad

  • 8/14/2019 Design of micro hydro power

    38/119

    ID-number

    Province:

    District:

    Village:

    Project type : M.H.P

    No F 256

    Penstock internal diameter (d / 2)=0.62/2 d = 508 mm

    Penstock thickness t = 3 mm

    Penstock internal diameter (Smaller) dsmall= 0 mm

    Gross head h gross= 8.5 m

    Surge head h surge= 0.10 m

    U/s penstock inclination 0.48869 R a= 28 D/s penstock inclination 0 b= 0

    L1u= 7.5 m

    L1d= 2.3 m

    Total H= hg + hsu h total= 8.60 m

    Buired depth of block at u/s face h1= 1.2 m

    Buired depth of block at d/s face h2= 0.4 m

    Ht. of block from base to CL of pipe at d/s h3= 0.59 m

    Ht. of block from CL of pipe to top at d/s h4= 0.91 m

    Ht. of block from CL of pipe to top at u/s h5= 0.85 m

    Length of block L = 2.51 m

    Width of block B = 2 m

    Bend position from u/s face of block b1= 2

    Uphill ground slope 0.20944 R i = 12 Angle of friction (soil) 0.5236 R fsoil= 30 Coefficient of friction steel onsteel with tar oaper in between f = 0.25

    Unit weight of soil gsoil= 20 KN/m3

    Allowable bearing pressure P = 100

    Coefficient of friction between soil and concrete m = 0.5

    No. of support piers u/s N = 0

    Unit weight of concrete gconcrete= 22 KN/m3

    Unit weight of steel gsteel= 77 KN/m3

    Unit weight of water gwater= 9.8 KN/m3

    28-2802-0014 -2A

    Design of Anchor Block # Type AB2

    Dist. to upper

    Dist. to lower

    Bamyan

    for stiff day soil

    shebar

    Gunbad

    for stiff day soil

  • 8/14/2019 Design of micro hydro power

    39/119

    2

    Ht. of block at u/s face= H1= 2.903 m

    Ht. of block at d/s face H2= 1.9 m

    Ht. of block from base to c.l. of bend h2+h3 H3= 0.99 m

    Bend position from u/s face of block B-b1 b2= 0 m

    Calculation of Block volume excluding volume of pipe

    Volume of pipe upper side a 0.4591 m

    Volume of pipe downward side b 0.0000 m

    Total volume of pipe a+b A 0.459 m

    Volume of block excluding pipe B 12.057 m

    Volume of block B-A 11.597 m

    Weight of the block Wb= B-A *concrate 255.14 KN

    Weight of pipe Wp= A 0.37 KN/m

    Weight of water Ww= B 1.99 KN/m

    Wp+ Ww = A+B 2.36 KN/m

    Calculate the relevant forces

    F1u= 15.609 KN

    F1d= 5.421 KN

    Hydrostatic force F3= [ = 15.4*htotal *d2*Sin( (b-a)/2)] -8.269 KN

    Soil force

    Ka= [ cosi - (cos2i - cos

    2f)0.5 / cosi + (cos2i - cos2f)0.5 0.365F10= [ gsoilh12Cosi Kaw / 2] 10.291 KN

    This force acts at from base. 0.400 m.Resolution of forces

    a= 28 o = 0.49 Rfsoil= 30 o = 0.52 R

    i = 12o

    = 0.21 R

    = 0o =

    0 R

    F1u= 15.609 - F1u *Sin -7.328 Fu1*Cosin 13.782

    F1d= 5.421 - F1u *Sin 0.000 F1d*Cosin 5.421

    F3= -8.269 F3*Sin((-)/2 2.001 F3*Coson((-)/2) 8.024

    F10= 10.29 F10*Sini 10.066 F10*Sini 2.140Wb= 255.144 0 255.144

    H = 10.066 Exp. V = 262.705 Exp.

    H = 12.066 Cont. V = 270.729 Cont.

    The center of gravity of the block from point O

    0.90 m.

    Weight of the block Wbacts at 0.895 from O.

    SUM

    SUM

    (H2*B + B*(H1-H2)*0.5)* L

    *d^2 / 4 ) * water

    Wp+ Ww )* L1u*COSa

    (d+t) * t * steel

    X - component (KN)

    h2+h3+h4

    ( h2+h3+h5+(b1*tan27)

    Y - component (KN)

    Wp+ Ww )* L1d*COSb

    Forces (KN)

    b1**d^2/ 4*Cosab2**d^2/ 4*Cosb

  • 8/14/2019 Design of micro hydro power

    40/119

    3

    Sum of horizontal forces that act at the bend H -F10x

    1. Expansion case 0.000 KN

    2. Contraction case 2.001 KN

    Acting at = 0.990 from O

    Sum of vertical forces that act at the bend V -F10y -Wb

    1. Expansion case 5.421 KN

    2. Contraction case 13.445 KN

    Acting at = 2 from O

    Check against overturning

    1. Expansion case

    M @O = 249.27

    d = 0.949 [ = M / V ]

    e = 0.051 [ = (B/2) -d ]

    eallowable= 0.333 >e ok [ = (B/6) ]

    2. Contraction c ase

    M @O = 267.30

    d = 0.987 [ = M / V ]

    e = 0.013 [ = (B/2) -d ]

    eallowable= 0.333 >e ok

    Check against bearing capacity

    1. Expansion case

    Pbase= 60.36 KN/m2

    [ = (V/Abase) (1 + 6e/Lbase) ]

    2. Contraction c ase

    Pbase= 55.98 KN/m2

    Pallowable= 100 >Pbase ok KN/m2

    Check against sliding

    1. Expansion case

    H < mV10.066 < 131.35 ok

    2. Contraction c ase

    H < mV12.066 < 135.36 ok

  • 8/14/2019 Design of micro hydro power

    41/119

    4

    i

    B

    bi

    H3

    H1

    H2

    h1

    h5

    h4

    h

    3

    h2

    b2

    l

    b= 0

  • 8/14/2019 Design of micro hydro power

    42/119

    ID-number

    Province:

    District:

    Village:

    M.H.P

    No F 256

    h= for in site 0.50 cm

    H Nrmal water level in canal 0.50 m

    Q flow in canal 0.55 m/s

    b space between bars (50 to 75 mm) 0.06 m

    t thickness bars 0.003 m

    Kt trashrack loss coefficient from tebal 2.40

    L= Length of trashrack 3.30 m

    g gravitation constant 9.81 m/s

    a= cross section area of water=L* H 1.65 m

    t/b ratio of maximum bar thickness to space btween bars 0.05 mm

    V approach velocity = desing flow / cross section area o (0.5 -1 ) m / s 0.34 m/s

