quarterly environment & social monitoring report (october
TRANSCRIPT
Quarterly Environment & Social Monitoring Report (October 2010 to December 2010)
The Environmental and Social Performance Report is a document of the borrower. The views expressed herein do not necessarily represent those of ADB’s Board of Directors, Management, or staff, and may be preliminary in nature. Your attention is directed to the “Terms of Use” section of this website.
Environmental and Social Performance Report February 2011
IND: Mundra Ultra Mega Power Project
Prepared by SENES Consultants India Pvt Ltd.
Quarterly Environment & Social Performance Report – Tata Ultra Mega Coal Fired Power Plant, Mundra
Period: October to December 2010
Submitted to: Coastal Gujarat Power Ltd (CGPL)
Prepared by: SENES Consultants India Pvt Ltd.
Table of Contents
1 Introduction ........................................................................................................................ 1
1.1 Background ............................................................................................................................. 1
1.2 Objective ................................................................................................................................. 1
1.3 Project Status .......................................................................................................................... 2
2 Environmental & Social Management ............................................................................... 2
2.1 ESPR Preparer ........................................................................................................................ 2
2.2 Environmental Management Plan (EMP) & Social Management Plan (SMP)
Implementation ................................................................................................................................... 3
3 Compliance with CGPL Environmental & Social Requirements ...................................... 3
3.1 Environmental Aspects ........................................................................................................... 3
3.2 Social Management ................................................................................................................. 4
4 Health & Safety .................................................................................................................. 5
4.1 Health & Safety Management ................................................................................................. 5
4.2 Safety Performance ................................................................................................................. 6
List of Annexure
Annexure 1: Persons Interviewed ........................................................................................................ 9
Quarterly Environmental & Social Performance Report – CGPL Power Plant, Mundra
November 2010 1 SENES
QUARTERLY ENVIRONMENTAL AND SOCIAL PERFORMANCE
REPORT
(ESPR)
Reporting Period: October to December 2010
Site visit date: 7th – 9th February 2011
1 Introduction
1.1 Background
Coastal Gujarat Power Limited (CGPL), a wholly owned subsidiary of the Tata Power
Company Limited will build, own and operate an ultra mega power plant at Mundra in
Gujarat. The project includes five supercritical units of 800 MW each, with total capacity of
4000 MW. The plant will use 12 Million Metric Ton Per Annum (MMTPA) of imported coal
as fuel, and sea water for once through cooling of condensers. Power will be evacuated
through six 400 KV power lines to benefits the states of Gujarat, Maharashtra, Punjab,
Haryana and Rajasthan.
The project has started in September, 2007 with the targeted commercial operation of the first
unit is February, 2011 and that of the fifth unit in June, 2012. CGPL has sought financial
loans from several international banks including the International Finance Corporation (IFC)
and Asian Development Bank (ADB). As per the common term schedule to loan agreement
between CGPL and the Lenders; Tata Power has entrusted SENES Consultants to carry out
Environment Health Safety and Social (EHSS) compliance audits on a quarterly and annual
basis during the construction period.
1.2 Objective
The purpose of this Quarterly Environmental & Social Performance Report (ESPR) is to
report on CGPL’s compliance with the Environmental and Social Performance Requirements
of IFC/ADB (including implementation of the Environmental Management Plan and the
Social Management Plan) and to asses any corrective actions implemented/proposed. The
ESPR encompasses implementation by CGPL of all phases of the Project. It includes:
Contact information for responsible individuals
Compliance by CGPL with environmental and social requirements for the Project
Environmental and social aspects of the Project under implementation
Occupational health and safety performance and significant incidents
Sustainable development initiatives and community relations
Quarterly Environmental & Social Performance Report – CGPL Power Plant, Mundra
February 2011 2 SENES
1.3 Project Status
The actual progress for the month has been 1.94% against an early schedule of 2.06% & late
schedule of 3.05%. Overall actual progress stands 70.76% against an early schedule of
89.41% and late schedule of 71.99%. Major engineering is completed and all packages
awarded with materials’ delivery continuing. Boiler#10 Duct air leak test & chemical
cleaning completed on 08/01/11 & 10/12/10 respectively. Pulverizer lube oil flushing
commenced on 03/01/11 and burner commissioning activities, ESP Pass–A insulation work
in progress. TG lube/seal oil flushing completed on 24/12/10. EHC (Electric Hydraulic
Control Unit) hydrotest completed on 24/12/10 and line flushing started on 27/12/10. TG#20
Turbine (HP, IP, LP-A&B) box-up completed on 07/01/11 and Lube oil piping is in progress.
