quantity calculator
TRANSCRIPT
-
8/11/2019 Quantity Calculator
1/96
Det. Length
Embankment
width
Length
(Unknown)Area Price cost cost
A= 6 1 6 19.08 114.48 40,983.84
Aggregate Subbase
Shoulder
LengthThickness
Length
(Unknown)VOLUME Price cost
V= 1 0.3 1 0.3 759 455.40
Aggregate base Course
Pavement
widthABC
Length
(Unknown)VOLUME Price cost
V= 4 0.1 1 0.4 839.5 335.80
PCCP
Thickness = 0.2
Pavement
width
Length
(Unknown)Area Price cost
A= 4 1 4 1,169.60 4,678.40
0.15 898.18
0.20 1169.6
TOTAL 5,584.08
LENGTH =DELIVERY
CHARGE
0.00
LENGTH =
say 358
I.
Embankment
widthLength
A= 6 358
ILLUSTRATION
Subgrade Preparation
Aggregate Subbase
Aggregate base Course
PCCP
Subgrade Prep.
Appropriation
2,000,000.00358.16
Subgrade Prep.
7m
5m 1m1m
ABC
PCCPSUB
BASE
SUB
BASE
-
8/11/2019 Quantity Calculator
2/96
A= 2148 @ 19.08
300sq.m/hr
EQUIPMENTS QTY HOURS TOTAL
Road Grader 2000 /hour 1 6 12000
Road Roller 1500 /hour 1 9 13500
Water truck 1000 /hour 1 3.5 3500 29,000.00
LABOR# of
workers
# of
DaysTOTAL
Foreman 500 /day 1 1 500
Laborers 300 /day 2 1 600 1,100.00
sub total 30,100.00
12% 3,612.00
Unit cost 19.15 10% 3,010.00
SAY 19.15 12% 4,406.64
TOTAL 41,128.64
40,983.84 41,134.20
II.
shoulder thickness Length
V= 1 0.3 358
V= 107.4 @ 759
214.80
COURSE W/ 15% 247.02 357.82
SHRINKAGE SAY 247 @ 350 86,450.00
MATERIALS
EQUIPMENTS 50 cu.m/hr QTY HOURS TOTAL
Road Grader 2000 /hour 1 7 14000
Road Roller 1500 /hour 1 9 13500
Water truck 1000 /hour 1 4.5 4500 32,000.00
LABOR# of
workers
# of
DaysTOTAL
Foreman 500 /day 1 1 500
Laborers 300 /day 2 1 600 1,100.00
sub total 119,550.00
12% 14,346.00
Unit cost 760.49 10% 11,955.00
SAY 760.49 12% 17,502.12
TOTAL 163,353.12
Aggregate Subbase
-
8/11/2019 Quantity Calculator
3/96
163,033.20 SAY 163,033.20
III.
pavement width ABC Length
V= 4 0.1 358
V= 143.2 @ 839.5
ABC W/ 15% 164.68 388.60
SHRINKAGE SAY 165 @ 400 66,000.00
MATERIALS
EQUIPMENTS QTY HOURS TOTAL
Road Grader 2000 /hour 1 4 8,000.00
Road Roller 1500 /hour 1 7 ########
Water truck 1000 /hour 1 1.5 1,500.00 20,000.00
LABOR# of
workers
# of
DaysTOTAL
Foreman 500 /day 1 1 500.00
Laborers 300 /day 2 1 600.00 1,100.00
sub total 87,100.00
12% 10,452.00
Unit cost 831.099 12% 8,710.00
SAY 831.1 12% 12,751.44
TOTAL 119,013.44
120,216.40 119,013.52
IV.