    A1 Area of discharch Q / V 1.65 m

    = angle of bars with horizontal 60.00

    = RADIANS 1.05 R

    S= Lenght of trashrack slop (H+freeboard) / sin 0.81 m

    A2= L * S all area 2.67 m

    A3= t+b= area steel and blank space 0.06 m

    NO= A2 / t+b 42.35 m

    A4= t *(A2 / t+b) 0.13 m

    A5= A2-A4 area balnk Space 2.54 noNO= no of balnk Space A5 / b 42.35 no

    h=kt* (t / b) 4 / 3*(V^2 / 2g)*sin 0.08 m

    Desing Trashrack for forbay

    h=head loss across trashrack

    28-2802-0014 -2A

    Bamyan

    shebar

    Gunbad

  • 8/14/2019 Design of micro hydro power

    43/119

    ID-number 28-2802-0008 -1 A

    Province: Bamyan

    District: Shebar

    Village: Ljalmesh CCD

    M,H,P

    No F 321

    H flood water level in rever 0.774 m

    Q Discharge through the oriffic during flood flow 0.799915069 m/s

    b space between bars (50 to 75 mm) 0.06 m

    t thickness bars 0.003 m

    Kt trashrack loss coefficient from tebal 2.4

    L= oriffice width 2.875 m

    L= for trashrack porovid 3.075 m

    g gravitation constant 9.81 m/s

    a= cross section area of water=L*H 2.38005 m

    t/b ratio of maximum bar thickness to space btween bars 0.05 mm

    V approach velocity Desing floow/ caras section wat (0.5 to 1 ) 0.336091708 m/s

    A1 Area of discharch Q / V 2.38005 m

    = angle of trashrack with horizontal 60

    = RADIANS 1.047197551 R

    S= Lenght of trashrack slop (H+freeboard) / sin 1.124678324 m

    A2= L * S all area trashrack 3.458385847 m

    A3= t+b= area steel and blank space 0.063 m

    NO= A2 / t+b 54.89501345 no

    A4= t *(A2 / t+b) 0.16468504

    A5= A2-A4 area balnk Space 3.293700807

    NO= no of balnk Space A5 / b 54.89501345 no

    h=kt* (t / b) 4 / 3*(V^2 / 2g)*sin 0.001005166 m

    Desing Trashrack for Oriffce

    h=head loss across trashrack

  • 8/14/2019 Design of micro hydro power

    44/119

    ID-nu

    Provi

    Distri

    Villag

    Proje M.H.P

    No F 256

    P= #### Kwat

    No- F= 256 K J H

    Wat / H= #### V= Volt 13.14 V= Vol 3.62 V= Volt 1.68

    Pf = 0.8 V=Volt 201.3 V=Volt 202.7 V=Volt 202

    Phase = three =(m) 300 L=(m) 200 L=(m) 50

    =(mm) 16 =(mm) 50 =(mm) 16No-F= 70 No-F= 49 No-F= 51

    power=wat 6311.5 p=wat 4418.07 p=wat 4598.4

    V= Volt 28.6 V=Volt14.14 V=Volt 4.5

    L=(m) 694 V=Volt 371.4 V=Volt 357.3 V=Volt 352.8

    =(mm) 50 A B CNo-F= 256 L=(m) 533 L=(m) 255 L=(m) 142

    power=wa = mm = mm = mmNo-F=no 153 No-F=no 98 No-F=(no) 30

    power=wat 13795.194 power=wat 8836.1 power=wat 2704.9

    P,H

    28-2802-0014 -2A

    shebar

    Bayan

    Gunbad

  • 8/14/2019 Design of micro hydro power

    45/119

    ID-number 28-2802-0014 -2A

    Province: shebar

    District: Bayan

    Village: Gunbad

    Project type : M.H.P

    No F 256 L=(m) 153

    P= Kwat =(mm) 16

    No- F= 256 No-F= 13 F V=

    Wat / H= power=wat 1172.14 V=Vol

    Pf = 0.8

    Phase = three L=(m) 200

    =(mm) 25 E

    No-F= 38 V= Volt 9.5

    power=wat 3426 V=Volt 197.6

    L=(m) 300 D

    =(mm) 35 V= Volt 7.3

    No-F= 85 V=Volt 207

    power=wat 7664 L=(m) 300 =

    =(mm) 50 V= Volt 8.61583 N

    No-F= 85 V=Volt 200.7 owe

    V= Volt 28.61 power=wat 7664 K L

    L=(m) 694 V=Volt 371.4 A V= Volt 5.1061 L=(m) 200

    =(mm) 50 V=Volt 209 =(mm) 35

    No-F= 256 L=(m) 500 G No-F= 49

    power=wat =(mm) 50

    V= Volt 8.6 power=wat 4418No-F= 86 V=Volt 206

    power=wat 7754 L=(m) 198 H

    =(mm) 35 V= Volt 7.8

    No-F= 44 V=Volt 198

    power=wat 3967

    =

    N

    powe

    23082

    23.08

    90.2

    P,H

  • 8/14/2019 Design of micro hydro power

    46/119

    ID-number

    Province:

    District:

    Village:

    Project typ M.H.P

    No F 256

    Community:

    No. of No of Total Length (40m spacing) No. of In

    Wires x-arms/pole of Wire (m) No. of Poles and Shac

    50mm2 PH-A 694 4 2 2,776 17 69

    A-G 500 2 1 1,000 13 25

    AK 300 2 1 600 8 15

    Total 1,494 4,376 37 109+20% sag 5,251

    Use 5,500

    Kgs of wire 1,500

    35mm2 K-L 200 2 2 400.0 5 10

    L-M 170 2 1 340 4 9

    A-D 300 2 1 600 8 15

    G-H 198 2 1 396 5 10

    0 0 0

    0 0

    Total 868 1,736 22 43

    +20% sag 2,083

    Use 2,200

    Kgs of wire 2,300

    25mm2 D-E 200 2 1 400 5 10

    H-I 175 2 1 350 4 9

    0 0 0

    0 0 0

    0 0 0

    0 0 0

    0 0 0

    Total 375 750 9 19

    +20% sag 900Use 1,000

    Kgs of wire 106

    16mm2 M-N 180 2 1 360 5 9

    E-F 153 2 1 306 4 8

    0 0 0

    0 0 0

    0 0 0

    0 0 0

    Gunbad

    MHP Equipment Estimating Utilities: Electrical materials, Pen

    28-2802-0014 -2A

    Bamyan

    shebar

    Toghi pain

    Summary of Electrical Materials

    Item Details Length

  • 8/14/2019 Design of micro hydro power

    47/119

    Total 333 666 8 17

    +20% sag 799

    Use 850

    Kgs of wire 90

    TOTALS

    Stay rods & Earthing Straight Length Kgs of Elec (40m spacing) No. of In

    Wire Sets Plates of Run Nuts & Bolts Kgs of wire No. of Poles and Shac

    (See map) 5 2,737 38 3,996 77 18

    1 L, 2S 1 L, 2 S 21 5 82 20

    2x4mm2 line Alum 40M*226HH 0 0 0

  • 8/14/2019 Design of micro hydro power

    48/119

    Electrical Parts of M:H :PID-number 28-2802-0014 -2A

    Province Bamyan

    District: Shebar

    Village Gunbad

    Project purpose M,H,P

    NO of family 256

    CDC Afg NSP Afg

    1 Genrator (30)kW, three Phase, Brush type 1 pc 30000 30000 0 30000

    2 ACSR d=50mm 5,500 meter 35 192500 0 192500

    ACSR d=35mm 2,200 meter 30 66000 0 66000

    3 ACSR d=25mm 1,000 meter 25 25000 0 25000

    4 ACSR d=16mm 850 meter 20 17000 0 17000

    5 D-Bracket and Insulator (complete set) 200 pc 100 20046.1 0 20046.1

    6 Cross -arms(50 cm long -10cmX10cm) 106 pc 300 31666.8 0 31666.8

    7 Stay sets (complete) 2 set 350 700 0 700 As

    8

    Earthing Set (60cmX60cmX3mm copper plate,

    10m long 4mm dia copper wire, 5m long 19mm

    dia GI Pipe, 10kg Salt, 1 bag charcoal)

    4 set 3000 12000 0 12000

    9 Control Panel (complete set) 1 pc 15000 15000 0 15000

    10 Signboard 1 pc 1000 1000 0 1000

    11 Tools & tool box 1 pc 1000 1000 0 1000

    124X35mm2 CU cable (to connect Gnerator and

    Control Panel)25 m 300 7500 0 7500

    134X50mm2 Al Cable (to connect control panel and

    first Pole)50 m 250 12500 0 12500

    14 7m high wooden pole 82 pc 1000 81750 71219.49 10530.51

    513662.9 71219.49 442443.4

    Note: Any other needed material can be added.

    No particular of item and delail of work Quantity Unit Unit price inAFS

    Total price inAfs

    Contribution

  • 8/14/2019 Design of micro hydro power

    49/119

    she

    No :Famil

    1 5.00 pc 100.00 500.00 500

    2 5.00 pc 200.00 1000.00 100

    3 1.00 pc 500.00 500.00 500

    4 2.00 pc 1500.00 3000.00 300

    5 6.00 pc 60.00 360.00 360

    6 20.00 m 20.00 400.00 400

    7 770.12 m 0 0.00 0.

    81986.26 bag 350 695192.50 6951

    9 553.18 m 1000 553184.89 5531

    10 5.20 m 100 520.00 520

    11 6.00 kg 10 60.00 60

    12 1.00 pc 3000 3000.00 300

    13 1.00 pc 3500 3500.00 350

    14 2.00 pc 800 1600.00 160

    15 4.61 kg 70 322.87 322

    16 3.12 m 200 624.75 624

    17 22.31 kg 15 334.67 334

    18 0.60 kg 200 120.44 120

    19 0.60 kg 10 6.02 6.