Unit#10 condenser shell side fill test completed and released for chemical cleaning; tube side
hydrotest is in progress. Air leak test of ESP#20 Pass-B completed on 28/12/10. Boiler
pressure parts’ erection in Unit# 30, 40 and 50 and structural erection in ESP Unit#30, 40 &
50 are in progress. The erection of TWS for Unit#10-50 and coarse screens for Unit#10 & 20
in progress. CW conduits’ hydrotest and concrete encasing completed for Unit#10,
preparation for Unit # 20 hydrotest is in progress. For Unit#10 the installation work of all 03
nos. generator transformers, station transformer (ST)-1 and unit transformer (UT)–1&2 are in
progress. Unit auxiliary transformer (UAT)-1 &2 testing work completed. Fire water system
commissioned and fire protection system for SAT-2, stock pile area and at 220kV switchyard
for 45MVA transformer completed. Fire fighting works in Unit#10 TG building, transformer
yard and ICHS in progress. Piping works in CW Forebay and Pump House area in progress
with hypochlorite storage tanks erection completed on 10/01/11.
Unit#10 Main plant building & MCB finishing works are in progress. UCB#20 Electrical &
HVAC equipment erection work in progress and in Unit#30 auxiliary equipment foundations,
grade slab, roof sheeting & side cladding works are in progress.TG#40 deck cast on 30/12/10.
1st flue connected to flue duct of Chimney 1 and1st segment of 2nd flue can erection
completed. Civil & structural erection works for ICHS except in Tunda-Vandh road area
completed. Reclaimer-B & stacker cum re-claimer-B erection work completed with belt
laying & conveyor sheeting work is in progress. BAH (Bottom Ash Hopper) refractory lining
completed on 29/12/10.
2 Environmental & Social Management
2.1 ESPR Preparer
Report prepared by: SENES Consultants India Pvt. Ltd.
Telephone: 022-27576298 / 32986995
E-mail: [email protected]
Signature:
Report Date: February 2011
Quarterly Environmental & Social Performance Report – CGPL Power Plant, Mundra
February 2011 3 SENES
2.2 Environmental Management Plan (EMP) & Social Management Plan (SMP)
Implementation
The following groups of the Tata Power Corporate Office and CGPL’s on-site team are responsible
for EMP and SMP implementation:
Tata Power Corporate Office : Sustainability & SHE Group; HR - Land Acquisition, R&R,
CSR
On-site team at Mundra: Safety & Environment; HR – Labour & Health; CSR
The list of individuals contacted during the site visit is given in Annexure 1.
3 Compliance with CGPL Environmental & Social Requirements
This section describes current compliance of the project with IFC/ADB’s environmental &
social policies and guidelines, Environmental & Social Management Plans and presents the
key environmental & social performance indicators. The current project activities have been
assessed with respect to observations and comments offered in the last audit.
3.1 Environmental Aspects
Although considerable improvement has
been observed in the management of
waste generated from work site, focused
efforts and enhanced accountability are
required to implement the same for waste
being generated from the labor camps.
Presently un-segregated waste is being
dumped into waste pits, followed by the
improper segregation (Photo 1) and
burning of recyclables (particularly
plastic). Further necessary efforts need to
be made to improve the availability
colored and properly labeled waste bins at
the new labor camp. Also with respect to the recycling of food waste CGPL need to explore
the feasibility of commissioning and operation of a Biogas Plant based on the prefeasibility
report prepared.
Efforts are being made to improve the performance of STP through proper chemical dosing,
sludge drying and recycling, improved housekeeping etc however the problem related to the
presence of adequate biological culture/growth in the aeration tanks – which is fundamental
to effective STP operation continues to persists. It is therefore recommended that CGPL
continues with its efforts towards engaging the deputed O&M personnel to ensure effective
STP performance.
Photo 1:Open burning of plastic wastes in pits
Quarterly Environmental & Social Performance Report – CGPL Power Plant, Mundra
February 2011 4 SENES
License requirement for onsite storage of hazardous chemicals viz. hydrochloric acid, sodium
hydroxide and ammonia needs to be reviewed with respect to the threshold quantities
specified for such chemicals as per the Manufacture, Storage & Import of Hazardous
Chemical Rules, 1989.
Nearly about 5000 nos. saplings have been planted in the second phase of green belt
development with plantation of another 5000 nos. saplings being under progress. However it
is reported that problems are being faced with respect to the proper distribution of treated
STP water over the large area of green belt being developed. A motor/pump need to be
installed and operated to boost the proper distribution of treated waste water throughout the
green belt area. Further there is a need for increased coordination to meet the increased water
demand for green belt during summer months.
Continued consumption of ground water to meet domestic water demand at labor colonies
over the next two years coupled with uncertainties experienced with respect to Narmada
water supply may possibly lead to significant impact on local ground water resources in near
future. The implementation of planned initiatives for replenishment of ground water
resources in the region through rain water harvesting/recharge structure need to be initiated
from construction phase. Further CGPL also need to assess the possibility of potable water
supply from desalination plant after catering to the project operational demand.