PCCP 108 sq.m/hr
pavement width Length
A= 4 358
A= 1432 @ 1,169.60
V= 286.4
MATERIALS QTY PRICE TOTALCement 10.5 3007.0 230 691610
Sand 0.5 143.5 600 86100
Gravel 1 287.0 700 200900
RSB 16mm 0.1 29.0 350 10150 7.8
Lumber 40 - 2 x 6 x 12 1.95 570.0 40 22800
0
Asphalt sealant 0.6 172.0 98 16856
C.u.nail 0.068 20.0 80 1600
Aggregate base Course
-
8/11/2019 Quantity Calculator
4/96
Diamond blade 0.5 15000 7500 1,037,516.00
EQUIPMENTS# of
Days/Day TRIPS TOTAL
TRANSIT MIXER 1 1650 57 94050
CONC. VIBRATOR 1 500 9 4500
CONC. SAW 1 1000 7 7000
BAR CUTTER 1 500 3 1500 107,050.00
LABOR# of
workers
# of
DaysTOTAL
Foreman 500 /day 1 22 11000
SKILLED 400 /day 2 22 17600
Laborers 300 /day 8 22 52800 81,400.00
sub total 1,225,966.00
12% 147,115.92
Unit cost 1,169.80 12% 122,596.60
SAY 1169.8 12% 179,481.42
TOTAL 1,675,159.94
1,675,153.60
1,998,654.57
1,674,867.20
-
8/11/2019 Quantity Calculator
5/96
Subgrade Preparation 2,148.00 19.15 41,134.20
Aggregate Subbase 214.80 760.49 163,353.25
Aggregate base Course 143.20 831.10 119,013.52
PCCP 1,432.00 1169.80 1,675,153.60Delivery Charge 1 -
TOTAL 1,998,654.57
cost
163,033.20
cost
120,216.40
cost
1,674,867.20
1,999,100.64
SUMMARY
.15m
.10m
-
8/11/2019 Quantity Calculator
6/96
28,410.25
29,510.25
119,315.87
88,382.12
29,833.74
-
8/11/2019 Quantity Calculator
7/96
64,119.52
19,461.35
86,561.35
3,007.20
143.20
286.40
28.64 2233.92
558.48
-
171.84
19.48
-
8/11/2019 Quantity Calculator
8/96
188,235.76
363,130.60
907,964.26
106,835.76
1,225,751.76
-
8/11/2019 Quantity Calculator
9/96
LENGTH
358.00
358.00
358.00
358.00
-
8/11/2019 Quantity Calculator
10/96
-
8/11/2019 Quantity Calculator
11/96
-
8/11/2019 Quantity Calculator
12/96
-
8/11/2019 Quantity Calculator
13/96
-
8/11/2019 Quantity Calculator
14/96
-
8/11/2019 Quantity Calculator
15/96
-
8/11/2019 Quantity Calculator
16/96
-
8/11/2019 Quantity Calculator
17/96
-
8/11/2019 Quantity Calculator
18/96
-
8/11/2019 Quantity Calculator
19/96
-
8/11/2019 Quantity Calculator
20/96
-
8/11/2019 Quantity Calculator
21/96
-
8/11/2019 Quantity Calculator
22/96
-
8/11/2019 Quantity Calculator
23/96
-
8/11/2019 Quantity Calculator
24/96
-
8/11/2019 Quantity Calculator
25/96
-
8/11/2019 Quantity Calculator
26/96
-
8/11/2019 Quantity Calculator
27/96
Det. Length
Subgrade PreparationEmbankment
width
Length
(Unknown)Area Price cost
A= 5.5 1 5.5 19.08 104.94
Length ThichnessLength
(Unknown)Price cost
V= 3.5 0.2 1 0.7 759.00 531.30
TOTAL 636.24
LENGTH =DELIVERY
CHARGE
26,000.00
LENGTH =
say 585
I.
Embankment
width Length
A= 5.5 585
A= 3217.5 @ 19.08
QTY HOURS TOTAL
Bulldozer 2000 /hour 1 28 56,000.00
21
LABOR# of
workers
# of
DaysTOTAL
Foreman 500 /day 1 3.5 1,750.00Laborers 300 /day 2 3.5 2,100.00
2.6
sub total
0.12
Unit cost 25.83 0.12
SAY 19.13 0.12
TOTAL
ILLUSTRATION
Subgrade Preparation
Aggregate base Course
EQUIPMENTS
Aggregate Subbase
Appropriation
1,000,000.00
1571.73
Subgrade Prep.
6.0
5.0
-
8/11/2019 Quantity Calculator
28/96
61,389.90 SAY
II.
WIDTH thickness Length
V= 3.5 0.2 585
V= 409.5 @ 759.00
COURSE W/ 15% 470.93 246.69
SHRINKAGE SAY 672 @ 400
QTY HOURS TOTAL
Road Grade 2000 /hour 1 10 20,000.00
Road Roller 1500 /hour 1 7 10,500.00
Water truck 1000 /hour 1 5 5,000.00
LABOR# of
workers
# of
DaysTOTAL
Foreman 500 /day 1 14 7,000.00
Laborers 300 /day 2 14 8,400.00
sub total
0.12
Unit cost 1,084.25 0.12
SAY 758.97 0.12TOTAL
310,810.50 SAY
Aggregate Subbase Course
MATERIALS
EQUIPMENTS
-
8/11/2019 Quantity Calculator
29/96
4386 19.13548.25 758.97
TOTAL
56,000.00
3,850.00
59,850.00 44,203.56
7,182.00
7,182.00
8,905.68
83,119.68
Subgrade Preparation
SUMMARY
Aggregate Subbase
0.15
-
8/11/2019 Quantity Calculator
30/96
61,550.78
268,800.00 165,776.21
58,021.67
103,023.79
(45,002.12)
35,500.00 (33,301.57)
15,400.00 (11,655.55)
319,700.00 223,797.88
38,364.00
38,364.00
47,571.36443,999.36
310798.215
500,009.48
-
8/11/2019 Quantity Calculator
31/96
LENGTH
83,904.18 797.4545416,105.30 783.2143
500,009.48
-
8/11/2019 Quantity Calculator
32/96
EXCAVATION
MASONRY
CONC WORKS
REINF. STEEL BARS
DOORS & WINDOWS
ROOFING WORKS
PAINTINGELECTRICAL WORKS\PLUMBING WORKS
EXCAVATION
Footing
V= 0 m 0.5 m 3 m 8 pcs. 0 cu.m.