    20 2.11 kg 200 422.82 422

    21 3.92 kg 65 254.48 254

    22 94.57 pc 300 28370.40 2837

    23 175.45 pc 200 35090.40 3509

    24 368.62 kg 60 22117.38 2211

    25 63.54 ml 300 19062.00 19062

    26 2.58 kg 80 206.43 206

    27 1.00 Pc 100 100.00 100

    28 657.28 md 700.00 460095.21 4600

    29 1400.90 md 350.00 490314.51 2445

    Instelation G,I hood

    Wair 1mm

    Unskilled labour on site

    Marble powder

    wooden beem 25 cm,L=4.00 m

    bourd 2X0.2X0.02

    Steel 10mm area

    oil

    wheel barrow

    Complete window(1X1)m

    Glasses

    Niel

    :)(

    28-28020014 - 2A Gunbad

    solt

    ...

    wooden beem 40 cm,L=5.00 m

    soil

    Straw

    Cement

    Sundy

    Rope

    Oil paint

    Complete Windows(1.5X1.5)m

    Stone

    Rubber bucket

    shovel with handl

    pickax with handl

    slodge hammer with handl

    Complete Doors (1.2X2.2)m

    powder paint

    Skilled labour on site

  • 8/14/2019 Design of micro hydro power

    50/119

    sh

    No :Famil 256

    30 1.00 pc 30000.00 30000.00 0

    31 5500.00 meter 35.00 192500.00 0

    32 2200.00 meter 30.00 66000.00 325

    33 1000.00 meter 25.00 25000.00 250

    34 850.00 meter 20.00 17000.00 170

    35 200.46 pc 100.00 20046.06 200

    36 105.56 pc 300.00 31666.81 316

    37 2.00 set 350.00 700.00 70

    38 4.00 set 3000.00 12000.00 120

    39 1.00 pc 15000.00 15000.00 150

    40 1.00 pc 1000.00 1000.00 100

    41 1.00 pc 1000.00 1000.00 100

    42 25.00 m 300.00 7500.00 750

    43 50.00 m 250.00 12500.00 125

    44 81.75 pc 1000.00 81750.00 817

    45

    1.00 set 80000.00 80000.00 800

    46

    9.00 m 2500.00 22500.00 225

    47 3.29 m 150.00 493.20 49

    48 15.00 m 150.00 2250.00 225

    49 2.67 m 4000.00 10692.00 106

    50 1.00 set 4000.00 4000.00 400

    51 1.00 set 3000.00 3000.00 300

    52 1.20 m 10000.00 12000.00 120

    53 1.20 m 10000.00 12000.00 120

    54 Ls Ls 30000.00 30000.00 300

    55 Ls Ls 15000.00 15000.00 150

    3025858 2304

    Sluice Gate ( 1.2m (H)X 1m (B)) for settling basin

    3" Valve with 2m GI Pipe

    7m high wooden pole

    Trahsrack (3.3mX0.81m) with frame, 20mm spacing of bar, bar

    size: 5mmX25mm for forbay

    508mm dia, 3mm thickness, MS Penstock Pipes with one

    bends and required washers, bolts and nuts (Bends are shown

    in DWG)

    ACSR d=35mm

    Cross -arms(50 cm long -10cmX10cm)

    Stay sets (complete)

    Signboard

    :28-28020014 - 2A

    Earthing Set (60cmX60cmX3mm copper plate, 10m long 4mm di

    us ng one . m a, . m e g , s s own n

    DWG

    A. : Turbine (33 kW, T12), B.: Adaptor for Turbine, C: . Base

    Frame for Turbine and Generator, D: . Intermediate Shaft, E.:

    Pulleys (-20" nos, 5" - 3 ) F: . D, V Belts-3 nos

    D-Bracket and Insulator (complete set)

    ACSR d=50mm

    Genrator (30)kW, three Phase, Brush type

    PVC Pipe for flushing (arani)

    Airvent pipe (diameter=30.62 mm) ( 1 .2inch)

    Control Panel (complete set)

    Tools & tool box

    4X50mm2 Al Cable (to connect control panel and first Pole)

    4X35mm2 CU cable (to connect Gnerator and Control Panel)

    Taransportation

    Probables

    Sluice Gate for geravaltiraos (1.2m(H) X0.1 m (B))

    ...

    ACSR d=16mm

    ACSR d=25mm

    Total

    Gunbad

  • 8/14/2019 Design of micro hydro power

    51/119

  • 8/14/2019 Design of micro hydro power

    52/119

    sheb

    No :Famil 256

    1 Tooles LS LS 5760 576

    2 Site preparation m 929.99 14 13019.8 0.0

    3 Excavation m 446.69 175 78171.4 0.0

    4 Stone massonary m 770.12 1628.9 1254456.4 107935

    5 Shutting m 47.28 1413.5 66835.9 635266 RCC(1:2:4) m 3.36 4250 14287.5 13110

    7 PCC(1:4:8) m 144.08 3550 511495.5 46106

    8 Mechanical Part Ls LS 0 146935.2 14693

    9 Electrical Part Ls LS 0 513662.9 44244

    10 Steel work kg 368.62 71.41 26323.4 25420

    11 Palastering m 435.26 205 89227.8 61806

    12 Ponting m 703.28 202.5 142415.0 10056

    13 Carpentary Work pc 4.00 2151 8604.0 8324

    14 Water Pinting m 30.11 34.2 1030.2 1030

    15 Installtionn woodenbeem 3/m L=5m M.L 63.54 321 20396.3 19729

    16 oil painting on wooden m 7.83 293.7 2299.7 2217

    17 Installation of glass 3mm m 2.98 238 708.1 666

    18 mud pull work of roof m 12.00 71.5 858.0 768

    19 mud & straw m 12.00 39.3 472.0 304

    20 fixing bourd on the roof m 13.44 546.9 7350.3 7162

    21 Filling m 4.00 275 1100.0 400

    22 geraval Levaling m 74.41 1014 75448.4 74406

    23 Transportation % LS 0 30000.0 3000

    24 Probables % LS 0 15000.0 1500

    Total(Afs) 3025858 25600

    NSPSNO Itam Unit Quantity Unit cost Total cost

    28-2802-0014 - 2A Gunbad

    :)(

  • 8/14/2019 Design of micro hydro power

    53/119

    ID-No : 028-28027-0014 -2A

    Provence : Bamyan

    District : Shebar

    CDC : Gunbad

    Sub Project : M,H,P Totl Budg:

    Unit Cost Total Cost Activity

    Af AF CDC NSP % 1 2 3 4 5 6 7

    1 Tooles LS LS 5760 5760 0.19362 Site preparation m 929.99 14 13019.8 13019.8 0.0 0.4376

    3 Excavation m 446.69 175 78171.4 78171.4 0.0 2.6275

    4 Stone massonary m 770.12 1628.9 1254456.4 175102.9 1079353.5 42.165

    5 Shutting m 47.28 1413.5 66835.9 3309.9 63526.1 2.24656 RCC(1:2:4) m 3.36 4250 14287.5 1176.6 13110.9 0.4802

    7 PCC(1:4:8) m 144.08 3550 511495.5 50429.1 461066.3 17.193

    8 Mechanical Part work Ls LS 0 146935.2 0.0 146935.2 4.9388

    9 Electrical Part work Ls LS 0 257662.9 71219.5 186443.4 8.6607

    10 Steel work kg 368.62 71.41 26323.4 903.1 25420.2 0.8848

    11 Palastering m 435.26 205 89227.8 27421.2 61806.6 2.9992

    12 Ponting m 703.28 202.5 142415.0 41845.4 100569.6 4.7869

    13 Carpentary Work pc 4.00 2151 8604.0 280.0 8324.0 0.2892

    14 Water Pinting m 30.11 34.21475 1030.2 0.0 1030.2 0.0346

    15 Installtionn woodenbeem M.L 63.54 321 20396.3 667.2 19729.2 0.6856

    16 oil painting on wooden m 7.83 293.7 2299.7 82.2 2217.5 0.0773

    17 Installation of glass 3mm m 2.98 238 708.1 41.7 666.4 0.0238

    18 mud pull work of roof m 12.00 71.5 858.0 126.0 732.0 0.0288

    19 mud & straw m 12.00 39.33333 472.0 168.0 304.0 0.0159

    20 fixing bourd on the roof m 13.44 546.9 7350.3 141.1 7209.2 0.2471

    21 Filling m 4.00 275 1100.0 700.0 400.0 0.037

    22 geraval Levaling m 74.41 1014 75448.4 1041.7 74406.7 2.536

    Total 2719098 465846.8 2253251

    1InstalationACSR 50mm

    tarnsmission Linem 5500.00 35.00 192500 192500 6.470

    2InstalationACSR 25mm

    tarnsmission Linem 1340.00 25.00 33500 33500 1.126

    3 Instalation genrator Pc 1 30000 30000 30000 1.008

    Total256000 256000

    G-Total2975098 465846.8 2509251 100

    FirstInstalment((90)%

    2nd

    Instal

    lment

    Summary Work Plan

    3025857

    Milstone No Discription Unit QuintityContribution

  • 8/14/2019 Design of micro hydro power

    54/119

    18

  • 8/14/2019 Design of micro hydro power

    55/119

    Project Summary Sheet

    Project

    No- F 256

    Goal of Sub Project: for light to family

    4-Fixing Torben & Genrator 5- Fixing line

    Budget

    Total: = 3025857.82 Afs NSP: = 2560000.0 Afs CDC:= 465857.82 A

    Expected Training needs: yes

    90% Afs Afs Afs

    Afs Afs

    Total buget 3025857.82

    Project Risks -NO

    Number of Disbursements: ----------TWO--------------------------------------------------------------------------------------------------------------

