quantity calculator

Upload: joselle-francene-anne-angeles

Post on 03-Jun-2018

224 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/11/2019 Quantity Calculator

    1/96

    Det. Length

    Embankment

    width

    Length

    (Unknown)Area Price cost cost

    A= 6 1 6 19.08 114.48 40,983.84

    Aggregate Subbase

    Shoulder

    LengthThickness

    Length

    (Unknown)VOLUME Price cost

    V= 1 0.3 1 0.3 759 455.40

    Aggregate base Course

    Pavement

    widthABC

    Length

    (Unknown)VOLUME Price cost

    V= 4 0.1 1 0.4 839.5 335.80

    PCCP

    Thickness = 0.2

    Pavement

    width

    Length

    (Unknown)Area Price cost

    A= 4 1 4 1,169.60 4,678.40

    0.15 898.18

    0.20 1169.6

    TOTAL 5,584.08

    LENGTH =DELIVERY

    CHARGE

    0.00

    LENGTH =

    say 358

    I.

    Embankment

    widthLength

    A= 6 358

    ILLUSTRATION

    Subgrade Preparation

    Aggregate Subbase

    Aggregate base Course

    PCCP

    Subgrade Prep.

    Appropriation

    2,000,000.00358.16

    Subgrade Prep.

    7m

    5m 1m1m

    ABC

    PCCPSUB

    BASE

    SUB

    BASE

  • 8/11/2019 Quantity Calculator

    2/96

    A= 2148 @ 19.08

    300sq.m/hr

    EQUIPMENTS QTY HOURS TOTAL

    Road Grader 2000 /hour 1 6 12000

    Road Roller 1500 /hour 1 9 13500

    Water truck 1000 /hour 1 3.5 3500 29,000.00

    LABOR# of

    workers

    # of

    DaysTOTAL

    Foreman 500 /day 1 1 500

    Laborers 300 /day 2 1 600 1,100.00

    sub total 30,100.00

    12% 3,612.00

    Unit cost 19.15 10% 3,010.00

    SAY 19.15 12% 4,406.64

    TOTAL 41,128.64

    40,983.84 41,134.20

    II.

    shoulder thickness Length

    V= 1 0.3 358

    V= 107.4 @ 759

    214.80

    COURSE W/ 15% 247.02 357.82

    SHRINKAGE SAY 247 @ 350 86,450.00

    MATERIALS

    EQUIPMENTS 50 cu.m/hr QTY HOURS TOTAL

    Road Grader 2000 /hour 1 7 14000

    Road Roller 1500 /hour 1 9 13500

    Water truck 1000 /hour 1 4.5 4500 32,000.00

    LABOR# of

    workers

    # of

    DaysTOTAL

    Foreman 500 /day 1 1 500

    Laborers 300 /day 2 1 600 1,100.00

    sub total 119,550.00

    12% 14,346.00

    Unit cost 760.49 10% 11,955.00

    SAY 760.49 12% 17,502.12

    TOTAL 163,353.12

    Aggregate Subbase

  • 8/11/2019 Quantity Calculator

    3/96

    163,033.20 SAY 163,033.20

    III.

    pavement width ABC Length

    V= 4 0.1 358

    V= 143.2 @ 839.5

    ABC W/ 15% 164.68 388.60

    SHRINKAGE SAY 165 @ 400 66,000.00

    MATERIALS

    EQUIPMENTS QTY HOURS TOTAL

    Road Grader 2000 /hour 1 4 8,000.00

    Road Roller 1500 /hour 1 7 ########

    Water truck 1000 /hour 1 1.5 1,500.00 20,000.00

    LABOR# of

    workers

    # of

    DaysTOTAL

    Foreman 500 /day 1 1 500.00

    Laborers 300 /day 2 1 600.00 1,100.00

    sub total 87,100.00

    12% 10,452.00

    Unit cost 831.099 12% 8,710.00

    SAY 831.1 12% 12,751.44

    TOTAL 119,013.44

    120,216.40 119,013.52

    IV.

