project scheduling: networks, duration estimation, and critical path

29
Project Scheduling: Networks, Duration estimation, and Critical Path

Upload: aliyah-robie

Post on 16-Dec-2015

229 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: Project Scheduling: Networks, Duration estimation, and Critical Path

Project Scheduling: Networks, Duration estimation,

and Critical Path

Page 2: Project Scheduling: Networks, Duration estimation, and Critical Path

Project Scheduling Terms• Successors

• Predecessors

• Network diagram

• Serial activities

• Concurrent activities

ED

C

B

A F

Page 3: Project Scheduling: Networks, Duration estimation, and Critical Path

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 9-3

Project Scheduling Terms

ED

C

B

A F

• Merge activities

• Burst activities

• Node

• Path

• Critical Path

Page 4: Project Scheduling: Networks, Duration estimation, and Critical Path

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 9-4

Network Diagrams

Show interdependence

Facilitate communication

Help schedule resources

Identify critical

activities

Determine project completion

Show start & finish dates

Page 5: Project Scheduling: Networks, Duration estimation, and Critical Path

AOA vs. AON

The same mini-project is shown with activities on arrow…

C

ED

B F

E

C

DB F

…and activities on node.

Page 6: Project Scheduling: Networks, Duration estimation, and Critical Path

Node Labels

Early Start

Activity Float Activity Descriptor

Late Start

ID Number

Activity Duration

Late Finish

Early Finish

Page 7: Project Scheduling: Networks, Duration estimation, and Critical Path

Duration Estimation Methods

• Past experience• Expert opinion• Mathematical derivation – Beta distribution

– Most likely (m)– Most pessimistic (b)– Most optimistic (a)

22 =

6

b aActivity Variance s

4 = TE

6

a m bActivity Duration

Page 8: Project Scheduling: Networks, Duration estimation, and Critical Path

Task Predecessor a m b

A -- 7 8 15

B A 13 16 19

C A 14 18 22

D B, C 12 14 16

E D 1 4 13

F D 6 10 14

G F, E 11 14 19

1. Sketch the network described in the table.

2. Determine the expected duration and variance of each activity.

Page 9: Project Scheduling: Networks, Duration estimation, and Critical Path

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 9-9

Constructing the Critical Path

• Forward pass – an additive move through the network from start to finish

• Backward pass – a subtractive move through the network from finish to start

• Critical path – the longest path from end to end which determines the shortest project length

Page 10: Project Scheduling: Networks, Duration estimation, and Critical Path

Rules for Forward/Backward Pass

Forward Pass Rules (ES & EF)– ES + Duration = EF– EF of predecessor = ES of successor– Largest preceding EF at a merge point becomes EF

for successor

Backward Pass Rules (LS & LF)– LF – Duration = LS– LS of successor = LF of predecessor– Smallest succeeding LS at a burst point becomes LF

for predecessor

Page 11: Project Scheduling: Networks, Duration estimation, and Critical Path

Task Predecessor Time

A -- 4

B A 9

C A 11

D B 5

E B 3

F C 7

G D, F 3

H E, G 2

K H 1

1. Sketch the network described in the table.

2. Determine the ES, LS, EF, LF, and slack of each activity

Page 12: Project Scheduling: Networks, Duration estimation, and Critical Path

Laddering Activities

Project ABC can be completed more efficiently if subtasks are used

A(3) B(6) C(9) ABC=18 days

Laddered ABC=12 days

A1(1) A2(1) A3(1)

B1(2) B2(2) B3(2)

C1(3) C2(3) C3(3)

Page 13: Project Scheduling: Networks, Duration estimation, and Critical Path

Hammock Activities

Used as summaries for subsets of activities

0 A 5

0 5 5

5 B15

5 1015

15 C 18

15 3 18

0 Hammock 18

0 18 18

Useful with a complex project or one that has

a shared budget

Page 14: Project Scheduling: Networks, Duration estimation, and Critical Path

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 9-14

Reducing the Critical Path

• Eliminate tasks on the CP• Convert serial paths to parallel when possible• Overlap sequential tasks• Shorten the duration on critical path tasks• Shorten

– early tasks– longest tasks– easiest tasks– tasks that cost the least to speed up

Page 15: Project Scheduling: Networks, Duration estimation, and Critical Path

Chapter 10

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 9-15

Page 16: Project Scheduling: Networks, Duration estimation, and Critical Path

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 10-16

Lags in Precedence Relationships

The logical relationship between the start and finish of one activity and the start and finish of another activity.