    10% Afs 0.00 256000.0

    Beneficiaries: All Family

    Project Milestones

    CDC NSP

    465858 2304000

    ID-number : 28-2802-0014 - 2 A

    Province : Bamyan

    District : Shebar

    Village : Gunbad

    M,H,P

    Brief descripption of main activities: 1-Excavation in the foundation 2-Stonemassonary 3- R.C.C & P.C.C

  • 8/14/2019 Design of micro hydro power

    56/119

  • 8/14/2019 Design of micro hydro power

    57/119

    (

    2058.2

    )10(

    )9(30000 6 30000 30000 1 30(192500 6 192500 35 5,500 50 66000 66000 30 2,200 35 25000 6 25000 25 1,000 25 17000 6 17000 20 850 16

    20046.0586 6 20046.05863 100 200 (31666.8078 6 31666.80782 300 105.6 101050

    700 6 700 350 2 12000 6 12000 3000 4 )3606015000 6 15000 15000 1 1000 6 1000 1000 1 1000 6 1000 1000 1 7500 6 7500 300 25 )10

    12500 6 12500 250 50 416(10530.51 71219 6 81750 1000 82

    80000 6 80000 80000 1 33(22500 6 22500 2500 9 3508493.2 6 493.2 150 3.288 3.3()1.22250 6 2250 150 15 15(

    10692 6 10692 4000 2.673 4000 6 4000 4000 1 250()3903000 6 3000 3000 1 3(

    12000 6 12000 10000 1.2 )705512000 6 12000 10000 1.2 )70138

    )(950409.7

    ))8 ))7 )()6(

    )()5(

    ))4 ))3 )2( //

    )( ))950409.7 461.8

  • 8/14/2019 Design of micro hydro power

    58/119

    0.0 6 0.0 0.0 770.1695192.5 6 695192.5 350.0 1986.3 553184.9 6 553184.9 1000.0 553.2

    520.0 6 520.0 100.0 5.2 60.0 6 60.0 10.0 6.0

    3000.0 6 3000.0 3000.0 1.0 3500.0 6 3500.0 3500.0 1.0 1600.0 6 1600.0 800.0 2.0

    322.9 6 322.9 70.0 4.6 624.8 6 624.8 200.0 3.1334.7 6 334.7 15.0 22.3120.4 6 120.4 200.0 0.6

    6.0 6 6.0 10.0 0.6422.8 6 422.8 200.0 2.1 254.5 6 254.5 65.0 3.9

    28370.4 6 28370.4 300.0 94.6 35090.4 6 35090.4 200.0 175.5 2.522117.4 6 22117.4 60.0 368.619062.0 6 19062.0 300.0 63.5

    206.4 6 206.4 80.0 2.6100.0 6 100.0 100.0 1.0

    460095.2 6 460095.2 700.0 657.3 24456.7 465858 6 490314.5 350.0 1400.9 5760.0 6 5760.0 5760.0 Ls

    30000.0 6 30000.0 30000.0 Ls 15000.0 6 15000.0 15000.0 Ls

    2488781 537077.3

    2488780.51 537077.31 ((

    Eng PMU Eng AFP

  • 8/14/2019 Design of micro hydro power

    59/119

    1

    2

    1

    2

    3

    4

    5

    6

    7

    8

    9

    10

    11

    12

    13

    14

    15

    16

    17

    18

    19

    20

    21

    2223

    24

  • 8/14/2019 Design of micro hydro power

    60/119

    25

    26

    27

    28

    29

    30

    31

    32

    33

    34

    35

    36

    37

    38

    39

    40

    41

    42

    43

    44

    45

    46

    47

    48

    49

    50

  • 8/14/2019 Design of micro hydro power

    61/119

    NO Family 256

    ID-number: 28-2802-0014 -2A

    Province: BamyanDistrict: shebar

    Village: GunbadProject purpose: M,H,P

    NO Equipment Unit QuantityUnit cost

    Afg

    Total cost

    Afg

    1 shovel with handl pc 5 100 500

    2 pickax with handl pc 5 200 1000

    3 slodge hammer with handl pc 1 500 500

    4 wheel barrow pc 2 1500 3000

    5 Rubber bucket pc 6 60 360

    6 Rope m 20 20 400

    5760

    Equipment sheet

    Total Cost Afs

  • 8/14/2019 Design of micro hydro power

    62/119

    Parawn Bamyan

    No :Fa 256

    A Mterials1 shovel with handl pc 5 100.00 500.02 pickax with handl pc 5 200.00 1000.03 slodge hammer with handl pc 1 500.00 500.04 wheel barrow pc 2 1500.00 3000.05 Rubber bucket pc 6 60.00 360.06 Rope m 20 20.00 400.07 Stone m 770 0.00 0.08 Cement bag 1986 350.00 695192.59 Sundy m 553 1000.00 553184.910 soil m 5 100.00 520.011 Straw kg 6 10.00 60.012 Complete Doors (1.2X2.2)m pc 1 3000.00 3000.013 Complete Windows(1.5X1.5)m pc 1 3500.00 3500.014 Complete window(1X1)m pc 2 800.00 1600.015 Niel kg 5 70.00 322.916 Glasses m 3 200.00 624.817 Marble powder kg 22 15.00 334.718 powder paint kg 1 200.00 120.419 solt kg 1 10.00 6.020 Oil paint kg 2 200.00 422.821 oil kg 4 65.00 254.522 wooden beem 25 cm,L=4.00 m pc 95 300.00 28370.423 bourd 2X0.2X0.02 pc 175 200.00 35090.424 Steel 10mm area kg 369 60.00 22117.4

    25wooden beem 40 cm,L=5.00 m ml 64 300.00 19062.0

    26 Wair 1mm kg 3 80.00 206.427 Instelation G,I hood Pc 1 100.00 100.0

    Total(Afs) 1369850.0

    Gunbad

    Proqurm

    Proqurm

    Proqurm

    Proqurment list

    Proqurm

    Proqurm

    Proqurm

    Proqurm

    Proqurm

    Proqurm

    Proqurm

    Proqurm

    Proqurm

    Proqurm

    Res

    Proqurm

    Proqurm

    Proqurm

    Proqurm

    Proqurm

    Proqurm

    Proqurm

    Proqurm

    Proqurm

    Proqurm

    Proqurm

    Proqurm

    Proqurm

    SNO CIVIL Unit Quantity Unit cost Total cost

    Proqurm

  • 8/14/2019 Design of micro hydro power

    63/119

    Parawn Bamyan

    No :Fa 256

    1 Genrator (30)kW, three Phase, Brush type pc 1 30000.00 30000.0

    2 ACSR d=50mm meter 5500 35.00 192500.0

    ACSR d=35mm meter 2200 30.00 66000.0

    3 ACSR d=25mm meter 1000 25.00 25000.0

    4 ACSR d=16mm meter 850 20.00 17000.0

    6 D-Bracket and Insulator (complete set) pc 200 100.00 20046.1

    7 Cross -arms(50 cm long -10cmX10cm) pc 106 300.00 31666.8

    8 Stay sets (complete) set 2 350.00 700.0

    9 Earthing Set (60cmX60cmX3mm copper plate, 10m long 4mm dia cop set 4 3000.00 12000.0

    10 Control Panel (complete set) pc 1 15000.00 15000.0

    11 Signboard pc 1 1000.00 1000.0

    12 Tools & tool box pc 1 1000.00 1000.0

    13 4X35mm2 CU cable (to connect Gnerator and Control Panel) m 25 300.00 7500.0

    14 4X50mm2 Al Cable (to connect control panel and first Pole) m 50 250.00 12500.0

    15 7m high wooden pole pc 82 1000.00 81750.0

    Total(Afs) 513662.9 0

    Gunbad

    Proqurment list

    Proqur

    Proqur

    Proqur

    Proqur

    C Electrical Unit Quantity Unit cost Total cost Res

    Proqur

    Proqur

    Proqur

    Proqur

    Proqur

    Proqur

    Proqur

    Proqur

    Proqur

    Proqur

    Proqur

  • 8/14/2019 Design of micro hydro power

    64/119

    Parawn Bamyan

    No :Fa

    256

    Dmechanical Unt Quantity Unit cost Total cost

    1

    A. : Turbine (33 kW, T12), B.: Adaptor for Turbine, C: . Base

    Frame for Turbine and Generator, D: . Intermediate Shaft, E.:

    Pulleys (-20" nos, 5" - 3 ) F: . D, V Belts-3 nos

    set 1.00 80000.00 80000

    2508mm dia, 3mm thickness, MS Penstock Pipes with one bends

    and required washers, bolts and nuts (Bends are shown in DWG)m 9.00 2500.00 22500