    PCCP 108 sq.m/hr

    pavement width Length

    A= 4 358

    A= 1432 @ 1,169.60

    V= 286.4

    MATERIALS QTY PRICE TOTALCement 10.5 3007.0 230 691610

    Sand 0.5 143.5 600 86100

    Gravel 1 287.0 700 200900

    RSB 16mm 0.1 29.0 350 10150 7.8

    Lumber 40 - 2 x 6 x 12 1.95 570.0 40 22800

    0

    Asphalt sealant 0.6 172.0 98 16856

    C.u.nail 0.068 20.0 80 1600

    Aggregate base Course

  • 8/11/2019 Quantity Calculator

    4/96

    Diamond blade 0.5 15000 7500 1,037,516.00

    EQUIPMENTS# of

    Days/Day TRIPS TOTAL

    TRANSIT MIXER 1 1650 57 94050

    CONC. VIBRATOR 1 500 9 4500

    CONC. SAW 1 1000 7 7000

    BAR CUTTER 1 500 3 1500 107,050.00

    LABOR# of

    workers

    # of

    DaysTOTAL

    Foreman 500 /day 1 22 11000

    SKILLED 400 /day 2 22 17600

    Laborers 300 /day 8 22 52800 81,400.00

    sub total 1,225,966.00

    12% 147,115.92

    Unit cost 1,169.80 12% 122,596.60

    SAY 1169.8 12% 179,481.42

    TOTAL 1,675,159.94

    1,675,153.60

    1,998,654.57

    1,674,867.20

  • 8/11/2019 Quantity Calculator

    5/96

    Subgrade Preparation 2,148.00 19.15 41,134.20

    Aggregate Subbase 214.80 760.49 163,353.25

    Aggregate base Course 143.20 831.10 119,013.52

    PCCP 1,432.00 1169.80 1,675,153.60Delivery Charge 1 -

    TOTAL 1,998,654.57

    cost

    163,033.20

    cost

    120,216.40

    cost

    1,674,867.20

    1,999,100.64

    SUMMARY

    .15m

    .10m

  • 8/11/2019 Quantity Calculator

    6/96

    28,410.25

    29,510.25

    119,315.87

    88,382.12

    29,833.74

  • 8/11/2019 Quantity Calculator

    7/96

    64,119.52

    19,461.35

    86,561.35

    3,007.20

    143.20

    286.40

    28.64 2233.92

    558.48

    -

    171.84

    19.48

  • 8/11/2019 Quantity Calculator

    8/96

    188,235.76

    363,130.60

    907,964.26

    106,835.76

    1,225,751.76

  • 8/11/2019 Quantity Calculator

    9/96

    LENGTH

    358.00

    358.00

    358.00

    358.00

  • 8/11/2019 Quantity Calculator

    10/96

  • 8/11/2019 Quantity Calculator

    11/96

  • 8/11/2019 Quantity Calculator

    12/96

  • 8/11/2019 Quantity Calculator

    13/96

  • 8/11/2019 Quantity Calculator

    14/96

  • 8/11/2019 Quantity Calculator

    15/96

  • 8/11/2019 Quantity Calculator

    16/96

  • 8/11/2019 Quantity Calculator

    17/96

  • 8/11/2019 Quantity Calculator

    18/96

  • 8/11/2019 Quantity Calculator

    19/96

  • 8/11/2019 Quantity Calculator

    20/96

  • 8/11/2019 Quantity Calculator

    21/96

  • 8/11/2019 Quantity Calculator

    22/96

  • 8/11/2019 Quantity Calculator

    23/96

  • 8/11/2019 Quantity Calculator

    24/96

  • 8/11/2019 Quantity Calculator

    25/96

  • 8/11/2019 Quantity Calculator

    26/96

  • 8/11/2019 Quantity Calculator

    27/96

    Det. Length

    Subgrade PreparationEmbankment

    width

    Length

    (Unknown)Area Price cost

    A= 5.5 1 5.5 19.08 104.94

    Length ThichnessLength

    (Unknown)Price cost

    V= 3.5 0.2 1 0.7 759.00 531.30

    TOTAL 636.24

    LENGTH =DELIVERY

    CHARGE

    26,000.00

    LENGTH =

    say 585

    I.

    Embankment

    width Length

    A= 5.5 585

    A= 3217.5 @ 19.08

    QTY HOURS TOTAL

    Bulldozer 2000 /hour 1 28 56,000.00

    21

    LABOR# of

    workers

    # of

    DaysTOTAL

    Foreman 500 /day 1 3.5 1,750.00Laborers 300 /day 2 3.5 2,100.00

    2.6

    sub total

    0.12

    Unit cost 25.83 0.12

    SAY 19.13 0.12

    TOTAL

    ILLUSTRATION

    Subgrade Preparation

    Aggregate base Course

    EQUIPMENTS

    Aggregate Subbase

    Appropriation

    1,000,000.00

    1571.73

    Subgrade Prep.

    6.0

    5.0

  • 8/11/2019 Quantity Calculator

    28/96

    61,389.90 SAY

    II.

    WIDTH thickness Length

    V= 3.5 0.2 585

    V= 409.5 @ 759.00

    COURSE W/ 15% 470.93 246.69

    SHRINKAGE SAY 672 @ 400

    QTY HOURS TOTAL

    Road Grade 2000 /hour 1 10 20,000.00

    Road Roller 1500 /hour 1 7 10,500.00

    Water truck 1000 /hour 1 5 5,000.00

    LABOR# of

    workers

    # of

    DaysTOTAL

    Foreman 500 /day 1 14 7,000.00

    Laborers 300 /day 2 14 8,400.00

    sub total

    0.12

    Unit cost 1,084.25 0.12

    SAY 758.97 0.12TOTAL

    310,810.50 SAY

    Aggregate Subbase Course

    MATERIALS

    EQUIPMENTS

  • 8/11/2019 Quantity Calculator

    29/96

    4386 19.13548.25 758.97

    TOTAL

    56,000.00

    3,850.00

    59,850.00 44,203.56

    7,182.00

    7,182.00

    8,905.68

    83,119.68

    Subgrade Preparation

    SUMMARY

    Aggregate Subbase

    0.15

  • 8/11/2019 Quantity Calculator

    30/96

    61,550.78

    268,800.00 165,776.21

    58,021.67

    103,023.79

    (45,002.12)

    35,500.00 (33,301.57)

    15,400.00 (11,655.55)

    319,700.00 223,797.88

    38,364.00

    38,364.00

    47,571.36443,999.36

    310798.215

    500,009.48

  • 8/11/2019 Quantity Calculator

    31/96

    LENGTH

    83,904.18 797.4545416,105.30 783.2143

    500,009.48

  • 8/11/2019 Quantity Calculator

    32/96

    EXCAVATION

    MASONRY

    CONC WORKS

    REINF. STEEL BARS

    DOORS & WINDOWS

    ROOFING WORKS

    PAINTINGELECTRICAL WORKS\PLUMBING WORKS

    EXCAVATION

    Footing

    V= 0 m 0.5 m 3 m 8 pcs. 0 cu.m.

