STC GURGAON SIGN & SEAL OF THE BIDDER 1 STAFF TRAINING CENTRE GURGAON TENDER NOTICE FOR SITC OF INDOOR TYPE THREE PHASE OIL COOLED 500 KVA DISTRIBUTION TRANSFORMER (11 KV / 0.433 KV) AT Staff Training Centre, Plot No 82, Sector 18, GURGAON Tender Reference No : UBI/STCG/103 Date of Tender : 23 September 2019 OWNER: UNION BANK OF INDIA, STAFF TRAINING CENTRE PLOT NO 82, SECTOR 18 GURGAON 122 001 TEL.NO: 0124-4805901

Upload: others

Post on 24-Sep-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 1

STAFF TRAINING CENTRE

GURGAON

TENDER NOTICE FOR

SITC OF INDOOR TYPE THREE PHASE OIL COOLED 500 KVA DISTRIBUTION TRANSFORMER

(11 KV / 0.433 KV)

AT Staff Training Centre, Plot No 82, Sector 18, GURGAON

Tender Reference No : UBI/STCG/103

Date of Tender : 23 September 2019

OWNER:

UNION BANK OF INDIA,

STAFF TRAINING CENTRE

PLOT NO 82, SECTOR 18

GURGAON – 122 001

TEL.NO: 0124-4805901

Page 2: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 2

NOTICE INVITING TENDER

To

M/s________________________________

________________________________

________________________________

Dear Sir,

SUB: TENDER FOR SITC OF 500 KVA OILED COOLED DISTRIBUTION TRANSFORMER,

AT Staff Training Centre, Plot No 82, Sector 18, GURGAON

Staff Training Centre, Gurgaon invites sealed tenders in single Bid system from Orignal

Equipment Manufacturer or their Authorized Distributors for the above work at Plot No. 82, Sec

18, Gurgaon, Haryana as per following details:

Name of the work : Supply, Installation, Testing and Commissioning

of 500 KVA Distribution transformer at STC,

Gurgaon.

Make : Crompton / ABB / Schneider / Kirloskar / Siemens

Estimated Cost of the Work : Rs.12,00,000.00 (Rs. Tweleve Lacs Only) plus applicable

GST.

Earnest Money Deposit : Rs.12,000/- in the form of pay order / Demand

Draft and drawn in favour of Union Bank of

India payable at Gurgaon.

Period of Completion : 60 days

Validity of Tender : 120 days

Date of Issue of Tender : 23.09.2019 during office hours

Pre-Bid Meeting : 09.10.2019 12.30 PM

Corrigendum to the tender : If required will be issued online by displaying on Bank’s

website & govt. portal within one week of pre-bid meeting.

Last date of submission of : Upto 03.00 p.m. on 14th

October 2019.

Tender

Date of Opening of Tender : At 4.30 p.m on 14th

October 2019.

Page 3: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 3

1) The tender document can be obtained from the office of STC Plot No. 82, Sec 18, Gurgaon,

Haryana payment of Rs. 500/- (non-refundable) in favour of Union Bank of India payable at

Gurgaon and should be submitted in original, duly stamped, signed and sealed in the same

office. The tender information can be downloaded from Bank’s website

www.unionbankofindia.co.in or www.tenders.gov.in. Bank reserves the right to change the

date, timings mentioned above or elsewhere in the tender document, which will be

communicated by placing the same as corrigendum under tender section on Bank’s website.

Bidders should check the Bank’s website before the submission of Tender document for the

corrigendum, if any.

2) The item rates under the contract include for full, final & entire completion of all works in all

respects described in contract. Contractor must quote item rates for all the items of work.

Tenders will be opened in the presence of contracting agencies or their authorized

representatives.

3) Tenders are to be submitted in one sealed envelope cover duly super scribed “Tender for

the Work of SITC of 500 KVA Distribution transformer at STC, Gurgaon” and put in the

Tender Box kept on at STC Gurgaon.

4) The tenderer must use only the tender forms issued for the purpose to fill in the rates.

Intimation of tender quoted by letter, telegrams / telex will not be acceptable.

5) Tenderers are advised not to make any alteration/modification in the tender documents,

Item of work or in any respect whatsoever. Violation of this requirement will make the

tender liable for rejection.

6) In case of postal delivery, the tenderer has to ensure that tender is reached before the due

date and time. The bank will not be responsible for damage in the transit and delay of

receipt of tender, if any or sent by a special messenger. Tender received late shall be

rejected.

7) Every page of the tender documents should be signed by the person or persons submitting

the tender in token of his/their having acquainted himself/themselves with the General and

Special Conditions of Contract, Specifications etc., as laid down. Any tender with any of the

documents not so signed will be subjected to rejection.

8) No consideration will be given to a tender received after the time stipulated above and no

extension will be allowed for submission of the tender.

9) The Union Bank of India shall not be bound to accept the lowest tender and reserves the

right to accept or reject any or all the tenders without assigning any reason whatsoever.

10) This notice inviting tenders, the conditions of tender and the duly completed form of tender

etc., will form part of the Agreement to be executed by the successful tenderer with the

bank.

Page 4: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 4

11) Bidders are advised not to make any alteration/modification in the tender document, item

of work or in any respect whatsoever. Violation of this requirement will make the tender

liable for rejection.

12) This notice inviting tender, the conditions of tender, the duly completed form of tender,

corrigendum if any issued etc. will form part of the Agreement to be executed by the

successful bidders with the Bank.

13) For queries and clarification regarding the tender, it is advisable to participate in Pre-Bid

meeting and seek clarification. Post pre-bid meeting and release of pre-bid clarifications, no

further queries or changes will be entertained.

14) Pre-bid queries to be submitted 2 days prior to the pre-bid meeting. A communication in

this regard to the tender queries need to be done to the following email

address:_________________________

15) Please note that all the information desired in the tender document needs to be provided.

Incomplete information may lead to non-selection. All Bids must be accompanied by EMD

as specified in the tender document.

For STAFF TRAINING CENTRE

ASST. GENERAL MANAGER

Page 5: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 5

INSTRUCTION WITH REGARD TO SUBMISSION OF TENDER

1) Rates should be quoted both in figures and words in columns specified. All erasures and

alterations made while initials of the tenderer must attest filling the tender. Overwriting

of figures is not permitted. Failure to comply with either of these conditions will render

the tender invalid and it will be the option of Union Bank of India to accept or reject the

tender. No request of any change in rate or conditions after opening of the tender will be

entertained.

2) In the case of figures, the word “Rs.” should be written before the figures of rupees and

the word `P' written after the decimal figures e.g. `. 3.25 P. In the case of words, the word

Rupee should similarly precede and the words "Paise only" should be written at the end,

closely following each the percentage rate. The word "only" should not be written in the

next line unless the rate quoted is in whole Rupees closely followed by the word "only":

The amount should invariably be upto two decimal places.

3) The different Schedules should be filled as follows:

(a) The “Rate" Column wherever applicable to be legibly filled in ink in both figures and

words.

(b) The "Amount" Column also to be legibly filled in ink in both figures and words.

(c) All corrections to be initialed.

(d) No over writing is allowed.

(e) The figure of percentage of rate shall be legibly filled in ink in both figure and

Words.

4) Errors in the bill of quantities shall be dealt with in the following manner.

a. In the event of any discrepancy between the rates quoted in words and the

rates in figures the former shall prevail.

b. In the event of an error occurring in the amount column of the bills of quantities

as a result of the wrong extension of the unit rate and the quantity, the unit rate

shall be regarded, as firm and extension shall be amended on the basis of the

rates.

c. All the errors in totaling in the amount column and in carrying forward the totals

shall be corrected.

5) The tender shall be signed and dated at all places provided therein. Also all pages,

drawings and corrections / alterations shall be initialed. The tender submitted on behalf

of a firm shall be signed by all the partners of the firm or by a partner who has the

necessary authority on behalf of the firm to enter into the proposed contract. Otherwise

Union Bank of India may reject the tender.

6) The time allowed for completion of works is 30 days from the date of commencement of

the work is reckoned from the tenth day from the date of issue of Work order after

Page 6: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 6

acceptance of Letter of Intent and signing of agreement with the Bank. Time shall be

considered the essence of contract.

7) Every tender shall be accompanied by earnest money of Rs. 12000/- (Rupees Twelve

Thousands only) by way of Demand Draft/Pay Order only favoring UNION BANK OF INDIA,

payable at Gurgaon. Tender submitted without earnest money shall be summarily

rejected. The contractor whose tender is accepted will have to deposit as initial security

deposit a further sum to make up 2% of the value of the accepted tender including the

earnest money. The initial security deposit will have to be made within 14 days from the

date of acceptance of tender, failing which the Bank at his discretion may revoke the

letter of acceptance and forfeit the earnest money deposit furnished along with the

tender.