No. of
Post
Size of
Post
AREA
(sq.m.)
0 0 0 0 0 PCS
MORTAR FOR BLOCK LAYINGCEMENT
SAND
0 0.00 bags 0.00 cu.m.
PLASTERING
0.00 bags 0.00 cu.m.
CHB FOOTING
0 40 0 bags 0
10,15,20 A,B
A,B,C,D
B
15 B 0
PERIMETERDIMENSION
(CM)
MIXTURE
CLASS
X 20 X 40 c
AREAMIXTURE
CLASSCEMENT SAND
CEMENT SAND GRA
SIZE OF CHBMIXTURE
CLASSCEMENT SAND
B,C,DGRAVEL
SU
CHB0 0
MASONRY
PERIMETER HEIGHT # OF CHB
o. ototal
-
8/11/2019 Quantity Calculator
33/96
No. of
Column
V= 189.50 m 6 m 0.25 m 1 284.25 cu.m.
0.00 m 0 m 0 m 0 0 cu.m.
V= 0.00 m 0.8 m 0.25 m 15 pcs. 0 cu.m.
0 m 0 m 0 m 0 pcs. 0 cu.m.
0
0
V= 0 m 0.3 m 53.45 m 0 cu.m.
BEAMS
LENGTH WidthNo. of
Beams VOLUME
V= 0.00 m 0.25 m 53.45 m 0 cu.m.
0 cu.m.
V= 0 m 4.1 m 0.1 m 0 cu.m.0 m 4 m 0.1 m 0 cu.m.
0 m 2.1 m 0.1 m 0 cu.m.
V= 0 m 1.5 m 0.1 m 0 cu.m.
others
V= 0 m 4.5 m 0.13 m 0 cu.m.
REINFORCEMENT STEEL
VERTICAL (tie wire)
AREALENGTH
OF TIES
25,30
160 30 467.77 m 343.25 m 7.58338 kg
40,60,80 2,3,4
40 3
COLUMNS
SPACING
(cm)
SPACING
LAYERS
VERTICAL
reinforcement
HORIZONTAL
REINFORCEMENT
# OF TIE WIRE
(kg)
LENGTH Width Thickness VOLUME
REINFORCEMENT STEEL BAR
FLOORING
LENGTH Width Thickness VOLUME TOTAL TOTAL V
0 cu.m.
84 5
CORRIDOR
LENGTH Width Thickness VOLUME
CONC. WORKS
COLUMNS
COLUMN
LENGTH
COLUMN
WIDTH
COLUMN
HEIGHTVOLUME TOTAL
284.25 cu.m.
Column Footing
Foundation
Length
Foundation
Width
Foundation
Height
No. of
ColumnVOLUME
Wall Footing
Width Thickness VOLUME
WALL
PERIMETER
-
8/11/2019 Quantity Calculator
34/96
12 mm 27 pcs 15 pcs 1 m 405 m 5.33 kg
10 mm 460 pcs 1 pcs 6 m 2760 m 0.61667 kg
16 mm 10 pcs 15 pcs 0.8 m 120 m 11.8375 kg
16 mm 4 pcs 15 pcs 6 m 360 m 1.57833 kg
10 mm 4 pcs 15 pcs 6 m 360 m 0.61667 kg
SINGLE
GUTTER
LENGTH
RAFTER
LENGTH
70 1 0.7 4.50 2.4 (8') 2.4 (8') 0
100 pcs 100 pcs 0
DOUBLE
GUTTER
LENGTH
RAFTER
LENGTH
70 1 0.7 4.80 3 (10') 2.1 (7') 0
200 pcs 200 pcs 0
18 2 0.6 5.40 3 (10') 2.7 (9') 0
60 pcs 60 pcs 0
3 2.7 0
SIDE
LAPPING
COMBINATION
OF LENGTH
copy # on the red
3 2.1 0
copy # on the red
2.4 2.4 0
Lengtho a
Unit Wt.
ROOFING
SIDE
LAPPING
COMBINATION
OF LENGTH
SIZE. o. o
-
8/11/2019 Quantity Calculator
35/96
0.00 bags
0.00 cu.m.
cu.m.
0 cu.m.
EL
MMARY
0 pcs.