    No. of

    Post

    Size of

    Post

    AREA

    (sq.m.)

    0 0 0 0 0 PCS

    MORTAR FOR BLOCK LAYINGCEMENT

    SAND

    0 0.00 bags 0.00 cu.m.

    PLASTERING

    0.00 bags 0.00 cu.m.

    CHB FOOTING

    0 40 0 bags 0

    10,15,20 A,B

    A,B,C,D

    B

    15 B 0

    PERIMETERDIMENSION

    (CM)

    MIXTURE

    CLASS

    X 20 X 40 c

    AREAMIXTURE

    CLASSCEMENT SAND

    CEMENT SAND GRA

    SIZE OF CHBMIXTURE

    CLASSCEMENT SAND

    B,C,DGRAVEL

    SU

    CHB0 0

    MASONRY

    PERIMETER HEIGHT # OF CHB

    o. ototal

  • 8/11/2019 Quantity Calculator

    33/96

    No. of

    Column

    V= 189.50 m 6 m 0.25 m 1 284.25 cu.m.

    0.00 m 0 m 0 m 0 0 cu.m.

    V= 0.00 m 0.8 m 0.25 m 15 pcs. 0 cu.m.

    0 m 0 m 0 m 0 pcs. 0 cu.m.

    0

    0

    V= 0 m 0.3 m 53.45 m 0 cu.m.

    BEAMS

    LENGTH WidthNo. of

    Beams VOLUME

    V= 0.00 m 0.25 m 53.45 m 0 cu.m.

    0 cu.m.

    V= 0 m 4.1 m 0.1 m 0 cu.m.0 m 4 m 0.1 m 0 cu.m.

    0 m 2.1 m 0.1 m 0 cu.m.

    V= 0 m 1.5 m 0.1 m 0 cu.m.

    others

    V= 0 m 4.5 m 0.13 m 0 cu.m.

    REINFORCEMENT STEEL

    VERTICAL (tie wire)

    AREALENGTH

    OF TIES

    25,30

    160 30 467.77 m 343.25 m 7.58338 kg

    40,60,80 2,3,4

    40 3

    COLUMNS

    SPACING

    (cm)

    SPACING

    LAYERS

    VERTICAL

    reinforcement

    HORIZONTAL

    REINFORCEMENT

    # OF TIE WIRE

    (kg)

    LENGTH Width Thickness VOLUME

    REINFORCEMENT STEEL BAR

    FLOORING

    LENGTH Width Thickness VOLUME TOTAL TOTAL V

    0 cu.m.

    84 5

    CORRIDOR

    LENGTH Width Thickness VOLUME

    CONC. WORKS

    COLUMNS

    COLUMN

    LENGTH

    COLUMN

    WIDTH

    COLUMN

    HEIGHTVOLUME TOTAL

    284.25 cu.m.

    Column Footing

    Foundation

    Length

    Foundation

    Width

    Foundation

    Height

    No. of

    ColumnVOLUME

    Wall Footing

    Width Thickness VOLUME

    WALL

    PERIMETER

  • 8/11/2019 Quantity Calculator

    34/96

    12 mm 27 pcs 15 pcs 1 m 405 m 5.33 kg

    10 mm 460 pcs 1 pcs 6 m 2760 m 0.61667 kg

    16 mm 10 pcs 15 pcs 0.8 m 120 m 11.8375 kg

    16 mm 4 pcs 15 pcs 6 m 360 m 1.57833 kg

    10 mm 4 pcs 15 pcs 6 m 360 m 0.61667 kg

    SINGLE

    GUTTER

    LENGTH

    RAFTER

    LENGTH

    70 1 0.7 4.50 2.4 (8') 2.4 (8') 0

    100 pcs 100 pcs 0

    DOUBLE

    GUTTER

    LENGTH

    RAFTER

    LENGTH

    70 1 0.7 4.80 3 (10') 2.1 (7') 0

    200 pcs 200 pcs 0

    18 2 0.6 5.40 3 (10') 2.7 (9') 0

    60 pcs 60 pcs 0

    3 2.7 0

    SIDE

    LAPPING

    COMBINATION

    OF LENGTH

    copy # on the red

    3 2.1 0

    copy # on the red

    2.4 2.4 0

    Lengtho a

    Unit Wt.

    ROOFING

    SIDE

    LAPPING

    COMBINATION

    OF LENGTH

    SIZE. o. o

  • 8/11/2019 Quantity Calculator

    35/96

    0.00 bags

    0.00 cu.m.

    cu.m.