8) The Earnest Money will be retained in the case of the successful tenderer as part of the

security for due fulfillment of the Contract. No interest shall be paid on this deposit.

Failure to enter into the Contract agreement within the stipulated time of 15 days from

the date of acceptance of work order shall entail the forfeiture of the Earnest money

Deposit. The Earnest money of unsuccessful tenderers will be released after issue of work

order, without any interest.

9) The tenderer shall submit his tender after carefully examining the whole of the tender

document and the terms and conditions of contract, the drawings and specifications, the

schedule of quantities etc., and also after examining the site and conditions prevailing in

and around site.

10) The Bank does not bind himself to accept the lowest or any tender and reserve to

themselves the right of accepting the whole or any part of the tender and tenderer is

bound to perform the same at the rates quoted. The Bank will not be bound to accept the

lowest tender and reserves the right to accept or reject any or the entire tender without

assigning any reasons whatsoever. The work may also be divided among the contracting

agencies depending on the exigencies of the bank.

11) Tenders shall remain valid for a period of 90 days from the date of opening of the tender

which period may be extended by mutual agreement and the tenderer shall not cancel or

withdraw the tender during the initial validity period of 90 days.

12) The successful tenderer shall be bound to implement the Contract and mobilize and sign

specified agreements within 7 days from the date of acceptance of Letter of Intent.

13) Tenderers must include in their rates, GST and any other tax & duty or other levy by the

central and state government applicable on the date of submitting tender. Due to

change in taxes structure by orders from Central Govt. / State Govt. after opening of

tenders shall be reimbursed to the contractor as per actual and upon verifying the proof

of having made the payment.

Page 7: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 7

14) This contract shall be an item rate contract. The Contractor shall be paid for actual

quantity of work done, as measured at site including any deviation plus or minus. The

rate of any non-schedule items of work shall be decided as mentioned in the conditions

of contract.

15) No correspondence will be entertained in respect of this tender other than any

clarifications strictly pertaining to this tender.

16) The tender price quoted by a tenderer shall be kept strictly confidential and shall not be

divulged to any other party even approximately before the time limit for delivery of

tender. The only exception be for obtaining an insurance quotation, you may give your

insurance company or agent any essential information they ask for, so long as it is done in

strict confidence. No information about other's tender price should be obtained and no

arrangement with any one else should be made whether or not he submit the tender.

17) Tenderer should sign at the end of every page prior to submitting the tender.

18) Conditional tenders will be summarily rejected.

22) COMPLETION PERIOD OF THE PROJECT WILL BE 30 DAYS.

Progress chart linked up with completion period to be counted from 10th

day of

acceptance of work order.

For STAFF TRAINING CENTRE

ASST. GENERAL MANAGER

Page 8: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 8

TENDER FORM

To,

The Asst. General Manager,

Union Bank of India,

Staff Training Centre,

Plot No. 82, sector 18,

Gurugram (Haryana).

Sub: TENDER FOR SITC OF 500 KVA OIL COOLED Distribution Transformer at

Union Bank of India, Staff Training Centre, Gurugram

Sir,

We have read and examined the complete set of tender document. We are well aware and

familiar with Dakshin Haryana Bijli Vitran Nigam, Schedule of Rates (latest) and their

specifications, Dakshin Haryana Bijli Vitran Nigam Specification, BIS publication and National

Building code, Indian Electricity Rules latest which shall apply to this contract to supplement any

missing details in this contract in order of preference.

Further to the above, we have visited and examined the site of the proposed works and have

acquired the requisite information relating thereto as affecting the tender invited by Bank.

1. We agree that any other terms or conditions of contract or any general reservation which

may be printed on any correspondence emanating from us in connection with this tender or

with any contract resulting from this tender shall not be applicable to this tender or to the

contract.

2. We have obeyed the rules about confidentiality of tenders and will continue to do so as long

as they apply.

3. We are enclosing along with our tender an earnest money of Rs. 12000/- (Rupees Twelve

Thousands only) favoring Union Bank of India, payable at Gurgaon (Pay Order No.-------

dated ----------- drawn on ----------------------). We hereby agree that this sum shall be forfeited

by Union Bank of India in the event of our tender being accepted and if we fail to execute

the contract when called upon to do so.

4. Subject to and in accordance with paragraphs 3 & 4 above and the terms and conditions

contained or referred to in the documents listed in paragraph 1, we agree and offer to

execute all the Works referred to in the said documents upon the terms and conditions

contained or referred to therein and to carry out such deviations as may be ordered to be

valued as per the conditions of contract.

5. We undertake to complete and deliver the whole of the works within a period i.e. 30 DAYS

as specified in the contract and further confirm that the time allowed for completion is

adequate. Time allowed for completion of entire job or part job assigned shall be reckoned

from the tenth day of the date of acceptance of work order. We shall be under the

Page 9: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 9

obligation to pay the sum as stated in the contract for every day that the works shall remain

incomplete, damages as compensation subject to the conditions of contract relating to

extension of time.

6. We hereby agree that unless & until a formal agreement is prepared & executed in

accordance with the Articles of agreement, this tender together with your acceptance

thereof, shall constitute a binding contract between us.

7. We agree to pay initial security deposit of 2% (including Earnest Money) of the contract

amount by way of DD/PO in favour of UNION BANK OF INDIA, payable at Gurugram. This

amount shall be released after completion of work.

8. We further agree for a deduction of 5% from the running bill as retention money payable

after 36 months of defect liability period. No interest will be paid on this amount. However,

this amount may be release by Bank on submission of performance Bank Guarantee of

equivalent amount and period.

9. Validity of the tender is 120 days from the date of opening of tender or it may be beyond

120 days if mutually accepted.

10. The bank is at liberty to accept or reject any tender, without assigning any reasons

whatsoever.

11. We are aware that the quantities of work indicated in the bill of quantities are approximate,

may vary to any extent, even it may be omitted; we will not have any claim of any kind

against the bank.

12. We have visited the site and seen the existing transformer and ready to take in buyback.

Signed in the capacity of duly authorized

to sign tenders for and on behalf of

Address ……………………………. Telephone No…………………………

……………………………………… Mobile No.______________

Date:

Page 10: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 10

ADDITIONAL CONDITIONS

1. Tenderer to inspect Site: The tenderer shall visit and examine the installation site and

satisfy himself as to the nature of the existing roads or other means of communications,

the character of the soil and the excavation, the extent of magnitude of the work and

facilities for obtaining material and shall obtain generally his own information on all

matters affecting the execution of the work. No extra charges made in consequence of

any misunderstanding or incorrect information on any of these points or on grounds of

insufficient description will be allowed. All expenses incurred by the contractor in

connection with obtaining information for submitting this tender including his visits to

the site or efforts in compiling the tender shall be borne by the Tenderer and no claim

for reimbursement thereof shall be entertained.

2. Access to Site: The tenderer is to include in his rates for forming access to the Site with

all temporary roads gangways required for the works.

3. Cost of transporting: The tenderer shall allow in his cost for all transporting, unloading

stacking and storing or supplies of goods and materials for this work on the site and in

the places approved from time to time by the Bank. The tenderer shall allow in his price

for transport of all materials controlled or otherwise to the site.

4. Materials, Workmanship & Samples: Materials shall be of approved quality and the best

of their kind available and shall generally conform to I.S. Specifications, The Contractor

shall order all the materials required for the execution of work as early as necessary and

ensure that such materials are on site well ahead of requirement for use in the work.

The work-involved calls for high standard of workmanship combined with speed and to

the entire satisfaction of the Bank.

5. Testing of work and material: The contractors will have to carryout testing of the

material at regular interval to proof quality, soundness and efficiency of the material.

Expenditure required for testing and transportations shall be borne by the tenderer.

Cost of testing and transport will be borne by contractors.

Any other materials will be tested by contractors at his own cost as per the

instruction of Bank and Bank from time to time.

If after any such test the work or portion of works is found in the opinion of the Bank to

be defective or unsound, the contractor shall pull down and re-do the same at his own

cost. Defective materials shall immediately be removed from the site.

6. Foremen and Tradesmen: All tradesmen shall be experienced men properly equipped

with suitable tools for carrying out the work in a first class manner and where the Bank

deemed necessary, the contractor shall provide any such tools, special or ordinary which

are considered necessary for carrying out the work in a proper manner.

Page 11: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 11

All such tradesmen shall work under an experienced and properly trained foremen, who

shall be capable executing work and the contractor shall also comply with other

conditions set out in Clause 9 of the conditions of the contract.