-
8/11/2019 Quantity Calculator
36/96
LUME
cu m
-
8/11/2019 Quantity Calculator
37/96
2158.7
1702
1420.5
568.2
222
# OF
SHEETS
G.I.
WASHERS
(kg)
100 2.4 2.4 0 2.4 2.4 0
0 1800 1800 0 1800 1800 0 7200 PCS
pcs PCS PCS 57.14 kg
Kg Kg
# OF
pcs
G.I.
WASHERS
200 3 2.1 0 3 2.1 0 8000 PCS
0 4400 3600 0 4400 3600 0
pcs PCS PCS 63 kg
Kg Kg
60 3 2.7 0 3 2.7 0 2640 PCS
0 1320 1320 0 1320 1320 0
pcs PCS PCS 21 kg
Kg Kg
TOTAL 13280 PCS 10640 PCS 21280 PCS
TOTAL 110.67 Kg 59 Kg 169 Kg
22 14.67
602640 2640
67 44.44
G.I. ROOFING
NAILS
G.I. RIVETS
(kg)
2008000.008000
30 20.00
100.00 3600 3600.00
G.I. ROOFING
NAILS
G.I. RIVETS
(kg)
Weight
-
8/11/2019 Quantity Calculator
38/96
-
8/11/2019 Quantity Calculator
39/96
-
8/11/2019 Quantity Calculator
40/96
3600 PCS 3600 PCS
10640 PCS 10640 PCS
142 Kg 89 Kg
107 kg 67
22 kg
PCS
35 kg
2640 PCS 2640
kg
LEAD
WASHERS
(kg)
8000 PCS 8000 PCS
48 kg 30
UMBRELLA
NAILS
(kg)
kg
LEAD
WASHERS
(kg)
UMBRELLA
NAILS
(kg)
-
8/11/2019 Quantity Calculator
41/96
-
8/11/2019 Quantity Calculator
42/96
-
8/11/2019 Quantity Calculator
43/96
ITEM: ROADWAY EXCAVATION ( Using Backhoe)
L = 500m
QTY: 4500 cu.m.
A = 1/2 (3) (6)
= 9 sq.m.
x 500
4500 cu.m.
x 170.79
768,555
I. MATERIALS
NONE
II. EQUIPMENTS
BACKHOE - 2 @ 16,000 / day x 17 days = 544,000.00
III. LABOR
Foreman - 1 @ 500 / day x 20 days = 10,000.00
Laborer - 3 @ 300 / day x 20 days = 18,000.00
28,000.00
3 m 3 m
-
8/11/2019 Quantity Calculator
44/96
-
8/11/2019 Quantity Calculator
45/96
Item # : CURB & GUTTER
L = 550 m = 80 cu.m.
I. MATERIALS
Portland Cement 800 bags @ 220 = 176,000.00Sand 41.5 cu.m @ 600 = 24,900.00
Gravel 3/4 83.5 cu.m @ 750 = 62,625.00
RSB 12mm 780 pcs. @ 198 = 154,440.00
Tie wire 65 kgs. @ 80 = 5,200.00
Plywood 1/2 10 pcs. @ 500 = 5,000.00
4- 2x2x12 160 B.f. @ 40 = 6,400.00
C.W. Nail 10 kgs. @ 80 = 800.00
434,565.00
Extra Delivery Charge CEMENT 5 trips @ 4000 = 20,000.00
SAND 7 trips @ 4000 = 28,000.00
GRAVEL 14 trips @ 4000 = 56,000.00
II. EQUIPMENTS 104,000.00
One Bagger mixer - 1 @ 15 days x 1,350.00 = 20,250.00
Water truck - 1 @ 15 days x 2,000.00 = 30,000.00
50,250.00
III. LABORER
Const. Foreman - 1 @ 15 days x 500.00 = 7,500.00
Skilled Laborers - 3 @ 15 days x 400.00 = 18,000.00
Unskilled Laborer - 6 @ 15 days x 300.00 = 27,000.00
52,500.00
102,750.00
641,315.00
CURB & GUTTER
VOLUME = [(O.17)(0.32) + ( O.60)(0.15)][550 m]
= ( O.0544 + 0.09) ( 550 m )= ( 0.1444) ( 550 m)
= 79.42 cu.m
RSB550 m
0.200.86 m @ 0.888 kg/m = 2,100.12 kg
+ ( 4 pcs ) ( 550 m) = 2,200 m @ 0.888 kg/m = 1,953.6 kg
4,053.72 kg
/ 5.328 kg/pcs.