    0 cu.m.

    EL

    MMARY

    0 pcs.

  • 8/11/2019 Quantity Calculator

    36/96

    LUME

    cu m

  • 8/11/2019 Quantity Calculator

    37/96

    2158.7

    1702

    1420.5

    568.2

    222

    # OF

    SHEETS

    G.I.

    WASHERS

    (kg)

    100 2.4 2.4 0 2.4 2.4 0

    0 1800 1800 0 1800 1800 0 7200 PCS

    pcs PCS PCS 57.14 kg

    Kg Kg

    # OF

    pcs

    G.I.

    WASHERS

    200 3 2.1 0 3 2.1 0 8000 PCS

    0 4400 3600 0 4400 3600 0

    pcs PCS PCS 63 kg

    Kg Kg

    60 3 2.7 0 3 2.7 0 2640 PCS

    0 1320 1320 0 1320 1320 0

    pcs PCS PCS 21 kg

    Kg Kg

    TOTAL 13280 PCS 10640 PCS 21280 PCS

    TOTAL 110.67 Kg 59 Kg 169 Kg

    22 14.67

    602640 2640

    67 44.44

    G.I. ROOFING

    NAILS

    G.I. RIVETS

    (kg)

    2008000.008000

    30 20.00

    100.00 3600 3600.00

    G.I. ROOFING

    NAILS

    G.I. RIVETS

    (kg)

    Weight

  • 8/11/2019 Quantity Calculator

    38/96

  • 8/11/2019 Quantity Calculator

    39/96

  • 8/11/2019 Quantity Calculator

    40/96

    3600 PCS 3600 PCS

    10640 PCS 10640 PCS

    142 Kg 89 Kg

    107 kg 67

    22 kg

    PCS

    35 kg

    2640 PCS 2640

    kg

    LEAD

    WASHERS

    (kg)

    8000 PCS 8000 PCS

    48 kg 30

    UMBRELLA

    NAILS

    (kg)

    kg

    LEAD

    WASHERS

    (kg)

    UMBRELLA

    NAILS

    (kg)

  • 8/11/2019 Quantity Calculator

    41/96

  • 8/11/2019 Quantity Calculator

    42/96

  • 8/11/2019 Quantity Calculator

    43/96

    ITEM: ROADWAY EXCAVATION ( Using Backhoe)

    L = 500m

    QTY: 4500 cu.m.

    A = 1/2 (3) (6)

    = 9 sq.m.

    x 500

    4500 cu.m.

    x 170.79

    768,555

    I. MATERIALS

    NONE

    II. EQUIPMENTS

    BACKHOE - 2 @ 16,000 / day x 17 days = 544,000.00

    III. LABOR

    Foreman - 1 @ 500 / day x 20 days = 10,000.00

    Laborer - 3 @ 300 / day x 20 days = 18,000.00

    28,000.00

    3 m 3 m

  • 8/11/2019 Quantity Calculator

    44/96

  • 8/11/2019 Quantity Calculator

    45/96

    Item # : CURB & GUTTER

    L = 550 m = 80 cu.m.

    I. MATERIALS

    Portland Cement 800 bags @ 220 = 176,000.00Sand 41.5 cu.m @ 600 = 24,900.00

    Gravel 3/4 83.5 cu.m @ 750 = 62,625.00

    RSB 12mm 780 pcs. @ 198 = 154,440.00

    Tie wire 65 kgs. @ 80 = 5,200.00

    Plywood 1/2 10 pcs. @ 500 = 5,000.00

    4- 2x2x12 160 B.f. @ 40 = 6,400.00

    C.W. Nail 10 kgs. @ 80 = 800.00

    434,565.00

    Extra Delivery Charge CEMENT 5 trips @ 4000 = 20,000.00

    SAND 7 trips @ 4000 = 28,000.00

    GRAVEL 14 trips @ 4000 = 56,000.00

    II. EQUIPMENTS 104,000.00

    One Bagger mixer - 1 @ 15 days x 1,350.00 = 20,250.00

    Water truck - 1 @ 15 days x 2,000.00 = 30,000.00

    50,250.00

    III. LABORER

    Const. Foreman - 1 @ 15 days x 500.00 = 7,500.00

    Skilled Laborers - 3 @ 15 days x 400.00 = 18,000.00

    Unskilled Laborer - 6 @ 15 days x 300.00 = 27,000.00

    52,500.00

    102,750.00

    641,315.00

    CURB & GUTTER

    VOLUME = [(O.17)(0.32) + ( O.60)(0.15)][550 m]

    = ( O.0544 + 0.09) ( 550 m )= ( 0.1444) ( 550 m)

    = 79.42 cu.m

    RSB550 m

    0.200.86 m @ 0.888 kg/m = 2,100.12 kg

    + ( 4 pcs ) ( 550 m) = 2,200 m @ 0.888 kg/m = 1,953.6 kg

    4,053.72 kg

    / 5.328 kg/pcs.