7. Clearing of Site: The contractor shall after completion of the work clear the site of all the

debris and left over materials at his own expense to the entire satisfaction of the Bank

and Municipal or other public authorities.

The whole of the work shall be thoroughly inspected by the contractor and all

deficiencies and defects put right. On completion of such inspection, the contractor shall

inform the Bank in writing that he has finished the work and it is ready for the Bank

inspection.

8. Vouchers: The contractor shall furnish the Bank with vouchers on request, to prove that

the materials are as specified and to indicate the rates at which the materials are

purchased in orders to work out the rate analysis of the non-tender items which he may

be called upon to carry thereafter.

1. COMPLETENESS OF TENDER: -

All sundry fittings, assemblies, accessories, hardware items, foundation bolts,

termination lugs for electrical connections as required, and all other sundry items which

are useful and necessary for proper assembly and efficient working of the various

components of the work shall be deemed to have been included in the tender, whether

such items are specifically mentioned in the tender documents or not.

2. RATES: -

The rates tendered shall be for complete items of work inclusive of Cost of material,

erection, connection, testing, labour, supervision, tool & plants, storage, contingencies,

breakage, wastage, execution at any level & height, all taxes (including works contract

tax, if any), duties, and levies etc. and all charges for items contingent to the work, such

as, packing, forwarding, insurance, freight and delivery at site for the materials to be

supplied by the contractor.

3. All the above work shall be complete in all respects up to the satisfaction of Bank as per

the details mentioned in BOQ (Bill of Quantity).

Unless and otherwise mentioned in the tender documents the following scope of works

shall be done by the contractor, and therefore their cost shall be deemed to be included

in their tendered cost:

a) Furnishing of all labour, skilled and unskilled, supervisory and administrative personnel,

erection tools and tackles, testing equipment, implements, supplies, consumables like

welding rods and gas, oil and grease, cleaning fluids, insulating tape, anti corrosive

paints, jute cotton waste etc., and hardware for timely and efficient execution of the

erection work.

Page 12: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 12

b) Transport vehicles necessary for efficient transportation of equipment from Owner's

stores to site of erection and excess materials back to owner's stores.

c) Complete assembly, erection and connection, testing and commissioning, putting into

successful and satisfactory commercial operations of above equipment.

d) The items of work to be performed on all equipment and materials shall include but not

limited to the following:

(i) Receiving, unloading and transportation at site. (To Owner or Contractor's

stores and from their upto actual place of erection).

(ii) Opening, inspecting and reporting all damages and short supply items.

(iii) Arranging to repair and/or re-order all damaged and short supply items.

(iv) Storing at site with suitable all weather protection.

(v) Assemblies, erection and complete Installation.

(vi) Final check-up, testing and commissioning in presence of Owner's

representative.

(vii) Obtaining Owner's written acceptance of satisfactory performance.

4. PRICES

a) The price quoted for supply items shall include all packing, GST and other taxes /

Octroi, Works Contract tax, insurance, freight, transportation, loading/ unloading,

handling & all other charges.

b) The price quoted for erection & commissioning shall include cost of all

consumables, taxes & duties. (if any). No additional taxes/duties shall be payable.

c) Prices quoted shall be firm and no variation shall be allowed during contract

period.

5. ELECTRIC POWER SUPPLY AND WATER SUPPLY: -

Power supply and water supply as may be required shall be arranged by the Bank for

installation and testing of the equipment’s at the site of work.

6. PROVISIONS AGAINST ACCIDENTS AND SAFETY MEASURES

a) All safety rules and codes as applicable to work including rules applicable as per factory

inspector shall be followed during execution of above work.

b) All safety appliances and protective devices including hand gloves, aprons, helmets,

shields, goggles, safety belts etc. shall be provided by Contractor for his personnel.

c) The Contractor shall arrange to provide guards and prominent display caution notices if

access to any equipment / area is considered unsafe and hazardous.

7. SPECIFICATIONS

In the absence of specifications for any work or materials, relevant Indian Standard

Specifications shall be applicable. If such codes for a particular subject have not been

Page 13: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 13

framed, the decision of the Employer / Bank will be final and binding.

8. VARIATION IN QUANTITY

a) The Owner shall have right to delete or increase / decrease quantity specified in this

specification as specified in preamble to Bill of Materials.

b) Quantities indicated in Bill of Materials are based on engineering status of the project as

on date. It is necessary that the contractor before procurement of material carry out

proper engineering.

c) For procurement of any material & sequential delivery at site from point of view of

erection etc. Contractor shall take prior approval from the employer.

d) All left over material for which payment has been made, has to be taken back by the

contractor. This amount will not be claimed by the contractor while submitting the bill.

9. SITE VISIT

It is recommended that contractor shall visit site before submission of his offer. Time

and date shall be fixed with employer.

10. TOOLS FOR HANDLING AND ERECTION: -

All tools and tackles required for handling of equipment and materials at site of work as

well as for their assembly and erection and also necessary test instruments shall be the

responsibility of the contractor.

11. CO-ORDINATION WITH OTHER AGENCY: -

The contractor shall co-ordinate with all other agencies viz. state electricity board etc., if

any for timely completion of work

12. CARE OF BUILDINGS: -

Care shall be taken by the contractor to avoid damage to the building during execution

of his part of the work. He shall be responsible for repairing all damages and restoring

the same to their original finish at his cost. He shall also remove at his cost all unwanted

and waste materials arising out of his work from the site, from time to time as designed

by the Engineer-in-charge.

13. STRUCTURAL ALTERATIONS TO BUILDINGS: -

i. No structural member in the building shall be damaged / altered, without prior

approval from the competent authority.

ii. Structural provisions like openings, cutouts if any, provided by the department

for the work, shall be used. Where these require modifications, or where fresh

provisions are required to be made, such contingent works shall be carried out

by the contractor at his cost.

Page 14: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 14

iii. All such openings in floors provided by the department shall be closed by the

contractor after installing the cables/conduits/rising mains etc. as the case may

be, by any suitable means as approved by the Engineer-in-charge without any

extra payment.

14. WORK IN OCCUPIED BUILDINGS: -

i. When work is executed in occupied buildings, there should be minimum of

inconvenience to the occupants. The work shall be programmed in consultation

with the Engineer-in-charge and the occupying department. If so required, the

work may have to be done even before and after working hours.

ii. The contractor shall be responsible to abide by the regulations or restrictions set

in regard to entry into, and movement within the premises.

iii. The contractor shall not tamper with any of the existing installations including

their switching operations or connections there to without specific approval

from the Engineer-in-charge.

15. STATUTORY REGULATION AND APPROVALS: -

All electrical works shall be carried out only by those Contractors who are licensed by

the concerned local authorities to execute this type of work. Only government approved

electrical contractor shall execute the job.

16. STANDARDS AND CODE OF PRACTICE: -

The work shall be carried out as per the enclosed Specifications of work and the

construction drawings to be issued from time to time. These specifications shall be read

in conjunction with National Building Code, National Electrical Code 1985, Relevant

Codes of Practices and Standards as issued by ISI and Indian Electricity Rules, CPWD

specifications for electrical works (all with the latest amendments). The installation shall

confirm in all respects to Indian Standard code of Practices. Following BIS codes shall be

referred –

a) National Electrical Code

b) IS: 694 – 1977: PVC insulated cables for working voltage up to and including 1100

volts

c) IS: 732 -1989: Electrical wiring installation

d) IS: 1225 -1938: Installation and Maintenance of power Cables up to and including 33

KV Rating

e) IS: 1554: PVC insulated heavy-duty electrical cables.

f) IS: 1860: Installation operation and maintenance of passenger and goods elevator.

g) IS: 2309 -1989: Protection of building and allied structures against lightning.

h) IS: 3043 -1987: Earthing

i) IS: 3646 (Part-1) -1992: Interior Illumination

j) IS: 3661 (Part-2) -1967: Current rating for cable

k) IS: 3661 (Part-5) -1968: Current rating for cable

Page 15: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 15

l) IS: 5216 (Part-1) -1982: Recommendations on safety procedures and practices in

electrical work.

m) IS: 7098 (1 & 2): XLPE insulated cables

n) IS: 10028 (Part-1) -1985: selection, Installation and Maintenance of Transformers

o) IS: 10118 (Part-1) -1982: Selection, Installation and Maintenance of switchgear and

Control gear

17. MATERIAL SAMPLES AND SHOP DRAWINGS: -

It shall also be the responsibility of the Contractor to submit without any extra charge

the samples of the materials/equipment as and when asked by the Engineer in charge. If

the Contractor wishes to use an alternative make due to non-availability of the approved

one, he should take the prior approval of the Bank. Under such situations the Contractor

shall show such promptness as not to hamper the progress of the work.

