project scheduling: networks, duration estimation, and critical path

15
9-1 Project Scheduling: Networks, Duration Estimation, and Critical Path Chapter 9 Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Upload: rossa

Post on 12-Jan-2016

52 views

Category:

Documents


1 download

DESCRIPTION

Project Scheduling: Networks, Duration Estimation, and Critical Path. Chapter 9. B. A. D. E. F. C. Project Scheduling Terms. Successors Predecessors Network diagram Serial activities Concurrent activities. B. A. D. E. F. C. Project Scheduling Terms. Merge activities - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Project Scheduling: Networks, Duration Estimation,  and Critical Path

9-1

Project Scheduling: Networks, Duration Estimation,

and Critical Path

Chapter 9

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Page 2: Project Scheduling: Networks, Duration Estimation,  and Critical Path

9-2

Project Scheduling Terms

• Successors

• Predecessors

• Network diagram

• Serial activities

• Concurrent activities

ED

C

B

A F

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Page 3: Project Scheduling: Networks, Duration Estimation,  and Critical Path

9-3

Project Scheduling Terms

ED

C

B

A F

• Merge activities

• Burst activities

• Node

• Path

• Critical Path

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Page 4: Project Scheduling: Networks, Duration Estimation,  and Critical Path

9-4

Network Diagrams

Show interdependence

Facilitate communication

Help schedule resources

Identify critical

activities

Determine project completion

Show start & finish dates

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Page 5: Project Scheduling: Networks, Duration Estimation,  and Critical Path

9-5

AOA Vs. AON

The same mini-project is shown with activities on arc…

C

ED

B F

E

C

DB F

…and activities on node.

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Page 6: Project Scheduling: Networks, Duration Estimation,  and Critical Path

9-6

Node Labels

Early Start

Activity Float Activity Descriptor

Late Start

ID Number

Activity Duration

Late Finish

Early Finish

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Page 7: Project Scheduling: Networks, Duration Estimation,  and Critical Path

9-7

Duration Estimation Methods

• Past experience• Expert opinion• Mathematical derivation – Beta distribution

– Most likely (m)– Most pessimistic (b)– Most optimistic (a)

22 =

6

b aActivity Variance s

4 = TE

6

a m bActivity Duration

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Page 8: Project Scheduling: Networks, Duration Estimation,  and Critical Path

9-8

Task Predecessor a b c

Z -- 7 8 15

Y Z 13 16 19

X Z 14 18 22

W Y, X 12 14 16

V W 1 4 13

T W 6 10 14

S T, V 11 14 19

1. Sketch the network described in the table.

2. Determine the expected duration and variance of each activity.

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Page 9: Project Scheduling: Networks, Duration Estimation,  and Critical Path

9-9

Constructing the Critical Path

• Forward pass – an additive move through the network from start to finish

• Backward pass – a subtractive move through the network from finish to start

• Critical path – the longest path from end to end which determines the shortest project length

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Page 10: Project Scheduling: Networks, Duration Estimation,  and Critical Path

9-10

Rules for Forward/Backward Pass

Forward Pass Rules (ES & EF)– ES + Duration = EF– EF of predecessor = ES of successor– Largest preceding EF at a merge point becomes EF

for successor

Backward Pass Rules (LS & LF)– LF – Duration = LS– LS of successor = LF of predecessor– Smallest succeeding LS at a burst point becomes LF

for predecessor

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Page 11: Project Scheduling: Networks, Duration Estimation,  and Critical Path

9-11

Task Predecessor Time

A -- 4

B A 9

C A 11

D B 5

E B 3

F C 7

G D, F 3

H E, G 2

K H 1

1. Sketch the network described in the table.

2. Determine the ES, LS, EF, LF, and slack of each activity

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Page 12: Project Scheduling: Networks, Duration Estimation,  and Critical Path

9-12

Laddering Activities

Project ABC can be completed more efficiently if subtasks are used

A(3) B(6) C(9) ABC=18 days

Laddered ABC=12 days

A1(1) A2(1) A3(1)

B1(2) B2(2) B3(2)

C1(3) C2(3) C3(3)Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Page 13: Project Scheduling: Networks, Duration Estimation,  and Critical Path

9-13

Hammock Activities

Used as summaries for subsets of activities

0 A 5

0 5 5

5 B15

5 1015

15 C 18

15 3 18

0 Hammock 18

0 18 18

Useful with a complex project or one that has

a shared budgetCopyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Page 14: Project Scheduling: Networks, Duration Estimation,  and Critical Path

9-14

Reducing the Critical Path

• Eliminate tasks on the CP• Convert serial paths to parallel when possible• Overlap sequential tasks• Shorten the duration on critical path tasks• Shorten

– early tasks– longest tasks– easiest tasks– tasks that cost the least to speed up

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Page 15: Project Scheduling: Networks, Duration Estimation,  and Critical Path

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 9-15