  • 8/11/2019 Quantity Calculator

    46/96

  • 8/11/2019 Quantity Calculator

    47/96

    LAYING

    CHB #4

    area pcs/sq.m. cell vol./ sq.m

    73.2 12.5 0.0375

    CHB #5area pcs/sq.m. cell vol./ sq.m

    194.4 12.5 0.05625

    CHB #6 pcs/sq.m. cell vol./ sq.m

    area

    320 12.5 0.075

    PLASTERING

    CHB #4

    area pcs/sq.m. plaster vol./ sq.m(two faces)

    124.8 12.5 0.0375

    CHB #5

    area pcs/sq.m. plaster vol./ sq.m(two faces)

    455.87 12.5 0.0375

    CHB REINFORCEMENT

    area vertical spacing length in FEET/sq.m. SUB-TOTAL length

    73.2 0.60m 6.875 503.25

    horizontal spacing

    every 3 layers 6.375 466.65

    QTY OF CEMENT, SAND, GRAVEL PER METER OF CHB FOOTING

    Length thickness width CEMENT class A bags

    115.2 6 inches 12 inches 41.472

    QUANTITY OF CEMENT, SAND, GRAVEL PER METER LENGTH OF POST, BEAM, AND GIRD

    Total length sizes in inches CEMENT class A CEMENT class B

    60 6 x 6 10.8 9.45

    6 x 8 14.4 12.6

    Length each post= 6 x 10 18 15.75

    2.5 6 x 12 21.6 18.9

    No. of Posts= 8 x 8 19.2 16.8

    24 8 x 10 24 21

    8 x 12 28.8 25.2

    8 x 14 33.6 29.4

    8 x 16 38.4 33.6

  • 8/11/2019 Quantity Calculator

    48/96

    10 x 10 30 26.25

    10 x 12 36 31.5

    10 x 14 42 36.75

    10 x 16 48 42

    10 x 18 54 47.2510 x 20 60 52.5

    QUANTITY OF CEMENT, SAND, GRAVEL PER SQUARE METER OF SLAB AND WALLS

    area thickness in inches CEMENT class A CEMENT class B

    18.5625 2 7.425 6.496875

    3 11.1375 9.7453125

    4 14.85 12.99375

    5 18.5625 16.2421875

    6 22.275 19.490625

    7 25.9875 22.7390625

    8 29.7 25.9875

    9 33.4125 29.2359375

    10 37.125 32.484375

    POST REINFORCEMENT::::LENGTH OF LATERAL TIE AND NUMBER IN ONE 6-M BAR

    Column Dimension Lateral tie dimension

    Length of post(M) W x L Width (inch) Length (inch)

    No. of Posts=

    15 6 x 8 3 5

    Length each Post=4 8 x 8 5 5

    Total Length of Post

    60

    No. of MAIN BARS=

    4

    8 x 10 5 7

    8 x 12 5 9

  • 8/11/2019 Quantity Calculator

    49/96

    8 x 14 5 11

    8 x 16 5 13

    10 x 10 7 7

    10 x 12 7 9

    10 x 14 7 11

    10 x 16 7 13

    10 x 18 7 15

    12 x 12 9 9

    12 x 14 9 11

    12 x 16 9 13

    12 x 18 9 15

    14 x 14 11 11

    MAIN REINFORCEMENT FOR COLUMN, BEAM, GIRDER

    Length (meter) No. of main Bars/ col Total Pcs of 20' Bar

    2.75 4 2

    6 3

    8 4

    10 5

    12 6

  • 8/11/2019 Quantity Calculator

    50/96

    CONCRETE SLAB REINFORCEMENT

    Bar

    area spacing (inch) 20' bar per SQ.M. Tie Wire KGS/SQ.M.

    54 4" 180.900 11.772

    5" 153.468 10.530

    6" 132.300 8.2087" 121.500 6.966

    8" 112.482 6.102

    9" 101.736 5.508

    10" 95.148 4.590

    11" 90.126 4.320

    12" 85.644 3.996

    BOARD FOOT OF STUDS AND CEILING JOISTPER SQUARE METER

    Area

    20.9 joist dimension (0.40m x 0.40m) (0.40m x 0.60m)

    2"x 2" 134.1153 113.80052"x 3" 201.1625 173.7208

    2" x 4" 268.2097 227.6219

    CEILING BOARD

    area sizes effective covering (sq.m) No. of pcs/ sq.m.

    20.9 12" x 12" 0.0929 11.250

    16" x 16" 0.1651 6.250

    16" x 24" 0.2477 4.250

    24" x 24" 0.3716 2.910

    3' x 6' 1.6720 0.675

    4' x 8' 2.9730 0.403

    SCAFFOLDING

    Length of column

    or size Vertical Horizontal

    Area of Floor(sq.m) in inches per Mt. height per Mt, height

    108.2 2" x 2" 505.294 2272.2

    2" x 3" 757.4 3426.694

    2" x 4" 1009.506 4568.204

    CORRUGATED G.I ROOFING

    Length Rivets

    in FEET 1-1/2 corrugation 2-1/2 corrugation Per sheet

    6' 0.70 m 0.60 m 14

    7' 0.70 m 0.60 m 19

    Effective Covering _ side lap

    One Way Slab

    joist spacing

    COLUMN (

  • 8/11/2019 Quantity Calculator

    51/96

    8' 0.70 m 0.60 m 19

    9' 0.70 m 0.60 m 19

    10' 0.70 m 0.60 m 24

    12' 0.70 m 0.60 m 29

    OOF ACCESSORIESMaterial No. of Pcs / kilo

    G.I roofing Nails 102

    Lead washers 75

    G.I Washers 126

    G.I rivets 180

    Tekscrew 7 pcs/sq.m.