The Contractor shall submit to Bank for approval the drawings at approved scale

indicating the custom built equipment, L.T. Panels, run of cables and conduits he

proposes to install.

18. TESTING AND COMMISSIONING: -

The Contractor shall be responsible for testing and commissioning the equipment

supplied with entire electrical installation described in these specifications and relevant

IS specifications and will demonstrate the operation of the systems to the entire

satisfaction of the Bank/Bank and to the Client approval.

19. GUARANTEE

At the close of work and before issue of final certificate of completion by Bank, the

contractor shall furnish a written guarantee indemnifying the owner against defective

materials and workmanship for a minimum period of 1 year after commissioning. The

contractor shall hold himself fully responsible for reinstallation or replacement of

defective material free of cost to the Bank.

20. DEFECTS AFTER COMPLETION

The contractor shall make good at his own cost and to the satisfactions of the Bank all

defects or faults, which may appear within 12 months after completion of the work. In

default the Bank may employ and pay other persons to amend and make good such

damages, losses and expenses consequent thereon or incidental there to shall be made

good and borne by the contractor and such damages, loss and expenses shall be

recoverable from him by the Bank or may be deducted by the Bank, in lieu of such

amending and making good by the contractor, deduct from any amount due to the

contractor, a sum equivalent to the cost of amending such work and in the event of the

amount retained being insufficient, recover that from the contractor from the amount

retained as retention money together with any expenses the Bank may have incurred in

connection therewith.

Page 16: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 16

21. INSPECTION

All equipment/material covered under this specification is liable for inspection by the

Bank/ its representative. The contractor shall furnish data sheets & other details.

Additional information, if desired by the bidder can also be furnished separately.

22. PAYMENT TERMS: -

a) No advance payment will be given against the subject work.

b) 80% against the total contract value after successful installation, testing &

commissioning as per tender BOQ.

c) 20% of the total contract value against submission of handover documents, virtual

completion certificate, providing training to client staff, completion certificate and Bank

Gurantee of equivalent amount valid till expiry of defects liability period of 1 year.

d) Period of honoring the final bill will be one month

e) Retention money / Security deposit @ 5% of final bill amount shall be retained by the

bank until completion of defect liability period of 1 year. No interest shall be applicable

on the retention money / Security deposit.

1.0 GENERAL INFORMATION

1.1 Ambient air temperature shall be taken as 50 deg. C for the purpose of designing of

electrical equipment.

1.2 This specification shall be read and constructed in conjunction with the drawings and

annexure to determine the scope of work.

1.3 All equipment shall be capable of continuous operation satisfactorily under the following

conditions:

a) Voltage variation : ± 10%

b) Frequency variation : ± 5%

c) Combined voltage & frequency variation : ± 10%

1.4 Nominal system supply available shall be as follows:

a) Incoming : 11 kV, 3 Ph., 50 Hz,

b) Utilization : 433 V, 3 Ph., 4 wire, 50 Hz

2.0 CODES AND STANDARDS

2.1 All equipment and materials specified herein or not, shall be designed, manufactured

and tested with the latest applicable standards & bureau of Indian standards.

2.2 All electrical equipment shall also conform to the latest electricity rules as regards safety

and other essential provisions.

2.3 All electrical installation work shall comply with the requirements of the following Act /

rules / codes as amended upto date:

a) Indian electricity act.

b) Indian electricity rules.

c) National electric code published by 818.

d) All relevant IS codes of practice.

e) Regulations published by tariff advisory committee.

Page 17: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 17

3.0 SYSTEM DESCRIPTION & TECHNICAL SPECIFICATIONS FOR THE PROPOSED 500 KVA

TRANSFORMER

Sr.No Particulars Remarks

01 Make Crompton /KIRLOSKAR /SIEMENS

/SCHNEIDER / ABB

02 Reference Standard IS 1180 LEVEL 2

03 KVA Rating 500

04 Type of cooling ONAN

05 Number of Phases & rated frequency 3 & 50 Hz

06 Rated Voltage at no Load HV /LV (in KV) 11 / 0.433

07 Connection (HV /LV ) & Vector Group Delta / Star & DYN 11

08 Insulation level – HV /LV L1 75 AC 28 /AC 3

09 Type of Tap changer – off circuit / on load Off Circuit tap changer

10 Tap range, Number of steps size & Location +5 % to -10% @2.5% in 6 steps

11 Temperature rise of top oil / winding (degree C) 40 / 45

12 Total Loss @ 50% Load (KW) 1.51 Max

13 Total Loss @ 100 % Loading (KW) 4.30 Max

14 % Impedance Volts at 75 degree Celsius rated

current & frequency

4.5% sub to +/- IS Tol

15 Noise Level As per NEMA TR -1

16 % Efficiency @ UPF & 0.8 PF Lagging

a. 100%

b. 75%

c. 50%

d. 25%

As per IS 1180 Level 2 losses

17 % Regulation at full Load and at UPF / AT 0.8 pf

Lag

As per IS 1180 Level 2 losses

18 Termination HV /LV HV Cable Box / LV Cable Box

It is the responsibility of the bidder / supplier to make necessary visiting arrangement of the

officials from the Bank to check / ensure the various technical tests to be conducted by the

Manufacturer while manufacturing as well as pre dispatch of the transformer which is to be

supplied.

4.0 DESIGN CRITERIA

4.1 GENERAL

a) The equipment shall be used in high voltage system having characteristics as listed in

this specification.

b) The equipment shall be installed in a hot, dusty, humid and tropical atmosphere.

c) There shall be no radio interference when the equipment are operated at maximum

service voltage.

d) The max. temp. in any part of the equipment at specified rating shall not exceed the

Page 18: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 18

permissible limits as stipulated in the relevant standards.

e) The equipment shall be capable of withstanding the dynamic and thermal stresses of

listed short circuit current without any damage or deterioration.

f) All equipment, accessories and wiring shall have tropical protection, involving special

treatment of metal and insulation against fungus, insects and corrosion.

g) The safety clearances of all live parts of the equipment shall be as per relevant

standards.

h) All equipment/components of identical rating shall be physically and electrically

interchangeable.

i) All outdoor equipment shall be suitable to mount on steel structure. Connectors shall be

bimetallic conductor.

j) Wherever single core cables are terminated in any equipment, gland plate shall be of

Aluminium (3-4 mm thick).

k) There shall be no straight through joints in power & control cables.

l) All cable terminations shall be with Double compression cable gland with Armour

holding system.

m) The lighting fixture shall have loop in & loop out facility.

GENERAL & TECHNICAL

Page 19: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 19

SPECIFICATION FOR SUPPLY AND INSTALLATION OF 11 KV/433 VOLTS

500 KVA DISTRIBUTION TRANSFORMER WITH ON LOAD TAP CHANGER

1.0 GENERAL:

1.1 Scope of Work:

This specification covers design, manufacture, test at works & site, insure, load and transport to

site, unload, and hand over 11 KV /433 Volts 500 KVA Distribution Transformer with OLTC/RTCC

and AVR to be installed for the proposed site. The scope shall cover Supply, Store, Installation,

Testing and Commissioning of outdoor type Step-down, transformers having the capacities and

rating mentioned below :-

11000/433 Volts, 500 KVA, 3 Phase 50 Cycles, Step down transformer with OLTC/RTCC and AVR.

This specification intends to give a general indication of the equipment and the Bidder shall

submit an offer for suitable equipment to meet the specification requirements. The Bidder

shall submit detailed technical specifications of the equipment together with illustrative

literature and equipment outline drawings.

2.0 Works Included:

Civil works like foundations for the equipment is not included in the scope of Bidder. The

successful Bidder shall furnish dimension drawings and relevant data required for planning the

equipment foundations, cable trenches etc and to be executed by Banks for approval. All base

channels and locking arrangements required to be grouted across the cable trenches shall be

provided by the successful Bidder/bidder.

3.0 Standards:

3.1 The design, manufacture and performance of equipment shall comply with all

currently applicable statutes, regulations and safety codes in the locality where the

equipment will be installed. Nothing in this specification shall be construed to relieve

the Bidder of his responsibility.

3.2 Unless otherwise specified equipment shall conform to the following latest applicable

Indian Standards:-

IS: 2026/1977 : Power Transformer.

IS: 363 : Fittings and Accessories for Power Transformer.

IS: 2099: High Voltage Porcelain Bushings

IS: 335 : Insulating Oil for Transformers & Switch gears.

IS: 6600: Guide for loading of Oil immersed transformers.