    3Airvent pipe (diameter=30.62 mm) ( 1 .2inch) m 3.29 150.00 493.2

    4PVC Pipe for flushing (arani) m 15.00 150.00 2250

    5

    Trahsrack (3.3mX0.81m) with frame, 20mm spacing of bar, bar

    size: 5mmX25mm for forbaym 2.67 4000.00 10692

    6Flushing Cone (0.440m dia,(17") 1.55m height), As shown in DWG set 1.00 4000.00 4000

    73" Valve with 2m GI Pipe set 1.00 3000.00 3000

    8Sluice Gate ( 1.2m (H)X 1m (B)) for settling basin m 1.20 10000.00 12000

    9Sluice Gate for geravaltiraos (1.2m(H) X0.1 m (B)) m 1.20 10000.00 12000

    Total(Afs) 146935.2 0

    Proqurment

    Proqurment

    Gunbad

    Proqurment

    Proqurment

    Proqurment

    Proqurment

    Proqurment

    Proqurment

    Respons

    Proqurment

    Proqurment list

  • 8/14/2019 Design of micro hydro power

    65/119

    256

    Cost per year

    Repair/replesments costs 5% of investments for the

    Salary (Estimated for the operator)

    Salary per month:Salary per year:

    Others: physical contingency 2%

    Mobil Oil (1%)

    Unit Cost

    Fuel consumption per hour

    Fuel consumption per day

    Fuel consumption per mounth

    Fuel consumption per yearTotal costs

    Cost participation of family

    256 No

    Participation family per year 262.7 Afs

    Participation family per month 21.9 Afs

    Participation Family per day 0.73 Afs

    4 3 2

    45950.195636

    5

    Fuel

    6

    67238.53

    No of family

    214875

    Repair/replesments costs per year 1487.5

    3

    100

    3000

    36000

    Village: Gunbad

    Project: M .H .P

    1Depreciation: 10% of total capital investment(include of power house rehabilitation cost etc.)for 10yearsTotal costs for 10 years 297509.782

    29751

    Power Group Membar ChargesNO-Famili =ID-number: 28-2802-0014 - 2 A

    Province: Bamyan

    District: Shebar NSP

  • 8/14/2019 Design of micro hydro power

    66/119

    ID-number

    Province

    District

    VillageProject type

    No- F 256

    1 Tooles

    2 Site preparation m 14 14 929.99 0.00 29.4 2.10 1064 76

    3 Excavation m 175 175 446.7 0.00 551.25 3.150 3,763.20 21.504

    4 Stone massonary m 1628.90 1628.900 770.1 0.00 61,548.96 37.795 Shutting m 1413.50 1413.50 47.28 0.00 6,360.75 4.5006 RCC(1:2:4) m 4250.00 4250.0 3.4 0.00

    7 PCC(1:4:8) m 3550.00 3550.0 144.1 0.00 12,022.7 3.4 28,517.01 8.033

    8 Mechanical Part Ls LS LS

    9 Electrical Part Ls Ls LS

    10 Steel work kg 71.41 71.41 368.6 0.00

    11 Palastering m 205.0 205.00 435.3 0.00 7,431.168 36.250

    12 Ponting m 202.5 202.5 703 0.00 7,776.00 38.40

    13 Carpentary Work pc 2151.00 2151.00 4.0 0.00

    14 Water Pinting m 34.21 34.21 30.1 0.00

    15 Installtionn woodenbeem 3/m L=5m M.L 321.00 321.00 63.5 0.00

    18 oil painting on wooden m 293.70 293.70 7.8 0.00

    19 Installation of glass 3mm m 238.00 238.00 3.0 0.00

    20 mud pull work of roof m 71.50 71.50 12.0 0.00

    21 mud & straw m 39.33 39.33 12.0 0.00

    22 fixing bourd on the roof m 546.90 546.90 13.4 0.00

    24 Filling m 275.00 275.00 4.000 0.00

    25 geraval Levaling m 1014.00 1014.00 74.407 0.00 425.880 0.420 12,168.000 12.000

    19,389.95 122,268.34

    1 Transportation % % 0.03 19,389.95 122,268.34

    2 Probables % % 0.02 0.00 0.00

    GRAND TOTAL

    No Itam Un it

    Untcost

    chek

    Unt

    costQun

    geravalterp

    sQun

    TOTAL

    An,bolack

    TOTAL

    Qun

    Unt cost

    chek

  • 8/14/2019 Design of micro hydro power

    67/119

    5760 5760.0

    728.00 52.00 222.95 15.93 13019.8

    4858.00 27.76 2784.4775 15.91 78171.4

    44859.906 27.54 47766.02649 29.32 1254456.4

    11194.92 7.92 37604.75 26.60 66835.9

    10017.12 2.36 14287.5

    23004 6.48 6484.43 1.83 511495.5

    146935 146935.2

    513663 513662.9

    20084.11 281 26323.4

    4805.20 23.440 5087.28 24.82 89227.8

    2976.75 14.700 5659 27.95 142415.0

    8604.0

    1030.2

    20396.3

    2299.7

    708.1

    858.0

    472.0

    7350.3

    1100.0

    18252 18.00 1309.72296 1.2916 75448.4

    110678.8 137020.3 666358 2980857.8

    110678.776 137020.3436 666358 30000.0

    0.0 0.0 0.0 15000.0

    ####### 3025857.8

    Total

    Tools QunForbay QunSpelway Qun

  • 8/14/2019 Design of micro hydro power

    68/119

    ID-number

    Province: BayanDistrict: shebar

    Village: Gunbad

    No-F 256

    Summary sheet of MAP

    F1 Micro hydro power Quantity Un cost Total cost

    A Civil Work:

    1 Construction cost of geraval tiraps 37.79 3235.844868 122268.3398

    2 Construction cost of 1m length of canal 386 2727.28 1,051,758

    3 Construction cost of settlement basin 31.46 2771.92 87198.96

    4 Construction cost of fore bay 29.32 4672.62 137020.34

    5 Construction cost of power house 28.722 3868.89 111122.27

    6 Construction cost of Turbine Area 10.68 4051.58 43251

    7 Construction cost of spillway 27.54 4018.84 110678.78

    8 Construction cost of Anc bolack and Suporter 3.39 5725.38 19389.95

    Sub total cost of civil work: 1,682,688.10

    B Mechanical with hydraulic work:

    1 A. : Turbine (33 kW, T12), B.: Adaptor for Turbine, C: 1 80000 80000

    2 508mm dia, 3mm thickness, MS Penstock Pipes with 9 2500 22500

    3 Airvent pipe (diameter=30.62 mm) ( 1 .2inch) 3.288 150 493.2

    4 PVC Pipe for flushing (arani) 15 150 2250

    5 Trahsrack (3.3mX0.81m) with frame, 20mm spacing o 2.673 4000 106926 Flushing Cone (0.440m dia,(17") 1.55m height), As sh 1 4000 4000

    7 3" Valve with 2m GI Pipe 1 3000 3000

    8 Sluice Gate ( 1.2m (H)X 1m (B)) for settling basin 1.2 10000 12000

    9 Sluice Gate for geravaltiraos (1.2m(H) X0.1 m (B)) 1.2 10000 12000

    Subtotal cost of mechanical work: 146935.2

    C 1 Electrical work: LS LS 513662.87

    2 Sub total cost of electrical part: 513662.87

    1 Transportation 0.05 5760.00 30000.00

    2 probables 0.03 15000.00 15000.00

    3 Tools LS 5760.00 5760.00

    4 Sub total cost 50760.00

    Total project cost: (A+B+C) 2,394,046.16

    28-2802-0014 -2A

  • 8/14/2019 Design of micro hydro power

    69/119

    canal 23480.53

    Forbay 6777.962

    house 3475.272

    al 1600

    Penstok 564.864

    Tarnmasio 6919.26

    Onther 1015.2

    Total 47880.92

  • 8/14/2019 Design of micro hydro power

    70/119

  • 8/14/2019 Design of micro hydro power

    71/119

  • 8/14/2019 Design of micro hydro power

    72/119

  • 8/14/2019 Design of micro hydro power

    73/119

  • 8/14/2019 Design of micro hydro power

    74/119

    Power house for MHP Plant

    Estimated total project cost

    Bold items to be filled by in tenderer (A1,A2,,An). Light items for cost estimation only by Title No. A* Diminsions Item Quantity Unit Unit cost Total cost