CGPL has carried out a coastal biodiversity assessment study through Bombay Natural
History Society (BNHS) in 2008-10 to document and analyze the coastal and marine
biodiversity along the Mandvi-Mundra coast, assess the impact on the coastal biodiversity
due to project activities and identify appropriate areas and parameters for restoration of
affected ecosystem. However based on the aforesaid study findings CGPL need to formulate
and implement a Coastal Biodiversity Management Plan to mitigate the identified impacts.
3.2 Social Management
The draft version of corporate sustainability framework under preparation during the last
audit has been formulated and is presently undergoing internal review. However the broad
aspects of the framework have been discussed with SENES and it is understood that CGPL
has planned for specific community development programs under this framework for which
procedures will be established to guide in the formulation, monitoring and evaluating the
effectiveness of the programs being identified. However the sustainability framework will be
shared with SENES following the internal review for necessary
suggestions/recommendations to be incorporated in this audit report at a later stage.
In line with IFC requirements cultural heritage and community resource conservation,
PAPs livelihood restoration, community interaction and overall community
development of neighbouring villages are reportedly covered under this framework.
CGPL need to assess the possibility of partnering with neighbouring corporate groups
in contributing towards local community development through government
development schemes/programs.
Quarterly Environmental & Social Performance Report – CGPL Power Plant, Mundra
February 2011 5 SENES
It is anticipated that programs planned to facilitate focused interaction with the PAPs
is likely to surface out some inherent conflicts likely to have been built up between
the land purchase stage and the current advanced stage of costruction. It is therefore
recommended that importance of PAP focused initiatives (livelihood restoration,
tracking changes in their socioeconomic status, local employment & business
opportunities) is in any way not undermined and sustained.
4 Health & Safety
CGPL has adopted the health and safety system (with guidance form Dupont) that includes
well defined performance standards, procedures and guidelines (HIRA, SCAR, etc), safety
awareness programs (Safety Time Out) and key performance indicators (e.g. lost time
incidents, severity rate, near miss etc.), which are used to track compliance with Health and
Safety (H&S) targets. Specific health and safety plans and onsite emergency plan have been
developed & augmented on regular basis by CGPL and communicated to contractors. The
plans outline the policies and strategies, the organization, resources and documentation
required, the HS risk management principles, and reporting requirements.
4.1 Health & Safety Management
With the augmentation in safety staffing by CGPL, proper implementation of specific plan
and procedures, communication between the contractor workers, safety training and
awareness, incident reporting, visual aids etc the onsite Health & Safety Management of
CGPL continues to demonstrate considerable improvement. However with the project
gradually undergoing transition from construction phase to operations major safety accidents
(flashovers from poor electrical modules and fall during mechanical erection works) have
been recorded as part of this transitional phase. Both preventive and corrective actions are
being taken by CGPL following such safety incidents viz. safety review of electrical
modules, driving the provision of insulated safety coveralls, hiring the services of ICRA for
carrying out electrical safety audit & training program etc. In this regard it is recommended
that CGPL make necessary efforts in identifying the risks associated with the transition and
operations stage and enhance the awareness of contractors/sub-contractor manpower on the
same to mediate an effective response.
Potential increase in safety risks are anticipated for CGPL employees resulting from the
heavy vehicular movement along the Mundra-Gandhidham/Bhuj road and increase in travel
frequency of CGPL employees with project progressing towards operations. Although CGPL
is striving towards addressing the aforesaid risks through construction of township/colony at
Mundra, maintenance of vehicular safety norms, training on safe driving etc it needs to
further assess the mitigation plans/measures being formulated to establish its reassurance and
share the same with SENES for validation.
CGPL continues to demonstrate considerable improvement in onsite health and safety aspects
through proper implementation of specific plan and procedures, communication with
contractors, safety training and awareness and inducing behavioural change among workers
Quarterly Environmental & Social Performance Report – CGPL Power Plant, Mundra
February 2011 6 SENES
through involvement of AAKAR – an NGO. However taking into account the presence of a
child worker as observed at Unit# 30 during the audit CGPL need to coordinate with the
major contractors for enhancing sub-contractor surveillance and supervision to prevent the
employment/recruitment of any form of child labour
With the housekeeping contract being finalized with a third party vendor considerable visible
improvement has been demonstrated by CGPL with respect to workplace housekeeping.
Presently the segregated recyclables (primarily wood and metals) stored onsite is being
removed by local waste recyclers on a daily basis. Further CGPL is also in the process of
constructing a waste management yard with proper fencing and designated compartments for
temporary storage of segregated recyclables to prevent littering and unauthorized access. A
plan to this regard has also been prepared and is in the process of finalization. It is
recommended that CGPL continues with its positive efforts towards effectively managing the
waste generated from work place activities. Provision of drinking water tanks has been
regularized throughout the site and portable toilets been made functional to cater to the
sanitation needs of the onsite workers.