-
8/11/2019 Quantity Calculator
46/96
-
8/11/2019 Quantity Calculator
47/96
LAYING
CHB #4
area pcs/sq.m. cell vol./ sq.m
73.2 12.5 0.0375
CHB #5area pcs/sq.m. cell vol./ sq.m
194.4 12.5 0.05625
CHB #6 pcs/sq.m. cell vol./ sq.m
area
320 12.5 0.075
PLASTERING
CHB #4
area pcs/sq.m. plaster vol./ sq.m(two faces)
124.8 12.5 0.0375
CHB #5
area pcs/sq.m. plaster vol./ sq.m(two faces)
455.87 12.5 0.0375
CHB REINFORCEMENT
area vertical spacing length in FEET/sq.m. SUB-TOTAL length
73.2 0.60m 6.875 503.25
horizontal spacing
every 3 layers 6.375 466.65
QTY OF CEMENT, SAND, GRAVEL PER METER OF CHB FOOTING
Length thickness width CEMENT class A bags
115.2 6 inches 12 inches 41.472
QUANTITY OF CEMENT, SAND, GRAVEL PER METER LENGTH OF POST, BEAM, AND GIRD
Total length sizes in inches CEMENT class A CEMENT class B
60 6 x 6 10.8 9.45
6 x 8 14.4 12.6
Length each post= 6 x 10 18 15.75
2.5 6 x 12 21.6 18.9
No. of Posts= 8 x 8 19.2 16.8
24 8 x 10 24 21
8 x 12 28.8 25.2
8 x 14 33.6 29.4
8 x 16 38.4 33.6
-
8/11/2019 Quantity Calculator
48/96
10 x 10 30 26.25
10 x 12 36 31.5
10 x 14 42 36.75
10 x 16 48 42
10 x 18 54 47.2510 x 20 60 52.5
QUANTITY OF CEMENT, SAND, GRAVEL PER SQUARE METER OF SLAB AND WALLS
area thickness in inches CEMENT class A CEMENT class B
18.5625 2 7.425 6.496875
3 11.1375 9.7453125
4 14.85 12.99375
5 18.5625 16.2421875
6 22.275 19.490625
7 25.9875 22.7390625
8 29.7 25.9875
9 33.4125 29.2359375
10 37.125 32.484375
POST REINFORCEMENT::::LENGTH OF LATERAL TIE AND NUMBER IN ONE 6-M BAR
Column Dimension Lateral tie dimension
Length of post(M) W x L Width (inch) Length (inch)
No. of Posts=
15 6 x 8 3 5
Length each Post=4 8 x 8 5 5
Total Length of Post
60
No. of MAIN BARS=
4
8 x 10 5 7
8 x 12 5 9
-
8/11/2019 Quantity Calculator
49/96
8 x 14 5 11
8 x 16 5 13
10 x 10 7 7
10 x 12 7 9
10 x 14 7 11
10 x 16 7 13
10 x 18 7 15
12 x 12 9 9
12 x 14 9 11
12 x 16 9 13
12 x 18 9 15
14 x 14 11 11
MAIN REINFORCEMENT FOR COLUMN, BEAM, GIRDER
Length (meter) No. of main Bars/ col Total Pcs of 20' Bar
2.75 4 2
6 3
8 4
10 5
12 6
-
8/11/2019 Quantity Calculator
50/96
CONCRETE SLAB REINFORCEMENT
Bar
area spacing (inch) 20' bar per SQ.M. Tie Wire KGS/SQ.M.
54 4" 180.900 11.772
5" 153.468 10.530
6" 132.300 8.2087" 121.500 6.966
8" 112.482 6.102
9" 101.736 5.508
10" 95.148 4.590
11" 90.126 4.320
12" 85.644 3.996
BOARD FOOT OF STUDS AND CEILING JOISTPER SQUARE METER
Area
20.9 joist dimension (0.40m x 0.40m) (0.40m x 0.60m)
2"x 2" 134.1153 113.80052"x 3" 201.1625 173.7208
2" x 4" 268.2097 227.6219
CEILING BOARD
area sizes effective covering (sq.m) No. of pcs/ sq.m.
20.9 12" x 12" 0.0929 11.250
16" x 16" 0.1651 6.250
16" x 24" 0.2477 4.250
24" x 24" 0.3716 2.910
3' x 6' 1.6720 0.675
4' x 8' 2.9730 0.403
SCAFFOLDING
Length of column
or size Vertical Horizontal
Area of Floor(sq.m) in inches per Mt. height per Mt, height
108.2 2" x 2" 505.294 2272.2
2" x 3" 757.4 3426.694
2" x 4" 1009.506 4568.204
CORRUGATED G.I ROOFING
Length Rivets
in FEET 1-1/2 corrugation 2-1/2 corrugation Per sheet
6' 0.70 m 0.60 m 14
7' 0.70 m 0.60 m 19
Effective Covering _ side lap
One Way Slab
joist spacing
COLUMN (
-
8/11/2019 Quantity Calculator
51/96
8' 0.70 m 0.60 m 19
9' 0.70 m 0.60 m 19
10' 0.70 m 0.60 m 24
12' 0.70 m 0.60 m 29
OOF ACCESSORIESMaterial No. of Pcs / kilo
G.I roofing Nails 102
Lead washers 75
G.I Washers 126
G.I rivets 180
Tekscrew 7 pcs/sq.m.