    Norm No L W H Afs Afs C

    A1 1.00 1 5.6 4.6 Site preparation 25.76 m2 14.00 360.64

    1.01 0.04 Site preparation, clearing site ect. 1.030 md 350.00 360.64

    A2 2.00 2 8.6 0.8 0.6 Foundation excavation 8.3 m3 175.00 1,444.80

    2.01 0.5 Unskilled labour 4.1 md 350.00 1,444.80

    A3 3.00 2 8.6 0.8 0.6 Stone work for the foundation 8.256 m3 1,628.90 13,448.20

    3.01 1 Stone 8.256 m3 - -

    3.02 0.385 Sand 3.2 m3 1,000.00 3,178.56

    3.05 77.7 Cement (M: 200, 1:5) 641.5 kg 7.00 4,490.44

    3.07 0.5 Skilled labour on site 4.1 md 700.00 2,889.60

    3.08 1 Unskilled labour on site 8.256 md 350.00 2,889.60

    A4 4.00 Stone work for walls 20.47 m3 1,628.90 33,337.07

    2 8.2 0.6 2.5 Wall 24.60 m3

    Negative -1 1.2 0.6 2.2 Door 1.584 m3

    -1 1.5 0.6 1.5 Window 1.35 m3

    -2 1 0.6 1 Window 1.20 m3

    4.01 1 Stone 20.5 m3 - -

    4.02 0.385 Sand 7.9 m3 1,000.00 7,879.41

    4.05 77.7 Cement (M: 200, 1:5) 1,590.2 kg 7.00 11,131.46

    4.07 0.5 Skilled labour on site 10.2 md 700.00 7,163.10

    4.08 1 Unskilled labour on site 20.5 md 350.00 7,163.10

    Village:

    Project type:

    No-f 256

    Norm/

    unit

    Gunbad

    Bill of Quantity (BoQ)

    ID-number:

    Province: Bamyan

    District:

    28-2802-0014 -2A

    shebar

  • 8/14/2019 Design of micro hydro power

    75/119

    A5 5.00 in site palastering M -300(1:4) 28.11 m2 205.00 5,762.55

    2 7 2.5 wall 35.00 m2

    Negative -1 1.2 2.2 Door 2.64 m2

    -1 1.5 1.5 Window 2.25 m2

    -2 1 1 Window 2.00 m2

    5.01 2 cement 56.2 kg 7.00 393.54 5.02 0.03 sand 0.84 m3 1,000.00 843.305.03 0.14 Skilled labour on site 3.94 md 700.00 2,754.78 5.04 0.18 Unskilled labour on site 5.06 md 350.00 1,770.93

    A6 6.00 Pointing stone work of power house 42.87 m2 202.50 8,680.37

    6.01 2 9.4 2.5 47.000 m2

    Negative -1 1.2 0.6 2.2 Door 1.584 m2

    -1 1.5 0.6 1.5 Window 1.350 m2

    -2 1 0.6 1 Window 1.200 m2

    0.01 Sand 0.429 m3 1,000.00 428.66

    6.02 2 Cement (M:400, 1:3) 85.7 kg 7.00 600.12

    6.03 0.17 Skilled labour on site 7.287 md 700.00 5,101.05

    6.04 0.17 Unskilled labour on site 7.287 md 350.00 2,550.53

    1 4 3 mud pole on th roof 12.00 m2 71.50 858.00

    0.05 soil 0.6 m3 100.00 60.00 0.08 Skilled labour on site 0.960 md 700.00 672.00

    0.03 Unskilled labour on site 0.36 md 350.00 126.00

    A7 7.00 1 4 3 Straw mud of roofing 12.00m2

    39.33 472.00 7.01 0.05 Soil 0.6 m3 100.00 60.00

    7.02 0.5 Straw 6.0 kg 10.00 60.00

    7.03 0.010 Skilled labour on site 0.1 md 700.00 84.00

    7.04 0.04 Unskilled labour on site 0.48 md 350.00 168.00

    7.05 1 Instelation G,I hood 1.0 pc 100.00 100.00

    A8 geraval Levaling 2.428 m3 1,014.00 2,461.99

    1 4.2 3.2 0.2 for floor 2.69 m3

    1 1.2 1.00 0.2 befoor door 0.24 m3

    Negative -1 2.5 1.00 0.2 turbin area 0.50 m3

    8.01 1 geraval 2.4 m3 1,000.00 2,428.00

    8.03 0.04 Unskilled labour on site 0.097 md 350.00 33.99

  • 8/14/2019 Design of micro hydro power

    76/119

    A9 9.00 PCC 0.7910 m3 3,550.00 2,808.05

    1 4.2 3 0.07 for floor 0.88 m3

    1 1.2 1.00 0.07 befoor door 0.08 m3

    Negative -1 2.5 1.00 0.07 turbin area 0.18 m39.01 250 cement 197.8 kg 7.00 1,384.25 9.02 1.1 sand 0.9 m3 1,000.00 870.109.03 0.5 Skilled labour on site 0.4 md 700.00 276.85 9.04 1 Unskilled labour on site 0.8 md 350.00 276.85

    A10 10.00 Doors + windows for power house 4.000 pc 2,151.00 8,604.00

    1 2.2 1.2 Complete Doors (1.2X2.2)m 1.000 pc 3,000.00 3,000.00

    1 1.5 1.5 Complete Windows(2X1.5)m 1.000 pc 3,500.00 3,500.00

    2 1 1 Complete Windows(1X1)m 2.000 pc 800.00 1,600.00

    10.01 0.08 Skilled labour on site 0.3 md 700.00 224.00

    10.02 0.2 Unskilled labour on site 0.8 md 350.00 280.00

    A11 11.00 Glass fitting for windows 2.9750 m2 238.00 708.05

    70% 1 1.5 1.5 1.575

    70% 2 1 1 1.411.01 1.05 Glasses 3.12 m2 200.00 624.75

    11.02 0.04 Skilled labour on site 0.119 md 700.00 83.30

    A12 12.00 1 5 2 0.4 Filling with soil and compaction 4.00 m3 275.00 1,100.00

    12.01 1 Soil 4.0 m3 100.00 400.00

    12.02 0.50 Unskilled labour on site 2.0 md 350.00 700.00

  • 8/14/2019 Design of micro hydro power

    77/119

    A13 13.00 Water painting 30.11 m2 34.21 1,030.21 2 7.4 2.5 wall 37.0 -

    Negative -1 1.2 2.2 Door 2.6-1 1.5 1.5 Window 2.3-2 1 1 Window 2.0

    13.01 0.603 Marble powder 22.3 kg 15.00 334.67 13.02 0.02 powder paint 0.6 kg 200.00 120.44 13.03 0.02 solt 0.6 kg 10.00 6.02 13.04 0.027 Skilled labor 0.8 kg 700.00 569.08

    A14 14.00 2 oiLPainting 7.830 m2 293.70 2,299.67 100% 2 1.2 2.2 for door 5.28 m2 -

    30% 2 1.5 1.5 for Window 1.35 m2 -

    30% 4 1 1 for Window 1.20 m3

    14.01 0.27 Oil paint 2.1 kg 200.00 422.82 14.02 0.5 oil 3.9 m3 65.00 254.48 14.03 0.046 Skilled labour on site 0.4 liter 700.00 252.13 14.04 0.5 Unskilled labour on site 3.9 md 350.00 1,370.25

    A15 15 instelation Wooden beem on the roof 63.54 m.L 321.000 20396.34

    3 4.2 4.4 Wooden beem L=4.4m D=40cm 55.4 ml

    3 2.5 0.6 Wooden beem for Lintal L=2.5m D=40cm 4.5 ml

    3 2 0.6 Wooden beem for Lintal L=2m D=40cm 3.6 ml

    0.01 Nail 0.6354 kg 70 44.47815.01 1 Wooden beem 63.54 ml 300 1906215.02 0.014 Skilled labour on site 0.88956 m/d 700.00 622.69215.03 0.030 Unskilled labour on site 1.9062 m/d 350.00 667.17

    A16 16 1 4.2 3.2 instelation wooden board on the beem 13.44 m2 546.9 7350.33616 0.4 bourd 2X0.2X0.02 33.6 pc 200 672016 0.12 Nail 1.6128 kg 70 112.89616 0.040 Skilled labour on site 0.5376 m/d 700.00 376.3216 0.03 Unskilled labour on site 0.4032 m/d 350.00 141.12

    - 111,122.27 Total cost of (A1+A2+A3+A5+A6+A7+A11+A12+A13+A14+A15+A16)

    Windows

    Windows

    Door

  • 8/14/2019 Design of micro hydro power

    78/119

    C.