    COMMON NAILS

    Size Length Approximate Number of Nailsinches No. to Lbs / Keg ( 45kgs )

    2d 1 876 85,700

    3d 1.1/4 568 54,800

    4d 1.1/2 316 29,800

    5d 1.3/4 271 25,500

    6d 2 181 17,900

    7d 2.1/4 161 15,300

    8d 2.1/2 106 10,100

    9d 2.3/4 96 8,900

    10d 3 69 6,600

    12d 3.1/4 63 6,20016d 3.1/2 49 4,900

    20d 4 31 3,100

    30d 4.1/2 24 2,400

    40d 5 18 1,800

    50d 5.1/2 14 1,300

    60d 6 11 1,100

    USED AND APPROX. QUANTITIES OF NAILS

    Material Unit Per Required Kilos Size

    1. Floor joist & Bridgin 1000 b.f 10.35 20d

    2. Flooring a. Soft 1000 b.f 14.34 8d

    b. Hard 1000 b.f 8.25 6d

    3. Studs 1000 b.f 10.43 8d

    4. Rafters,Purlins & cl 1000 b.f 18.38 20d

    5. Trusses 1000 b.f 7.93 20d

    6. Facia Board 1000 b.f 9.57 8d

    7. Ceiling Joist 1000 b.f 16.3 8d

  • 8/11/2019 Quantity Calculator

    52/96

    12.93 20d

    or 9.20 6d

    or 6.07 10d

    8. Ceiling Board ( 1 x 1000 b.f 4.55 6d

    9. Plywood Ceiling 18 pcs 1 2d

    10. Sidings 1000 b.f 4.55 6d11. Base Board 1000 b.f 6.08 6d

    12. Ballustrade 1000 b.f 8.2 6d

    13. Scaffolding mt. ht of column 0.73 20d

    14. Forms

    a. T & G 1000 b.f 6.33 6d

    b. Plywood 1/4 pc 0.07 2d

    1/2 pc 0.22 4d

    TILING WORKS

    AREA Tile size no. of pcs / sq.m. TOTAL pcs as to given area70 20cm x 20cm 25 1750

    30cm x 30cm 11.11 777.7

    40cm x 40cm 6.25 437.5

    60cm x 60cm 2.78 194.6

    EXCAVATION FOR STRUCTURE

    Column footing

    depth no. of footings size volume

    1 8 0.50m x 0.50m 2

    0.60m x 0.60m 2.88

    0.80m x 0.80m 5.121.00m x 1.00m 8

    1.20m x 1.20m 11.52

    wall footing

    length depth w/ 2 layer CHB width volume

    38.1 0.5 0.3 5.715

    PAINTING WORKSAREA coverage in sq.m. / gal. no. of coating total gallos required

    170.9 30 1 5.70

    2 11.39

    3

    Note: 1 tin = 4 gallons

    1 gal = 4 ltrs

  • 8/11/2019 Quantity Calculator

    53/96

    NOTE: tinting color

    1 gal = 4 quarts @

    1 quart = 4 pints@

    1/2 quart @

    1/4 quart @

    1/8 quart @

    SOIL POISONING

    AREA coverage sq.m. no. of chlordane_ltr

    101.4 4 mixture 1:100

    coverage 4ltrs mixture/sq.m. of slab

    4.056

    length of wall footing

    length coverage / mtr

    100 5.685 mixture 1:100

    coverage 4gal mixture/10ft length/ft. depth

    or 1.5 ltr mixture / ft. length of wallor 5.685 ltr mixture / mtr of wall

    5.685

    WOOD PRESERVATIVE

    AREA coverage sq.m./ltr no. of solignum_ltr

    100 o 8 sq.m. of wood surface / 5

    20

  • 8/11/2019 Quantity Calculator

    54/96

    laying vol./ sq.m TOTAL CHB SAND CEMENT

    0.00625 915 3.2025 28.8225

    laying vol./ sq.m TOTAL CHB SAND CEMENT

    0.008125 2430 12.5145 112.6305

    laying vol./ sq.m TOTAL CHB SAND CEMENT

    0.01 4000 27.2 244.8

    SAND CEMENT

    4.68 42.12

    SAND CEMENT

    17.095125 153.856125

    TOTAL LENTGH TOTAL # OF PCS TIE WIRES #16

    KGS/sq. m.

    969.9 48.495 1.3908

    SAND cu.m. GRAVEL cu.m. TIES SPACING o. pcs horizontal reinf.

    2.592 5.184 8" 40.42

    6" 40.42

    R

    SAND cu.m. GRAVEL cu.m.