IS: 3637 : Specification for gas operated relays.

IS: 1271: Classification of Insulating materials.

IS: 3202: Code of practice, for climate proofing.

4.0 Special Site Conditions:

4.1 All equipment shall be designed for operating in tropical humid and salt ladder

climate with ambient temperature of 45 degree centigrade maximum and 14 degrees

centigrade as minimum.

Page 20: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 20

4.2 Extreme care shall be taken to make the enclosed equipment proof against entry of

rats, lizards and other vermin. All ventilation and other openings provided in the

equipment shall have suitable oil seal.

4.3 Continuity of power supply is the first consideration and the equipment design shall be

such as to provide facilities to simplify maintenance, inspection, testing and general

repairs at site.

4.4 Climatic Conditions:

Maximum temperature - 50 Degree Centigrade.

Minimum temperature - As per minimum temperature recorded for the site.

Relative Humidity - 65%

5.0 Equipment Specification

The general technical specification and Essential features for Distribution

Transformer are as stated below :-

5.1 General Specification:

a) System of Supply:

11 kV, 3 Phase, 50 Cycles, Solidly earthed system.

b) Rating :

500 kVA Rated Transformer as per the design considerations and as shown in

drawings.

c) No load Voltage :

11000 Volts on H.V. Side and 433 Volts on L. V. Side.

d) Ratio :

11000/433 Volts.

e) Connections :

Delta on H.V. side and Star on L.V. side with Neutral terminal brought out for solid

earthing.

f) Vector Groups :

Corresponding to the Vector Symbol Dyn-11

g) Impedance :

The Transformers shall be so designed and manufactured to have matched

impedance for a parallel operation. Impedance shall not exceed 6.25% and

variation in impedance of the ultimate finished product shall be with +/- 5% of the

nominal impedance value.

h) Type :

Page 21: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 21

Out door.

5.2 Essential Features of Transformers-

Constructional Features:

a) Similar parts, particularly removable ones, interchangeable.

b) Exposed parts shall not leave pockets where water can collect.

c) Internal design of transformer shall ensure that air is not trapped in any location.

d) Materials in contact with oil shall be such as not to contribute to the formation of

acid in oil. Surfaces in contact with oil shall not be galvanized or cadmium plated.

Core:

a) The magnetic circuit shall be of “Mitred Core type" construction. The core shall be

built out of High grade, non ageing, low loss, high permeability, cold rolled grain

oriented silicon steel laminations.

b) The finally assembled core shall be free from distortion. It shall be rigidly clamped

to ensure adequate mechanical strength and to prevent vibrations during

operation.

c) The core shall be provided with lugs suitable for lifting the complete core and coil

assembly.

d) The core and coil assembly shall be so fixed in the tank that shifting will not occur

during transport or short circuits.

Internal Earthing:

All internal metal parts of transformer shall be earthed.

Winding:

a) Winding shall be subjected to shrinking and seasoning process, so that no further

shrinkage occurs during service. Adjustable devices shall be provided for taking

up possible shrinkage in service.

b) Materials used in the insulation and assemble of the windings shall be insoluble,

non-catalytic and chemically inactive in hot transformer oil, and shall not soften

or be otherwise affected under the operating conditions.

c) In case of Dyn 11 transformers, neutral shall be brought out in open for solid

earthing on the secondary side, separately on the tank.

d) The windings shall be of copper wound.

e) The winding shall be so designed that it can withstand the specified thermal

and dynamic short circuit current.

Tank:

a) Tank shall be made from good commercial grade low carbon steel and shall be of

welded construction.

Page 22: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 22

b) Tank shall be designed to permit lifting, by crane or jacks, of the complete

transformer assembly filled with oil. Accordingly the base shall be suitably

reinforced to prevent any distortion.

c) The material used for gaskets shall be cork neoprene or approved equivalent.

d) All fasteners and bolts etc. shall be galvanized or zinc passivated.

Oil:

a) Transformer shall be supplied with first filling oil conforming to IS: 335. First filling

of oil as per Indian Standard Specifications.

b) Additional 25 litres of oil shall be supplied in non-returnable tin for each

transformer, for tapping purposes etc.

ON Load Tap Changer Switch with RTCC and AVR ("ON Load Tap Changer")

On load tap changing arrangement with RTCC and AVR on H.V. side. The tapping to be provided

for variation of HV Voltage from +10% to - 15% in a basic steps of 1.56% each, with RTCC and

AVR arrangement. An on-load Tap Changer with RTCC and AVR is to be provided. The RTCC Panel

shall be ready to hook up with BMS system.

Specifications For On Load Tap Changer:

The On Load Tap Changer meeting all manufacturing Standards with high Speed, Resistor is to be

provided. It should be self contained and should be designed such that it should be directly bolt

to a port flange of transformer. The assembly should comprise following parts:

a) Tank

b) Selector Switch

c) Driving Mechanism

d) Barrier Board

e) Local Control Gear.

f) Control Cable Termination.

a) Tank:

The complete tap-changer should be housed in a single tank designed to bolt directly to a part

flange on the transformer. The tank of welded sheet steel construction, is divided into

two separate compartments, to house the selector switch, Driving mechanism and Local

control gear. Access to the compartments is made easy by means of removable covers and a

weatherproof door. Anti condensation heater is provided in the compartment which houses

driving mechanism and control gear.

b) Selector Switch:

The Three phases of the tap-changer are adequately spaced for full inter phase insulation

but mounted as a common assembly using vertical synthetic resin-bonded insulating boards,

each carrying a circle of fixed contacts. Insulating rods and tubes are used for the horizontal

spacing of the phases and fixed contacts are connected via the barrier board to appropriate

tapping in the transformer winding. Each phase has a single rotary contact take-off connection.

This ring carries separately insulated spring loaded snap action moving contacts which are

electrically connected by a non inductive resistance unit accommodated on the contact

carrier. One contact is connected directly to the centre boss take-off point, the second

Page 23: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 23

‘transition moving contact’ being connected to the resistor. The three contact support rings are

attached to central insulating drive shaft, which rotates in self aligning ball bearings in the two

outer phase boards. This centre shaft is of glass reinforced synthetic resin construction. Access

to the selector switch is via removable cover on the top of the tank.

c) Driving Mechanism:

Operation of the selector switch shaft is by means of a stored energy spring device having a

positive snap action for rotating the moving contacts quickly through the angle required for each

tap change. The driving mechanism compartment is external to the oil-filled switch tank. The

rotary drive from the driving mechanism to the selector switch passes through a frictionless

positive oil-tight gland.

The angular movement of the selector switch shaft is controlled by an indexing wheel which

is positively locked by the periphery of the operating cam except during the actual time of

tap change operation. The operating cam is freely mounted on its shaft, rotation being

imparted to it by means of tension springs attached radially between the operating cam hub

and the periphery of concentric spring carrying gear wheel. The spring carrying gear wheel is

rotated by the driving motor through reduction gearing and thus rotates the operating cam.

When the drive pin on the operating cam enters the slot in the indexing wheel the lock is

disengaged but rotation is prevented by the locking arm pawl engaging in another slot of the

indexing wheel. The spring carrying gear wheel continues to rotate thus charging the springs.

When sufficient energy has been stored a trip pin on the gear wheel lifts the locking arm

restraining the indexing wheel and the spring energy is released to move the tap selector

switch one position, the cam locking coming into operation, accurately controlling the

angular movement.

The operation of the selector switch is thus positively assured, and is dependent only upon the

quick release of the spring energy. It is thus independent of the motor drive. The tap changing

sequence is now complete and driving motor is brought to rest by the resetting of auxiliary

switches and mechanical friction device. For protective purposes automatic declutching by

shear pins is incorporated in the drive.

Auxiliary switches:-

The mechanism is provided with the auxiliary switches necessary for its own operation. A step

by step switch for position indication is also fitted and additional paralleling and out of

step switches can be provided. A tap change mechanical counter, mechanical tap position

indicator, mechanical end stops and electrical limit switch arrangements are also provided.

Hand Operation :-

A detachable handle for hand operation is provided. The fitting of this handle automatically

disconnects the motor drive shaft by the operation of a simple spring loaded dog clutch and at

the same time isolates the electrical control supply.

d) Barrier Board:

The connections from the transformer winding are taken through an insulating, terminal

barrier board which is supplied loose for clamping to the transformer port flange. Thus the

Page 24: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 24

transformer may be treated and filled with oil before the tap changer is fitted. This arrangement

allows the tap selector switch contacts to be inspected or the complete tap changer to be

handled separately without disturbing the oil level in the transformer.

e) Local Control Gear:

The motor reversing contactors and associated local gear are housed in the same

compartment as the driving mechanism with a common hinged weatherproof door.

