PRESENTATION ON SUMMER INTERNSHIP AT

SARPI COAL MINE PROJECT, JMS INDIA

BY: MINING MACHINERY ENGINEERING ISM DHANBAD

Page 2: sarpi coal mine project

AN OVERVIEW OF THE PRESENTATION

AN INTRODUCTION TO SARPI PROJECT. VARIOUS MACHINERIES DEPLOYED IN THE

MINE. DEVELOPMENT AND DEPILLARING PATTERN

FOLLOWED IN THE MINE. COST OF THE CONTINUOUS MINER

PACKAGE. SHUTTLE CAR: a) SPECIFICATIONS b) VARIOUS MECHANICAL AND HYDRAULIC

SYSTEMS IN A SHUTTLE CAR. c) SAFETY FEATURES.

Page 3: sarpi coal mine project

INTRODUCTION TO THE SARPI CONTINUOUS MINER PROJECT.

BORD AND PILLAR TYPE OF MINING IS FOLLOWED. MINE IS STILL IS IN DEVELOPMENT PHASE. CONTINUOUS MINER IS USED FOR CUTTING THE COAL

INSTEAD OF CONVENTIONAL DRILLING BLASTING METHOD.

DAILY PRODUCTION OF THE CONTINUOUS MINER PANEL IS ABOUT 1500 TONNES.

THE DEPTH OF THE SHAFT IS 159m. 5 HEADING DEVELOPMENT IS DONE. THE WIDTH AND HEIGHT OF THE GALLERIES IS 6mX4.6m. THE DIMENSIONS OF THE PILLAR IS 32mX32mX4.6m. DEGREE OF GASSINESS-II

Page 4: sarpi coal mine project

Actually Continuous Miner is a package of machinery including-Coal Cutting Machine :- Continuous MinerCoal Hauling Machine :- Shuttle CarCoal Lump Breaking & Feeding Machine to Conveyors :- Feeder BreakerFace Supporting Machine :- Quadbolter Face & Road Cleaning Machine :- LHDPower Distribution :- Load Centre As Continuous Miner is large underground machinery, so lowering the package of CM machinery can only be done through incline of proper cross section & gradient – not through any shaft / pit.

OPERATING MACHINERIES

Page 5: sarpi coal mine project

Typical Development Layout

The standard layout consists of a five road development, with the main conveyor and feeder breaker positioned in the central roadway. This provides working areas to carry out all the main development functions:

One heading for the CM to be cuttingOne heading ready for cuttingOne heading for ventilation rearrangement and survey workOne heading for cleaning by LHDOne heading for supporting by Quadbolter

Page 6: sarpi coal mine project

Typical De-pillaring layout

Page 7: sarpi coal mine project

Breaker lines installed for 3 rows before extraction commences6Extraction sequence

Breaker lines installed during pillar split

Remote Reading Telltale (3m + 10m) 2 x 2.4m SG bolts (breaker line) Pillar stress cells (5m + 10m)

Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10m)

BA

RR

IER

PIL

LA

R

Proposed Monitoring Scheme CM1 Panel

1

Auto warning telltale installed during pillar split

Page 8: sarpi coal mine project

Breaker lines installed for 3 rows before extraction commences6Extraction sequence

Breaker lines installed during pillar split

Remote Reading Telltale (3m + 10m) 2 x 2.4m SG bolts (breaker line) Pillar stress cells (5m + 10m)

Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10m)

BA

RR

IER

PIL

LA

R

Proposed Monitoring Scheme CM1 Panel

1

Auto warning telltale installed during pillar split

2

Page 9: sarpi coal mine project

Breaker lines installed for 3 rows before extraction commences6

Breaker lines installed during pillar split

Remote Reading Telltale (3m + 10m) 2 x 2.4m SG bolts (breaker line) Pillar stress cells (5m + 10m)

Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10m)

BA

RR

IER

PIL

LA

R

Proposed Monitoring Scheme CM1 Panel

1

Auto warning telltale installed during pillar split

2

3

Page 10: sarpi coal mine project

4

Breaker lines installed for 3 rows before extraction commences6Extraction sequence

Breaker lines installed during pillar split

Remote Reading Telltale (3m + 10m) 2 x 2.4m SG bolts (breaker line) Pillar stress cells (5m + 10m)

Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10m)

BA

RR

IER

PIL

LA

R

Proposed Monitoring Scheme CM1 Panel

1

Auto warning telltale installed during pillar split

2

3

Page 11: sarpi coal mine project

4

Breaker lines installed for 3 rows before extraction commences6Extraction sequence