    0.675 1.3500

    0.9 1.8000

    1.125 2.2500

    1.35 2.7000

    1.2 2.4000

    1.5 3.0000

    1.8 3.6000

    2.1 4.2000

    2.4 4.8000

  • 8/11/2019 Quantity Calculator

    55/96

    1.875 3.7500

    2.25 4.5000

    2.625 5.2500

    3 6.0000

    3.375 6.75003.75 7.5000

    FOOTING CemSAND cu.m. GRAVEL cu.m. Size of Footing thickness in inches

    0.4640625 0.928125 Length= 2

    0.66268125 1.3921875 0.75 3

    0.928125 1.85625 Width= 4

    1.16015625 2.3203125 0.75 5

    1.3921875 2.784375 6

    1.62421875 3.2484375 No. of Longitudinal= 7

    1.85625 3.7125 4 8

    2.08828125 4.1765625 No. of Transverse= 9

    2.3203125 4.640625 4 10

    No. of Footing=

    24

    Length of each Tie No. of pcs in one bar spacing in (inches)

    20 12 6

    824 10 6

    8

    10

    12

    14

    16

    28 8 6

    8

    10

    12

    14

    16

    32 7 6

    8

    10

    12

    14

    16

  • 8/11/2019 Quantity Calculator

    56/96

    36 6 6

    8

    10

    12

    14

    1640 6 8

    32 7 6

    8

    10

    12

    14

    16

    36 6 6

    8

    1012

    14

    16

    40 6

    44 5

    48 5

    40 6 6

    8

    10

    12

    14

    16

    44 5

    48 5

    52 4

    48 5

    enter

    total no. of ties per comp tie wire kgs/m

    100 2.264150943

    50 1.698113208

    50 2.264150943

    50 2.830188679

    50 3.396226415

  • 8/11/2019 Quantity Calculator

    57/96

    20' bar per SQ.M. Tie Wire KGS/SQ.M.

    224.100 24.786

    185.760 21.006

    164.160 15.228137.700 10.692

    126.900 7.128

    109.080 5.670

    98.280 4.482

    92.340 3.726

    86.400 3.024

    (0.60m x 0.60m)

    93.5066140.2599

    187.0132

    TOTAL pcs as to given area

    235.125

    130.625

    88.825

    60.819

    14.1075

    8.4227

    Brace TOTAL Vertical Horizontal

    per Meter height bd.ft. / meter height / meter. height

    1262.694 4040.188 432.8 505.294

    1893.5 649.2 757.4

    2524.306 865.6 1009.506

    Purlin

    Distance

    30"

    24"

    Two Way Slab

    Bd, Ft ) BEAM (Bd. Ft. )

  • 8/11/2019 Quantity Calculator

    58/96

    28"

    32"

    27"

    27"

    ITEMS Effective LengthGutter 2.4

    Valley Roll 2.4

    Flashing 2.3

    Hipped 2.2

    Ridge Roll 2.2

    Soldering Lead 1/4 bar / soldering joint

    Muriatic Acid 10 cc / soldering lead

    Kind

    CWN

    Flr Brads

    Flr Brads

    CWN

    CWN

    CWN

    CWN

    CWN

  • 8/11/2019 Quantity Calculator

    59/96

    CWN

    CWN

    CWN

    Casing Brads

    Finishing

    CWNFinishing

    Finishing

    CWN

    CWN

    CWN

    CWN

    CWN

    tile grout 2kg pack tile adhesive 25kg pack cement sand3.5 7.56 11.025 1.75

    Ration = 1:4 Ration = 1:100 sq.m. Ration = 4:100 sq.m. Ration = 1quart:4galthinner for QDE paints in gal Putty _ gal sand paper #240, #320 tinting color

    1.42 1.71 6.84 1.42

    2.85 2.85

  • 8/11/2019 Quantity Calculator

    60/96

  • 8/11/2019 Quantity Calculator

    61/96

    ties total CHB footing reinf. Tie wire

    28.85 69.27

    38.45 78.87

    CHB FOOTING REINFORCEMENT

  • 8/11/2019 Quantity Calculator

    62/96

    nt, sand ,Gravel, Reinforcement, tie wireCEMENT class A CEMENT class B SAND cu.m. GRAVEL cu.m.