Weatherproof local control switches when required are mounted in an accessible position below

the door.

Electrical sequence of operation:-

An impulse is received, either from a remote control or from a local manual operation switch,

which energies the appropriate raise/lower contactor to initiate a tap changer in the required

direction. The contactor when energized, seals itself via its own contact and the driving motor

commences to run. At a predetermined point a directional sequences switch closes, taking over

the holding duties of the contactor whose original self hold circuit is isolated. At the completion

of the tap change the directional sequence de-energies the driving motor. This arrangement

ensures that a short period initiating pulse will be accepted by the control gear.

Parallel Control:-

Various forms of parallel control can be accommodated and the equipment can, in general, be

arranged to operate in parallel with units of manufacture. I.e Master and Follower Scheme

are to be provided.

f) Control Cable Termination:

A detachable undrilled gland plate and the terminal stations for all external connections are

provided in the driving mechanism compartment of the tap changer.

g) Temperature rise :

Continuously rated for full load, temperature rise not to exceed 50 degree centigrade by

thermometer in oil (55 degree centigrade by resistance).

h) Cooling :

Natural oil cooling by means of pressed/round tubes/ radiators around transformer tank, ONAN

type.

i) Accessories and Fittings :

The following accessories and fittings shall be provided:-

a) Inspection Covers :

Inspection cover on top of the transformer shall be provided.

b) Lifting lugs :

The arrangement of lifting the active part of the transformer along with the cover of

the tank by means of lifting lugs without disturbing the connections. Also complete

transformer lifting lugs shall be provided. Lifting arrangement for core and coils shall

also be provided.

Page 25: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 25

c) Jacking Pads :

Jacking pads shall be provided on the transformer.

d) Earthing Pads :

2 Nos. earthing pads shall be provided of copper or non-corrodible material on

transformer tank and suitable earthing terminals on cable boxes.

e) Diagram and Rating Plate :

One diagram and rating plate indicating the details of transformer, connecting

diagram, Vector Group, tap changing diagram etc.

f) Air Release :

An air release hole with plug is to be provided on the top of the tank cover to

facilitate the release of the entrapped air while filling of oil.

g) Breather :

The transformer to be provided with an indicating dehydrating silica gel-breather of

sufficient capacity.

h) Oil Valves :

The transformers should be provided with the following Oil Valves: All free end of the

valves to be blinded.

i. Filling Valve.

ii. Main tank drain valve with flanged or threaded connection. The drain shall be

so designed such that, the 90% of the oil can be drained off in 10 minutes.

iii. Top and bottom filter valves.

iv. Oil sampling valve.

v. Pressure relief device or explosion vent.

vi. Shut off valve between conservator and the Buchholz relay.

vii. Shut off valve between Buchholz relay and main tank.

Oil Conservator :

The transformer to be provided with a conservator with welded end plates. It is to be bolted to

the cover and can be dismounted for purposes of transport. It has to be provided with oil

level gauge with marking for minimum level and an oil filling hole with a cap which can be

used for filtering oil. For draining purposes a plug is to be provided. A connection pipe between

the conservator and main tank to be provided which projects inside the conservator.

Rollers - Bi-directional Rollers:

4 Nos. bi-directional plain rollers shall be provided to the transformers on cross channels to

facilitate easy movement and positioning of the transformer. Suitable locking arrangement of

the rollers shall also be provided.

Thermometer Pocket

Page 26: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 26

A pocket for reading oil temperature by thermometer along with thermometer 0-120 degree

centigrade mercury in glass thermometers shall be provided. This pocket shall have waterproof,

dust proof and weatherproof design to avoid contamination of transformer oil, under outdoor

usage.

Buchholz Relay :

Suitable for 30 Volts D.C operation with alarm and Trip contact is required.

Dial type Thermometer :

A dial type thermometer having 150 mm dia. and with maximum set pointer at 90 Degree

Centigrade. The indicating instrument shall have 2 electrical independent contacts for electrical

alarm and trip at high temperature and at 2 distinctly different temperatures, suitable

for 30 Volt D. C. auxiliary contacts.

Magnetic Oil Level Indicator :

Suitable for 30 Volts D.C operation with alarm contact is required.

Explosion Vent :

The tank shall be provided with a pressure release device. The device shall be weatherproof and

shall be provided with a diaphragm. The Equalizer pipe shall be connected to the pressure

release device (explosion vent) to the conservator. The vent shall be placed in such a manner so

that in case of diaphragm rupture the discharge of oil shall not be on the transformer.

Cable end boxes :

a) On H.V. Side :

Cable End Box suitable for 3.0 Core x 240 sq.mm 11 kV XLPE Cable. Further the box

shall be suitable to accept the cable entry from Top.

b) On L. V. Side :

On L.V. Side cable end box shall be provided suitable to accept 1250 Amps Sandwich

Type Copper BUS-DUCT OR 3.5Cx300 sq.mm. A2XFY cables. The Cable terminal box

shall be provided with suitable Solid Copper flats of proper size. The extended copper

flats shall be suitable to accept the BUS-DUCT flexible connections.

Marshalling Box

A Marshalling box shall be provided on the Transformer to have the following contact blocks: -

a) Alarm and Trip contacts for Oil Temperature Indicator, suitable for 30 Volt D.C. Supply.

b) Alarm and Trip contacts for Buchholz Relay, suitable for 30 Volt D.C. Supply.

c) Alarm and Trip contacts for Winding Temperature, suitable for 30 Volt D.C. Supply.

d) Alarm contacts for Magnetic Oil Gauge, suitable for 30 Volt D.C. Supply.

e) 1 No. 5 Amps Tumbler Switch with Lamp Holder suitable for 1 No. Incandescent lamp.

f) Strip Heater suitable for 415 Volts A.C Supply System with On/Off Switch.

Painting :

Page 27: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 27

a) The interior of transformer tank, other oil filled chambers and internal structural

steel work shall be painted with heat resistant, oil insoluble insulating varnish

after thorough cleaning of all scales and dust.

b) Steel surfaces exposed to the weather shall be thoroughly cleaned and applied

first coat of zinc chromates, second coat of oil and weather resistant paint and

final coat of glossy oil and weather resistant non fading paint.

Noise :

The audible sound level measured at one feet from the external surface of the transformer shall

not exceed as per NEMA Standards.

Testing :

The Transformer shall be subjected to the following tests at the factory before dispatching

the same shall be witnessed by the Bank /Consultant and test certificates shall be furnished :-

a) Measurement of winding resistance.

b) Ratio polarity and phase relationship

c) Impedance Voltage.

d) Load losses, copper losses.

e) No load loss and no load current.

f) Insulation resistance.

g) Induced over voltage withstand.

h) Separate source voltage withstands.

i) Heat Run Test

j) Magnetic Core Balance Test

Manufacturer testing lab must have the in-house facility for conducting Impulse test and

heat run test. Testing lab must be accredited / certified by NABL.

Instructions Manual:

The successful bidder shall submit six copies of manual of complete instructions for the

installation, operation, maintenance and repairs, circuit diagram, foundation and trenching

details shall be provided with the transformers.

Rejection:

The Consultant/Bank may reject any transformer if during tests or service any of the following

conditions arises:-

a) No load loss exceeds the guaranteed value by 5% or more.

b) Load loss and copper losses exceeds the guaranteed value by 5% or more.

c) Impedance value exceeds the guaranteed value by +/- 5% or more.

d) The difference in impedance values of any two phases during single phase short

circuit impedance test exceeds 2 percent of the average value guaranteed by the

Manufacturer.

Page 28: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 28

e) Oil or winding temperature rise exceeds the specified value by 5 Degree

Centigrade.

f) Transformer fails on power frequency voltage withstand test.

g) Transformer is proved to have been manufactured not in accordance with the

agreed specification.

h) The Bank, reserves the right to retain the rejected transformer and take it in to

service until the Successful Bidder replaces, at no extra cost to the Owners the

defective transformer by a new transformer.

i) Alternatively the Bidder shall replace the transformer within a reasonable period

to the Bank, to the satisfaction and at no extra cost to the Bank.

DATA SHEET

Make: _____________________

Page 29: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 29

1. MEASUREMENT: -

i. Contractor shall measure the work jointly with the Bank and prepare measurement

sheets in triplicate. Three copies of measurement sheets shall be submitted along

Sr.

