Transcript
Page 1: Project Scheduling: Networks, Duration Estimation,  and Critical Path

9-1

Project Scheduling: Networks, Duration Estimation,

and Critical Path

Chapter 9

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Page 2: Project Scheduling: Networks, Duration Estimation,  and Critical Path

9-2

Project Scheduling Terms

• Successors

• Predecessors

• Network diagram

• Serial activities

• Concurrent activities

ED

C

B

A F

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Page 3: Project Scheduling: Networks, Duration Estimation,  and Critical Path

9-3

Project Scheduling Terms

ED

C

B

A F

• Merge activities

• Burst activities

• Node

• Path

• Critical Path

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Page 4: Project Scheduling: Networks, Duration Estimation,  and Critical Path

9-4

Network Diagrams

Show interdependence

Facilitate communication

Help schedule resources

Identify critical

activities

Determine project completion

Show start & finish dates

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Page 5: Project Scheduling: Networks, Duration Estimation,  and Critical Path

9-5

AOA Vs. AON

The same mini-project is shown with activities on arc…

C

ED

B F

E

C

DB F

…and activities on node.

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Page 6: Project Scheduling: Networks, Duration Estimation,  and Critical Path

9-6

Node Labels

Early Start

Activity Float Activity Descriptor

Late Start

ID Number

Activity Duration

Late Finish

Early Finish

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Page 7: Project Scheduling: Networks, Duration Estimation,  and Critical Path

9-7

Duration Estimation Methods

• Past experience• Expert opinion• Mathematical derivation – Beta distribution

– Most likely (m)– Most pessimistic (b)– Most optimistic (a)

22 =

6

b aActivity Variance s

4 = TE

6

a m bActivity Duration

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Page 8: Project Scheduling: Networks, Duration Estimation,  and Critical Path

9-8

Task Predecessor a b c

Z -- 7 8 15

Y Z 13 16 19

X Z 14 18 22

W Y, X 12 14 16

V W 1 4 13

T W 6 10 14

S T, V 11 14 19

1. Sketch the network described in the table.

2. Determine the expected duration and variance of each activity.

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Page 9: Project Scheduling: Networks, Duration Estimation,  and Critical Path

9-9

Constructing the Critical Path

• Forward pass – an additive move through the network from start to finish

• Backward pass – a subtractive move through the network from finish to start

• Critical path – the longest path from end to end which determines the shortest project length

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Page 10: Project Scheduling: Networks, Duration Estimation,  and Critical Path

9-10

Rules for Forward/Backward Pass

Forward Pass Rules (ES & EF)– ES + Duration = EF– EF of predecessor = ES of successor– Largest preceding EF at a merge point becomes EF

for successor

Backward Pass Rules (LS & LF)– LF – Duration = LS– LS of successor = LF of predecessor– Smallest succeeding LS at a burst point becomes LF

for predecessor

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Page 11: Project Scheduling: Networks, Duration Estimation,  and Critical Path

9-11

Task Predecessor Time

A -- 4

B A 9

C A 11

D B 5

E B 3

F C 7

G D, F 3

H E, G 2

K H 1

1. Sketch the network described in the table.

2. Determine the ES, LS, EF, LF, and slack of each activity

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Page 12: Project Scheduling: Networks, Duration Estimation,  and Critical Path

9-12

Laddering Activities

Project ABC can be completed more efficiently if subtasks are used

A(3) B(6) C(9) ABC=18 days

Laddered ABC=12 days

A1(1) A2(1) A3(1)

B1(2) B2(2) B3(2)

C1(3) C2(3) C3(3)Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Page 13: Project Scheduling: Networks, Duration Estimation,  and Critical Path

9-13

Hammock Activities

Used as summaries for subsets of activities

0 A 5

0 5 5

5 B15

5 1015

15 C 18

15 3 18

0 Hammock 18

0 18 18

Useful with a complex project or one that has

a shared budgetCopyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Page 14: Project Scheduling: Networks, Duration Estimation,  and Critical Path

9-14

Reducing the Critical Path

• Eliminate tasks on the CP• Convert serial paths to parallel when possible• Overlap sequential tasks• Shorten the duration on critical path tasks• Shorten

– early tasks– longest tasks– easiest tasks– tasks that cost the least to speed up

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall

Page 15: Project Scheduling: Networks, Duration Estimation,  and Critical Path

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 9-15


Top Related