Breaker lines installed during pillar split

Remote Reading Telltale (3m + 10m) 2 x 2.4m SG bolts (breaker line) Pillar stress cells (5m + 10m)

Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10m)

BA

RR

IER

PIL

LA

R

Proposed Monitoring Scheme CM1 Panel

1

Auto warning telltale installed during pillar split

2

35

6

Page 12: sarpi coal mine project

4

Breaker lines installed for 3 rows before extraction commences6Extraction sequence

Breaker lines installed during pillar split

Remote Reading Telltale (3m + 10m) 2 x 2.4m SG bolts (breaker line) Pillar stress cells (5m + 10m)

Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10m)

BA

RR

IER

PIL

LA

R

Proposed Monitoring Scheme CM1 Panel

1

Auto warning telltale installed during pillar split

2

35

6

7

8

Page 13: sarpi coal mine project

4

Breaker lines installed for 3 rows before extraction commences6Extraction sequence

Breaker lines installed during pillar split

Remote Reading Telltale (3m + 10m) 2 x 2.4m SG bolts (breaker line) Pillar stress cells (5m + 10m)

Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10m)

BA

RR

IER

PIL

LA

R

Proposed Monitoring Scheme CM1 Panel

1

Auto warning telltale installed during pillar split

2

35

6

7

8

9

10

Page 14: sarpi coal mine project

4

Breaker lines installed for 3 rows before extraction commences6Extraction sequence

Breaker lines installed during pillar split

Remote Reading Telltale (3m + 10m) 2 x 2.4m SG bolts (breaker line) Pillar stress cells (5m + 10m)

Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10m)

BA

RR

IER

PIL

LA

R

Proposed Monitoring Scheme CM1 Panel

1

Auto warning telltale installed during pillar split

2

35

6

7

8

9

10

11

1213

Page 15: sarpi coal mine project

4

Breaker lines installed for 3 rows before extraction commences6Extraction sequence

Breaker lines installed during pillar split

Remote Reading Telltale (3m + 10m) 2 x 2.4m SG bolts (breaker line) Pillar stress cells (5m + 10m)

Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10m)

BA

RR

IER

PIL

LA

R

Proposed Monitoring Scheme CM1 Panel

1

Auto warning telltale installed during pillar split

2

35

6

7

8

9

10

11

1213 14

Page 16: sarpi coal mine project

154

Breaker lines installed for 3 rows before extraction commences6Extraction sequence

Breaker lines installed during pillar split

Remote Reading Telltale (3m + 10m) 2 x 2.4m SG bolts (breaker line) Pillar stress cells (5m + 10m)

Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10m)

BA

RR

IER

PIL

LA

R

Proposed Monitoring Scheme CM1 Panel

1

Auto warning telltale installed during pillar split

2

35

6

7

8

9

10

11

1213 14

Page 17: sarpi coal mine project

16154

Breaker lines installed for 3 rows before extraction commences6Extraction sequence

Breaker lines installed during pillar split

Remote Reading Telltale (3m + 10m) 2 x 2.4m SG bolts (breaker line) Pillar stress cells (5m + 10m)

Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10m)

BA

RR

IER

PIL

LA

R

Proposed Monitoring Scheme CM1 Panel

1

Auto warning telltale installed during pillar split

2

35

6

7

8

9

10

11

1213 14

Page 18: sarpi coal mine project

16154

Breaker lines installed for 3 rows before extraction commences6Extraction sequence

Breaker lines installed during pillar split

Remote Reading Telltale (3m + 10m) 2 x 2.4m SG bolts (breaker line) Pillar stress cells (5m + 10m)

Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10m)

BA

RR

IER

PIL

LA

R

Proposed Monitoring Scheme CM1 Panel

1

Auto warning telltale installed during pillar split

2

35

6

7

8

9

10

11

1213 14

17

18

Page 19: sarpi coal mine project

16154

Breaker lines installed for 3 rows before extraction commences6Extraction sequence

Breaker lines installed during pillar split

Remote Reading Telltale (3m + 10m) 2 x 2.4m SG bolts (breaker line) Pillar stress cells (5m + 10m)

Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10m)

BA

RR

IER

PIL

LA

R

Proposed Monitoring Scheme CM1 Panel

1

Auto warning telltale installed during pillar split

2

35

6

7

8

9

10

11

1213 14

17

18

19

20

Page 20: sarpi coal mine project

16154

Breaker lines installed for 3 rows before extraction commences6Extraction sequence