No

Description Unit Tender specifications Confirmation

from Bidder

1 Rated Capacity (Continuously

rated)

kVA 500

2 Primary Voltage Volts 11 KV

3 Secondary Voltage Volts 433

4 No. of phase 3

5 Type of cooling ONAN

6 Frequency 50 Hz

7 Vector Group Dyn 11

8 Tap changing To be filled by bidder

9 Reference ambient temperature ˚C 50

10 Maximum temperature rise (at full

load) – Oil \ Wdg

˚C 50\ 55

11 Physical Dimensions ( max )

Length Mm To be filled by bidder

Width Mm To be filled by bidder

Height Mm To be filled by bidder

12 % Impedance % To be filled by bidder

13 No Load Losses (Iron losses) at

normal voltage ratio (Max.)

kW Shall be as per ECBC

14 Load Losses (Copper loss) at

normal voltage ratio ( Max)

kW Shall be as per ECBC

15 Efficiency at unity power factor

(Min)

To be filled by bidder

Full load % To be filled by bidder

75% load % To be filled by bidder

50% load % To be filled by bidder

25% load % To be filled by bidder

16 Regulation at 50 % loading & 0.9

PF

% To be filled by bidder

17 Approximate weight

18 Core & winding Kgs To be filled by bidder

19 Total Weight Kgs To be filled by bidder

20 Oil

Ltrs To be filled by bidder

Page 30: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 30

with running account bills. Bills received without proper measurements of work

shall not be considered submitted.

ii. Should the contractor neglect to measure the work, then the measurement taken

by Bank or a person approved by the Bank shall be final and binding to him. Such

measurements shall be taken in accordance with the mode of measurements

wherever specified or as per actual executed quantities.

iii. All authorized extra works; omissions and all variations made without the Bank’s

knowledge, or subsequently sanctioned by him in writing (with the prior approval of

the contractor in writing) shall be included in such measurement.

iv. All bills for the work shall be submitted in the tender price bid format.

2. CONFORMITY TO I.E. ACT, I.E. RULES AND STANDARDS:

i. All electrical works shall be carried out in accordance with the provisions of the

Indian Electricity Act, 1910 and Indian Electricity Rules 1956 amended up to

date.

ii. The work shall also conform to relevant Indian Standard codes of practice for

the type of work involved.

iii. In all electrical installation works, relevant safety codes of practice shall be

followed.

iv. The complete wiring installation shall confirm to IS: 732 amended up to date.

3. GENERAL REQUIREMENTS OF COMPONENTS:-

3.1 QUALITY OF MATERIALS:-

All materials and equipment supplied by the contractor shall be new. They shall be of

such design, size and material as to satisfactorily function under the rated conditions of

operation and to withstand the environmental conditions at site.

3.2 RATING OF COMPONENTS:-

i. All components in a wiring installation shall be of appropriate ratings of voltage, current

and frequency, as required at the respective sections of the electrical installation in

which they are used.

ii. All conductors, switches and accessories shall be of such size as to be capable of carrying

the maximum current, which will normally flow through them, without their respective

ratings being exceeded.

3.3 CONFORMITY OF STANDARDS:-

All components shall conform to relevant Indian Standard specification, wherever

existing. Materials with ISI certification mark shall be preferred. However for conduits,

wiring cables, piano/tumbler switches and socket outlets, ISI marked materials shall only

be permitted.

4. WORKMANSHIP:-

Page 31: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 31

i. Good workmanship is an essential requirement to be complied with. The entire

work of manufacture/fabrication, assembly and installation shall conform to

sound engineering practice.

ii. The work shall be carried out under the direct supervision of a first class licensed

foreman, or of a person holding a certificate of competency issued by the state

Government for the type of work involved, employed by the contractor, who

shall rectify then and there the defects pointed out by the Engineer-in-charge

during the progress of work.

5. COMMISSIONING ON COMPLETION:-

Before the workman leaves the work finally, he must make sure that the installation is in

commission, after due testing.

6. COMPLETION PLAN AND COMPLETION CERTIFICATE:-

For all works completion certificate after completion of work shall be submitted to the

Bank.

7. ADDITION TO AN INSTALLATION:-

An addition, temporary or permanent, shall not be made to the authorised load of an

existing installation until it has been definitely ascertained that the current carrying

capacity and the condition of the existing accessories, conductors, switches etc affected,

including those of the supply Authorities, are adequate for the increased load.

8. EARTHING REQUIREMENTS:-

As per Indian standard

8.1 DIMENSIONAL DETAILS OF RIGID NON-METALLIC CONDUITS

(All dimensions in mm)

Sr.No. Nominal

outside

diameter

(In mm)

Maximum

outside

diameter

(In mm)

Minimum inside

diameter

(In mm)

Maximum

permissible

eccentricity

(In mm)

Maximum

permissible

ovality

(In mm)

1. 20 20 +0.3

17.2 0.2 0.5

2. 25 25 +0.3

21.6 0.2 0.5

3. 32 32 +0.3

28.2 0.2 0.5

4. 40 40 +0.3

35.8 0.2 0.5

5. 50 50 +0.3

45.0 0.4 0.6

8.2 MAXIMUM NUMBER OF PVC INSULATED 650/ 1100-VOLT GRADE COPPER CONDUCTOR CABLE THAT CAN BE

DRAWN INTO RIGID PVC CONDUIT

Page 32: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 32

Nominal cross sectional area of

conductor in Sq.mm.

20

mm

25

mm

32

mm

40

mm

1.50 5 10 14 -

2.50 5 8 12 -

4.00 3 8 10 -

6.00 2 5 8 -

10.00 - 3 5 6

16.00 - - 3 6

25.00 - - 2 4

Note: - The above table shows the maximum capacity of conduits for a simultaneous drawing of

cables.

8.3 ORDINARY CLIPS OR GIRDER CLIPS.

Sr.No.

Size of conduit Width Thickness

1. 20 mm & 25 mm 19 mm 20 SWG (0.9144 mm)

2. 32 mm & above 25 mm 18 SWG (1.219 mm)

CABLES

1. GENERAL

All cables shall be supplied, inspected, laid tested and commissioned in accordance

with drawings, specifications, relevant Indian standards specifications and cable

manufacturer's instructions. The cable shall be delivered at site in original drums with

manufacturer's name clearly written on the drum.

The recommendations of the cable manufacturer with regard to jointing and sealing

shall be strictly followed.

The laying of cable shall be done as per IS 1255 amended up to date.

Cable Identification

Cable identification shall be provided by embossing on the outer sheath the following:

(i) Manufacturer's name or trade mark

(ii) Voltage grade

(iii) Year of manufacture

(iv) Type of insulation

(v) Printing of cable length on each meter

Core Identification

Respective cores of power/control cables shall be identified with the following pattern:

2 core : red (R), black (BK)

3 core : 5 core red (R), yellow (Y), blue (BL)

Page 33: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 33

4 core : red (R), yellow (Y), blue (BL), black (BK)

5 core : red (R), yellow (Y), blue (BL), black (BK) & grey (GY)

7&14 cores : cores shall be numbered.

Tests

(i) Shop Tests

The cables shall be subject to shop tests in accordance with relevant

standards to prove the design and general qualities of the cables as below:

(ii) Routine tests on each drum of cables.

(iii) Acceptance tests on drums chosen at random for acceptance of the lot.

(iv) Type tests on each type of cable, inclusive of measurement of armour D.C.

resistance of power cables.

2. MATERIAL

L T Power Cables :

The 1.1 KV cables shall be XLPE insulated PVC sheathed aluminium conductor armoured

conforming to IS: 7098 (part - 1) amended up to date or PVC insulated, extruded PVC

inner sheath, steel strip armored and extruded PVC overall sheath conforming to

15:1554 (PI) as mentioned in the Bill of Quantities and drawings, laid in trenches, ducts

and underground as per instruction given by Bank.

Control Cables

Control cables shall be of stranded annealed copper conductors with cross section area

of 1.5/2.5 sq.mm, PVC insulated, colour coded or with core identification, extruded inner

sheathed, steel wire armoured and over all PVC extruded outer sheath etc. The cable

shall conform to 15: 1554 (P-I).

Cable Termination

L T power, control cable termination

(i) LT cable termination shall be provided with compression cable glands of

brass suitable for holding the armour of the cable.

(ii) Lugs shall be crimping type and shall be of copper suitable for copper

conductor cable and of aluminum for aluminum conductor cable.

(iii) Termination shall be carried out as per details furnished in this specification.

Compression Glands

Cable glands shall be made of brass casting, machined accurately to the required size

with protective coating of nickel.

Cable glands shall be of heavy duty type and shall consist of: gland nipple, neoprene seal

for inner sheath, armour clamping cone, gland body, neoprene seal for outer sheath,

skid washer, gland body nut.

Page 34: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 34

The Aluminium conductor shall be stranded; grade H4 class 2 as per IS 8130 and copper

conductor shall be annealed copper class 2 as per IS 8130.