COMMON NAILS
Size Length Approximate Number of Nailsinches No. to Lbs / Keg ( 45kgs )
2d 1 876 85,700
3d 1.1/4 568 54,800
4d 1.1/2 316 29,800
5d 1.3/4 271 25,500
6d 2 181 17,900
7d 2.1/4 161 15,300
8d 2.1/2 106 10,100
9d 2.3/4 96 8,900
10d 3 69 6,600
12d 3.1/4 63 6,20016d 3.1/2 49 4,900
20d 4 31 3,100
30d 4.1/2 24 2,400
40d 5 18 1,800
50d 5.1/2 14 1,300
60d 6 11 1,100
USED AND APPROX. QUANTITIES OF NAILS
Material Unit Per Required Kilos Size
1. Floor joist & Bridgin 1000 b.f 10.35 20d
2. Flooring a. Soft 1000 b.f 14.34 8d
b. Hard 1000 b.f 8.25 6d
3. Studs 1000 b.f 10.43 8d
4. Rafters,Purlins & cl 1000 b.f 18.38 20d
5. Trusses 1000 b.f 7.93 20d
6. Facia Board 1000 b.f 9.57 8d
7. Ceiling Joist 1000 b.f 16.3 8d
-
8/11/2019 Quantity Calculator
52/96
12.93 20d
or 9.20 6d
or 6.07 10d
8. Ceiling Board ( 1 x 1000 b.f 4.55 6d
9. Plywood Ceiling 18 pcs 1 2d
10. Sidings 1000 b.f 4.55 6d11. Base Board 1000 b.f 6.08 6d
12. Ballustrade 1000 b.f 8.2 6d
13. Scaffolding mt. ht of column 0.73 20d
14. Forms
a. T & G 1000 b.f 6.33 6d
b. Plywood 1/4 pc 0.07 2d
1/2 pc 0.22 4d
TILING WORKS
AREA Tile size no. of pcs / sq.m. TOTAL pcs as to given area70 20cm x 20cm 25 1750
30cm x 30cm 11.11 777.7
40cm x 40cm 6.25 437.5
60cm x 60cm 2.78 194.6
EXCAVATION FOR STRUCTURE
Column footing
depth no. of footings size volume
1 8 0.50m x 0.50m 2
0.60m x 0.60m 2.88
0.80m x 0.80m 5.121.00m x 1.00m 8
1.20m x 1.20m 11.52
wall footing
length depth w/ 2 layer CHB width volume
38.1 0.5 0.3 5.715
PAINTING WORKSAREA coverage in sq.m. / gal. no. of coating total gallos required
170.9 30 1 5.70
2 11.39
3
Note: 1 tin = 4 gallons
1 gal = 4 ltrs
-
8/11/2019 Quantity Calculator
53/96
NOTE: tinting color
1 gal = 4 quarts @
1 quart = 4 pints@
1/2 quart @
1/4 quart @
1/8 quart @
SOIL POISONING
AREA coverage sq.m. no. of chlordane_ltr
101.4 4 mixture 1:100
coverage 4ltrs mixture/sq.m. of slab
4.056
length of wall footing
length coverage / mtr
100 5.685 mixture 1:100
coverage 4gal mixture/10ft length/ft. depth
or 1.5 ltr mixture / ft. length of wallor 5.685 ltr mixture / mtr of wall
5.685
WOOD PRESERVATIVE
AREA coverage sq.m./ltr no. of solignum_ltr
100 o 8 sq.m. of wood surface / 5
20
-
8/11/2019 Quantity Calculator
54/96
laying vol./ sq.m TOTAL CHB SAND CEMENT
0.00625 915 3.2025 28.8225
laying vol./ sq.m TOTAL CHB SAND CEMENT
0.008125 2430 12.5145 112.6305
laying vol./ sq.m TOTAL CHB SAND CEMENT
0.01 4000 27.2 244.8
SAND CEMENT
4.68 42.12
SAND CEMENT
17.095125 153.856125
TOTAL LENTGH TOTAL # OF PCS TIE WIRES #16
KGS/sq. m.
969.9 48.495 1.3908
SAND cu.m. GRAVEL cu.m. TIES SPACING o. pcs horizontal reinf.
2.592 5.184 8" 40.42
6" 40.42
R
SAND cu.m. GRAVEL cu.m.