    NSP, Afs360.64

    360.64

    1,444.80

    1,444.80

    13,448.20

    -

    3,178.56

    4,490.44

    2,889.60

    2,889.60

    33,337.07

    -

    7,879.41

    11,131.46

    7,163.10

    7,163.10

    ution

  • 8/14/2019 Design of micro hydro power

    79/119

    5,762.55

    393.54

    843.30

    2,754.78

    1,770.93

    8,680.37

    428.66

    600.12

    5,101.05

    2,550.53

    858.00

    60.00

    672.00

    126.00

    472.0060.00

    60.00

    84.00

    168.00

    100.00

    2,461.99

    2,428.00

    33.99

  • 8/14/2019 Design of micro hydro power

    80/119

    2,808.05

    1,384.25

    870.10

    276.85

    276.85

    8,604.00

    3,000.00

    3,500.00

    1,600.00

    224.00

    280.00

    708.05

    624.75

    83.30

    1,100.00

    400.00

    700.00

  • 8/14/2019 Design of micro hydro power

    81/119

    1,030.21

    -

    334.67

    120.44

    6.02569.08

    2,299.67

    -

    -

    422.82

    254.48

    252.13

    1,370.25

    20,396.34

    44.47819062

    622.692

    667.17

    7350.336

    6720

    112.896

    376.32

    141.12

    111,122.27

  • 8/14/2019 Design of micro hydro power

    82/119

  • 8/14/2019 Design of micro hydro power

    83/119

    A5 5.00 Pointing stone work 232.54 m2 202.5 47089.4 0.0

    2 151.000 0.77 for walls 232.54 m2

    5.01 0.01 Sand 2.33 m3 1000.0 2325.4 0.0

    5.02 2 Cement (M:400, 1:3) 465.08 kg 7.0 3255.6 0.0

    5.04 0.17 Skilled labour on site 39.53 md 700.0 27672.3 0.0

    5.05 0.17 Unskilled labour on site 39.53 md 350.0 13836.1A6 6.00 geraval Levaling 24.16 m3 1014.0 24498.2 0.0

    1 151.0 0.80 0.2 for floor 24.16 m3

    6.01 1 geraval 24.16 m3 1000.0 24160.0 0.0

    6.02 0.04 Unskilled labour on site 0.97 md 350.0 338.2

    A7 7.00 PCC 42.88 m3 3550.0 152238.2 0.0

    2 151.000 0.6 0.07 for on the walls 12.68 m3

    2 151.000 1.00 0.1 under the wall foundtion 30.20 m3

    1 151.000 1.00 0.07 for floor 10.57 m3

    7.01 250 cement 10721.00 kg 7.0 75047.0 0.0

    7.02 1.1 sand 47.17 m3 1000.0 47172.4 0.0

    7.03 0.5 Skilled labour on site 21.44 md 700.0 15009.4 0.0

    7.04 1 Unskilled labour on site 42.88 md 350.0 15009.4

    A8 8 palastering M :300 (1:4) 211.40 m2 205.0 43337.0 0.0

    2 151.000 0.70 in site 211.40 m2

    8 2 cement 422.80 kg 7.0 2959.6 0.0

    8 0.03 sand 6.34 m3 1000.0 6342.0 0.0

    8 0.14 Skilled labour on site 29.60 md 700.0 20717.2 0.0

    8 0.18 Unskilled labour on site 38.05 md 350.0 13318.2

    0.0 773050.2 1362Total cost of (A1+A2+A3+A5+A6+A7+A8)

  • 8/14/2019 Design of micro hydro power

    84/119

    NSP, Afs

    0.0

    0.0

    0.0

    0.0

    185389.3

    0.0

    55809.6

    78843.7

    50736.0

    0.0

    184200.1

    0.0

    53716.7

    75887.1

    48833.4

    5762.9

    bution

  • 8/14/2019 Design of micro hydro power

    85/119

    47089.4

    2325.4

    3255.6

    27672.3

    13836.1

    24498.2

    24160.0

    338.2

    152238.2

    75047.0

    47172.4

    15009.4

    15009.4

    43337.0

    2959.6

    6342.0

    20717.2

    13318.2

    636752.3

  • 8/14/2019 Design of micro hydro power

    86/119

    Turbine Area for MHP Plant

    Item Quantity Unit Unit cost Total cost

    No L W H Afs Afs CDC, Afs NS

    A1 1.00 1 4.8 2.6 0.8 Site excavation 9.98 m3 175.00 1,747.20 0.00 1,7

    1.01 0.5 Unskilled labour 5.0 md 350 1,747.20 1,7

    foundation excavation 6.278 m3 175 1,098.72 0.00 1,0

    2 3.1 0.8 0.6 for walls 2.976 m3

    3 1.96 0.8 0.6 for basin 2.822 m3

    1 1.00 0.8 0.6 for basin 0.480 m3

    0.5 Unskilled labour 3.1 md 350 1,098.72 1,0

    A2 2.00 Stone work for the foundation 5.338 m3 1,628.90 8,694.42 0.00 8,6

    2 3.1 0.8 0.6 for walls 2.976 m3

    2 1.96 0.8 0.6 for basin 1.882 m3

    1 1.00 0.8 0.6 for basin 0.480 m3

    2.01 1 Stone 5.3 m3 0.00 0.00 0

    2.02 0.385 Sand 2.1 m3 1,000.00 2,054.98 2,0

    2.05 77.7 Cement (M: 200, 1:5) 414.7 kg 7.00 2,903.12 0.00 2,9

    2.07 0.5 Skilled labour on site 2.7 md 700.00 1,868.16 0.00 1,8

    2.08 1 Unskilled labour on site 5.3 md 350.00 1,868.16 1,8

    A3 3.00 Stone work for walls of TA 5.338 m3 1,628.90 8,694.42 0.00 8,6

    2 3.1 0.6 0.8 for walls 2.976 m3

    2 2.0 0.6 0.80 for basin 1.882 m3

    1 1.0 0.6 0.80 for basin 0.480 m3

    3.01 1 Stone 5.3 m3 0.00 0.00 0.00 0

    3.02 0.385 Sand 2.1 m3 1,000.00 2,054.98 2,0

    3.05 77.7 Cement (M: 200, 1:5) 414.7 kg 7.00 2,903.12 0.00 2,9

    3.07 0.5 Skilled labour on site 2.7 md 700.00 1,868.16 0.00 1,83.08 1 Unskilled labour on site 5.3 md 350.00 1,868.16 1,8

    Village:

    Project purpose:

    No-F 256

    Title No. Norm/

    unit

    A*

    Norm

    Diminsions Contribution

    ID No:

    Province:

    District:

    28-2802-0014 -2A

    Bamyan

    shebar

    Gunbad

  • 8/14/2019 Design of micro hydro power

    87/119

    A4 4.00 Westeg Shuttering 8.260 m2 1,413.50 11,675.51 0.00 11,6

    2 3.1 0.8 Shuttering for walls 5.0 m2

    3 1.0 1 Shuttering for bsin walls 3.0 m2

    1 1.0 0.3 Shuttering for bsin walls 0.3

    4.01 0.4 20% Wooden plank 24.780 pcs 200.00 4,956.00 0.00 4,95

    4.02 2 Wooden pole 4m long 16.52 pcs 300.00 4,956.00 4,95

    4.03 0.05 Nail 0.413 kg 70.00 28.91 0.00 28

    4.04 0.2 Skilled labour on site 1.652 md 700.00 1,156.40 0.00 1,15

    4.05 0.2 Unskilled labour on site 1.652 md 350.00 578.20 57

  • 8/14/2019 Design of micro hydro power

    88/119

    A5 geraval Levaling 0.820 m3 1,014.00 831.48 - 8

    1 4.1 1.0 0.2 floor 0.8 m3

    5.01 1 geraval 0.8 m3 1,000.00 820.00 8

    5.03 0.04 Unskilled labour on site 0.033 md 350.00 11.48

    A6 6.00 Turbine Area RCC 1.005 m3 4,250.00 4,270.40 0.00 4,27

    2 3.1 0.08 0.8 for Walls 0.397 m3

    3 1 0.08 1 for basin Walls 0.240 m3

    1 1 0.08 0.3for basin Walls

    0.024 m3

    1 4.1 1 0.08 Floor 0.328 m3

    1 1 0.5 0.08 Slab 0.040 m3

    6.01 1.1 Sandy gravel 1.1 m3 1,000.00 1,105.28 0.00 1,10

    6.02 350 Cement (M: 200, 1:5) 351.7 kg 7.00 2,461.76 0.00 2,46

    6.03 0.5 Skilled labour on site 0.5 md 700.00 351.68 0.00 351

    6.04 1 Unskilled labour on site 1.0 md 350.00 351.68 351

    A7 7.00 No L(m) h(m) Steel working 87.372 kg 71.41 6,239.26 0.00 6,23

    6.3 3.1 0.8 for Walls @15cm c/c 19.63 ml

    21.7 0.8 3.1 for Walls @15cm c/c 17.33 ml

    7.7 3.0 1 for Walls @15cm c/c 23.00 ml

    21.0 1 3.0 for Walls @15cm c/c 21.00 ml

    7.7 3.1 1.0 for floor @15cm c/c 23.77 ml

    21.7 1.0 3.1 for floor @15cm c/c 21.67 ml

    7.7 1 1.0 for basin floor @15cm c/c 7.67 ml

    7.7 1 1.0 for basin floor @15cm c/c 7.67 ml

    1.0 1 0.5 for slab @15cm c/c 1.00 ml

    1.0 0.5 1 for slab @15cm c/c 0.50 ml

    7.01 0.61 Steel bar 10 mm 87.4 Kg 60.00 5,242.34 0.00 5,24

    7.02 0.007 Wire 1 mm 0.6 Kg 80.00 48.93 0.00 48

    7.03 0.012 Skilled labour on site 1.048 md 700.00 733.93 0.00 733

    7.04 0.007 Unskilled labour on site 0.6 md 350.00 214.06 214

    0.00 43,251.4 0 432Total cost of (A1+A2+A3+A4+A5+A6+A7)