Technical data sheets for above cables, including all electrical & mechanical parameters

shall be furnished with offer.

INDIAN STANDARD LT EQUIPMENT SPECIFICATIONS

1. LT air Circuit Breakers : IS 2516 - Latest PART

I & II Section – I, 8828 /

BS- 5311, 4752

2. Fuse switch units and switch

Fuse units not exceeding

1000 V AC or 1200 V DC : IS 4064 Latest/

BS-5419/IEC-408

3. Switch gear Bus bar : IS 375 Latest

4. H R C fuse Links : IS 2208 Latest

5. Distribution Boards : IS 2675 Latest

6. Enclosures for low voltage

Switch gears : IS 2147

7. P V C cables (Heavy Duty) : IS 1554 Latest

8. P V C cables (Working Voltage

up to and including 1100V) : IS 694 Latest

9. Tabular Fluorescent lamps : IS 2418 Latest

10. Tungsten filament lamps : IS 415 Latest

11. Ceiling fan : IS 374 Latest

12. Flood light : IS 1947 Latest

13. Industrial light fittings : IS 1771 Latest

14. Water proof electrical fittings : IS 3553 Latest

15. Steel boxes for enclosure of : IS 5133 Latest

Page 35: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 35

16. Electrical accessories

Fittings for rigid steel conduit : IS 2667 Latest

Mild steel conduit for

Electrical wiring : IS 653 Latest

Accessories for rigid steel

Conduit for electrical wiring : IS 3837 Latest

Switch socket outlets : IS 4615 Latest

Three pin plug& socket outlet :IS 1293 Latest

Switches for domestic and

Similar Purposes : IS 3854 Latest

Call bell and buzzers : IS 2268 Latest

Earthing : IS 3043 Latest

Electrical wiring installation : IS 732 Latest

17. Switch gear : IS 3072 Latest

18. Lighting protection : IS 2309 Latest

19. HT Cable : IS 7098 Latest

20. Power transformer : IS 1886 Latest

21. Current Transformer : IS 2705 Latest

22. MCCB : IS 2516 part I & II/ Sector I

Latest

23. Relays : IS 3231 Latest

24. Indicating Instruments : IS 1248 Latest

25. Auxiliary contactors : IS 2959 Latest

26. Capacitors : IS 2834 Latest or

27. PVC / Metal conduiting : IS 9357 Latest Part I, 2,3 & 4

Page 36: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 36

28. Bus-bar support insulators : IS 2544 Latest

29. Voltage Transformer : IS-3156/BS-3941IEC-44,186

30. Electrical relays : IS-3231, 3842

31. Contactors for voltage not exceeding

1000V AC or 1200V DC Control Switches : IS-6875/BS-4794/IEC-377

32. High Voltage fuse : IS-9385/BS-2692/IEC-269

33. Low Voltage fuse : IS-1248/BS-89/IEC-51

34. Indicating instruments A.C. electricity Meters IEC-of induction type 45,211

: IS-722, 8530 / BS-5685 /

35. Porcelain post insulators for system with nominal

voltages greater than 1000 volts. : IS-2544

36. Resistance wire, tapes and

strips for heating elements : IS-3725

37. Wrought aluminium and aluminium

alloy bars, rods, tubes and sections

for electrical purposes. : IS-5082

38. Toggle switches : IS-3452 / BS-3676

39. Metal enclosed switchgear and control

gear for voltage above 1000V, but not

Exceeding 11000V : IS-3427 / BS-162

40. General requirement for switchgear and

control gear for voltage not exceeding

1000 volts : IS-4237/BS-5486/IEC-439

41. Degree of protection provided by

enclosures for low voltage Switchgears

and control gear : IS-2147/IEC-144

43. Dimensions for panel mounted indicating

and recording electrical instrument : IS-2419

44. Marking and arrangement for switch-

gear, bus-bars, main connection and

auxiliary wiring. : IS-375

Page 37: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 37

45. Code of practice for selection, Installations

and maintenance of fuses. : IS-10118

APPROVED LIST OF ELECTRICAL MATERIAL

Description Brand

11 KV CIRCUIT BREAKER PANEL ABB / SEIMENS / AREVA

11 KV / 0.4 KV TRANSFORMERS CROMPTON / KIRLOSKER / SEIMENS/ABB /

SCHNEIDER

BATTERY CHARGING PANEL KELTRON / NELCO

BATTERIES EXIDE / AMCO / STANDARD

L T PANEL FROM STANDARD MANUFACTURING

COMPANY IN THE REGION

11 KV Isolator and D O Fuses AMEI / ELLPRO / STERLING

Capacitor L & T / DUCATI / EPCOS

APFC relay L & T KHATAU / DUCATI / SYNTRON

M.C.B. / RCCB / RCBO LEXIC / HAGER / ABB /MDS / GE

Distribution Boards LEXIC / HAGER / ABB / MDS / GE

Switch Fuse Units With HRC fuses GE / L&T / ABB / GE

Moulded Case Circuit Breaker (MCCB) ABB (T max) / L & T (D sine) / GE

Air Circuit Breakers ABB (EMEX/L&T(C POWER)

Current Transformer / Meters / Voltage

Transformers / Relays / Starters / Contactors /

Selector Switch / Indicating Lamps

L & T / SIEMENS / AUTOMATIC ELECTRIC /

CONTROL & SWITCH GEARS / ABB

Change Over Switches GE / L&T / HH ELCON

Cable Glands and Sockets SIEMENS

PVC insulated Copper conductor wires FINOLEX / RR / POLYCAB

Telephone Wires and cables FINOLEX / RPG/ POLYCAB

Television Coaxial cable FINOLEX / RR /RPG / L&T

PVC / XLPE Insulated 11 KV / 1.1 KV Cables UNIVERSAL /FORT CLOSTER / NICCO /

FINOLEX/POLYCAB

Switches and Sockets outlets (Conventional

piano type)

LT (ORIS) / LEGRAND / ANCHOR

Switches and Sockets outlets (Modular type) LT (ORIS) / MK / MDS-MOSAIC / ANCHOR

Industrial outlet LEXIC / HAGER / ABB

MIS Conduits and Accessories B.E.C./AKG/MK

PVC Conduits and accessories AKG/BEC/CAP/SEIKO / [POLYCAB

Electronic Energy Meters SECURE / L&T

MCB Distribution Board MOS/LEGRAND/SIEMENS /HAGER

HRC Switch Fuse nits SIEMENS ABB/GE/L&T

Cable Glands/Lugs SIEMENS/DOWELLS

Electronic Regulator MK/ANCHOR/ROMA/DEGRAND/MDS

Contactors SIEMENS/L&T/ABB/SCHNIEDER

Geysers/water/heater SPHERE HOT /RACOLD/USHA

Page 38: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 38

FRLS COPPER WIRE FINOLEX, RR KABEL, KEI, POLYCAB

MCBS AND DBS LEGRAND, INDO ASIAN, SIEMENS, ABB

UG CABLES 1.1KV POLYCAB, KEI, FINOLEX, RALLISON

SDF/MCCB L&T, MERLIN GERIN, SIEMENS

PVC CONDUIT AVON PLAST, BAJAJ PLAST, PRECISION

MS CONDUIT BEC, VIMCO, MK, AKG

KRONE BLOCK HOUSING HENZEL

CAPACITORS SIEMENS, L&T

TIMERS MERLIN GERIN, L&T

CONTACTORS TE, SIEMENS, L&T, ABB

APFC RELAY SIEMENS, L&T

MULTIFUNCTION METER CADEL, SOCOMEC

PVC CONDUIT (2MM THICK) AVON PLAST, EMJAY, AKG, BEC, CAP, SEIKO

MS CONDUIT 20MM ISI VIMCO, GB, BEC, AKG, MK

SCHEDULE OF QUANTITES

Page 39: STAFF TRAINING CENTRE GURGAON - Union Bank of India · 3) Tenders are to be submitted in one sealed envelope cover duly super scribed ^Te nder for the Work of SITC of 500 KVA Distribution

STC GURGAON SIGN & SEAL OF THE BIDDER 39

Sr.No Description Qty Price Amount

01 Supply of 500 KVA oil immersed 3 Phase

Distribution Transformer as per

specification of the RFP.

01

Add GST @

Total A

02 Installation, testing & commissioning of

the above transformer as per the

direction of Engineer in charge at site.

Add GST @

Total B

G. TOTAL (A+B)= (C)

03 Less: Buyback cost of existing

transformer (D)

04 Net Cost (E) = (C-D)

Total Amount in words: -------------------------------------------------------------