regulatory incentives for reduction of network losses

20
Document number Grid regulation incentives for network loss reduction Webinar prepared for the European Copper Institute Sebastiaan Hers, Christian Redl, Martijn Duvoort 09/12/13

Upload: european-copper-institute

Post on 20-Aug-2015

1.014 views

Category:

Technology


0 download

TRANSCRIPT

Docum

ent

num

ber

Grid regulation incentives for network loss reduction Webinar prepared for the European Copper Institute

Sebastiaan Hers, Christian Redl, Martijn Duvoort

09/12/13

Agenda

Energy efficiency and network loss reduction in Europe

Approaches for grid regulation

Incentivising energy efficiency in networks

- Financial incentives

- Non-financial incentives

Conclusions

2

3

Energy efficiency and network loss reduction in Europe

Energy efficiency and network losses in Europe

EU energy policy targets

- By 2020, reduce GHG emissions by 20% (compared to 1990), meet 20% of energy needs by

renewable energy (RE) and increase energy efficiency by 20%

Electricity sector crucial

- Electrification of end-use applications

- Cost-effective options for RE deployment

Electricity grids and energy efficiency

- Technical electricity network losses single biggest source of power “demand”

- 7% of electricity is lost in transmission and distribution networks (Targosz et al., 2012)

o Technical losses in European transmission grids vary between 1 and 2.6%

o Losses in the distribution grids can be as high as 11.7%

Losses critical for the sector´s energy efficiency performance

Losses represent cost for society

- Generation costs of additional power generation needed for compensation borne by society

- Environmental costs of additional power generation

4

Network loss reduction and grid regulation

How to facilitate investments in energy-efficient grid technologies?

- Broader energy efficiency policies

- Grid regulation

Energy efficiency policies

- EU directive on energy efficiency (Directive 2012/27/EU)

- Article 15 requests national energy regulators to take into account energy efficiency

- By June 2015 concrete measures have to be identified

Grid regulation

- Incentives for grid operators to invest in energy-efficient equipment depend on implemented

grid regulation methodology

5

6

Approaches for grid regulation

Grid regulation

Electricity supply chain

Why regulate TSOs and DSOs?

- Transmission and distribution grid operators (TSOs and DSOs) business’ constitutes natural

monopoly Competition does not work

- Regulation shall ensure that TSOs/DSOs charge reasonable prices and operate efficiently at

adequate quality standards (Petrov, 2009)

o Protect consumer interests and eliminate monopoly inefficiency

o Ensure financial viability of industry participants (efficient cost coverage)

o Ensure equal conditions and non-discrimination of all sector participants

7

Generation Transmission &

Distribution

Retail Supply/

End Use

Competition Regulated Competition

Price regulation approaches

8

– Prices or revenues based on costs plus “fair” rate of return

– Frequent regulatory reviews

– No/low incentives for cost reductions / efficiency improvements

– Overcapitalisation and gold plating (Averch/Johnson Effect)

– Establishes upper limit on prices or revenue

– Applies longer regulatory lag (some 3-5 years)

– Requires explicit efficiency increase via price formula (X factor)

– Allows retention of efficiency gains; should address quality of

supply

– Strong incentives for efficiency improvements

– Decouples individual costs from allowed prices / revenue

– Allowed prices / revenues linked to regulated industry performance

– Strong incentives for efficiency improvements

– Effect similar to the dynamics of competitive forces

Rate-of-Return regulation

Cap regulation

Yardstick regulation

Source: Petrov (2009)

Rate-of-Return vs. Cap Regulation

9

Source: Petrov (2009)

10

Incentivising energy efficiency in networks

Investment in energy efficient equipment

Project perspective

- Balance between increased capital expenditures and resulting reduction in operational costs

- Projects with minimum lifecycle costs (LCC) optimal

Project perspective and regulated environment

- Trade-offs between CAPEX/OPEX need to be considered

- To incentivise TSO/DSO making efficient decision, regulatory framework should embed LCC

Options to accommodate LCC in Rate-of-Return regulation

- Non-financial incentives

Options to accommodate LCC in cap regulation

- Financial incentives

- Non-financial incentives

11

Cap regulation and reduction of network losses

Price control formula

- Revt= CAPEXt + OPEXt-1*(1+RPI-X) + Inc*(PerfTarget,t - PerfActual,t)

Options for reduction of network losses

- Treatment of CAPEX (investments) directly affects recovery of investment costs

- If OPEX savings (from investments in energy efficient equipment) can be retained then

investments may be induced

- If suppliers/retailers are responsible for loss procurement, explicit incentive term can

embrace energy-efficient operation of the grid by TSOs/DSOs nonetheless

Costs for purchasing losses (OPEX)