  • 8/14/2019 Design of micro hydro power

    89/119

    Project type: Fore Bay for MHP Plant

    No-F

    Item Quantity Unit Unit cost Total cost

    No L W H Afs Afs CDC, Af

    A1 1.00 1 4.90 3.25 Site preparation 15.93 md 14.00 222.95 222.91.01 0.04 Unskilled labor 0.64 md 350.00 222.95 222.9

    A2 2.00 Excavation 15.911 m3 175.00 2,784.48 2,784.4

    1 3.30 1.65 1.00 for site 5.445 m3

    2 6.55 1 0.7 for Fundation 9.170 m3

    1 1.49 1 0.87 for falshcon place 1.296 m3

    2.01 0.5 Unskilled labor 7.96 md 350.00 2,784.48 2,784.4

    A3 3.00 Stone work 29.324 m3 1,628.9 47,766.03 10,263.4

    0.60 2 6.55 0.8 0.6 for fundation 6.29 m3

    2 1.65 0.70 2.81 for short walls 6.49 m3

    0.80 1 4.50 0.70 2.81 for long wall 8.85 m4

    1 4.50 0.70 2.11 for bufet wall 6.65 m31 1.49 0.50 0.60 for falshcon wall 0.45 m3

    2 1.00 0.50 0.60 for falshcon wall 0.60 m3

    3.01 1 Stone including transportation 29.32 m3 - -

    3.02 0.39 Sand 11.29 m3 1,000 11,289.78

    3.05 77.7 Cement (M: 200, 1:5) 2278.48 kg 7.00 15,949.38 -

    3.07 0.5 Skilled labor on site 14.66 md 700.00 10,263.44 -

    3.08 1 Unskilled labor on site 29.32 md 350.00 10,263.44 10,263.4

    A4 4.00 PCC-M200 1.827 m3 3,550.0 6,484.43 639.3

    2 6.15 0.6 0.07 On the walls 0.52 m3

    2 6.55 1 0.1 under the foundtion 1.31

    4.01 1.1 Sandy gravel 2.009 m3 1,000.0 2,009.26 -

    4.04 250 Cement (M:120, 1:6) 456.650 kg 7.00 3,196.55 -

    4.06 0.5 Skilled labor on site 0.913 md 700.00 639.31 -

    4.07 1 Unskilled labor on site 1.827 md 350.00 639.31 639.3

    256

    shebar

    GunbadVillage:

    Norm

    / unit* Nor

    Diminsions ConTitle No.

    Bill of Quantity (BoQ)

    ID-number

    Province: Bamyan

    District:

    28-2802-0014 -2A

  • 8/14/2019 Design of micro hydro power

    90/119

    A5 geraval Levaling 1.292 m3 1,014.0 1,309.72 18.0

    1 3.30 1.65 0.2 floor 1.1 m3

    1 1.49 0.68 0.2 for falshcon floor 0.2 m3

    5.01 1 geraval 1.3 m3 1,000.0 1,291.64 -

    5.03 0.04 Unskilled labour on site 0.052 md 350.00 18.08 18.0

    A6 6.00 In site Plastering Mortar (1:3) 24.816 m2 205.00 5,087.28 1,563.4

    1 6.60 2.74 for for three wall 18.084 m2

    1 3.300 2.04 for bufet wall 6.732 m2

    6.01 0.03 Sand 0.74 m3 1,000.0 744.48 -

    6.02 2 Cement 50 kg 7.00 347.42 -

    6.03 0.14 Skilled labor on site 3 md 700.00 2,431.97 -

    6.04 0.18 Unskilled labor on site 4 md 350.00 1,563.41 1,563.4

    A7 7.00 Shuttering 26.604 m2 1,413.5 37,604.75 1,862.2

    20% 1 6.60 2.74 for for three wall 18.084 m2

    1 3.300 2.04 for bufet wall 6.732 m2

    2 1.490 0.60 for falshcon wall 1.788 m2

    7.01 0.4 20% Wooden plank 79.812 pcs 200.00 15,962.40 -

    7.02 2 Wooden pole 4m long 53.2080 pcs 300.00 15,962.40 -

    7.03 0.05 Nail 1.330 kg 70.00 93.11 -

    7.04 0.2 Skilled labor on site 5.321 md 700.00 3,724.56 -

    7.05 0.2 Unskilled labor on site 5.321 md 350.00 1,862.28 1,862.2

    A8 8.00 No L(m) w(m) h(m) Steel working For forbay 281.251 kg 71.41 20,084.11 689.0

    19 6.60 2.74 for three @15cm c/c 127.16 ml

    45 2.74 6.60 for three @15cm c/c 123.30 ml

    15 3.30 2.04 for bufet wall @15cm c/c 48.18 ml

    23 2.04 3.30 for bufet wall @15cm c/c 46.92 ml

    12 3.30 1.65 for floor @15cm c/c 39.60 ml

    23 1.65 3.30 for floor @15cm c/c 37.95 ml

    5 1.00 0.60 four wall for falshcon l @ 15 cm 5.00 ml

    8 0.60 1.00 four wall for falshcon @ 15 cm 4.60 ml

    8 1.49 1.00 for falshcon floor @ 15 cm C/C 11.42 ml

    11 1.00 1.49 for falshcon floor @ 15 cm C/C 10.93 ml

    5 0.60 0.60 for flashcon slab @ 15cm C/C 3.00 ml

    5 0.60 0.60 for flashcon slab @ 15cm C/C 3.00 ml

    8.02 0.61 Steel bar diameter 10 mm 281.25 Kg 60.00 16,875.04 -8.04 0.01 Wire 1 mm 2.0 Kg 80.00 157.50 -

    8.05 0.01 Skilled labor on site 3.4 md 700.00 2,362.51 -

    8.06 0.01 Unskilled labor on site 2.0 md 350.00 689.06 689.0

    Westeg

    Westeg

  • 8/14/2019 Design of micro hydro power

    91/119

    A9 9.00 RCC work 2.357 m3 4,250.0 10,017.12 824.9

    1 6.60 0.07 2.74for three walls

    1.266 m3

    1 3.30 0.07 2.04for bufet wall

    0.471 m3

    1 3.30 1.65 0.07

    for floor

    0.381 m3

    2 1.00 0.60 0.07for flashcon wall

    0.084 m3

    1 1.49 1.00 0.07for flashcon floor

    0.104 m3

    1 0.60 1.20 0.07for flashcon slab

    0.050 m3

    9.01 1.1Sandy gravel

    2.6 m3 1,000.0 2,592.67

    9.04 350Cement (M: 200, 1:5)

    824.9 kg 7.00 5,774.58 -

    9.06 0.5Skilled labor on site

    1.178 md 700.00 824.94 -

    9.07 1 Unskilled labor on site 2.4 md 350.00 824.94 824.9

    A10 10.00Pointing stone work

    27.948 m 202.50 5,659.47 1,662.9

    2 2.85 2.74for tow walls

    15.62 m2

    1 4.50 2.74for one wall

    12.33 m2

    110 0.01Sand

    0.279 m3 1,000.0 279.48 -

    10 2Cement (M:400, 1:3)

    55.896 kg 7.00 391.27 -

    10 0.17Skilled labour on site

    4.751 md 700.00 3,325.81 -

    10 0.17 Unskilled labour on site 4.751 md 350.00 1,662.91 1,662.9

    - 137020.34 20530.9Total cost of (A1+...+A11)

  • 8/14/2019 Design of micro hydro power

    92/119

    Settelment basin

    Bold items to be filled by in tenderer (A1,A2,,An). Light items for cost estimation only by CDC,FP,OC.Title No. A* Item Quantity Unit Unit cost Total cost

    Norm No L W H Afs Afs CDC,

    A1 1.00 1 10 4.90 Site preparation 49.00 md 14.00 686.00

    1.01 0.04 Site preparation, clearing site ect. 2.0 md 350.00 686.00

    A2 2.00 Foundation excavation 17.150 m3 175.00 3,001.25

    2 10.0 1 0.7 f