Breaker lines installed during pillar split

Remote Reading Telltale (3m + 10m) 2 x 2.4m SG bolts (breaker line) Pillar stress cells (5m + 10m)

Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10m)

BA

RR

IER

PIL

LA

R

Proposed Monitoring Scheme CM1 Panel

1

Auto warning telltale installed during pillar split

2

35

6

7

8

9

10

11

1213 14

17

18

19

20

21

22

Page 21: sarpi coal mine project

16154

Breaker lines installed for 3 rows before extraction commences6Extraction sequence

Breaker lines installed during pillar split

Remote Reading Telltale (3m + 10m) 2 x 2.4m SG bolts (breaker line) Pillar stress cells (5m + 10m)

Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10m)

BA

RR

IER

PIL

LA

R

Proposed Monitoring Scheme CM1 Panel

1

Auto warning telltale installed during pillar split

2

35

6

7

8

9

10

11

1213 14

17

18

19

20

21

22

23

24

Page 22: sarpi coal mine project

16154

Breaker lines installed for 3 rows before extraction commences6Extraction sequence

Breaker lines installed during pillar split

Remote Reading Telltale (3m + 10m) 2 x 2.4m SG bolts (breaker line) Pillar stress cells (5m + 10m)

Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10m)

BA

RR

IER

PIL

LA

R

Proposed Monitoring Scheme CM1 Panel

1

Auto warning telltale installed during pillar split

2

35

6

7

8

9

10

11

1213 14

17

18

19

20

21

22

23

2425

27

26

28

Page 23: sarpi coal mine project

16154

Breaker lines installed for 3 rows before extraction commences6Extraction sequence

Breaker lines installed during pillar split

Remote Reading Telltale (3m + 10m) 2 x 2.4m SG bolts (breaker line) Pillar stress cells (5m + 10m)

Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10m)

BA

RR

IER

PIL

LA

R

Proposed Monitoring Scheme CM1 Panel

1

Auto warning telltale installed during pillar split

2

35

6

7

8

9

10

11

1213 14

17

18

19

20

21

22

23

2425

27

26

28

29

30

31

32

Page 24: sarpi coal mine project

16154

Breaker lines installed for 3 rows before extraction commences6Extraction sequence

Breaker lines installed during pillar split

Remote Reading Telltale (3m + 10m) 2 x 2.4m SG bolts (breaker line) Pillar stress cells (5m + 10m)

Auto warning telltale (single height 10m – trigger 5mm)Remote Rib Exto. (3m + 10m)

BA

RR

IER

PIL

LA

R

Proposed Monitoring Scheme CM1 Panel

1

Auto warning telltale installed during pillar split

2

35

6

7

8

9

10

11

1213 14

17

18

19

20

21

22

23

2425

27

26

28

30

29

32

31

33

34

35

36

Page 25: sarpi coal mine project

PRICE LIST OF DIFFERENT MACHINERIES IN THE CM PANEL

Sl. No.

Equipment Quantity

Country of Origin

Unit Price US $

Total Price US $

1 Continuous Miner 12CM15-10D

1 no. USA 2,791,265.00 2,791,265.00

2 Shuttle Car10SC32B

2 no. RSA 934,617.00 1,869,234.00

3 Feeder BreakerBF14B-3-7C

1 no. USA 743,312.00 743,312.00

4 Quad Bolter 1 no. Australia 1,183,225.00 1,183,225.00

5 Electrical Equipment

1 no. UK 971,115.00 971,115.00

TOTAL PACKAGE VALUE – US DOLLARS 7,558,151.00(US Dollars Seven million Five hundred Fifty Eight thousand one hundred Fifty One only)

Page 26: sarpi coal mine project

SHUTTLE CAR 10SC32

Page 27: sarpi coal mine project

ROLE OF SHUTTLE CAR IN THE OVERALL PROCESS.

The function of shuttle car is to transport the coal that is sheared by continuous miner from the face to the place where feeder breaker is installed.

Capacity of a 10SC32 shuttle is 10.19 tons and the fill

factor is about 0.85.