- Can be treated as non-controllable which makes them a cost-pass through item

- Or treated as controllable which makes them subject to the X-factor

Investment costs of energy-efficient equipment (CAPEX)

- Can be part of the allowed cost which allows earning a return on capital

- If not part of allowed costs than only retaining OPEX benefits can induce any investment

12

Loss Reduction under Cap Regulation

13

– Separate assessment of CAPEX and OPEX

– Controllable OPEX costs are incentivised through X factor

– Non-controllable costs are passed through to consumers

– Incentive to reduce losses if part of controllable costs and if

investments in EE equipment is allowed

– Gradual adjustment of costs to account for short regulation periods

– Only total costs are assessed

– Controllable costs are incentivised through X factor

– Non-controllable costs are passed through to consumers

– Incentive to reduce losses if part of controllable costs

– Regulatory arrangements should include loss cost allowance

– If not, adverse incentives arise yielding CAPEX reduction

– If suppliers are responsible for loss procurement (costs for losses

do not emerge in TSO/DSO accounting),TSO/DSO can still be

incentivised

– Bonus/malus depending on actual losses vs. target losses

Building Blocks

TOTEX

Loss reduction

Incentive Scheme

Investment in energy efficient equipment; Example

14

[EU

R]

Net Present Value of investment in energy efficient equipment

Discounted OPEX savings of energy efficient equipment

Additional investment costs of energy efficient equipment

Time

Project with minimum

LCC

Amortization period >

Regulation period

Retention of cost

savings should be

allowed for a

sufficient period of

time in order to

reflect the LCC

Regulation period Future cost advantages need to be retained by TSO/DSO to

facilitate investment

Non-financial incentives for loss reduction

Technical standards

- Setting mandatory minimum energy efficiency standards for equipment design and sizing

Obligation or certificate schemes

- Setting specific targets for savings to be met by grid operators, assuming trading is allowed

Voluntary agreements

- Agreement on non-binding guidelines for maximum share of grid losses in power

transmission and distribution

Labelling schemes

- Labelling equipment on the market in terms of efficiency

Information campaigns

- Information campaign targeting information gaps with regulators and/or grid operators

R&D support

- Support scheme for R&D targeting development of technical measures for grid efficiency

15

Scorecard incentives for loss reduction

16

Regulatory

Embedding

Implementation

Costs

Stakeholder

Acceptance

Economic

Effects

Effectiveness

Technical

Standards + +/- +/-

+/-

++

Financial

Incentives + +/- + +/- +

Obligations or

Certificate

Schemes

+/- - +/- + +/-

Voluntary

Agreements + + + + -

Labelling

Schemes + +/- + + -

Information

Campaigns + + o

+/-

--

R&D Support + + + o --

Source: Papaefthymiou at al. (2013)

Main drawbacks and benefits incentives for loss reduction

17

Incentive Main benefit Main drawback

Technical Standards - High effectiveness - Affects investments, not

operation

Financial Incentives - Moderate effectiveness - Potential economic inefficiency

through information asymmetry

Obligations or Certificate Schemes

- Moderate performance with

regard to economic efficiency

- Limited effectiveness

Voluntary Agreements - Moderate performance in most

respects

- Limited effectiveness

Labelling Schemes - Moderate performance in most

respects

- Limited effectiveness

Information Campaigns - Limited implementation costs

- Poor effectiveness

R&D Support - Moderate performance in most

respects

- Poor effectiveness

18

Conclusions

Conclusions

Strong energy efficiency measures in the electricity sector required

- Network losses are single biggest source of power “demand”

- Network losses represent cost to society and environment

- These costs not necessarily relevant for TSOs/DSOs which results in low priority

Financial incentives facilitating energy-efficient grid investments

- Explicitly induce LCC driven decision making

o Allow required CAPEX for investments in efficient equipment

o Allow retention of OPEX cost savings related to network loss reduction (apply long-run average for

OPEX in tariff setting)

- If suppliers instead of TSOs/DSOs procure grid losses

o Incentive schemes for TSOs/DSOs based on grid loss reduction relative to a target

Non-financial incentives

- Can also stimulate investments in energy efficient equipment

o E.g. Technical standards

19

www.dnvkema.com

www.dnv.com

© KEMA Nederland B.V., Arnhem, the Netherlands. All rights reserved.

It is prohibited to change any and all versions of this document in any manner whatsoever, including but not limited to dividing it into parts. In case of a

conflict between the electronic version (e.g. PDF file) and the original paper version provided by KEMA, the latter will prevail.

KEMA Nederland B.V. and/or its associated companies disclaim liability for any direct, indirect, consequential or incidental damages that may result from

the use of the information or data, or from the inability to use the information or data contained in this document.

The contents of this report may only be transmitted to third parties in its entirety and provided with the copyright notice, prohibition to change, electronic

versions’ validity notice and disclaimer.