Four logical relationships between tasks

1. Finish to Start

2. Finish to Finish

3. Start to Start

4. Start to Finish

Page 17: Project Scheduling: Networks, Duration estimation, and Critical Path

Finish to Start Lag

• Most common type of sequencing

• Shown on the line joining the modes– Added during forward pass– Subtracted during backward pass

0 A 6Spec Design

6

6 B 11Design Check

5

15 C 22Blueprinting

7

Lag 4

This lag is not the same as activity slack

Page 18: Project Scheduling: Networks, Duration estimation, and Critical Path

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 10-18

Finish to Finish Lag

Two activities share a similar completion point– The mechanical inspection cannot happen until

wiring, plumbing, and HVAC installation are complete

10 B 16Plumbing

6

16 C 24HVAC

5

24 D 25Inspection

1

15 A 21Wiring

6

Lag 3

Page 19: Project Scheduling: Networks, Duration estimation, and Critical Path

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 10-19

Start to Start Lag

Logic must be maintained by both

forward and backward pass

31 B 32Plumbing

1

33 C 36HVAC

5

36 D 37Inspection

1

30 A 36Wiring

6

Lag 3

Page 20: Project Scheduling: Networks, Duration estimation, and Critical Path

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 10-20

Start to Finish Lag

• Least common type of lag relationship

• Successor’s finish dependent on predecessor’s start

22 B 28Plumbing

6

28 C 33HVAC

5

33 D 34Inspection

1

30 A 36Wiring

6 Lag 3

Page 21: Project Scheduling: Networks, Duration estimation, and Critical Path

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 10-21

Gantt Charts

Establish a time-phased network Can be used as a tracking tool

Benefits of Gantt charts

1. Easy to create and comprehend

2. Identify the schedule baseline network

3. Allow for updating and control

4. Identify resource needs

Page 22: Project Scheduling: Networks, Duration estimation, and Critical Path

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 10-22

Create a Gantt chart based on the activities listed in the table.

Task Time Pred

A 8 --

B 5 A

C 8 A

D 4 B,C

E 5 D

Page 23: Project Scheduling: Networks, Duration estimation, and Critical Path

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 10-23

Crashing

The process of accelerating a project

Principal methods for crashing

Improving existing resources’ productivity Changing work methods Increasing the quantity of resources

Page 24: Project Scheduling: Networks, Duration estimation, and Critical Path

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 10-24

Managerial Considerations

• Determine activity fixed and variable costs

• The crash point is the fully expedited activity

• Optimize time-cost tradeoffs

• Shorten activities on the critical path

• Cease crashing when– the target completion time is reached– the crashing cost exceeds the penalty cost

Page 25: Project Scheduling: Networks, Duration estimation, and Critical Path

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 10-25

What is the lowest cost to complete this project in 52 weeks? Times are in weeks and costs in dollars. Plot the AON & AOA networks and the GANTT chart.

Activity Pred Normal Time

Min Time

Normal Cost

Crash Cost

A -- 14 9 500 1500

B A 5 2 1000 1600

C A 10 8 2000 2900

D B, C 8 5 1000 2500

E D 6 6 1600 1600

F D 9 6 1500 3000

G E, F 7 4 600 1800

H G 15 11 1600 3600

Page 26: Project Scheduling: Networks, Duration estimation, and Critical Path

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 10-26

Activity on Arrow Networks

Activities represented by arrows

Widely used in construction

Event nodes easy to flag

Forward and backward pass logic similar to AON

Two activities may not begin and end at

common nodes

Dummy activities may be required

Page 27: Project Scheduling: Networks, Duration estimation, and Critical Path

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 10-27

1. Use AOA to sketch the network that represents the project as described in the table.

2. Calculate early and late event times for all activities.

Activity Time Pred Activity Time Pred

A 4 -- F 15 E

B 2 A G 4 E

C 10 A H 7 D,F,G

D 3 B I 11 H

E 15 B,C

Page 28: Project Scheduling: Networks, Duration estimation, and Critical Path

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 10-28

Activity on Arrow Network

A H

F

D

E

C

B I

G

Page 29: Project Scheduling: Networks, Duration estimation, and Critical Path

Copyright © 2010 Pearson Education, Inc. Publishing as Prentice Hall 10-29

Controversies in the Use of Networks

Networks can be too complex

Poor network construction creates problems

Networks may be used inappropriately

When employing subcontractors– The master network must be available to them– All sub-networks must use common methods

Positive bias exists in PERT networks