project management case study
TRANSCRIPT
1/30/2016
1
Group Project
• Kumudini Bandara • Nadun Wijayanga • A.A.Upul Chanaka • Amila Madushan • Sanjaya Senarathne • Geethani Bamunusinghe
Group 01
Growthink PLC Company
1/30/2016
3
To have a IT System to handle farmer loan/payment process
CEO initially mention about the budget IT Manager gives sufficient budget for this Project
1/30/2016
4
Capital Expenses
IT & Operation managers take out the budget with out any forecast analysis
1/30/2016
6
IT manager request written proposal from each vender
Vender Proposal sends to the perches manager
1/30/2016
7
IT manager secretory open all bids
Get a period of one month time to evaluate the proposals
1/30/2016
8
Use to general guide line for supplier evaluation process
Carefully analysis 17 proposals and select 4
1/30/2016
9
IT ,operation & perches managers select the vendors
Only 3 members select the final vendor
1/30/2016
10
Shorted list Proposal directly send to the CEO and CEO decide which one
good for farther processing
Easy Going Pvt Ltd
• Doing Vender payment quickly
1/30/2016
11
Cross functional team Use to implement the project
Easy Going Pvt Ltd doing system Analysis
1/30/2016
12
Critical Bugs
Easygoing Pvt Limited provided system with in a 4 month but it has many critical issues
1/30/2016
14
System also has pending modification and The system not to fit the business
requirements
1/30/2016
16
After system implementation Easygoing Pvt Limited not to provide any service and
Easygoing Pvt Limited said their warranty period is over and want to sign new contract for maintain
System
Additional Chargers
1/30/2016
18
If I was the IT Manager,
Will have a discussion with all the department heads of the company about their requirements of the new system
Form a team from each area to get the ideas about the
new system implementation. Finalize the requirements informed by the departments
heads . Market analyses about the system Will inform the CEO and the corporate management
about the new system requirement and the benefits to the company gain from the new system implementation .
Set up a committee covering all areas of the company to select the vendors .
Call for bids .
1/30/2016
19
Analyzes the bids with following’s.
Price Years in market Owners of the company Company profile After sales Previous projects handle by the vendors Experienced staff in the company Will select the five vendors from the the bids . Will do a cost analysis for those venders for next 5 years Submit the selected vendors to the CEO and the higher
authority for approvals .
Analyzes the bids with following’s. Price Years in market Owners of the company Company profile After sales Previous projects handle by the vendors Experienced staff in the company Will select the five vendors from the the bids . Will do a cost analysis for those venders for next 5 years Submit the selected vendors to the CEO and the higher
authority for approvals .
1/30/2016
20
Develop GrowThink’s IT Department using EasyGoing Company employees
which worked in Farmer handling project
Established New IT Company and get all employees which are working in
the Farmer handling project at EasyGoing Company
1/30/2016
21
Get to help from another IT company
• Take the staff member from easygoing to growthink as a permanent IT staff member who was huddling the critical issues
1/30/2016
22
Again doing manual process with some part of the IT system
Assumptions Made
• Easygoing company not do any formal system study before start the development
• IT manager not to consider time value of the system
• CEO depends on IT/ Operation manager
• CEO always more concern about the cost
• Decision making has always done by CEO with out board of directors