    6.174 5.488 0.343 0.686

    9.261 8.232 0.514 1.029

    12.348 10.976 0.686 1.372

    15.434 13.720 0.857 1.715

    18.521 16.463 1.029 2.058

    21.608 19.207 1.200 2.401

    24.695 21.951 1.372 2.744

    27.782 24.695 1.543 3.087

    30.869 27.439 1.715 3.430

    No. of RSB TIES x 20'G.I. TIE WIRE NEEDED

    No.of RSB per meter length of post

    6.70 33.500 9.102

    5.15 25.750 6.9966.70 40.200 9.102

    5.15 30.900 6.996

    4.13 24.780 5.611

    3.43 20.580 4.660

    3.00 18.000 4.075

    2.71 16.260 3.682

    6.70 50.250 9.102

    5.15 38.625 6.996

    4.13 30.975 5.611

    3.43 25.725 4.660

    3.00 22.500 4.075

    2.71 20.325 3.682

    6.70 57.429 9.102

    5.15 44.143 6.996

    4.13 35.400 5.611

    3.43 29.400 4.660

    3.00 25.714 4.075

    2.71 23.229 3.682

    ATERAL TIES

  • 8/11/2019 Quantity Calculator

    63/96

    6.70 67.000 9.102

    5.15 51.500 6.996

    4.13 41.300 5.611

    3.43 34.300 4.660

    3.00 30.000 4.075

    2.71 27.100 3.682-

    6.70 57.429 9.102

    5.15 44.143 6.996

    4.13 35.400 5.611

    3.43 29.400 4.660

    3.00 25.714 4.075

    2.71 23.229 3.682

    6.70 67.000 9.102

    5.15 51.500 6.996

    4.13 41.300 5.6113.43 34.300 4.660

    3.00 30.000 4.075

    2.71 27.100 3.682

    6.70 67.000 9.102

    5.15 51.500 6.996

    4.13 41.300 5.611

    3.43 34.300 4.660

    3.00 30.000 4.075

    2.71 27.100 3.682

  • 8/11/2019 Quantity Calculator

    64/96

    FLOOR

    bd. Ft

    / SQ. METER

    660.02

    984.62

    1309.22

  • 8/11/2019 Quantity Calculator

    65/96

  • 8/11/2019 Quantity Calculator

    66/96

  • 8/11/2019 Quantity Calculator

    67/96

  • 8/11/2019 Quantity Calculator

    68/96

  • 8/11/2019 Quantity Calculator

    69/96

    Reinf. Tie wire

    24 2.174

    24 2.174

    24 2.174

    24 2.174

    24 2.174

    24 2.174

    24 2.174

    24 2.174

    24 2.174

  • 8/11/2019 Quantity Calculator

    70/96

  • 8/11/2019 Quantity Calculator

    71/96

  • 8/11/2019 Quantity Calculator

    72/96

  • 8/11/2019 Quantity Calculator

    73/96

  • 8/11/2019 Quantity Calculator

    74/96

  • 8/11/2019 Quantity Calculator

    75/96

  • 8/11/2019 Quantity Calculator

    76/96

  • 8/11/2019 Quantity Calculator

    77/96

  • 8/11/2019 Quantity Calculator

    78/96

  • 8/11/2019 Quantity Calculator

    79/96

  • 8/11/2019 Quantity Calculator

    80/96

  • 8/11/2019 Quantity Calculator

    81/96

  • 8/11/2019 Quantity Calculator

    82/96

  • 8/11/2019 Quantity Calculator

    83/96

  • 8/11/2019 Quantity Calculator

    84/96

  • 8/11/2019 Quantity Calculator

    85/96

  • 8/11/2019 Quantity Calculator

    86/96

    LABOR# of

    workers

    # of

    DaysTOTAL

    Foreman 500 /day 1 1 500

    Laborers 300 /day 2 1 600 1,100.00

    sub total 10,975.00

    12% 1,317.00

    Unit cost 700.785 12% 1,317.00

    SAY 700.5 12% 1,633.08

    TOTAL 15,242.08

    18,259.13 15,235.88

    II.

    PCCP

    pavement width Length

    A= 1 870

    A= 870 @ 898.18

    V= 87

    MATERIALS QTY PRICE TOTAL

    Cement 9 54 230 12420

    Sand 0.5 3 600 1800

    Gravel 1 6 700 4200

    RSB 10mm 7.15 43 145 6235

    Lumber 15 - 2 x 2 x 12 1.95 12 45 540

    Plywood 0.7 5 350 1750C.u.nail 0.068 0.5 80 40

    Tie wire 0.2 1.5 80 120 27,105.00

    418,567.65

    EQUIPMENTS# of

    Days/Day TRIPS TOTAL

    TRANSIT MIXER 1 1650 9 14850 14,850.00

    17.4

    LABOR# of

    workers

    # of

    Days

    TOTAL

    Foreman 500 /day 1 2 1000

    SKILLED 400 /day 1 2 800

    Laborers 300 /day 5 2 3000 4,800.00

    sub total 46,755.00

    12% 5,610.60

    Unit cost 74.64 12% 5,610.60

    SAY 1015.1 12% 6,957.14

  • 8/11/2019 Quantity Calculator

    87/96

    TOTAL 64,933.34

    883,137.00

    898,372.88

    784,764.13

  • 8/11/2019 Quantity Calculator

    88/96

  • 8/11/2019 Quantity Calculator

    89/96

    Aggregate base Course 21.75 700.50 15,235.88

    PCCP 870.00 1015.10 883,137.00

    Delivery Charge 1 -

    TOTAL 898,372.88

    cost

    18,259.13

    cost

    781,416.60

    799,675.73

    9,738.82

    SUMMARY0.10

    0.025

  • 8/11/2019 Quantity Calculator

    90/96

    3,456.25

    13,147.41

    783.00 783

    43.50 44

    87.00 87

    622.05 622

    169.65 170

    60.90 615.92 6

    17.40 18

    565,066.33

  • 8/11/2019 Quantity Calculator

    91/96

    200,000.0087,122.92

    112,877.08

  • 8/11/2019 Quantity Calculator

    92/96

  • 8/11/2019 Quantity Calculator

    93/96

  • 8/11/2019 Quantity Calculator

    94/96

  • 8/11/2019 Quantity Calculator

    95/96

    5

    7

    11

    0.20

    0.10

  • 8/11/2019 Quantity Calculator

    96/96

    PATHWAY