0.675 1.3500
0.9 1.8000
1.125 2.2500
1.35 2.7000
1.2 2.4000
1.5 3.0000
1.8 3.6000
2.1 4.2000
2.4 4.8000
-
8/11/2019 Quantity Calculator
55/96
1.875 3.7500
2.25 4.5000
2.625 5.2500
3 6.0000
3.375 6.75003.75 7.5000
FOOTING CemSAND cu.m. GRAVEL cu.m. Size of Footing thickness in inches
0.4640625 0.928125 Length= 2
0.66268125 1.3921875 0.75 3
0.928125 1.85625 Width= 4
1.16015625 2.3203125 0.75 5
1.3921875 2.784375 6
1.62421875 3.2484375 No. of Longitudinal= 7
1.85625 3.7125 4 8
2.08828125 4.1765625 No. of Transverse= 9
2.3203125 4.640625 4 10
No. of Footing=
24
Length of each Tie No. of pcs in one bar spacing in (inches)
20 12 6
824 10 6
8
10
12
14
16
28 8 6
8
10
12
14
16
32 7 6
8
10
12
14
16
-
8/11/2019 Quantity Calculator
56/96
36 6 6
8
10
12
14
1640 6 8
32 7 6
8
10
12
14
16
36 6 6
8
1012
14
16
40 6
44 5
48 5
40 6 6
8
10
12
14
16
44 5
48 5
52 4
48 5
enter
total no. of ties per comp tie wire kgs/m
100 2.264150943
50 1.698113208
50 2.264150943
50 2.830188679
50 3.396226415
-
8/11/2019 Quantity Calculator
57/96
20' bar per SQ.M. Tie Wire KGS/SQ.M.
224.100 24.786
185.760 21.006
164.160 15.228137.700 10.692
126.900 7.128
109.080 5.670
98.280 4.482
92.340 3.726
86.400 3.024
(0.60m x 0.60m)
93.5066140.2599
187.0132
TOTAL pcs as to given area
235.125
130.625
88.825
60.819
14.1075
8.4227
Brace TOTAL Vertical Horizontal
per Meter height bd.ft. / meter height / meter. height
1262.694 4040.188 432.8 505.294
1893.5 649.2 757.4
2524.306 865.6 1009.506
Purlin
Distance
30"
24"
Two Way Slab
Bd, Ft ) BEAM (Bd. Ft. )
-
8/11/2019 Quantity Calculator
58/96
28"
32"
27"
27"
ITEMS Effective LengthGutter 2.4
Valley Roll 2.4
Flashing 2.3
Hipped 2.2
Ridge Roll 2.2
Soldering Lead 1/4 bar / soldering joint
Muriatic Acid 10 cc / soldering lead
Kind
CWN
Flr Brads
Flr Brads
CWN
CWN
CWN
CWN
CWN
-
8/11/2019 Quantity Calculator
59/96
CWN
CWN
CWN
Casing Brads
Finishing
CWNFinishing
Finishing
CWN
CWN
CWN
CWN
CWN
tile grout 2kg pack tile adhesive 25kg pack cement sand3.5 7.56 11.025 1.75
Ration = 1:4 Ration = 1:100 sq.m. Ration = 4:100 sq.m. Ration = 1quart:4galthinner for QDE paints in gal Putty _ gal sand paper #240, #320 tinting color
1.42 1.71 6.84 1.42
2.85 2.85
-
8/11/2019 Quantity Calculator
60/96
-
8/11/2019 Quantity Calculator
61/96
ties total CHB footing reinf. Tie wire
28.85 69.27
38.45 78.87
CHB FOOTING REINFORCEMENT
-
8/11/2019 Quantity Calculator
62/96
nt, sand ,Gravel, Reinforcement, tie wireCEMENT class A CEMENT class B SAND cu.m. GRAVEL cu.m.