Page 28: sarpi coal mine project

Joy Shuttle Car Model 10SC32B Specifications

General•Type : JOY 10SC32•Operating voltage: 1050 V•Voltage Rating: ±10%•Total Rated Power: 202.6kW

2 × 85 kW Traction Motors1 × 18.6 kW Conveyor Motor1 × 14 kW Pump Motor

•Weight 20,500kg (approximately) empty•Cubic Capacity : 10.19cu meters•Dimensions (l × w × h): 8.99m × 3.05m × 1.31m •Ground clearance: 290mm (Nominal)•Ground Bearing Pressure: 520 kPa empty; 830 kPa loaded•Gradient (in line of advance): Below 6 degrees. If greater than 6 degrees, a new gear with reduction of 66.56: 1 could be used.•Cross gradient: not greater than 5 degrees •Total Service Life: 1.5 million tones

Page 29: sarpi coal mine project

VARIOUS PARTS IN A SHUTTLE CARSHEAVE WHEELS

CABLE REEL COMPARTMENTCHAIN CONVEYOR

TRACTION MOTOROPERATOR’S CABINCONVEYOR DRIVE MOTOR

TYRESHYDRULIC PUMP MOTOR COMPARTMENT

Conveyor boom

headlights

Page 30: sarpi coal mine project

MAIN MECHANISMS IN A SHUTTLE CAR

CABLE REEL MECHANISM.

BOOM LIFTING MECHANISM.

STEERING MECHANISM.

DUMPING MECHANISM.

OPERATION OF SERVICE JACKS.

Page 31: sarpi coal mine project

NEED FOR CABLE REELING

Page 32: sarpi coal mine project

Pump motor compartment

Cable reel compartment

Traction motorControllerConveyor motor

Conveyor reducer

Operatorcompartment

Design

Page 33: sarpi coal mine project

CABLE REEL SYSTEM

HYDRAULIC MOTOR

SHEAVE WHEELS

SPOOLING MECHANISM

Page 34: sarpi coal mine project

SHEEVE WHEEL

Page 35: sarpi coal mine project

BOOM LIFTING MECHANISM

Boom lifting mechanism is present so to adjust with variable discharge heights.

Telescopic type of cylinder is used. Atmospheric vent is provided in the cylinder to prevent the

cylinder from damage during roof fall condition. extend pressure: 120.6-127.5 bar. atmosphere relief pressure: 227.7 bar. Dual output pump is used 46 lpm and 34lpm.

The high volume stage of pump delivers (46LPM) fluid to cable reel valve(Since here, shuttle car is in stationary mode, cable reel motor will be in stalled position) & conveyor elevating cylinder.

The Low volume Stage delivers (34LPM) fluid to hydraulic cylinders in steering mechanism and Brake circuits (emergency/ park & service).

Page 36: sarpi coal mine project

POSITION OF BOOM ELEVATING AND LOWERING CYLINDER

Page 37: sarpi coal mine project

BOOM ELEVATE CIRCUIT

Page 38: sarpi coal mine project

BOOM LOWERING CIRCUIT

Page 39: sarpi coal mine project

STEERING MECHANISM

FOUR WHEEL STEERING MECHANISM IS USED IN JOY SHUTTLE CARS TO NEGOTIATE TIGHTER TURNS.

Page 40: sarpi coal mine project

Steering Arrangement

Page 41: sarpi coal mine project

HYDRAULIC CIRCUIT FOR LEFT TURN

Page 42: sarpi coal mine project

HYDRAULIC CIRCUIT FOR RIGHT TURN

Page 43: sarpi coal mine project

LOADING AND DISCHARGE END OF SHUTTLE CAR

LOADING END

DISCHARGE END

CONVEYOR

DISCHARGE BOOM.

Page 44: sarpi coal mine project

DUMPING MECHANISM

Page 45: sarpi coal mine project

DUMPING MECHANISM

Page 46: sarpi coal mine project

SERVICE JACKS

Four floor jack cylinders are provided at four corners of the shuttle car so that the machine can be lifted from the ground for maintenance.

Page 47: sarpi coal mine project

SAFETY FEATURES OF SHUTTLE CAR AT A GLANCE

Drum limit switch Emergency stops Oil temperature Oil level Brake pressure switch E/Leakage Relays off load and on load Overloads Pre-start Alarm Emergency and Service Brakes

NOTE:- All the machine have DANGER,WARNING,CAUTION, SIGNS mounted on them.

Page 48: sarpi coal mine project

FireExtinguisher

Safety Features of SC

Boom SafetyPins

Low CableCut-Out

Poly RearBumpers

EmergencyStops

BrakePressureSwitch

Oil TemperatureLevel Sensor

Load LocksConveyor & Floor Jack

Cylinders

AudibleAlarm

EmergencyStop

EmergencyStop

BrakeHead Light

Head Light

Head Light