4.2 Safety Performance
The health and safety performance of the project monitored with respect to safety
performance indicators for the period Oct-Dec 2010 is presented in the Table-1 below.
Table 1: Safety Performance Indicator Status (Oct to Dec 2010)
Sl.No Performance Indicators Reporting Period
Oct-10 Nov-10 Dec-10
1 Induction Training Attendees 3578 3573 2981
2 LTIs 1 4 4
3 First Aid Cases 209 142 166
4 Medical Treatment Cases (MTC) 6 2 3
5 Safe Man Hours Worked till last fatality 65848 731200 143712
6 Total Person Hours Worked 3652588 3628616 4086716
7 LTI Frequency Rate 0.27 1.10 0.98
8 Severity Index 3.10 3.14 3.24
9 Fire Cases 10 8 21
10 Near Misses 92 80 107
11 Fatality 0 1 0
A total of one fatality reported during the quarter has been adequately investigated and
findings documented and communicated.
Quarterly Environmental & Social Performance Report – CGPL Power Plant, Mundra
November 2010 7 SENES
Table 2: Safety Action Plan
Sl.
No. Items Targets
Oct Nov Dec
Tar Act Tar Act Tar Act
1 Safety Sub-Committee meeting (Dates)
a) CSC 12 1
1
1
b) Incident Investigation 12 1
1
1
c) Contractor Safety management Mr.PKS 12 1
1
1
2 STOP Observation
a) Nos. of observers 44 (55) 55
55
55
b) Nos. of observations 176 (220) 202 161 75 150 169 149
3 C F S A (as applicable) 4 4 4 4 4 4 4
4 HIRA / JSA (as applicable to SBU) Yet to Finalized
a) New
56
45
51
b) Review in 5 working days
49
36
49
5 Site Specific safety Procedures As and when
a) New additions
b) Review / Updation of existing procedures
6 External / Statutory audits -Safety Audit (as applicable to SBU) 1
7 Emergency Preparedness drill 12 1 1 1 1 1 1
a) Scenario / periodicity
1
8 Training plan- CGPL training plan.
a) Train the trainers in standards Monthly 1
1
1
b) Training sessions on safety standards by trainers Monthly 1
1
1
9 Audits plan by site safety officers- 1
( System Audit) -For major contractors
(Cross function team to be made- )
10 Safety inspections schedule - ( By safety stewards) 4 Inspection/ month
a) Lifting equipment & accessories - Mr. Parth - 6 monthly
1 1
b) Housekeeping- Mr.PKS - Monthly
1 1 1 1 1 1
Quarterly Environmental & Social Performance Report – CGPL Power Plant, Mundra
November 2010 8 SENES
Sl.
No. Items Targets
Oct Nov Dec
Tar Act Tar Act Tar Act
c) PPE usage -(PPE Inspection - Safety harness,helmet )
1 1 1 1 1 1
d) Handtools- Power tools-
e) Access & work platform- NA
f) Pressure vessels & gas cylinders - NA
g) Portable electrical equipment- (Welding and cutting)
1 1
h) Firefighting equipment ( Fixed Systems/ Fire extinguishers)
1 1 1 1 1 1
i) Fire alarm system NA
j) Fire exits, escape routes marking. Office area.
1 1
k) Buildings, plant structures NA
l) Plant lighting
1 1 1 1 1 1
(m) Safety signage’s -
(n) Conveyors NA
(o) Moving machinery NA
(p) Vehicle Inspection -
13 "On-The-Job" Safety events
a) Environment day celebration- VCS - June'10 1
b) Electrical Safety week Mr.PKS -Oct'10 1 1 1
c) Housekeeping week Mr.PKS-Sept'10 1
d) Road safety week- Mr.PR- Jan- 2011 1
e) Safety week celebration HSE department -Mar 2011 1
f) Fire awareness week- Mr.PR - 1
14 "Off-The-Job" Safety events 3
a) Home safety- Sept'10, MBB/Mr.PKS 1
b) Defensive driving-(Traffic safety awarness)- Mr.VCS 1
c) Environment & Hygiene -Feb'11 - VCS/KAS 1
d) Electrical Safety - Mr.PKS
Quarterly Environmental & Social Performance Report – CGPL Power Plant, Mundra
November 2010 9 SENES
Annexure 1: Persons Interviewed
Sl. No. Name Position
CGPL
1 Mr. Vinay Mittal Site In charge
2 Mr. Sharad Baijal Head – Operations
3 Mr. Subhashish Dutta Group Head, Finance
4 Mr. Ramesh K Dhawan Chief – SHE
6 Mr. Himanshu Shrivastav Member, HR
7 Mr. Pradeep Ghosal Associate Group Head – CSR
8 Mr. Ravi Puranik Head - CSR