6.174 5.488 0.343 0.686
9.261 8.232 0.514 1.029
12.348 10.976 0.686 1.372
15.434 13.720 0.857 1.715
18.521 16.463 1.029 2.058
21.608 19.207 1.200 2.401
24.695 21.951 1.372 2.744
27.782 24.695 1.543 3.087
30.869 27.439 1.715 3.430
No. of RSB TIES x 20'G.I. TIE WIRE NEEDED
No.of RSB per meter length of post
6.70 33.500 9.102
5.15 25.750 6.9966.70 40.200 9.102
5.15 30.900 6.996
4.13 24.780 5.611
3.43 20.580 4.660
3.00 18.000 4.075
2.71 16.260 3.682
6.70 50.250 9.102
5.15 38.625 6.996
4.13 30.975 5.611
3.43 25.725 4.660
3.00 22.500 4.075
2.71 20.325 3.682
6.70 57.429 9.102
5.15 44.143 6.996
4.13 35.400 5.611
3.43 29.400 4.660
3.00 25.714 4.075
2.71 23.229 3.682
ATERAL TIES
-
8/11/2019 Quantity Calculator
63/96
6.70 67.000 9.102
5.15 51.500 6.996
4.13 41.300 5.611
3.43 34.300 4.660
3.00 30.000 4.075
2.71 27.100 3.682-
6.70 57.429 9.102
5.15 44.143 6.996
4.13 35.400 5.611
3.43 29.400 4.660
3.00 25.714 4.075
2.71 23.229 3.682
6.70 67.000 9.102
5.15 51.500 6.996
4.13 41.300 5.6113.43 34.300 4.660
3.00 30.000 4.075
2.71 27.100 3.682
6.70 67.000 9.102
5.15 51.500 6.996
4.13 41.300 5.611
3.43 34.300 4.660
3.00 30.000 4.075
2.71 27.100 3.682
-
8/11/2019 Quantity Calculator
64/96
FLOOR
bd. Ft
/ SQ. METER
660.02
984.62
1309.22
-
8/11/2019 Quantity Calculator
65/96
-
8/11/2019 Quantity Calculator
66/96
-
8/11/2019 Quantity Calculator
67/96
-
8/11/2019 Quantity Calculator
68/96
-
8/11/2019 Quantity Calculator
69/96
Reinf. Tie wire
24 2.174
24 2.174
24 2.174
24 2.174
24 2.174
24 2.174
24 2.174
24 2.174
24 2.174
-
8/11/2019 Quantity Calculator
70/96
-
8/11/2019 Quantity Calculator
71/96
-
8/11/2019 Quantity Calculator
72/96
-
8/11/2019 Quantity Calculator
73/96
-
8/11/2019 Quantity Calculator
74/96
-
8/11/2019 Quantity Calculator
75/96
-
8/11/2019 Quantity Calculator
76/96
-
8/11/2019 Quantity Calculator
77/96
-
8/11/2019 Quantity Calculator
78/96
-
8/11/2019 Quantity Calculator
79/96
-
8/11/2019 Quantity Calculator
80/96
-
8/11/2019 Quantity Calculator
81/96
-
8/11/2019 Quantity Calculator
82/96
-
8/11/2019 Quantity Calculator
83/96
-
8/11/2019 Quantity Calculator
84/96
-
8/11/2019 Quantity Calculator
85/96
-
8/11/2019 Quantity Calculator
86/96
LABOR# of
workers
# of
DaysTOTAL
Foreman 500 /day 1 1 500
Laborers 300 /day 2 1 600 1,100.00
sub total 10,975.00
12% 1,317.00
Unit cost 700.785 12% 1,317.00
SAY 700.5 12% 1,633.08
TOTAL 15,242.08
18,259.13 15,235.88
II.
PCCP
pavement width Length
A= 1 870
A= 870 @ 898.18
V= 87
MATERIALS QTY PRICE TOTAL
Cement 9 54 230 12420
Sand 0.5 3 600 1800
Gravel 1 6 700 4200
RSB 10mm 7.15 43 145 6235
Lumber 15 - 2 x 2 x 12 1.95 12 45 540
Plywood 0.7 5 350 1750C.u.nail 0.068 0.5 80 40
Tie wire 0.2 1.5 80 120 27,105.00
418,567.65
EQUIPMENTS# of
Days/Day TRIPS TOTAL
TRANSIT MIXER 1 1650 9 14850 14,850.00
17.4
LABOR# of
workers
# of
Days
TOTAL
Foreman 500 /day 1 2 1000
SKILLED 400 /day 1 2 800
Laborers 300 /day 5 2 3000 4,800.00
sub total 46,755.00
12% 5,610.60
Unit cost 74.64 12% 5,610.60
SAY 1015.1 12% 6,957.14
-
8/11/2019 Quantity Calculator
87/96
TOTAL 64,933.34
883,137.00
898,372.88
784,764.13
-
8/11/2019 Quantity Calculator
88/96
-
8/11/2019 Quantity Calculator
89/96
Aggregate base Course 21.75 700.50 15,235.88
PCCP 870.00 1015.10 883,137.00
Delivery Charge 1 -
TOTAL 898,372.88
cost
18,259.13
cost
781,416.60
799,675.73
9,738.82
SUMMARY0.10
0.025
-
8/11/2019 Quantity Calculator
90/96
3,456.25
13,147.41
783.00 783
43.50 44
87.00 87
622.05 622
169.65 170
60.90 615.92 6
17.40 18
565,066.33
-
8/11/2019 Quantity Calculator
91/96
200,000.0087,122.92
112,877.08
-
8/11/2019 Quantity Calculator
92/96
-
8/11/2019 Quantity Calculator
93/96
-
8/11/2019 Quantity Calculator
94/96
-
8/11/2019 Quantity Calculator
95/96
5
7
11
0.20
0.10
-
8/11/2019 Quantity Calculator
96/96
PATHWAY